USING VISTRO TO EFFECTIVELY EVALUATE TRAFFIC IMPACTS FOR NEW DEVELOPMENTS

Size: px
Start display at page:

Download "USING VISTRO TO EFFECTIVELY EVALUATE TRAFFIC IMPACTS FOR NEW DEVELOPMENTS"

Transcription

1 USING VISTRO TO EFFECTIVELY EVALUATE TRAFFIC IMPACTS FOR NEW DEVELOPMENTS Nate Chanchareon Managing Director PTV Asia/Pacific

2 TYPICAL TRAFFIC ENGINEERING STUDY Requires multiple tools Capacity Analysis / Signal Optimization Tool Scenario Management / Mitigation Analysis TIA Functionality Tool Reporting Tool (Tables and Figures) Completion of traffic engineering Study I Slide 2

3 PTV VISTRO: ALL-IN-ONE Report-Ready Tables & Figures Mitigation Analysis Scenario Management Traffic Impact Analysis Signal Optimization Capacity Analysis I Slide 3

4 EVOLUTION OF PTV VISTRO 1987 Dowling Associates TRAFFIX 2006 Dowling Associates PTV Partnership 2010 TRAFFIX Powered by VISUM Released New Software with Rich Heritage 2008 Begin Joint Development of Next TRAFFIX I Slide 4

5 HOW DOES VISTRO FIT INTO THE VISION TRAFFIC SUITE? I Slide 5

6 PTV VISTRO USE CASES 1 Conducting Traffic Impact Analyses (TIA): Evaluate the impacts of proposed future developments on the transportation network trip generation, distribution, and assignment of development traffic multiple scenario management mitigation testing and evaluation comprehensive, report-ready tables and figures preview future development traffic with the integrated PTV Vissim viewer Developing Transportation Master Plans: Transportation Master Plans can be quickly developed through efficient data entry and storage integration with PTV Visum for incorporation of long-range forecasting data I Slide 6

7 PTV VISTRO USE CASES 2 Conducting Signal Timing and System Evaluations: PTV Vistro expedites the analysis of signal systems operations and re-timing studies intersection, corridor, and network optimization seamless transition to PTV Vissim for micro simulation Performing Corridor Studies: Use PTV Vistro for quick and easy analysis of corridors, including re-design of facilities identifying proper traffic control devices evaluating future mitigation needs I Slide 7

8 TYPICAL WORKFLOW Build Base Model Geometry Volumes Traffic Control Run Base Model Analysis Build Future Model Update Geometry Update Volumes Update Traffic Control including Optimization Run Future Model Analysis and Generate Reports Optional TIA Steps Zones & Gates Trip Generation Trip Distribution Trip Assignment Repeat for Scenarios Export to Simulation Optional Mitigation I Slide 8

9 TYPICAL WORKFLOW BUILDING THE MODEL Based on Background Images BING Image Files Automation: Network Model Import Visum ANM Synchro Traffic Counts Copy & Paste I Slide 9

10 TYPICAL VISTRO WORKFLOW Obtain Data Build Base Network Model Geometry Volumes Traffic Control Run Base Network Analysis and Generate Output Generate Future Model Update Geometry Update Volumes Update Traffic Control Traffic Control Changes Signal Timing Updates, including Optimization Run Future Model Analysis and Generate Output Repeat for Scenarios (Export to Simulation) I Slide 10

11 INTERSECTION ANALYSIS Four Control Types Multiple Analysis Methodologies HCM 2010 HCM 2000 Kimber (Roundabout) Critical Movement (Circular 212 / ICU) A Clear Box Concept Software Detailed Parameter Sets for Capacity Analysis Different Methodologies within the Same Network Signal Warrant Analysis (Volume-Based) I Slide 11

12 TRAFFIC IMPACT ANALYSIS (TIA) FUNCTIONALITY Network Component for TIA (Zone), (Gate), (Path) Trip Generation Trip Generation Manual or Custom Trip Generation Data (e.g. OTISS Import) One-Click Land Use Updates Multiple Zones for Redevelopment or Mixed Use Development Cases Negative Trip Generation Volume Adjustment In-process / Approved, Diverted, Pass-by, etc. I Slide 12

13 TYPICAL VISTRO WORKFLOW I Slide 13

14 TRAFFIC IMPACT ANALYSIS (TIA) FUNCTIONALITY Trip Distribution Tabular Input To / From Development Zones Mirror Trips (From / To Trips) Trip Assignment Shortest Path Search Manual Input for Paths Visual Display of Paths Automatic Error Check I Slide 14

15 TYPICAL WORKFLOW REPORTING Tables Intersection Summaries Detailed Intersection Analysis (HCM) Figures Turning Volumes (with options for various volume types) LOS Summary by Intersection Geometry and Traffic Control Time Space Diagram Formats PDF, (Excel, CSV, HML) I Slide 15

16 TYPICAL WORKFLOW REPORTING I Slide 16

17 VISTRO REPORTING Quantitative Reports Network Summaries Analysis Summary Trip Generation / Distribution Volume Summary Intersection Analysis Report PDF, HTML, csv Graphical Reports Turning Volumes (with options for various volume types) Turning Volume Percentage by Zone (Fair Share) Link Volume Percentage Distribution (Zone Gate) LOS Summary by Intersection Geometry I Slide 17

18 VISTRO ADDITIONAL FEATURES Mitigation Analysis Parameters Compare Mitigation Strategies for Intersections Geometry / Lane Configuration Traffic Control Scenario Management Various analysis hours, years Various Network configurations All in one project setup Data Import / Export Visum Vissim Synchro I Slide 18

19 PTV VISTRO GUI: COMPLETELY NEW INTERFACE Focus on: -ease of use -support of workflows -modern, clean elements Tabs to support the workflow Bing maps / aerials as background for efficient network modeling Efficient tabular data entering I Slide 19

20 PTV VISTRO GUI Intersection Set-Up Set up geometry and basic intersection configuration I Slide 20

21 PTV VISTRO GUI: SOME NICE DETAILS Intersection details Efficient lane configuration through templates and dialog I Slide 21

22 PTV VISTRO GUI Traffic Volume Define volumes: -Base volume -Diverted trips -Pass by trips -In process volume -other I Slide 22

23 PTV VISTRO GUI Traffic Control Level of Service calculation (industry standard methodologies) HCM 2010/200 Kimber ICU circular and more to come I Slide 23

24 PTV VISTRO GUI TIA Functionality (3 Steps) I Slide 24

25 PTV VISTRO GUI 1. Trip Generation Generate Trips by entering - Trip generation rate - Quantity or by directly entering the number of generates trips. Additional information by zone: - Land use code - Name I Slide 25

26 PTV VISTRO GUI 2. Trip Distribution Distribute Shares from zones to all gates/zones in the network. I Slide 26

27 PTV VISTRO GUI 3. Trip Assignment Assign Volume shares for every OD relation to a user defined set of paths. I Slide 27

28 PTV VISTRO GUI Signal Optimisation Assign weights to corridors Network wide signal optimisation Display time space diagrams for selected corridors I Slide 28

29 PTV VISTRO GUI Mitigation Options Mitigation options To analyse and present several options for each intersection I Slide 29

30 VISTRO TRANSPORTATION ANALYSIS: ST. LUKE S MEDICAL CENTER CASE STUDY Presented by: Tony Woody, CH2M Amy Elliott, CH2M 2015 PTV User s Group Meeting Portland, OR October 2015

31 OVERVIEW OF ST. LUKE S MEDICAL CENTER Idaho s largest health care organization Located in downtown Boise, ID More than 8,000 employees in the region Long history in the area over 100 years in Boise Currently embarking on a Master Plan process Extensive facility improvements to meet future demands Traffic analysis was used to support the Master Plan Assessed vehicular, pedestrian, and bicycle traffic I Slide 31

32 ST. LUKE S MEDICAL CENTER CAMPUS CURRENT AND PLANNED FACILITIES 3 1) Children s Pavilion 2) Central Hospital Expansion 3) Central Plant/ Parking Garage ) Shipping and Receiving 5) Warm Spring Medical Office Building 5 N I Slide 32

33 ST. LUKE S MEDICAL CENTER CAMPUS PROPOSED EXPANSION Closure of Jefferson Avenue to Vehicle Traffic 3 2 1) Children s Pavilion 2) Central Hospital Expansion 4 X X X X X X X X X X 1 3) Central Plant/ Parking Garage 4) Shipping and Receiving 5) Warm Spring Medical Office Building 5 N I Slide 33

34 ST. LUKE S MEDICAL CENTER TRIP GENERATION Trip Generator AM Peak PM Peak Children s Pavilion Central Hospital Expansion Shipping and Receiving Warm Springs Medical Office TOTAL I Slide 34

35 APPLYING VISTRO FOR THE PROJECT 35

36 GOALS OF TRAFFIC ANALYSIS - Evaluate multiple land use scenarios and network scenarios - Analysis to support the Master Plan - Communication of impacts to stakeholders - Determine mitigation for project I Slide 36

37 ANALYSIS TIMELINE - Small TIA Type Study - Expansion to Larger Study Area - Expanded # of Scenarios - Initial TIS Completed - Synchro + Spreadsheets - Master Plan Update w/synchro - Converted to VISTRO - Additional Scenario Testing Start of Traffic Study: Started as small study - TIA type study, completed in Synchro & Excel - Too complicated with too many land use scenarios - Spreadsheet tracking was not working well - VISTRO Analysis: Expansion to larger study/master Plan searched for tools to use and TRAFFIX/VISTRO was selected - CH2M s 1 st project in VISTRO Started in VISTRO 1.0/updated to VISTRO I Slide 37

38 ANALYSIS ASSUMPTIONS - Network Assumptions - Closure of Jefferson Avenue (Project Alternative) - Conversion of 3 rd -4 th and 5 th -6 th couplets to 2-Way street (Planned) - Land Use Assumptions - 5 Land Use scenarios evaluated in Master Plan - 1 Land Use scenario analyzed in VISTRO - Peak Hour/Forecast Years - AM/PM Peak hours analyzed (Existing), 2024 and 2035 Forecast years I Slide 38

39 STUDY AREA INTERSECTIONS - 23 Study Intersections - Generally bounded by - Fort Street/State Street (north) - 5 th Street (west) - Main Street (south) - Avenue B (east) I Slide 39

40 TRIP GENERATION AND TRIP DISTRIBUTION/ASSIGNMENT - Trip Generation based on previous ITE calculations - Input into VISTRO from Excel Spreadsheet - Did not calculate trips using rate inputs into VISTRO - Trip Distribution/Assignment - Based upon counts, regional forecasts, and local judgment - Patient surveys also used to determine future patterns - 40% - south, 30% -west, 20% - north, 10% - east I Slide 40

41 VISTRO NETWORK - 10 Trip Generation Zones - 9 Gates - 23 Intersections - 9 Signals - 13 Unsignalized - 1 Roundabout I Slide 41

42 VISTRO NETWORK OTHER NOTES - Traffic Analysis - HCM 2010 Methodology - Initially Integrated with a VISSIM network, but did not fully develop out that network due to change in project goals - Calculated trip generation in Excel, transferred to VISTRO - Modeling adjustment made at key locations - Jefferson Street Closure - Grid Network Assignment - 1-Way to 2-Way Conversion I Slide 42

43 VISTRO NETWORK SCENARIO TESTING - Standard Scenarios - Existing, No Build, Build , 2024, 2035 for AM and PM Peak hours - Additional Testing - Signals vs. Roundabouts - Closures vs. Non Closure (Jefferson, 1 st Avenue) - 2-way vs. 1-way traffic operations - Land Use Growth: High vs. Low intensity - Site Plan Adjustments I Slide 43

44 VISTRO NETWORK JEFFERSON CLOSURE Closure of Jefferson Avenue to Vehicle Traffic - Negative Trip Generation & Distribution for link via Zones 14/15 and 16/17 - Manual assignment based on counts/models runs I Slide 44

45 VISTRO NETWORK GRID NETWORK ADJUSTMENTS - For some areas, dummy nodes were created to accommodate paths - Especially prevalent in grids with many paths between O-D pairs - Lesson Identify dummy nodes ahead of time to keep network consistent Dummy Nodes on 2 nd Street to accommodate Paths I Slide 45

46 VISTRO NETWORK COUPLET TO 2-WAY CONVERSION - Manually adjusted volumes within Base network based on demand models - Decided against negative distributions like the Jefferson closure since it was not part of core study area - Affected 6 study intersections 3 rd /4 th Couplet to 2-Way Traffic I Slide 46

47 VISTRO GRAPHICS AND FIGURES: SCREENSHOTS 2024 Build 2035 Build I Slide 47

48 VISTRO GRAPHICS AND FIGURES: BUILT-IN REPORTS - PDF Reports are great assets provided - Signal Warrants Analysis - Turning movement counts can be converted for report purposes I Slide 48

49 VISTRO ADVANTAGES & IMPROVEMENTS 49

50 VISTRO KEY ADVANTAGES - Combined Trip Generation/Distribution, Assignment, and Analysis in one place - Documentation/History - Built-in Graphics in PDF format Quick to create, minimal adjustments to incorporate into reports - Automation of Analysis Lots of supply and demand scenarios can be tested quickly after base model is set up - Integration w/vissim - Built-in Signal Warrants I Slide 50

51 PTV TRAFFIC SOFTWARE SUITE Network modelling large scale, national, regional and local transport network developments and demand modelling Detailed microscopic modelling of individual vehicles covering all modes of transport multi-modal micro-simulation Advanced microscopic pedestrian simulation, both inside and outside buildings A solution for all traffic analysis needs Real-time traffic simulation model, based on offline strategic model (PTV Visum), fused with real-time data (simulated by PTV Vissim) Interconnected Management tool for accident analysis prevention I Slide 51

52 Name, Title Date

53 PTV VISTRO 簡介

54 為何選用 VISTRO? 國內 TIA 現況問題 分析方式無統 一規定 桃園縣規定軟體值需以現況 延滯調查校估 其餘縣市無特別規定 分析軟體功能 未見齊備 THCS 僅能分析單一路口, 無 法考量路網多路口 Synchro 能分析路網中多路口, 但無法計算衍生量與指派 報告分析內容 現況分析軟體多無指派功能, 無法掌握全貌 僅依據分析者另外計算 計算過程無法於報告中完整 呈現, 正確性無法完全掌握 VISTRO 已正受顧問公司廣泛使用 以美國加州為例, 幾乎所有顧問公司皆使用 VISTRO 進行 TIA 評估

55 為何選用 VISTRO? VISTRO 的優勢 整合分析! 就是一套 交通影響評估 (TIA) 專業軟體 計算路口服務水準 預測新開發之影響 管理多種評估情境 產出完整分析報表 最佳化路口時制計畫 評估交通影響改善對策

56 VISTRO 各項功能簡介 計算路口服務水準 圖形化呈現 ( 整體路口 各方向服務水準 )

57 VISTRO 各項功能簡介 預測新開發之影響 衍生旅次量計算 旅次分布比例

58 VISTRO 各項功能簡介 預測新開發之影響 路徑指派

59 VISTRO 各項功能簡介 管理多種評估情境

60 VISTRO 各項功能簡介 產出完整分析報表

61 VISTRO 各項功能簡介 最佳化路口時制計畫 路網最佳化 群組最佳化

62 VISTRO 各項功能簡介 評估交通影響改善對策 VISSIM 微觀模擬預覽

63 VISTRO 應用案例 國內 基隆和平島東南側水岸都市更新後聯外動線調整及改善計畫 松山機場民航關聯產業廊帶開發整體規劃及民間參與建設營運 (BOT) 可行性評估 林口產專區交評 宜蘭住宅交評 國外 重慶台北城開發計畫交通諮詢與規劃服務 廈門集美區 IOI 集美棕櫚城交通諮詢與規劃服務

64 VISTRO 版本 最新版本 : V4.0 單一規格 : 2500 nodes, 6000 links, 400 zones

65 VISTRO 如何購買 請洽詢 PTV 台灣授權經銷商 鼎漢國際工程顧問股份有限公司 聯絡方式 (02) 分機 316 高啓涵先生