Table 6A. Income and Cash Operating Cost Summary, Upland Cotton, 1996 Page 19

Size: px
Start display at page:

Download "Table 6A. Income and Cash Operating Cost Summary, Upland Cotton, 1996 Page 19"

Transcription

1 Table 6A. Income and Cash Operating Cost Summary, Upland Cotton, 1996 Page 19 Item Unit Quantity Price Budgeted Total Your Farm /Unit /Acre /Acre Budget INCOME -> Lint Pound 1, $ $ Cottonseed Ton $ CASH LAND PREPARATION AND GROWING EXPENSES (including sales tax) Paid Labor (including benefits) Tractor/Self Propelled Hand 6.66 Irrigation Other/Contract 0.88 Chemicals & Custom Applications Fertilizers Insecticides Herbicides Farm Machinery and Vehicles Diesel Fuel Repairs & Maint Irrigation Water (excluding labor) Other Purchased Inputs & Services Seed/Transplants 9.07 Other Services & Rentals 9.00 TOTAL CASH LAND PREPARATION AND GROWING EXPENSES CASH HARVEST AND POST HARVEST EXPENSES Paid Labor (including benefits) Tractor/Self Propelled 4.69 Other/Contract 5.37 Chemicals & Custom Applications Other Chemicals Farm Machinery and Vehicles Diesel Fuel 7.06 Repairs & Maint Custom Harvest/Post Harvest 3.33 Cotton Ginning Crop Assessments 7.99 Other Materials 1.67 TOTAL HARVEST AND POST HARVEST EXPENSE OPERATING OVERHEAD->PICKUP USE OPERATING INTEREST AT 9.0% ========== ============ TOTAL CASH OPERATING EXPENSES $ RETURNS OVER CASH OPERATING EXPENSES $ Notes: The above figures do not include ownership costs, see Table 6B on Next Page for detailed cost allocation.

2 Table 6B. Allocation of Ownership Costs; Upland Cotton, 1996 Page 20 - CASH COST BASIS ($/ACRE) - - TOTAL COST BASIS ($/ACRE) - Item Income & Costs Net Returns Income & Costs Net Returns TOTAL INCOME at $ /Lb + 2nd Crop $ $ TOTAL OPERATING EXPENSES RETURN OVER CASH OPERATING EXPENSES $ $ CASH OVERHEAD EXPENSES Taxes, Housing & Insur., Farm Machinery Gen. & Off. Overhead ( 5% of Tot. Oper. Exp.) General Farm Maint. ( 3% of Tot. Oper. Exp.) Total Cash Overhead Expenses Total Cash Oper. & Over. Cost RETURNS OVER CASH OPER. & OVER. EXPENSES CAPITAL ALLOCATIONS (100% Equity) Capital Replacement, Machinery & Vehicles Interest on Equity, Machinery & Vehicles Total Capital Allocations RETURNS TO LAND, CAPITAL, MANAGEMENT & RISK > RETURNS TO LAND, MANAGEMENT & RISK > LAND COSTS / OWNERSHIP (100% Equity) Property Taxes ($540 X 16% X.14778) Opport. Inter. on Land (100% X 6.0% X $540) Total Land Costs RETURNS TO MANAGEMENT, CAPITAL & RISK > RETURNS TO MANAGEMENT & RISK > Management Services ( 8% of Tot. Oper. Exp.) TOTAL OWNERSHIP COST ========= ========= TOTAL COST $ $ RETURN TO MANAGEMENT, CAPITAL & RISK > $ RETURN TO RISK (PROFITS) > $66.51 BREAK-EVEN PRICE TO COVER OPERATING COST (PER Lb) $ $ BREAK-EVEN PRICE TO COVER OWNERSHIP COST $ $ BREAK-EVEN PRICE TO COVER TOTAL COST $ $0.6596

3 Table 6C. Variable Operating Costs; Upland Cotton, 1996 Page 21 First Hours * Operating Costs ($/Acre*) Tot. Cash No. Month Operation Machine Labor Fuel/Rps. Labor Cust/Ser. Materials Total Times Expense Class 1 Jan Rip L 2 Jan Plow L 3 Jan Landplane L 4 Jan Apply Herbicide/Ground G 5 Jan Disk L 6 Jan List L 7 Jan Disk Ends G 8 Jan Buck Rows G 9 Jan Preirrigate G 10 Apr Mulch L 11 Apr Plant L 12 Apr Remove Cap G 13 May Cultivate G 14 Jun Cultivate G 15 Jun Hand Weeding G 16 Jun Apply Herbicide/Ground G 17 Jun Irrigate G 18 Jun Soil Fertility G 19 Jun Field Scouting G 20 Jun Irrigate/Run Fertilizer G 21 Jun Apply Insect./Ground G 22 Jun Apply Insect./Ground G 23 Jul Apply Insecticide/Air G 24 Aug Apply Insecticide/Air G 25 Sep Apply Defoliant/Air H 26 Sep Prepare Ends H 27 Sep Cotton, First Pick H 28 Sep Cotton, Make Modules H 29 Sep Haul, Custom 0.2 Mu H * NOTES: See next page for notes.

4 Table 6C. Variable Operating Costs; Upland Cotton, 1996 Page 22 First Hours * Operating Costs ($/Acre*) Tot. Cash No. Month Operation Machine Labor Fuel/Rps. Labor Cust/Ser. Materials Total Times Expense Class 30 Nov Cotton, Second Pick H 31 Oct Cotton Ginning 32.4 Cs P 32 Dec Cotton Classing 2.2 Ba M 33 Dec Crop Assessment 2.2 Ba M 34 Nov Cut Stalks P 35 Nov Disk Residue L Pickup Use 60 Mi/Ac O Operating Interest at 9.00% O TOTAL CASH OPERATING EXPENSES: $ $76.56 $ $ $ T * NOTES: Machine and labor hours and operating cost are for one time over the designated acreage. The Tot. Cash Expense column and the TOTAL CASH OPERATING EXPENSES: row include all operations, all times over. Classes are defined below. OPERATING COST SUMMARY BY CLASS SENSITIVITY OF NET REVENUES OVER TOTAL CASH EXPENSES ($/Acre) Land Preparation (L) $56.89 Prices -> -25% -10% Budgeted +10% +25% Growing (G) Harvest (H) Yields $0.54 $0.64 $0.72 $0.79 $0.90 Break-even Post Harvest (P) Marketing (M) % Operating Overhead (O) % Budgeted 1, Total (T) $ % 1, % 1, Break-even Yield 1,

5 Table 6D. Resource and Cash Flow Requirements; Upland Cotton, 1996 Page 23 Water Operating Cost ($/Acre) Number Applied Total Purchased Fuel, Oil Other Month * Irrig. (Inches) Labor (Hrs) Water & Repairs Labor Chemicals Purchases Services Total JAN C FEB C MAR C APR C MAY C JUN C JUL C AUG C SEP C OCT C NOV C DEC C Pickup Use 60 Mi/Ac Operating Interest at 9.0% Total % TOTAL RESOURCES REQUIREMENTS(/Acre) TOTAL ENERGY REQUIREMENTS(/Acre) Total N lbs Diesel Fuel 31.0 Gal Total P 0.0 lbs Regular Gas 0.0 Gal Total K 0.0 lbs NonLead Gas 6.0 Gal Total Labor 9.8 Hrs Total Water 42.0 AI All Direct Energy 5.0 M BTU EQUIPMENT REQUIREMENTS(/Acre) Tractor, 150 PTO HP, MFWD 2.61 Hrs V-Ripper, 5 Shnk 0.18 Hrs Moldboard Plow, Way 0.40 Hrs Landplane 12 X 45' 0.26 Hrs Saddle Tk Sprayer, 2 Tk 8 Row 0.56 Hrs Offset Disk, 13.5' 0.61 Hrs Lister, 7 Bottom 0.18 Hrs Tractor, 70 PTO HP, MFWD 1.44 Hrs Rowbuck, 10' 0.11 Hrs Power Mulcher, 6 Rw 0.30 Hrs Planter, 6 Row 0.23 Hrs Section Harrow, 3 Section 0.13 Hrs Rolling Cultivator, 6 Rw 0.93 Hrs Cultivator, Sweep, 6 Rw 0.23 Hrs Directed Spray Rig, 16 Row 0.18 Hrs Cotton Picker, 4 Row 0.69 Hrs Tractor, 80 PTO HP, MFWD 0.30 Hrs Module Builder 0.30 Hrs Rotary Stalk Cutter, 4 Row 0.18 Hrs Pickup Truck, 1/2 Ton 2.00 Hrs MATERIALS REQUIREMENTS(/Acre) Prometryn 5.00 Pt Trifluralin 1.00 Pt Water, District AI Upl Cotton Sd+NU-Flow ND Lb Cyanazine 1.00 Qt , URAN 32, Lqd Ga 0.50 Pt Chlorpyrifos 0.25 Pt Endosulfan 2.00 Pt Acephate 0.50 Lb Lambdacyhalothrin 6.40 Oz Acephate 1.34 Lb Thidiazuron 0.20 Lb Endothall 0.75 Pt Module Tarps CW LABOR REQUIREMENTS(/Acre) Tractor 5.70 Hrs Other 0.13 Hrs Irrigators 2.25 Hrs Hand Weeders 1.00 Hrs Harvest 0.77 Hrs * NOTE: P = Previous Year C = Current Year N = Next Year

6 Table 6E. Schedule of Operations; Upland Cotton, 1996 Page 24 First Equipment/Custom Oper. Job Rate Material Use & Cost Service Cost Labor No. Month Times Operation HP Self-Prop./Implem. Acres/Hr Name Appl. Rate $/Unit $/Unit Type 1 Jan 0.5 Rip 150 V-Ripper, 5 Shnk 2.50 Tractor 2 Jan 1.0 Plow 150 Moldboard Plow, Tractor 3 Jan 1.0 Landplane 150 Landplane 12 X 45' 3.50 Tractor 4 Jan 1.0 Apply Herbicide/Groun150 Saddle Tk Sprayer, 2 Tk 6.00 Prometryn 2.50 Pt Ga Tractor Trifluralin 1.00 Pt Ga 5 Jan 1.0 Disk 150 Offset Disk, 13.5' 4.00 Tractor 6 Jan 1.0 List 150 Lister, 7 Bottom 5.00 Tractor 7 Jan 6.0 Disk Ends 150 Offset Disk, 13.5' Tractor 8 Jan 5.0 Buck Rows 70 Rowbuck, 10' Tractor Other 9 Jan 1.0 Preirrigate 1.11 Water, District AI AF Irrigator 10 Apr 1.0 Mulch 150 Power Mulcher, 6 Rw 3.00 Tractor 11 Apr 1.0 Plant 70 Planter, 6 Row 4.00 Upl Cotton Sd+NU-F Lb CW Tractor 12 Apr 1.0 Remove Cap 150 Section Harrow, 3 Secti 7.00 Tractor 13 May 2.0 Cultivate 70 Rolling Cultivator, 6 R 3.00 Tractor 14 Jun 2.0 Cultivate 70 Rolling Cultivator, 6 R 5.50 Tractor 15 Jun 0.5 Hand Weeding 0.50 Hand Weed 16 Jun 1.0 Apply Herbicide/Groun150 Cultivator, Sweep, 6 Rw 4.00 Prometryn 2.50 Pt Ga Tractor Saddle Tk Sprayer, 2 Tk Cyanazine 1.00 Qt Ga 17 Jun 2.0 Irrigate 2.22 Water, District 6.00 AI AF Tractor 18 Jun 1.0 Soil Fertility CST Soil Analysis (Surf 3.00 Ac 19 Jun 1.0 Field Scouting CST Scout For Insects 6.00 Ac 20 Jun 3.0 Irrigate/Run Fertiliz 2.22 Water, District 6.00 AI AF Irrigator , URAN 32, Ga Tn 21 Jun 1.0 Apply Insect./Ground 70 Saddle Tk Sprayer, 2 Tk Pt Ga Tractor Directed Spray Rig, Jun 1.0 Apply Insect./Ground 70 Saddle Tk Sprayer, 2 Tk Chlorpyrifos 0.25 Pt Ga Tractor Directed Spray Rig, Jul 1.0 Apply Insecticide/Air CST Air Spray, 3 Gal Mi Endosulfan 2.00 Pt Ga 6.00 Ac Acephate 0.50 Lb 9.23 Lb 24 Aug 2.0 Apply Insecticide/Air CST Air Spray, 3 Gal Mi Lambdacyhalothrin 3.20 Oz Ga 6.00 Ac Acephate 0.67 Lb 8.78 Lb 25 Sep 1.0 Apply Defoliant/Air CST Air Spray, 5 Gal Mi Thidiazuron 0.20 Lb Lb 8.32 Ac Endothall 0.75 Pt Ga 26 Sep 1.0 Prepare Ends 150 Offset Disk, 13.5' Tractor 27 Sep 1.0 Cotton, First Pick Cotton Picker, 4 Row 2.00 Harvest 28 Sep 1.0 Cotton, Make Modules 80 Module Builder 3.00 Module Tarps CW 0.05 CW Tractor 29 Sep 1.0 Haul, Custom CST Haul Cotton Modules 0.00 Mu 30 Nov 0.8 Cotton, Second Pick Cotton Picker, 4 Row 3.00 Harvest 31 Oct 1.0 Cotton Ginning CST Gin Upland Cotton 3.00 Cs 32 Dec 1.0 Cotton Classing CST Class Cotton, HVI 1.50 Ba 33 Dec 1.0 Crop Assessment CST Upland (Low Elev) 3.60 Ba 34 Nov 1.0 Cut Stalks 150 Rotary Stalk Cutter, Tractor 35 Nov 1.0 Disk Residue 150 Offset Disk, 13.5' 3.00 Tractor NOTES at the bottom of the next page.

7 Table 6E. Schedule of Operations; Upland Cotton, 1996 Page 25 First Equipment/Custom Oper. Job Rate Material Use & Cost Service Cost Labor No. Month Times Operation HP Self-Prop./Implem. Acres/Hr Name Appl. Rate $/Unit $/Unit Type Pickup Use 60 Mi/Ac Pickup Truck, 1/2 Ton 0.50 * NOTE: Machine times, labor times, and material rates are for one time over the designated acreage.