Market Simulation Presentation Spring 2014 Release

Size: px
Start display at page:

Download "Market Simulation Presentation Spring 2014 Release"

Transcription

1 Market Simulation Presentation Spring 2014 Release Christopher McIntosh Lead Market Simulation Coordinator Spring 2014 Release April 24 th, 2014

2 Agenda Spring 2014 Market Simulation Initiatives and Timelines Spring 2014 MAP Stage Availability Spring 2014 Deployment Plan Acceptable Use Policy Phase 1 FERC 764 with Dynamic Transfers Adjacent BA FMM Scheduling Support Spring Release Known Issues RIMPR Phase 1 with Post Emergency BCR Spring 2014 Release Structured Scenario Execution Report Next Steps Reference Slides Page 2

3 Spring 2014 Release Market Simulation Initiatives and Timelines Spring Release Market Simulation - MAP-Stage will remain open and the ISO will continue to support unstructured scenario support through 4/30/14 FERC Order 764 Compliance with 15 Minute Market and Dynamic Transfers - February 11 th April 18 th, 2014 (Structured and Unstructured) Post Emergency Filing Bid Cost Recovery (BCR) with Mandatory Multi- Stage Generations (MSG), Renewable Integration Market and Product Review (RIMPR) Phase, Bid Cost Recovery (BCR) Mitigation Measures and Bid Floor Cap - February 11 th April 23 rd, 2014 (Structured and Unstructured) Revisions to Price Corrections - February 17 th March 7 th, 2014 (Unstructured) - Completed Acceptable Use Policy Phase 1 (Enforcement) - March 28 th, 2014 Page 3

4 Spring 2014 Release MAP Stage Availability Upcoming Scheduled Maintenance - Closing April 24 th, 16:00-20:00 No Outage April 25 th, 2014 MAP Stage Spring Release Daily Maintenance Window - 16:00-20:00 MAP Stage Weekly Maintenance Window - Friday s, 09:00-20:00 Page 4

5 Spring 2014 Release Updated Deployment Plan Updated 4/ Deployment/Activation Bridge USA Toll-Free: USA Caller Paid: For Other Countries: Click Here to View Global Conference Access Numbers Web Conference URL: Meeting Number: or Access Code: Timing 4/30/14 starting at 1 PM until all systems have recovered CAISO Page 5

6 Spring 2014 Cutover Timelines Start Finish # Task Description 1 Hold cutover and reversion table top Date Time Date Time Related Artifacts 2 Use IRDR 5.1 (IRDT 3.0 is decommissioned) 03/31/14 3 Upgrade to ADS Client Version /17/14 4 Submit request for 5 or 15 minute-meter data for each resource ID to mdas@caiso.com before Finish Date/Time (Or default submission interval for all generators not providing AS or Imbalance Energy SQMD will be hourly) 04/17/14 17:00 5 Submit MSG Registration Form and Generator Resource Data Template (RDT) before Finish Date/Time for trade day 5/1/14 effective date 04/24/14 17:00 6 Submit Variable Energy Resource (VER) registration documents to RDT@caiso.com for 5/1/14 effective date 04/16/14 17:00 04/24/14 17:00 7 Receive final Settlements Configuration File posted in MRI-Settlements 04/28/14 10:00 04/28/14 13:00 8 OMAR Outage - Resume activity upon system availability 04/28/14 14:00 04/28/14 16:00 9 Before 22:45 on 04/30, submit RT self-schedules for VER resources and energy trades for trade day 05/01/14 Hour Ending 1 through 4 through SIBR API Version 1 o Submit inter-tie and generator resources for first four hours on 05/01/2014 (assume hourly for first four hours) 04/30/14 13:00 04/30/14 22:45 10 SLIC Outage - Submit forced outages (generation and transmission) by contacting ISO Operations 04/30/14 14:00 04/30/14 16:00 11 OASIS Outage - Data will be back-filled for intervals during outage by Finish Time; Resume activity upon availability; OASIS Application Release Version 6.5 will be available at Finish Time; See Release Notes 12 CMRI Outage - Data will be back-filled for intervals during outage by Finish Time; Resume activity upon availability; CMRI Application Release Version will be available at Finish Time; See Release Notes 04/30/14 14:00 04/30/14 16:00 m/documents/relea senotes_oasis_sp ringrelease2014_v 1_2_Clean.pdf 04/30/14 14:00 04/30/14 16:00 m/documents/relea senotes_cmri_spri ngrelease2014_v1 _2_Clean.pdf 13 Receive last HASP instructions from ADS (Ignore additional hourly pre-dispatch instructions from ADS if published) 04/30/14 22:00 04/30/14 22:00 14 SIBR Outage - See task #9 for operating instructions 04/30/14 23:00 05/01/14 1:00 Page 6

7 Spring 2014 Cutover Timelines Start Finish # Task Description Date Time Date Time Related Artifacts 15 SIBR API selected Version 1 Decommissioned at Start Time; SIBR APIs Version 2 will be available at Finish Time 04/30/14 23:00 05/01/14 1:00 ents/sibr_interfacespecific ation- BiddingServicesV10Spring2 014Clean.pdf 16 ADS Outage - Follow DAM or ISO Operator instructions manually o Internal resources with RA capacity to follow last good RT ADS dispatch o Intertie resources with no HASP ADS dispatch should follow DAM RUC schedules unless otherwise instructed by ISO Operator o For ancillary service awards, if you do not receive a RT instruction, follow your DAM awards o Contact ISO RT Operations for approval prior to transitioning or shutting down generation resources during this window 04/30/14 23:00 05/01/14 1:00 17 ADS client v5.1.9.x: Decommissioned; Receive last 5-minute binding dispatches from old client; Use new ADS client v /30/14 23:00 ents/iso_automateddispatc hsystemclient_ _available-spring2014.htm 18 ADS API selected Version 4 & 5 Decommissioned; ADS APIs Version 6 will be available at Finish Time 04/30/14 23:00 1:00 ttp:// nts/spring2014adsapiversi on6technicalspecifications. htm 19 Possible Missing Results for STUC, RTPD, RTD for HE24 and HE1 (and possibly HE2 and HE3) during transition; Please do not submit CIDI tickets for these intervals 04/30/14 23:00 05/01/14 1:00 20 FERC 764, RIMPR, Revisions to Price Corrections and RDRP Activated 05/01/14 1:00 21 Submit first 15-minute e-tags 04/30/14 1:00 22 Submit first 15-minute market bids into SIBR 05/01/14 1:00 23 Submit VER forecasts into SIBR 05/01/14 1:00 24 Receive first 15-minute market LMPs in OASIS 05/01/14 1:30 25 Receive first 15-minute advisory and financially-binding energy schedules and ancillary services awards every fifteen minutes through CMRI 05/01/14 1:30 27 Reminder: DA Inter-SC Trade Market for trade date 5/2/14 closes at 11:00 am PPT on 5/1/14 due to Revisions to Price Corrections 05/01/14 11:00 28 Publish initial expected energy with 15-minute market results in CMRI 05/02/14 15:00 29 End reversion window 05/02/14 0:00 30 See Settlement Calendar ) for meter data submission and settlement statement publication ( ments/iso_paymentscalend ar2014.pdf 31 Last chance to retrieve advisory energy and ancillary service schedules (these are purged from CMRI on day TD+6) 05/05/14 23:59 ents/spring2014release- ProductionAdvisoryDataRete ntionapr18_2014.htm 32 Acceptable Use Policy Phase I Activation 05/19/14 0:00 ents/acceptableusepolicyen forcement- TechnicalSpecificationsPost edmar12_2014.htm Page 7

8 Acceptable Use Policy Phase 1 The Acceptable Use Policy Phase 1 Simulation timeline Acceptable Use Policy Phase 1 Enforcement OASIS only: March 28 th, 2014 (Unstructured) OASIS Services Implemented TRNS_CURR_USAGE AS_OP_RSRV SLD_FCST_PEAK Page 8

9 FERC 764 with Dynamic Transfers Simulation The FERC Order 764 Compliance with 15 Minute Market and Dynamic Transfers Simulation timeline Structured Scenarios Complete FERC Order 764 Compliance with 15 Minute Market and Dynamic Transfers: February 11 th April 18 th, 2014 (Structured and Unstructured) Structured Scenario Execution Dates Week 1 Scenario s #1 & #2 TD 2/13 Structured Scenario Execution Dates Week 2 Scenario #8 TD 2/18 and Scenario #9 TD 2/19 Structured Scenario Execution Dates Week 3 Scenario #7 TD 2/25 Structured Scenario Execution Dates Week 4 No Scenarios Run Structured Scenario Execution Dates Week 5 Scenario #1 & #2 TD 3/13 Structured Scenario Execution Dates Week 6 Scenario #5 TD 3/18, Scenario #6 TD 3/19 and Scenario #3 & #4 TD 3/20 Page 9

10 Adjacent BA FMM Scheduling Support Balancing Authority LADWP: 15 minute scheduling support 5/1/14 (15 minute tags will not be supported on the PDCI and the IPPDC.) BPA: Sometime between August October 2014 APS: 11/1/13 SRP: 11/1/13 PAC: 11/1/13 CFE:? NV Energy: 11/12/13 BANC: 4/1/14 WAPA: 4/1/14 IID:? TID:? Page 10

11 FERC 764 Known Issues # Application Severity (H/M/L) New or Existing Variance Variance Description Resolution Expectations 1 OASIS L Existing 2 SIBR L New 3 ADS L New OASIS SLD_REN_FCST report RTD and RTPD responses fail XSD validation. The start and end times in the cancel trade response not in GMT. Decline and Partial functionality not available in the ADS GUI for specific intertie resources. To be fixed by 4/25. To be fixed by 4/25. To be fixed by 4/25. Page 11

12 RIMPR Phase 1, Mandatory MSG, Post Emergency Filing BCR and BCR Mitigation Measures with Bid Floor Cap Simulation The RIMPR Phase 1, BCR changes with Bid Floor and Mandatory MSG Structured Scenarios Complete RIMPR Phase 1, BCR changes with Bid Floor and Mandatory MSG: February 11 th April 23 rd, 2014 (Structured and Unstructured) Bid Floor Cap Structured Scenario Execution Date Scenario #1 TD 2/27 Page 12

13 Spring 2014 Market Simulation Structured Scenario Execution Report 2014 Spring Release Structured Scenario Execution Report FERC 764 with Dynamic Transfers Scenarios Execution Date Status RIMPR Scenario Scenario #1 03/13/14 Passed Scenario #2 03/13/14 Passed Scenario #3 03/20/14 Passed Scenario #4 03/20/14 Passed Scenario #5 03/18/14 Passed Scenario #6 03/19/14 Passed Scenario #7 02/25/14 Passed Scenario #8 02/18/14 Passed Scenario #9 02/19/14 Passed Scenario #1 02/27/14 Passed Page 13

14 Next Steps The next teleconference will take place at 13:00 PPT on Monday, April 28 th, Page 14

15 Reference Slides Reference Slides Page 15

16 Spring 2014 Production Deployment Plan Page 16

17 Spring 2014 Release Market Simulation Plan Release%20planning/Spring%202014%20release/Sprin g%202014%20release%20-%20plans Page 17

18 ISO System Access Documentation ion_marketparticipants.pdf Page 18

19 ISO Market Simulation Support Hours - 09:00-18:00, PST (Monday through Friday) Phone - (916) ISO s 24X7 Help Desk - (916) (Connectivity, Endpoints) - MarketSim@caiso.com Page 19

20 Market Simulation Issue Management Submit all issues to the CIDI case management system. CIDI tickets will need to have Functional Environment = Market Simulation Spring 2014 to be reviewed by ISO SME s. Page 20

21 Spring 2014 Release Communication Plan ISO will host Bi-weekly call on Mondays and Thursdays starting February 3 rd, 2014 Date January February March 28 Kick Off Call 3, 6, 10,13, 18, 20, 24, 27 3, 6, 10, 13, 17, 20, 24, 27 Time 1:00 p.m. to 2:30 p.m. (Pacific Time) The web conference details are different for each scheduled meeting. Please refer to the California ISO public calendar at for current login information relevant for each meeting. Please note ISO has shifted the normally scheduled call from February 17 th to 18 th, 2014 in observance of Presidents Day. Page 21

22 Web Service Impacts CMRI Report Release Affected API Version Expected Energy GoLive MSG GMT Fall 2013 Spring 2014 GoLive RetrieveExpectedEnergy_PTR_AP RetrieveExpectedEnergy_PTR_DocAttach_AP RetrieveExpectedEnergy_PTRv _AP RetrieveExpectedEnergy_PTRv _DocAttach_AP RetrieveExpectedEnergy_CMRIv1_AP RetrieveExpectedEnergy_CMRIv1_DocAttach_AP RetrieveExpectedEnergy_CMRIv2_AP RetrieveExpectedEnergy_CMRIv2_DocAttach_AP RetrieveExpectedEnergyAllocationDetails_PTR_AP RetrieveExpectedEnergyAllocationDetails_PTR_DocAttach_AP Availability as of spring 2014 release Remain supported Remain supported To be decommissioned New version will be supported Remain supported Expected Energy Allocation MSG GMT Fall 2013 RetrieveExpectedEnergyAllocationDetails_PTRv _AP RetrieveExpectedEnergyAllocationDetails_PTRv _DocAttach_AP RetrieveExpectedEnergyAllocationDetails_CMRIv1_AP RetrieveExpectedEnergyAllocationDetails_CMRIv1_DocAttach_AP Remain supported To be decommissioned Spring 2014 RetrieveExpectedEnergyAllocationDetails_CMRIv2_AP RetrieveExpectedEnergyAllocationDetails_CMRIv2_DocAttach_AP New version will be supported GoLive RetrieveISOCommitmentCostDetails_PTR_AP RetrieveISOCommitmentCostDetails_PTR_DocAttach_AP Remain supported ISO Commitment Cost Details MSG GMT Fall 2013 RetrieveISOCommitmentCostDetails_PTRv _AP RetrieveISOCommitmentCostDetails_PTRv _DocAttach_AP RetrieveISOCommitmentCostDetails_CMRIv1_AP RetrieveISOCommitmentCostDetails_CMRIv1_DocAttach_AP Remain supported To be decommissioned Spring 2014 RetrieveISOCommitmentCostDetails_CMRIv2_AP RetrieveISOCommitmentCostDetails_CMRIv2_DocAttach_AP New version will be supported Market Schedules Spring 2014 RetrieveMarketSchedules_CMRIv1_AP RetrieveMarketSchedules_CMRIv1_DocAttach_AP New version will be supported Non- Dispatchable Time Ranges Spring 2014 RetrieveNonDispatchableTimeRanges_CMRIv1_AP RetrieveNonDispatchableTimeRanges_CMRIv1_DocAttach_AP New version will be supported Market Forecast Spring 2014 RetrieveMarketForecast_CMRIv1_AP RetrieveMarketForecast_CMRIv1_DocAttach_AP New version will be supported Page 22

23 Web Service Impacts OASIS Current Transmission Usage Transmission Interface Usage Market Available Transfer Capacity TRNS_CURR_USAGE TRNS_USAGE TRNS_ATC CAISO Demand Forecast Wind and Solar Forecast SLD_FCST SLD_REN_FCST Locational Marginal Prices - 15 minute PRC_RTPD_LMP (new) level Page 23

24 Web Service Impacts Service Operation Version 4 Multi-Stage Generator Version 5 Contingency Dispatch Enhancements Version 6 FERC764 Retrieve/Request getdispatchbatchessinceuid getbatchstatus getbatchheader getdispatchbatch isnewtrajdata gettrajectorydata submitmsslfrequest validatedispatchbatch To be decommissioned upon spring 2014 ADS deployment Will still be supported New; to be supported upon spring 2014 ADS deployment Response acceptinstruction declineinstruction partialacceptinstruction To be decommissioned upon spring 2014 ADS deployment To be decommissioned upon FERC 764 activation New; to be supported upon spring 2014 ADS deployment Page 24