NEI Draft White Paper. Use of the Generic Letter Process and Alternative Source Terms in the Context of Control Room Habitability
|
|
- Samuel Morgan
- 6 years ago
- Views:
Transcription
1 I. Current Situation A number of plants either have conducted, or plan to conduct in the near term, tracer gas testing of the control room envelope to determine if design and licensing basis inleakage assumptions are satisfied. If measured in-leakage is greater than the amount assumed in the licensing basis radiological consequences analysis, the licensee must perform an operability determination to verify that the control room ventilation system can accomplish necessary safety functions. This is considered a generic issue. Given the low probability of a design basis accident and the conservatism inherent in dose calculations, including the conservatism in the source term itself, the issue is not considered an immediate safety concern. II. Problem Statement A generic licensing issue has been raised by NRC reviewers and inspectors about the acceptability of licensees using an alternative source term (without prior NRC staff review and approval) in a Generic Letter evaluation to justify continued operation with a control room ventilation envelope that has been shown by tracer gas test to be in a degraded or nonconforming condition. III. The Generic Letter Process Generic Letter 91-18, Revision 1, directs licensees to make an operability determination and take follow-up corrective action whenever a structure, system, or component (SSC) is found to be degraded or nonconforming. A degraded condition is a condition of an SSC in which there has been a loss of quality or functional capability. A nonconforming condition is a condition of an SSC in which there is failure to meet requirements or licensee commitments. The scope of applicable SSCs is given in the Generic Letter. The primary reference defining operability is the plant-specific Technical Specifications. The primary reference for defining functionality is the set of plantspecific design and licensing basis documents, primarily the Updated Final Safety Analysis Report. The primary reference for defining the restoration of full qualification is 10 CFR 50, Appendix B, Criterion XVI, Corrective Action. The operability determination must be prompt, with timeliness commensurate with the safety significance of the issue. The determination can be based on analysis, testing, experience, compensatory measures, engineering judgment, or a combination of these factors, taking into consideration system functional requirements described in design and licensing basis documents. The scope of the determination must be sufficient to address the capability of relevant SSCs to perform their safety functions given the degraded or nonconforming condition. Additional information on safety functionality is given in NEI 97-04, Revision 1. 1
2 If the operability determination has a positive outcome, the plant may continue to operate on an interim basis with a degraded or nonconforming condition. Timely corrective action must then be taken to reconcile the degraded or nonconforming condition (i.e., restore full qualification in accordance with the plant s licensing basis, or revise the licensing basis in accordance with the appropriate regulatory change process). IV. The Alternative Source Term Regulation (10 CFR 50.67) A final rule on the use of alternative source terms at operating reactors was promulgated in The final rule recognized that significant advances have been made in understanding fission product releases from severe accidents. The revised source terms discussed in the final rule offer a more representative description of radionuclide composition and release timing. 10 CFR 50.67(b)(1) specifies that a licensee who seeks to revise its current accident source term in the design basis radiological consequence analyses shall apply for a license amendment under In other words, a licensee cannot use 10 CFR to change its licensing basis to incorporate alternative source term methodology without prior NRC staff review and approval. However, the final rule does not discuss the use of alternative source terms in the context of the Generic Letter process, which is not a process for changing the licensing basis, but is a process for justifying continued operation until corrective action can be taken to reconcile a degraded or nonconforming condition. One option chosen by a licensee to reconcile a degraded or nonconforming condition may in fact be a formal license amendment request under 10 CFR to revise the licensing basis, in this case to formally incorporate an alternative source term. Another option would be to perform an engineering evaluation to establish interim operability pending corrective action (an engineering evaluation in the context of Generic Letter is not considered a change to the licensing basis and is not considered a compensatory action). V. Use of Alternative Source Terms in a Generic Letter Evaluation of Control Room Habitability Regulatory Guide 1.196, Control Room Habitability at Light Water Nuclear Power Reactors, Regulatory Position 2.7.3, addresses methods available to address short term degraded or nonconforming conditions. RG refers to additional guidance in NEI 99-03, RG 1.183, RG 1.194, and RG However, this guidance is limited to the use of self-contained breathing apparatus (SCBA) or potassium iodide (KI) as compensatory measures. The purpose of this White Paper is to establish engineering judgment, with 2
3 reliance on alternative source terms, as another valid option to address short term degraded or nonconforming conditions. The option of performing an engineering evaluation using an alternative source term would be an effective initial approach to realistically evaluate control room radiological consequences. It is important to note that use of an alternative source term in an engineering evaluation conducted as part of the Generic Letter process is not a compensatory action subject to further evaluation under 10 CFR if it does not involve a plant modification, a procedure change, or a change to the design or licensing basis. Additional detail on the relationship between compensatory actions and 10 CFR can be found in NEI 96-07, Revision 1. Long-term corrective action would involve full restoration of the design and licensing basis described in relevant documentation. This may involve, for example: 1. a facility or procedure modification to reduce the in-leakage to a value within that assumed in the safety analysis, 2. a license amendment request for NRC staff approval of a change to the licensing basis to recognize the benefits of the alternative source term and to increase the allowable in-leakage, 3. a license amendment request for NRC staff approval of a change to the licensing basis to accept the as-found in-leakage condition, or 4. a combination of the above. VI. Industry Proposal If a tracer gas test indicates a degraded or nonconforming condition (design or licensing basis control room in-leakage assumptions are not satisfied), the least burdensome corrective action to establish interim operability would be to perform an engineering evaluation based on an alternative source term. The licensee could then determine the most efficient and effective way to exit the corrective action process, which likely would be to incorporate the alternative source term into the plant s design and licensing basis (example 3 above). VII. Proposed Followup Action NRC and industry perform a peer review of this White Paper to facilitate joint acceptance of the near-term use of alternative source terms by licensees in a Generic Letter context to justify continued plant operation following deficient tracer gas test results, assuming such operation does not conflict with any laws, regulations, license conditions, or Technical Specifications. NRC/NEI conduct public meetings to assist implementation of generic resolution. 3
4 VIII. References 1. NRC, 10 CFR 50, Appendix A, General Design Criterion 19, Corrective Action. 2. NRC, Generic Letter 91-18, Rev. 1, October 8, NRC, Final Rule, 64 FR 71990, Use of Alternative Source Terms at Operating Reactors, December 23, NRC, NUREG -0800, Standard Review Plan, Chapter , Radiological Consequence Analyses Using Alternative Source Terms, Rev. 0, July NRC, NUREG-1430 through NUREG-1434, Standard Technical Specifications, Rev NRC, Regulatory Guide 1.183, Alternative Radiological Source Terms for Evaluating Design Basis Accidents at Nuclear Power Reactors, July NRC, Regulatory Guide 1.187, Guidance for Implementation of 10 CFR 50.59, Changes, Tests, and Experiments, November NRC Regulatory Guide 1.194, Atmospheric Relative Concentrations for Control Room Radiological Habitability Assessment at Nuclear Power Plants, June NRC, Regulatory Guide 1.196, Control Room Habitability at Light Water Nuclear Power Reactors, May NRC, Regulatory Guide 1.197, Demonstrating Control Room Envelope Integrity at Nuclear Power Reactors, May NRC, Generic Letter , Control Room Habitability, June 12, NRC, Transcript of Operability Workshop held on August 14, 2003 (ADAMS Accession Number ML ). 13. NEI, Guideline 96-07, Revision 1, Guidelines for 10 CFR Implementation, November NEI, Guideline 97-04, Revision 1, Design Basis Program Guidelines, February NEI, Guideline 98-03, Revision 1, Guidelines for Updating Final Safety Analysis Reports, June NEI, Guideline 99-03, Revision 1, Control Room Habitability Guidance, March
5 17. NEI, Guideline 99-04, Guidelines for Managing NRC Commitment Changes, July Technical Specification Task Force, TSTF Traveler 448, Revision 1, Control Room Habitability, August 18,
NRC INSPECTION MANUAL
NRC INSPECTION MANUAL IRIB INSPECTION PROCEDURE 71124 RADIATION SAFETY PUBLIC AND OCCUPATIONAL PROGRAM APPLICABILITY: IMC 2515 EFFECTIVE DATE: January 1, 2010 71124-01 INSPECTION OBJECTIVE To independently
More informationProposed - For Interim Use and Comment
Proposed - For Interim Use and Comment U.S. NUCLEAR REGULATORY COMMISSION DESIGN-SPECIFIC REVIEW STANDARD FOR mpower TM ipwr DESIGN 14.2 INITIAL PLANT TEST PROGRAM - DESIGN CERTIFICATION AND NEW LICENSE
More informationDivision of Spent Fuel Management Interim Staff Guidance 2, Revision 2. Fuel Retrievability in Spent Fuel Storage Applications
Division of Spent Fuel Management Interim Staff Guidance 2, Revision 2 Issue: Fuel Retrievability in Spent Fuel Storage Applications Introduction: This Interim Staff Guidance (ISG) provides guidance to
More informationNRC BULLETIN : MITIGATING STRATEGIES - Utility Fast Turnaround Response Required Submitted by NUCBIZ on May 20, :16 NRC BULLETIN
NRC BULLETIN 2011-01: MITIGATING STRATEGIES - Utility Fast Turnaround Response Required Submitted by NUCBIZ on May 20, 2011-17:16 NRC BULLETIN 2011-01 The U.S. Nuclear Regulatory Commission (NRC) is issuing
More information6.0 ENGINEERED SAFETY FEATURES
Engineered Safety Features Materials 6.0 ENGINEERED SAFETY FEATURES This chapter of the U.S. EPR Final Safety Analysis Report (FSAR) is incorporated by reference with supplements as identified in the following
More informationRegulatory Challenges and Solutions High-Enriched to Low-Enriched Uranium Fuel Conversion
Regulatory Challenges and Solutions High-Enriched to Low-Enriched Uranium Fuel Conversion Alexander Adams Jr. Senior Project Manager Research and Test Reactor Program Office of Nuclear Reactor Regulation
More informationFederal Authority for Nuclear Regulation UAE
Federal Authority for Nuclear Regulation UAE 2012 International ISOE ALARA Symposium Session VIII: New Developments in ALARA Programs Development of the FANR RP Program During Design Phases of New Builds
More information\C) NRC Attach. 10 CFR 50.54(q) 10 CFR 50 Appendix E (IV)(B) May 2, 2001
NRC-01-055 Committed to Nuclear Excellenc>V Kewaunee Nuclear Power Plant N490, State Highway 42 Kewaunee, Wl 54216-9511 920-388-2560 Operated by Nuclear Management Company, LLC 10 CFR 50.54(q) 10 CFR 50
More informationRegulatory Guide Monitoring the Effectiveness of Maintenance at Nuclear Power Plants
Regulatory Guide 1.160 Revision 2 Page 1 of 14 Revision 2 March 1997 Regulatory Guide 1.160 Monitoring the Effectiveness of Maintenance at Nuclear Power Plants Publication Information (Draft issued as
More informationSeptember 19, Mr. Biff Bradley, Director Risk Assessment Nuclear Energy Institute Suite I Street, NW Washington, DC
September 19, 2007 Mr. Biff Bradley, Director Risk Assessment Suite 400 1776 I Street, NW SUBJECT: FINAL SAFETY EVALUATION FOR NUCLEAR ENERGY INSTITUTE (NEI) TOPICAL REPORT (TR) 04-10, REVISION 1, RISK-INFORMED
More informationNUREG-1549: Decision Methods for Dose Assessment to Comply With Radiological Criteria for License Termination
NUREG-1549: Decision Methods for Dose Assessment to Comply With Radiological Criteria for License Termination Abstract This draft NUREG-series report describes a methodology for calculating doses to demonstrate
More informationMarch 16, Mr. William M. Dean Director, Office of Nuclear Reactor Regulation U.S. Nuclear Regulatory Commission Washington, DC
ANTHONY R. PIETRANGELO Senior Vice President and Chief Nuclear Officer 1201 F Street, NW, Suite 1100 Washington, DC 20004 P: 202.739.8081 arp@nei.org nei.org March 16, 2015 Mr. William M. Dean Director,
More informationConversion of NEK Standard Technical Specifications into Improved Technical Specifications
International Conference Nuclear Energy for New Europe 2003 Portorož, Slovenia, September 8-11, 2003 http://www.drustvo-js.si/port2003 Conversion of NEK Standard Technical Specifications into Improved
More informationTracer Gas Inleakage Testing. What have we learned in Twenty Years?
Tracer Gas Inleakage Testing. What have we learned in Twenty Years? Kevin R. Grot, MS, CIH Peter L. Lagus, Ph.D., CIH Lagus Applied Technology, Inc. Escondido, CA 32 nd Nuclear Air Cleaning Conference
More informationRegulatory Guide Developing Software Life Cycle Processes for Digital Computer Software Used in Safety Systems of Nuclear Power Plants
Regulatory Guide 1.173Developing Software Lif... Page 1 of 10 September 1997 Regulatory Guide 1.173 Developing Software Life Cycle Processes for Digital Computer Software Used in Safety Systems of Nuclear
More informationRegulatory Guide An Approach For Plant-Specific Risk-informed Decisionmaking Inservice Inspection of Piping
Regulatory Guide 1.178An Approach For Plant-S... Page 1 of 32 July 1998 Regulatory Guide 1.178 An Approach For Plant-Specific Risk-informed Decisionmaking Inservice Inspection of Piping Publication Information
More informationCornerstone Development
Cornerstone Development Contents 1.0 Background... 1 2.0 RFCOP Regulatory Framework... 1 3.0 Consideration of Different Cornerstone Approaches... 2 3.1 Consideration of the Hazards Analysis-Based Cornerstones...
More informationNRC INSPECTION MANUAL
NRC INSPECTION MANUAL QVIB INSPECTION PROCEDURE 70702 PART 52, INSPECTION OF PREOPERATIONAL TEST PERFORMANCE PROGRAM APPLICABILITY: 2504 70702-01 INSPECTION OBJECTIVES 01.01 To provide guidance for inspection
More informationNovember 17, 2000 PROJECT NUMBER: 689. Dear Mr. Matthews:
NUCLEAR ENERGY INSTITUTE Anthony R. Pietrangelo DIRECTOR, LICENSING NUCLEAR GENERATION DIVISION November 17, 2000 Mr. David B. Matthews Division of Regulatory Improvement Programs Office of Nuclear Reactor
More informationRadiological Emergency Planning and Response Perception of Risk
Radiological Emergency Planning and Response Perception of Risk Patricia A. Milligan, CHP Senior Technical Advisor Office of Nuclear Security and Incident Response The Perception Gap When fears don't match
More informationNuclear power plant licensees are required to control
The Industry Ground Water Protection Initiative: A Watershed Moment By Kathleen C. Yhip, George J. Oliver, and Ralph L. Andersen Nuclear power plant licensees are required to control releases of radioactive
More informationOyster Creek Nuclear Generating Station Renewed Facility Operating License No. DPR-16 NRC Docket Nos and 72-15
Exelon Generation Michael P. Gallagher Vice President License Renewal and Decommissioning 200 Exelon Way Kennett Square. PA 19348 610 765 5958 Office 610 765 5658 Fax www.exeloncorp.com michaelp.gallagher@exeloncorp.com
More informationPage 1 / 11. Version 0 June 2014
Page 1 / 11 CORRESPONDENCE MATRIX NQSA NSQ-100 version 0 NUCLEAR SAFETY AND QUALITY MANAGEMENT SYSTEM REQUIREMENTS Model for quality management in design & development, manufacturing, erection, commissioning
More informationIndustry Responses to NRC Request for Additional Information Concerning the Industry s September 15, 2010 Proposal on Changes during Construction
ATTACHMENT 1 Industry Responses to NRC Request for Additional Information Concerning the Industry s September 15, 2010 Proposal on Changes during Construction The following provides the additional information
More informationRECOMMENDATION 2.3: SEISMIC. The U.S. Nuclear Regulatory Commission (NRC) is issuing this information request for the following purposes:
RECOMMENDATION 2.3: SEISMIC PURPOSE The U.S. Nuclear Regulatory Commission (NRC) is issuing this information request for the following purposes: To gather information with respect to Near Term Task Force
More informationNRC INSPECTION MANUAL
NRC INSPECTION MANUAL INSPECTION PROCEDURE CQV/EQV INSPECTION OF COMMERCIAL-GRADE DEDICATION PROGRAMS PROGRAM APPLICABILITY: 2504, 2507, 2700-01 INSPECTION OBJECTIVES 01.01 To verify that the dedicating
More informationINTRODUCTION - PART 2
NUREG-0800 U.S. NUCLEAR REGULATORY COMMISSION STANDARD REVIEW PLAN INTRODUCTION - PART 2 Standard Review Plan for the Review of Safety Analysis Reports for Nuclear Power Plants: Light-Water Small Modular
More informationGuidance on the Use of Deterministic and Probabilistic Criteria in Decision-making for Class I Nuclear Facilities
DRAFT Regulatory Document RD-152 Guidance on the Use of Deterministic and Probabilistic Criteria in Decision-making for Class I Nuclear Facilities Issued for Public Consultation May 2009 CNSC REGULATORY
More informationASME As a Help to Export! Our Topic today: Nuclear Quality Assurance ASME NQA 1
ASME As a Help to Export! Our Topic today: Nuclear Quality Assurance ASME NQA 1 Karte: Wikipedia CIS GmbH Experts in ASME Code Consulting CIS GmbH Consulting Inspection Services 3 rd Party Inspection Training
More informationAND CONTENT OF PHYSICAL PROTECTION PROGRAM OF NUCLEAR INSTALLATION(S)
PNRA-RG-909.02 (Rev.0) March, 2018 FORMAT AND CONTENT OF PHYSICAL PROTECTION PROGRAM OF NUCLEAR INSTALLATION(S) REGULATORY GUIDE PAKISTAN NUCLEAR REGULATORY AUTHORITY For Further Details Directorate of
More informationU.S. NUCLEAR REGULATORY COMMISSION STANDARD REVIEW PLAN. Organization responsible for mechanical engineering reviews
NUREG-0800 U.S. NUCLEAR REGULATORY COMMISSION STANDARD REVIEW PLAN 5.2.1.2 APPLICABLE CODE CASES REVIEW RESPONSIBILITIES Primary - Organization responsible for mechanical engineering reviews Secondary
More information25th DOE/NRC NUCLEAR AIR CLEANING AND TREATMENT PROBLEMS WITH THE LABORATORY TESTING OF NUCLEAR-GRADE ACTIVATED CHARCOAL
25th DOE/NRC NUCLEAR AIR CLEANING AND TREATMENT CONFERENCE PROBLEMS WITH THE LABORATORY TESTING OF NUCLEAR-GRADE ACTIVATED CHARCOAL John P. Segala Office of Nuclear Reactor Regulation U. S. Nuclear Regulatory
More informationREGULATORY GUIDE An Approach for Using Probabilistic Risk Assessment In Risk-Informed Decisions On Plant-Specific Changes to the Licensing Basis
REGULATORY GUIDE 1.174 An Approach for Using... Page 1 of 38 July 1998 REGULATORY GUIDE 1.174 An Approach for Using Probabilistic Risk Assessment In Risk-Informed Decisions On Plant-Specific Changes to
More informationRETS-REMP Workshop June, 2013 Westminster, CO
RETS-REMP Workshop June, 2013 Westminster, CO Does anyone know if there is a regulatory requirement to perform XOQDOQ calculations annually? RG 1.109 and NUREG 0133 all make use of historical meteorology
More informationRegulatory Standard Format and Content of License Termination Plans for Nuclear Power Reactors
01-179.html at www.nrc.gov Page 1 of 11 January 1999 Regulatory 1.179 Standard Format and Content of License Termination Plans for Nuclear Power Reactors Publication Information A. INTRODUCTION (Draft
More informationImproved Technical Specifications and Related Improvements to Safety in Commercial Nuclear Power Plants
Congreso Internacional Conjunto Cancún 2004 LAS/ANS-SNM-SMSR/International Joint Meeting Cancun 2004 LAS/ANS-SNM-SMSR XV Congreso Anual de la SNM y XXII Reunión Anual de la SMSR/XV SNM Annual Meeting and
More informationOverview of US NRC Decommissioning Surveys, Surface and Subsurface, Release Criteria and Records
Overview of US NRC Decommissioning Surveys, Surface and Subsurface, Release Criteria and Records R2D2P Workshop on Release of Buildlings and Sites/Final Survey Research Reactors Eureka, CA September 28
More informationPERMITTING CHALLENGES FOR THE NEW GENERATION OF NUCLEAR POWER PLANTS
PERMITTING CHALLENGES FOR THE NEW GENERATION OF NUCLEAR POWER PLANTS Ping K. Wan Environmental Technology Manager Bechtel Power Corporation Frederick, Maryland 1.0 INTRODUCTION The electric power industry
More informationIvica Basic and Ivan Vrbanic
Ivica Basic and Ivan Vrbanic OVERVIEW AND COMPARISON OF INTERNATIONAL PRACTICES CONCERNING THE REQUIREMENTS ON SINGLE FAILURE CRITERION WITH EMPHASIZE ON NEW WATER-COOLED REACTOR DESIGNS I. BASIC APoSS
More informationLong Term Operation of Nuclear Power Plants in Spain: Preparing for the Future
XXVIII Congreso Anual de la Sociedad Nuclear Mexicana - 2017 LAS/ANS Symposium Long Term Operation of Nuclear Power Plants in Spain: Preparing for the Future Ignacio Marcelles, Eva Frutos, Xavier Jardí
More informationAccepting Supplier ISO 9000 Quality Programs
Accepting Supplier ISO 9000 Quality Programs IEEE Subcommittee on Qualification October 7-8, 2004 Leigh A. Aparicio PSE Technical Leader aparicio@epri.com Project Overview ISO 9000 Phase I Initiated in
More informationAssessing the Radiological Consequences of Accidental Releases of Radioactive Materials from Liquid Waste Tanks for Combined License Applications
DESIGN CERTIFICATION/COMBINED LICENSE DC/COL-ISG-013 Assessing the Radiological Consequences of Accidental Releases of Radioactive Materials from Liquid Waste Tanks for Combined License Applications Interim
More informationNUPIC General Membership and Vendor Meetings June Greg Galletti Quality Electrical Vendor Branch Office of New Reactors U.S.
NUPIC General Membership and Vendor Meetings June 2014 Greg Galletti Quality Electrical Vendor Branch Office of New Reactors U.S. NRC 1 Insights from the Fukushima Event 2014 NRC Vendor Inspections Recent
More informationL11. Integration of Deterministic Safety Assessment (DSA) and PSA into a Risk-informed Decision Making Process
L11. Integration of Deterministic Safety Assessment (DSA) and PSA into a Risk-informed Decision Making Process John Fraser Preston john.preston@poyry.com ANSN Regional Workshop on Integrated Deterministic
More informationDevelopment of an Update to ISA S67.04 and RP 67.04: Setpoints for Nuclear Safety-Related Instrumentation for Nuclear Power Plants
Development of an Update to ISA S67.04 and RP 67.04: Setpoints for Nuclear Safety-Related Instrumentation for Nuclear Power Plants Wayne Marquino Chairman, ISA S67.04 Committee Team Leader, ESBWR System
More informationNUCLEAR REGULATORY COMMISSION. [Docket Nos. STN , STN , 72-73, , , 72-68, ,
This document is scheduled to be published in the Federal Register on 06/19/2018 and available online at https://federalregister.gov/d/2018-13089, and on FDsys.gov [7590-01-P] NUCLEAR REGULATORY COMMISSION
More informationNRC REGULATORY ISSUE SUMMARY (2014-XX) REPORTING OF H-3, C-14, Tc-99, and I-129 ON THE UNIFORM WASTE MANIFEST
ADDRESSEES UNITED STATES NUCLEAR REGULATORY COMMISSION OFFICE OF NUCLEAR REACTOR REGULATION OFFICE OF NEW REACTORS OFFICE OF FEDERAL AND STATE MATERIALS AND ENVIRONMENTAL MANAGEMENT PROGRAMS OFFICE OF
More informationRegulatory Decision Making and PRA
Regulatory Decision Making and PRA George Apostolakis Head, Nuclear Risk Research Center apostola@mit.edu 2nd JEA Nuclear Standards Committee Symposium Tokyo June 4, 1 1 The Traditional Approach Prior
More informationNUREG-1536: Standard Review Plan for Dry Cask Storage Systems
NUREG-1536: Standard Review Plan for Dry Cask Storage Systems Page 1 of 212 NUREG-1536: Standard Review Plan for Dry Cask Storage Systems Section Contents [ VIEW IN FRAMES DOCUMENT OUTLINE ACRONYMS ] PUBLICATION
More informationExperiences gained from a Living PSA workshop held on the PSA Castle Meeting in April 2013 in Stockholm.
Experiences gained from a Living PSA workshop held on the PSA Castle Meeting in April 2013 in Stockholm. Ralph Nyman*, Per Hellström, Frida Olofsson Swedish Radiation Safety Authority, Stockholm, Sweden
More informationNRC Activities. Matthew McConnell Senior Electrical Engineer Office of Nuclear Reactor Regulation
NRC Activities Matthew McConnell Senior Electrical Engineer Office of Nuclear Reactor Regulation Agenda Nuclear Power Plant Reviews Inspection News Regulatory Guide News Research Activities IEC/IEEE Joint
More informationEPRI Utility Requirement Document
EPRI Utility Requirement Document 11 February 2015 Sang-Baik KIM Analyst, NEA NDD Overview of URD Background and Objectives - Purpose of the URD is to present a clear, comprehensive set of design requirements
More informationNRC INSPECTION MANUAL INSPECTION PROCEDURE 35065
NRC INSPECTION MANUAL INSPECTION PROCEDURE 35065 DQASIP PROCUREMENT, RECEIVING, AND STORAGE PROGRAM APPLICABILITY: 2512 35065-01 INSPECTION OBJECTIVES To determine whether equipment procurement specifications
More informationCurrent and Future Application of Seismic Research Activities at the NRC in Response to the Accident at the Fukushima Dai-ichi Nuclear Power Plant
Current and Future Application of Seismic Research Activities at the NRC in Response to the Accident at the Fukushima Dai-ichi Nuclear Power Plant Jon Ake, Jose Pires and Clifford Munson U.S. Nuclear Regulatory
More informationREGULATORY GUIDE OFFICE OF NUCLEAR REGULATORY RESEARCH. REGULATORY GUIDE 1.61 (Draft was issued as DG-1157, dated October 2006)
U.S. NUCLEAR REGULATORY COMMISSION March 2007 Revision 1 REGULATORY GUIDE OFFICE OF NUCLEAR REGULATORY RESEARCH REGULATORY GUIDE 1.61 (Draft was issued as DG-1157, dated October 2006) DAMPING VALUES FOR
More informationNuclear I&C Systems Safety. The Principles of Nuclear Safety for Instrumentation and Control Systems
Nuclear I&C Systems Safety The Principles of Nuclear Safety for Instrumentation and Control Systems Legal and Regulatory Framework Legal framework, regulatory bodies and main standards of Nuclear Power
More informationUNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C August25, 2016
UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 August25, 2016 Mr. Jon A. Franke Site Vice President Susquehanna Nuclear, LLC 769 Salem Boulevard NUCSB3 Berwick, PA 18603-0467 SUBJECT:
More informationMeteorological Information Needs For An Early Site Permit Application
Meteorological Information Needs For An Early Site Permit Application Ping Wan Bechtel Power Corporation Frederick, Maryland ABSTRACT The DOE s Nuclear Power 2010 Initiative announced by the Secretary
More informationPrairie Island Nuclear Generating Plant. EAL Reference Manual. Revision 9
Prairie Island Nuclear Generating Plant EAL Reference Manual Notice to Users This document has been prepared for the Prairie Island Nuclear Generating Plant (PINGP). Its purpose is to provide general information
More informationFormat and Content of the Safety Analysis Report for Nuclear Power Plants - Core Set -
Format and Content of the Safety Analysis Report for Nuclear Power Plants - Core Set - 2013 Learning Objectives After going through this presentation the participants are expected to be familiar with:
More informationA.B. HULL, I.J. DOZIER, K.C. CHANG, P.T. KUO, F.P. GILLESPIE, NRC (USA) NPP license renewal and aging management: extrapolating American experience
A.B. HULL, I.J. DOZIER, K.C. CHANG, P.T. KUO, F.P. GILLESPIE, NRC (USA) NPP license renewal and aging management: extrapolating American experience A. B. Hull, I. J. Dozier, K. C. Chang, P. T. Kuo, and
More informationBHG Operational Awareness Program May 8, 1998 Performance Assessment Guide ENA 7.1 Revision 0 Engineering Program Page 1 of 10 ENGINEERING PROGRAM
Engineering Program Page 1 of 10 ENGINEERING PROGRAM 1.0 Objective The objective of this performance assessment is to evaluate the effectiveness of the laboratory's engineering program as implemented in
More informationQuality Management Manual Revision 19
Quality Management Manual Revision 19 959 Concord Street Framingham, MA 01701 508-875-2121 www.epm-inc.com with offices in Knoxville, TN and Raleigh, NC Rev. 19 PROPRIETARY INFORMATION NOTICE Page ii
More informationIAEA SAFETY STANDARDS for protecting people and the environment. Predisposal Management of Radioactive Waste from Nuclear Fuel Cycle Facilities
DS447 Date: 20 February 2015 IAEA SAFETY STANDARDS for protecting people and the environment STATUS: SPESS STEP 12 For submission to CSS Predisposal Management of Radioactive Waste from Nuclear Fuel Cycle
More informationATTACHMENT Guidance for Conducting an Independent NRC Safety Culture Assessment
ATTACHMENT 95003.02 Introduction Guidance for Conducting an Independent NRC Safety Culture Assessment The purpose of this assessment is for the NRC to assess the licensee s safety culture. Safety culture
More informationREGULATORY GUIDE OFFICE OF NUCLEAR REGULATORY RESEARCH. REGULATORY GUIDE 1.97 (Draft was issued as DG-1128, dated June 2005)
U.S. NUCLEAR REGULATORY COMMISSION Revision 4 June 2006 REGULATORY GUIDE OFFICE OF NUCLEAR REGULATORY RESEARCH REGULATORY GUIDE 1.97 (Draft was issued as DG-1128, dated June 2005) CRITERIA FOR ACCIDENT
More informationUNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C April 19, 2012
UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 April 19, 2012 Mr. Timothy S. Rausch Senior Vice President and Chief Nuclear Officer PPL Susquehanna, LLC 769 Salem Boulevard Berwick,
More informationKey Observations and Challenges
Key Observations and Challenges George Apostolakis Head, NRRC Workshop on Risk-Informed Decision Making: A Survey of U.S. Experience Tokyo, Japan, June 1-2, 2017 External Influence Regulatory agencies
More informationOctober 22, 2013 SUBJECT: THREE MILE ISLAND STATION, UNIT 1 - NRC SUPPLEMENTAL INSPECTION REPORT / AND ASSESSMENT FOLLOW-UP LETTER
UNITED STATES NUCLEAR REGULATORY COMMISSION REGION I 2100 RENAISSANCE BOULEVARD, SUITE 100 KING OF PRUSSIA, PENNSYLVANIA 19406-2713 EA-13-046 October 22, 2013 Mr. Michael J. Pacilio Senior Vice President,
More informationImplementation of the EQ program can be accomplished through work requests,
Activity: nvironmental Qualification 1.0 Purpose: To provide a guideline for the performance of quality surveillances to assure implementation of the nvironmental Qualification (Q) program. NOT: Implementation
More informationReactor Oversight Process
Reactor Oversight Process Mark A. Cunningham NRRC Workshop on Risk-Informed Decision Making: A Survey of U.S. Experience Tokyo, Japan, June 1-2, 2017 Introduction The USNRC modified its reactor inspection
More informationDIABLO CANYON POWER PLANT DIGITAL PROCESS PROTECTION SYSTEM REPLACEMENT LICENSING EXPERIENCE USING ISG-06
DIABLO CANYON POWER PLANT DIGITAL PROCESS PROTECTION SYSTEM REPLACEMENT LICENSING EXPERIENCE USING ISG-06 Kenneth J. Schrader, MSNE Pacific Gas & Electric Co. PO Box 56 Avila Beach, CA 93424 kjse@pge.com
More informationNRC INSPECTION MANUAL
NRC INSPECTION MANUAL NMSS/RII INSPECTION PROCEDURE MECHANICAL COMPONENTS PROGRAM APPLICABILITY: 2630-01 INSPECTION OBJECTIVES 01.01 To determine whether the technical requirements detailed or referenced
More information7/15/2015 Federal Register, Volume 80 Issue 44 (Friday, March 6, 2015)
[Federal Register Volume 80, Number 44 (Friday, March 6, 2015)] [Rules and Regulations] [Pages 12073-12078] From the Federal Register Online via the Government Printing Office [www.gpo.gov] [FR Doc No:
More informationSafety Considerations in the Transition from Operation to Decommissioning of Research Reactors
Safety Considerations in the Transition from Operation to Decommissioning of Research Reactors Research Reactor Safety Section Division of Nuclear Installation Safety - EBP Workshop on the Transition Period
More informationAPPLICATION OF THE GIP METHODOLOGY TO DEMONSTRATE SEISMIC ADEQUACY OF NEW AND REPLACEMENT EQUIPMENT AND PARTS IN USI A 46 PLANTS
~ r----------------------------------------------, This material may be protected by Copyright law (Title 17 U.S. Code) PVP-Vol. 275-2. Seismic Engineering - Volume 2 ASME 1994 APPLICATION OF THE GIP METHODOLOGY
More informationNUCLEAR REGULATORY COMMISSION. 10 CFR Part 20 [NRC ] RIN 3150-AJ17. Prompt Remediation of Residual Radioactivity During Operation
This document is scheduled to be published in the Federal Register on 10/06/2017 and available online at https://federalregister.gov/d/2017-21546, and on FDsys.gov [7590-01-P] NUCLEAR REGULATORY COMMISSION
More informationASME Section XI Code Meeting November 2007
Code Actions of Interest: 1. NDE Coverage Calculations (05-1176) ASME Section XI Code Meeting November 2007 This action is to revise Section XI to include IWA-2200(c) which will establish NDE coverage
More informationAppendix J STEAM GENERATOR TUBE INTEGRITY FINDINGS SIGNIFICANCE DETERMINATION PROCESS
Appendix J STEAM GENERATOR TUBE INTEGRITY FINDINGS SIGNIFICANCE DETERMINATION PROCESS 1.0 INTRODUCTION The significance determination process (SDP) provides a method to place inspection findings in context
More informationDRAFT REGULATORY GUIDE
Purpose U.S. NUCLEAR REGULATORY COMMISSION December 2011 OFFICE OF NUCLEAR REGULATORY RESEARCH Division 4 DRAFT REGULATORY GUIDE DRAFT REGULATORY GUIDE DG-4014 (Proposed New Regulatory Guide) Contact:
More informationNRC REGULATORY ISSUE SUMMARY RETURN/RE-USE OF PREVIOUSLY DISCHARGED RADIOACTIVE EFFLUENTS
UNITED STATES NUCLEAR REGULATORY COMMISSION OFFICE OF NUCLEAR MATERIAL SAFETY AND SAFEGUARDS OFFICE OF NUCLEAR REACTOR REGULATION WASHINGTON, DC 20555-0001 February 13, 2008 NRC REGULATORY ISSUE SUMMARY
More information1.0 PURPOSE 2.0 REFERENCES
Page 1 1.0 PURPOSE 1.1 This Advisory Circular provides Aerodrome Operators with guidance for the development of corrective action plans to be implemented in order to address findings generated during safety
More informationDraft Design Safety Requirements for Proposed Nigeria NPPs to SMRs and probable Application Challenges G. O. Omeje
Draft Design Safety Requirements for Proposed Nigeria NPPs to SMRs and probable Application Challenges G. O. Omeje TM on Challenges in the application of Design Safety Requirements for NPPs to SMRs 4th
More informationExample AMP for Localized Corrosion and Stress Corrosion Cracking of Welded Stainless Steel Dry Storage Canisters
Example AMP for Localized Corrosion and Stress Corrosion Cracking of Welded Stainless Steel Dry Storage Canisters Darrell S. Dunn, NRC/NMSS/DSFM/RMB Chloride-Induced Stress Corrosion Cracking Regulatory
More informationDivision of Spent Fuel Management Overview
Division of Spent Fuel Management Overview Anthony Hsia Deputy Director, Division of Spent Fuel Management Office of Nuclear Material Safety and Safeguards U.S. Nuclear Regulatory Commission INMM Spent
More informationRole of Licensing in Advanced Reactor Design
Role of Licensing in Advanced Reactor Design January 28, 2009 Current LWR Licensing Process Reactor vendors obtain design certification (DC) Approval of generic reactor plant design Vendor submits reactor
More informationEnvironmental Qualification Program for Krsko NPP
HR9800119 Environmental Qualification Program for Krsko NPP Janko Cerjak, Peter Klenovsek Nuclear Power Plant Krsko, Vrbina 12, Krsko, SLOVENIA Janez Pavsek Elektroinstitut Milan Vidmar, Hajdrihova 2,
More informationBIOSCRIP, INC. CHARTER OF THE AUDIT COMMITTEE OF THE BOARD OF DIRECTORS
BIOSCRIP, INC. CHARTER OF THE AUDIT COMMITTEE OF THE BOARD OF DIRECTORS Statement of Purpose 1. Oversight Responsibility. The purpose of the Audit Committee of the Board of Directors of BioScrip, Inc.,
More informationAPPENDIX E DISPOSITION OF THE NRC ADVISORY COMMITTEE ON REACTOR SAFEGUARDS (ACRS) CONSULTANTS ELECTRICAL AND STRUCTURAL COMMENTS
APPENDIX E DISPOSITION OF THE NRC ADVISORY COMMITTEE ON REACTOR SAFEGUARDS (ACRS) CONSULTANTS ELECTRICAL AND STRUCTURAL COMMENTS This Page Intentionally Left Blank E-ii E.1 INTRODUCTION The NRC Advisory
More informationDRAFT PROJECT PLAN TO PREPARE THE U.S. NUCLEAR REGULATORY COMMISSION TO LICENSE AND REGULATE ACCIDENT TOLERANT FUEL
DRAFT PROJECT PLAN TO PREPARE THE U.S. NUCLEAR REGULATORY COMMISSION TO LICENSE AND REGULATE ACCIDENT TOLERANT FUEL The Offices of Nuclear Reactor Regulation (NRR), New Reactors, Nuclear Material Safety
More informationAgreement to modify the 14 Dock Reactor Access House by introduction of a Seismic Trigger System under Arrangements made under Licence Condition 20(1)
Title of document Devonport Royal Dockyard Ltd. 14 Dock Reactor Access House Agreement to modify the 14 Dock Reactor Access House by introduction of a Seismic Trigger System under Arrangements made under
More informationCana a. Licence Conditions Handbook Effective date: July 01, 2010 (LCU-SRBT-ROOO)
.+ Canadian Nuclear Comm ssio l canadien e Salely Commis.sion de sure eal(e Effective date: July 01, 2010 (LCU-SRBT-ROOO) Compliance Framework Document associated to the SRB Technologies (Canada) Inc.
More informationRisk-informed Seismic Design of US Nuclear Power Plants
Dr. Annie Kammerer NC State University 10 th Structural Engineering & Mechanics Symposium March 2011 Risk-informed Seismic Design of US Nuclear Power Plants Atomic Energy Commission (1954) Energy Reorganization
More informationU. S. Department of Energy. Consolidated Audit Program Treatment, Storage and Disposal Facilities. Checklist 1 Quality Assurance Management Systems
U. S. Department of Energy Consolidated Audit Program Treatment, Storage and Disposal Facilities Checklist 1 Quality Assurance Management Systems Revision 1.3 December 2013 Audit ID: Date: Quality Assurance
More informationConcepts of Exemption and Clearance
Concepts of Exemption and Clearance name of presenter (e-mail) training event title dates location, host organization, host country International Atomic Energy Agency Overview Concept of controlling radioactive
More informationStandard Review Plan for Review of License Renewal Applications for Nuclear Power Plants
NUREG-1800, Rev. 1 Standard Review Plan for Review of License Renewal Applications for Nuclear Power Plants Manuscript Completed: September 2005 Date Published: September 2005 Division of Regulatory Improvement
More information4 Environmental and Seismic Qualification of Equipment - Issue 19
4-1 4 Environmental and Seismic Qualification of Equipment - Issue 19 Table of Contents 4 Environmental and Seismic Qualification of Equipment - Issue 19... 1 4.1 Introduction...1 4.2 Identified Problems...1
More informationIAEA-TECDOC-1229 Regulatory review of probabilistic safety assessment (PSA) Level 2
IAEA-TECDOC-1229 Regulatory review of probabilistic safety assessment (PSA) Level 2 Prepared jointly by the International Atomic Energy Agency and the OECD Nuclear Energy Agency July 2001 The originating
More informationNUCLEARINSTALLATIONSAFETYTRAININGSUPPORTGROUP DISCLAIMER
NUCLEARINSTALLATIONSAFETYTRAININGSUPPORTGROUP DISCLAIMER Theinformationcontainedinthisdocumentcannotbechangedormodifiedinanywayand shouldserveonlythepurposeofpromotingexchangeofexperience,knowledgedissemination
More informationDRAFT REGULATORY GUIDE
U.S. NUCLEAR REGULATORY COMMISSION June 2007 OFFICE OF NUCLEAR REGULATORY RESEARCH Division 1 DRAFT REGULATORY GUIDE Contact: Satish Aggarwal (301) 415-6005 DRAFT REGULATORY GUIDE DG-1132 QUALIFICATION
More information