Spate Irrigation Project Annual Meeting, Sudan, 29 th April to 3 rd May

Size: px
Start display at page:

Download "Spate Irrigation Project Annual Meeting, Sudan, 29 th April to 3 rd May"

Transcription

1 Spate Irrigation Project Annual Meeting, Sudan, 29 th April to 3 rd May Spate Irrigation for Rural Economic Growth and Poverty Alleviation Ethiopia Dr Tena and Abebe

2 Contents 2011 achievements and challenges 2012 planned activities - Strengthening the Spate Irrigation Network - Solution Oriented Research Projects - Capacity Building, Continuous Knowledge Development & Dissemination - Supporting IFAD and Others project within Ethiopia

3 Introduction. Spate Irrigation is getting focus in Ethiopia. ** 9+3; River basins are not evenly situated it is the potential and sometimes the only alternatives for the low and mid-lands water centre development Due to climate change, population(human, livestock) pressure streams are becoming seasonal

4 2011 activities Hosting the launching of the IFAD-Spate irrigation project and steering committee meeting

5 1. Strengthening spate irrigation network Strengthening spate irrigation network Planned Status of activities accomplishment 1 Develop country network plan Prepared; Country network plan stating vision, mission, mandates and major activities for the period 2011 to 2014

6 1. Strengthening spate irrigation network 2 Develop country database of spate specialists There are , registered spate irrigation network members

7 1. Strengthening spate irrigation network 3 Identificatio n of organizatio ns key to implementi ng spate irrigation In addition to project implementing educational institutions (Haramaya and Arba Minch University) and OWMEB, the southern region pastoralist development bureau, Regional water resource bureaus, farmer organizations (Boru Dodota at Bililo), Hawasssa and Bahridar universities as well as NGOs (IFAD and MERET) were identified as key to implement spate irrigation activities.

8 1. Strengthening spate irrigation network 3... Training workshop was conducted where the listed key organizations participated. Lecturers, exercises and field trip was conducted as part of the workshop activities and this familiarized the participants with different technical, institutional, social and economic aspects of spate irrigation. Further tailored support to the implementing organizations will be provided in 2012.

9 2. Solution Oriented Research Projects Planned Activities 1 Reconnaissance survey to spate irrigation schemes accomplishme nt Once done and second round will also be done

10 2. Innovative Action Research Projects Planned Activities 2 identify a menu of action research topics 3 Organize meeting with key stakeholders aimed at identifying two action research topics 4 Preparing concept notes for the two action researches accomplishment Done Done Three concept notes were Ready

11 2. Solution oriented research agendas On- farm Water Management and Soil Moisture Optimum operation of flow control structures towards effective flood and sediment management Spate irrigation development potentials and options in the vast virgin lowlands

12 2. Innovative Action Research Projects 5 Develop full proposals for the two action researches Done

13 3. Capacity Building, Continuous Knowledge Development & Dissemination Activities 1 Organize a training workshop Status of accomplishment Workshop was conducted Syllabus of pate irrigation course/module; The participants from Jimma and other universities have reported to include spate irrigation as chapter in the course that they are teaching Spate irrigation is incorporated as a course under Flood and Drought management module of the IRBM programme (MSc programme to be implemented in 8 Ethiopian universities)

14 3. Capacity Building, Continuous Knowledge Development & Dissemination 2 Translation, preparation, adaptation of practical notes 3 Preparation of spate program development charter as annex to the Country policy Translation of one practical note and preparation of technical document are done - Only the activity is iniated - Registering The SpN

15 3. Capacity Building, Continuous Knowledge Development & Dissemination 4 Prepare a handbook for a Joint Haramaya University - UNESCO-IHE MSc program on Agricultural Water Management in collaboration with UNESCO-IHE staff 5 Selection of three participants for the Joint MSc Programme Done Done Three participants started their studies within the framework of the Join MSc Programme

16 3. Capacity Building, Continuous Knowledge Development & Dissemination 6 Selection of one participant for spate short course 7 Purchasing one laptop, one video camera, one combined printer and scanner or projector, Two participant completed short Not done

17 4. Cooperation with other IFAD and other country programmes Joint activity programme developed between IFAD and the Central SpN on hands-on training on the design of spate irrigation systems and knowledge sharing in the establishment and strengthening of WUAs. The content of the programmes have been agreed upon, discussion on the budget is still to be finalized. A proposal has been developed for joint IMAWESA-SpN Ethiopia for 2012

18 Lesson Learnt from Sudan Participating MSc students, Sudan Shortly after this meeting stakeholders consultation meeting will be re-conducted: identifying the real challenges at the ground, and also put us in better position to support our parent farmers and selected schemes will be visited and to work actively on 2012 activities

19 2012 plan

20 1. Strengthening the Spate Irrigation Network 1 Plan Updating the list of active country Spate Specialists and also informing them with spate news Deliverables Updated spate specialists contact details Additional spate network members will be registered and the number of members will be raised more than 40 at the end of 2012.

21 2 1. Strengthening the Spate Irrigation Network Plan Tailor made support, training, to regional water, mine and energy Bureau and pastoralist development offices in the SNNPR of Ethiopia. Lecture will be given to GC students and staffs in University Meeting will also be conducted with farmer WUAs to discuss about spate irrigation practices and learn about their challenge on spate irrigation scheme. Deliverables Report document: that discusses about the organization, the support it earns, goal of the support.

22 2. Solution Oriented Action Research Implementation of action research: International and national MSc students will lead this. This approach can significantly contribute to capacity building of the local students and also creates an opportunity for joint supervision and hence exchange of experience among Ethiopia staff and staff from international universities/institutes First hand analysis, result and draft thesis report of MSc papers/ Preliminary research report document

23 3. Capacity Building, Continuous Knowledge Development & Dissemination Plan Contribution to preparation of spate program development charter as annex to the Country policy on land and water management and development Deliverables Prepare a draft spate irrigation charter that outlines experiences of spate irrigation in Ethiopia, details alternative programs for spate irrigation development in the country and the relevant supportive land and water policy required

24 3. Capacity Building, Continuous Knowledge Development & Dissemination Plan Translation, preparation, adaptation of practical notes Farmer-to-farmer knowledge sharing Exchange visits programme among farmers from Oromia and Tigray and SNNPR spate irrigation systems will be prepared, Deliverables preparation of one practical note and translation of two practical notes Exchange visit conducted, practical knowledge shared and visions, missions and activities of SpN Ethiopia explained The visit is video documented

25