X470 Project Management UC Berkeley Extension, Business and Management August 2009

Size: px
Start display at page:

Download "X470 Project Management UC Berkeley Extension, Business and Management August 2009"

Transcription

1 X470 Project Management UC Berkeley Extension, Business and Management August 2009 Anuradha Vaddadi Miguel Rivera Prasada Martala Wayne Harriman Archina Vishen Kiumars Golriz

2 Table of Contents 1. Project Scope Statement. 3 a. Vision b. Business Need c. Project Description d. Project Deliverables e. Project Objectives f. Assumptions g. Constraints h. High Level Risks i. Approval Signatures 2. Stakeholder Analysis Project Lifecycle Work Breakdown Structure (WBS) Cost Baseline Schedule Baseline Communications Management Plan Responsibility Assignment Matrix Risk Response Plan...31 a. Prioritization of risk types b. Risk Assessment Metric The Leeders - August

3 Project Scope 1.a Vision Eco Solutions Inc. is a leading player in Construction Industry with a mission to provide sustainable solutions for eco friendly lifestyle. 1.b Business Need Eco Solutions Inc., with it s headquarters in Baltimore, MD, has branches through out the USA. Company leadership decided to provide cutting edge green solutions to one of it s existing office buildings with an objective to get LEED certification from USGBC. To achieve this objective Eco Solutions decided to get the building LEED certified from USGBC under Existing Building Operations and Maintenance. The company s focus was to achieve maximum operational efficiency in a cost effective manner while maintaining minimal environmental impact. The Leeders - August

4 Project Scope (contd ) 1.c Project Description The project involves providing sustainable design solutions, strategies, technologies, synergies and trade-offs to existing office building in San Mateo, California. The key emphasis was to drive down operational costs, increase productivity in an environmentally responsible manner. Some of the essential strategies include- parking for fuel efficient vehicles, photovoltaic solar panels, occupant sensors, mercury lamps with low mercury content. The office space includes entrance lobby, reception and waiting area, workstations, executive cabins, conference room, server station, storage area, machinery and equipment area, pantry and restrooms. (contd ) The Leeders - August

5 Project Scope (contd ) 1.c Project Description The Following are the essential Project features:- Property type Location Status Building size Total no. of Stories LEED Rating system Points targeted & achieved - Commercial - San Mateo, CA - Existing, 1996 built - 12,000 sf. (small size office building) - 1 story - Certified under Existing Building O&M - 39 (Required Points for certification is 34 42) Date of commencement of project - 8 / 3 / 09 Date of completion of project - 10 / 31 / 11 (Including performance period and Final certification) Total duration of project - 2 years 2 months 28 days Total cost of project - $429,075 The Leeders - August

6 Project Scope (contd ) 1.d Project Deliverables Is LEED Certification Green Building Solar Panel Installation Mercury Lamp installation Is Not Remodeling Interior Design Redoing the roof Redoing electrical connections Designating parking spaces for fuel efficient vehicles Duties & Responsibilities of LEED AP Not increasing parking area Credentials of LEED AP Installation of occupant control sensors Automatic doors The Leeders - August

7 Project Scope (contd ) 1.e Project Objectives Eco Solutions Inc. intends to meet the requirements by achieving LEED certified rating under Existing Building Operations and maintenance from USGBC. The objectives also include accomplishing the goal within the budget and schedule while achieving maximum operational efficiency with minimum disruption to company s day to day Operations. 1.f Assumptions Contracts to be awarded to authorized vendors only LEED certification requirements do not change during project implementation Electric and plumbing connections already in place The Leeders - August

8 Project Scope (contd ) Building is not going to under go major renovations Building will be fully occupied for at least 12 months proceeding certification application Building is in compliance with Federal, State and Local laws and regulations Project scope includes 100% floor area of the building All prerequisites and other credits as mentioned in planning phase are met and approved by USGBC for certification 1.g Constraints Budget is $429,075 Certification to be achieved by October Adhere to LEED for existing buildings O&M policy model Some work is to be performed during non business hours The Leeders - August

9 Project Scope (contd ) 1.h High Level Risks Risk Description Materials Cost increase Trigger Economy Recovery and Commodities going higher Impact (Cost(C), Scope (S), Time(T) C Inspection Failure Not in compliance with city requirements S,C,T USGBC Credits assumed as ready to be audited, Fail Operations might be stopped due to Vendor not adjusting to schedule Ambient Conditions may delay Schedule Failing to meet the certification requirements Pre - Audit failure Time delays not in Schedule Bad Weather Certification Audit Failure S,C,T C, T C, T S The Leeders - August

10 Project Scope (contd ) Approval Signatures Sponsor: CEO, ECO Solutions Inc. Other approvals USGBC The Leeders - August

11 Stakeholder Analysis Stakeholder Name Need Expectation Sponsor Project s budget Interested to know how budget is spent Reorganization from Leadership Team Project Manager Project Team Members Company Employees Vendor(s) To secure resources and budget approvals -Tools to finish work -Project timeline details Clear instructions if impacted by the project -Access to design documents -Access to premises -Permits from city -Resource availability -Sponsor support Recognition and Promotion Project timelines and it s affect on day-to-day work -Timely payment -More business -Good coordination from Project Manager USGBC Reviewer Approved documents Company adheres to city code The Leeders - August

12 Project Lifecycle : Linear Approach Monitor and Control Initiation Planning Execution & Audit Close - Out The Leeders - August

13 Project Lifecycle : Linear Approach (contd ) Phase Name Initiation Planning Execution & Audit Close-Out Project Management Deliverables Project Charter Project Manager assigned Authorization to engage resources Scope statement Work Breakdown structure Project Schedule Project Cost Baseline Status report Approved/Rejected change requests Lessons learned Close-out Meeting Product Process Deliverables Approved application from USGBC Scorecard for certification requirements List of credit requirements and strategies for Submittals Permit drawings, construction drawings and specifications for- Alternate commuting transportation plan High efficiency plumbing management plan Final permits approval and inspections. List of executed and completed work by General Contractor List of approved vendors Submission of Submittals to USGBC completed Performance period recorded Awarded LEED Certified certification from USGBC Stakeholder signoff The Leeders - August

14 Project Lifecycle : Linear Approach (contd ) Phase Name Initiation Planning Execution & Audit Close-Out Product Process Deliverables Energy efficiency retrofit plans Minimum energy efficiency performance plan Occupant control lighting system plan Final certification from USGBC performance period Acceptance of final certification by sponsor The Leeders - August

15 Work Breakdown Structure 1. Initiation Phase 1.1. Project management deliverables Preliminary scope of statement Project charter Project manager assigned Authorization to engage resources 1.2 Product process deliverables Register Project online with USBC Approved online application from USGBC Documentation of Preliminary Review of Scorecard Documentation of data for project requirements through online resource center of USGBC LEED AP appointed 2. Planning Phase 2.1 Project management deliverables Project management plan Scope statement WBS- work breakdown structure Project schedule The Leeders - August

16 Work Breakdown Structure Cost baseline RAM- risk assessment management Communication management plan Risk response plan Conduct Gate review & Obtain sponsor's approval 2.2. Product process deliverables List of Categories, prerequisites, credits with requirements and strategies Sustainable site Alternate commuting transportation plan Documentation of strategies for alternate transportation program Site plan showing number and location of fuel efficient vehicles, bike spaces, carpools Permit drawings for approval of site plan Water efficiency High efficiency plumbing management plan Documentation of strategies to reduce indoor plumbing fixtures and fitting through control technologies Calculation sheet for baseline water consumption The Leeders - August

17 Work Breakdown Structure Plumbing drawings Permit drawings Construction drawings Specifications for plumbing design Energy and Atmosphere- Energy efficiency retrofit plans Documentation of strategies for energy saving techniques Plans showing Photovoltaic Solar panel details Roof plan, electrical and mechanical drawings Permit drawings Construction drawings Specifications Material and Resources- Minimum energy efficiency performance plan Documentation of strategies and technologies for usage of low mercury content lamps List of existing and new indoor and outdoor lamps with low mercury content The Leeders - August

18 Work Breakdown Structure Electrical and lighting drawings showing low mercury lamps layout Permit drawings Construction drawings Specifications Indoor environmental quality Occupant control lighting system plan Document individual and multitask spaces Lighting and electrical layout plans Permit drawings Construction drawings Specifications Innovation in Operations LEED AP responsibility plan Documentation of the requirements for LEED application for project registration with USGBC obtained Documentation of strategies of submittals to complete scorecard Complete set of drawings, calculations, and documents to be submitted with the submittal Documentation of certification process. The Leeders - August

19 Work Breakdown Structure Documentation of final Review of credit submittals List of vendor for approval Painting Signage Plumbing fixtures and fittings Photovoltaic solar panels low mercury lamps Lighting system and occupant control sensors 3. Execution and Audit Phase 3.1. Project management deliverables Status report Change control document Change requests/ approval document Vendor contract management plan Formal vendor contract document Terms and conditions document 3.2. Product process deliverables 3.3. Documentation of finalized design strategies Final permits approval Inspection and final approval by city inspector The Leeders - August

20 Work Breakdown Structure 3.4. List of procurement of materials from approved vendors 3.5. List of executed and completed work by General Contactor Parking layout completed as per approved site plan Painting and signage work performed as per approved site plan and specifications Electrical work performed as per approved drawings and specifications Plumbing work performed as per approved drawings and specifications Photovoltaic solar panels performed as per approved design and specifications Occupant control sensors and system implemented as per approved drawings and specifications Status review and maintenance report for performance period 3.7. List of approved vendors 3.8. Implementation of certification process Submissions of submittals to USGBC completed List of addressed CIRs (credit interpretation request) recorded Inspection and maintenance record maintained on monthly basis Performance period recorded Final certification from USGBC after the end of performance period 3.9. Acceptance of final certification by sponsor The Leeders - August

21 Work Breakdown Structure 3.10 Documentation of Audit and Certification for the 523 days Documentation of operational maintenance Documentation of monthly data for 523 days Audit data Submitted 4.Close- Out 4.1. Project management deliverables.1.1. Lessons learned Close out 4.2. Product process deliverables Awarded LEED Certified certification from USGBC Stakeholders sign off All contracts formally ended for the project. The Leeders - August

22 Cost Baseline (Cont ) Item Man Days Labor Cost Total Phase Initiation Phase 15 $8, Cost ($) Approved online application from USGBC and Fees $4, Project Certification fees $2, Project Charter $1, Planning Phase 10 $23, Alternate commuting transportation plan 2 $2, High efficiency plumbing management plan 2 $2, Energy efficiency retrofit plans 2 $2, Minimum energy efficiency performance plan 1 $1, Occupant control lighting system plan 1 $1, Project Management Plan 10 $11, The Leeders - August

23 Cost Baseline (Cont ) Item Man Days Labor Cost Total Phase Cost ($) Execution Phase 559 $402, Status review and maintenance report until Certification completion 559 $20, Final permits approval and inspections. 3 $3, Executed and completed work by General Contactor 38 $377, Submission of Submittals to USGBC completed 1 $ Close- Out phase 2 $3, Awarded LEED Certified certification from USGBC 1 $ Lessons learned 1 $ Close-out Meeting 1 $ Stakeholder sign- off 2 $ Total Cost for the Project $429, The Leeders - August

24 Cost Baseline (contd ) Cost(K) Initiation Planning Execution Turn Over Phase Cost Accum. Cost The Leeders - August

25 Schedule Baseline The Leeders - August

26 Schedule Baseline (contd ) The Leeders - August 2009

27 Schedule Baseline (contd ) The Leeders - August

28 Communications Management Plan Document Frequency Method of distribution Format Project scope statement Once Hard copy, Ms Word I,S O R R S P O N S O R P M R G O R J E C T P T R E O A J M E C T V E N D o R s U S G B C Stake holder analysis Once Hard copy, Ms Word I,S,O O Work break down structure Upon Change Hard copy, Excel I,S O Resource assignment matrix Once/ as needed Hard copy, Excel I,S O Project schedule Once/ as needed Hard copy, Ms Project I,S O R R Project cost baseline Until approved Hard copy, Excel I,S O Risk plan Once Hard copy, Ms Word I,S O Status report As needed/ weekly Ms Word I,S O Stake holder sign-off Once Hard copy, Ms Word Lessons learned Once Ms Word I,S O Site plan, roof plan Once Hard copy, AutoCad I,S I,S O R,I Mechanical, electrical, plumbing, lighting drawing specification Once Hard copy, Excel I,S I,S O R,I The Leeders - August

29 Communications Management Plan (Contd ) Document Scorecard for certification requirements Frequency Method of distribution Format S P O N S O R P M R G O R J E C T P T R E O A J M E C T Once Hard copy, Ms Word S O O Stake holder sign-off Once Hard copy, Ms Word Lessons learned Once Ms Word I,S O Site plan, roof plan Once Hard copy, AutoCad I,S I,S O R,I Mechanical, electrical, plumbing, lighting drawing specification Once Hard copy, Excel I,S I,S O R,I Scorecard for certification requirements Once Hard copy, Ms Word S O O Approved application from USGBC Once Hard Copy Ms Word R,S R O Legend: I:Input S:Sign-off, O:Owner, R:Read V E N D o R s U S G B C The Leeders - August

30 Responsibility Assignment Matrix Deliverable Project Sponsor Project Manager Project Charter S I I Project Team USGBC Vendor Application form for Project Registration Authorization to engage resources S I I S I Scope Statement R I I Mechanical, electrical, lighting specifications R I I Solid Waste Management Plan R I Status Reports R I I Installation of equipments/devices to meet credits Submittals to USGBC/ CIRs R R I S I Lessons learned review R I I Stakeholder signoff S I S S Legend I = input required S = Signoff R = Reviewer The Leeders - August

31 Risk Assessment Metric for Risk Response Plan Risk Assessment Metric Assessment Probability Impact High >35% Medium 15% - 35% Low < 15% Major Disruption of the Project scope, Cost, Schedule. Potential disruption to the Project Scope, Cost and Schedule. Has none or little impact on the project scope, schedule and/or cost. The LEEDERS have taken a Conservative approach because of the sensitivity to Failure of the scope The Leeders - August

32 Prioritization of Risk types Impact Probability Low Medium High High *Materials Cost increase Medium *Ambient Conditions may delay Schedule *Failing to meet the certification requirements *Downtime in normal operations *Inspection Failure *USGBC Credits assumed as ready to be audited, Fail Low *Cost Increase due to Outsourced Consulting recommendations *Funding Cut *USGC Certification requirements may change in the 2 year waiting period Area of Focus for the LEEDERS The Leeders - August

33 Risk Response Plan Risk Type Risk Description Risk Trigger Impacted Areas Probability Impact Priority Strategy Owner Status External Legal/ Regulatory *USGC Certification requirements may change in the 2 year waiting period Requireme nts document revision Scope Low High Low Acceptance PM Closed Project Management *USGBC Credits assumed as ready to be audited, Fail Audit failure Scope Cost Medium High High Mitigation PM Open Resources *Budget Increase due to Outsourced Consulting recommendati ons Higher Costs Cost Low Medium Low Transfer (outlined in contract) PM Closed Project Management Inspection Failure Not in compliance with city requiremen ts Scope Medium High High Mitigation PM Open The Leeders - August

34 Risk Response Plan (contd ) Risk Type Risk Description Impacted Risk Trigger Areas Probability Impact Priority Strategy Owner Status Resources *Materials Cost increase Economy Recovery and Commodities going higher Cost High High Medium Acceptance PM Closed External Environmental *Ambient Conditions may delay Schedule Rain/ other causes Schedule Cost Medium Medium Low Acceptance PM Closed Schedule Downtime in normal operations *Time Delays because Vendor not adjusting to schedule Scope High Medium High Mitigation Project Team Open Resources Legal Project Management Funding Cut *Failing to meet the certification requirements Bank Pulls out Scope Low High Medium Transferen ce Sponsor Closed Scope Scope Medium High High Mitigation PM Open *Affected Area/s: Quality, Schedule, Cost *Impact: Low, Medium, High *Probability: Low, Medium, High *Status: Open (O) or Close (C) The Leeders - August

35 The Leeders - August

Project Green House. Green Team. Making the world greener one house at a time

Project Green House. Green Team. Making the world greener one house at a time Project Green House Making the world greener one house at a time UC Berkeley Extension, Business and Management UCB X470 Project Management February 2008 Green Team Lori Plein Anne Cairney Ferdinand Bueno

More information

1.0 ABOUT THE NU GUIDELINES

1.0 ABOUT THE NU GUIDELINES Construction Policies & Procedures Northeastern University Guidelines for Capital Project Design & Implementation.0 ABOUT THE NU GUIDELINES This document is intended to describe in a comprehensive manner

More information

Green Ordinance Implementation City of Dallas, TX

Green Ordinance Implementation City of Dallas, TX Green Ordinance Implementation City of Dallas, TX City of Dallas BUILDING INSPECTION DEPARTMENT Phase 1 Effective Date October 1, 2009 Applications for building permits Structure One ordinance amending

More information

REQUIREMENTS DOCUMENTATION

REQUIREMENTS DOCUMENTATION REQUIREMENTS DOCUMENTATION Project Title: Date Prepared: Stakeholder Requirement Category Priority Acceptance Criteria REQUIREMENTS DOCUMENTATION Project Title: Date Prepared: Stakeholder Requirement Category

More information

Slipstream Office Relocation Project February 2008

Slipstream Office Relocation Project February 2008 Slipstream ffice Relocation Project February 2008 Team embers Jill Carley Ruchi Chopra Yelena Faynburd Suchir Gupta Darren Petersen Rudolph Rico Dipali Shah Prem Sujan Dee Wise Team Slipstream Table of

More information

LEED Certified Health Center

LEED Certified Health Center Nottawaseppi Huron Band of Potawatomi LEED Certified Health Center Fulton, Michigan LEED Leadership in Energy & Environmental Design The following briefly outlines the process for LEED Certification and

More information

CONTENTS. 71 Section 01352, #7 (Life Cycle Cost and Life Cycle Assessment) 2/1/12 Modified entire section 72 Section 01352, #8 (Sustainability

CONTENTS. 71 Section 01352, #7 (Life Cycle Cost and Life Cycle Assessment) 2/1/12 Modified entire section 72 Section 01352, #8 (Sustainability 01352 Sustainable Design Requirements This document provides design standards only, and is not intended for use, in whole or in part, as a specification. Do not copy this information verbatim in specifications

More information

3 PART THREE: WORK PLAN AND IV&V METHODOLOGY (SECTION 5.3.3)

3 PART THREE: WORK PLAN AND IV&V METHODOLOGY (SECTION 5.3.3) 3 PART THREE: WORK PLAN AND IV&V METHODOLOGY (SECTION 5.3.3) Emagine IT s approach to Independent Verification and Validation (IV&V) has been shaped over the years by hands-on experience and contributions

More information

GREEN BUILDING IMPLEMENTATION GUIDELINES

GREEN BUILDING IMPLEMENTATION GUIDELINES PLANNING AND BUILDING SERVICES DEPARTMENT GREEN BUILDING IMPLEMENTATION GUIDELINES Application Materials: A. Discretionary Planning Entitlements. Application materials for all Covered Projects subject

More information

<PROJECT NAME> PROJECT MANAGEMENT PLAN

<PROJECT NAME> PROJECT MANAGEMENT PLAN PROJECT MANAGEMENT PLAN Version VERSION HISTORY [Provide information on how the development and distribution of the Project Management Plan was controlled and tracked.

More information

Copyright 2013 Pearson Education, Inc. Publishing as Prentice Hall 5-1

Copyright 2013 Pearson Education, Inc. Publishing as Prentice Hall 5-1 Copyright 2013 Pearson Education, Inc. Publishing as Prentice Hall -1 Learning objectives Manage the planning process of a project Understand the work breakdown structure of a project Understand different

More information

Request for Proposals. 42nd Avenue Pump Station Rehabilitation. Public Works Department City of San Mateo 330 West 20th Avenue San Mateo, CA 94403

Request for Proposals. 42nd Avenue Pump Station Rehabilitation. Public Works Department City of San Mateo 330 West 20th Avenue San Mateo, CA 94403 42nd Avenue Pump Station Rehabilitation Public Works Department City of San Mateo 330 West 20th Avenue San Mateo, CA 94403 May 24, 2015 The City of San Mateo (City) is accepting proposals to select a qualified

More information

RFQ for Architectural Services - Attachment 5 North Campus Student Housing Phase IV(b) Haggett Hall Replacement and Oak Hall Project No.

RFQ for Architectural Services - Attachment 5 North Campus Student Housing Phase IV(b) Haggett Hall Replacement and Oak Hall Project No. SPECIAL CONDITIONS Article I, Section A delete this paragraph in its entirety and replace it with the following language: Owner s representative to act on its behalf with respect to this Agreement shall

More information

Mumbai Existing Building Operation & Maintenance

Mumbai Existing Building Operation & Maintenance 2013 Mumbai Existing Building Operation & Maintenance GREEN BUILDING RATING SYSTEM DEVANSHI DADIA PAUL RUELL CARNEGIE MELLON UNIVERSITY SCHOOL OF ARCHITECTURE 48-795: LEED GREEN DESIGN AND BUILDING RATING

More information

Prerequisite. prerequisite.

Prerequisite. prerequisite. LEED v4 for Building Operations and Maintenance Summary of changes from LEED 2009 LOCATION AND TRANSPORTATION SUSTAINABLE SITES Alternative Transportation Site Management Policy LEED Certified Design and

More information

S.No RFP Particulars Project Management Equipment Planning: Measurement & Payment:

S.No RFP Particulars Project Management Equipment Planning: Measurement & Payment: S.No RFP Particulars Project Management Can project initiation approval process be created, 1 planned, managed and tracked in the system? Can different types of project lifecycle be defined and 2 managed

More information

Construction Specifications Canada Conference May 23, BOMA BESt

Construction Specifications Canada Conference May 23, BOMA BESt Construction Specifications Canada Conference May 23, 2013 BOMA BESt Creating a sustainable environment one building at a time. BOMA Calgary BOMA Canada BOMA Calgary BOMA BESt local administrator BOMA

More information

Sustainable Building Operations & Upgrades

Sustainable Building Operations & Upgrades Sustainable Building Operations & Upgrades LEED for Existing Buildings 2010 Energy / Facilities Connections Conference Brightworks & Glumac Eric Baxter and Todd McGuire 12 May, 2010 The Value Proposition

More information

Introduction. Scope Management Approach. Roles and Responsibilities. Processes included in Scope Management are:

Introduction. Scope Management Approach. Roles and Responsibilities. Processes included in Scope Management are: Introduction Scope Management involves the management of techniques that make sure that the project comprises a Processes included in Scope Management are: 1. Collect Requirements In this process, project

More information

Energy Use Intensity Each project will calculate the predicted energy use

Energy Use Intensity Each project will calculate the predicted energy use San Fancisco Civic Center Sustainable Master Plan FEMA Headquarters, LEED Certified ARCHITECTS 2011 EUI 1 300 250 200 150 100 050 000 ELECTRICITY NATURAL GAS WATER CARBON EMISSIONS BASELINE TARGET (50%)

More information

LEED v4 for Homes, Residential Project Summary and Checklist One and Two Family New Construction

LEED v4 for Homes, Residential Project Summary and Checklist One and Two Family New Construction LEED v4 for Homes, Residential Project Summary and Checklist One and Two Family New Construction Summary Date of Application Path Project Project Address Owner Architect Third Party Third Party Provider

More information

Making the Most Out of Prop 39: School Energy Retrofits, Conservation & Education

Making the Most Out of Prop 39: School Energy Retrofits, Conservation & Education Making the Most Out of Prop 39: School Energy Retrofits, Conservation & Education Session Purpose Help to design holistic school energy initiatives including facility upgrades, conservation, and student

More information

Information Technology Services Project Management Office Operations Guide

Information Technology Services Project Management Office Operations Guide Information Technology Services Project Management Office Operations Guide Revised 3/31/2015 Table of Contents ABOUT US... 4 WORKFLOW... 5 PROJECT LIFECYCLE... 6 PROJECT INITIATION... 6 PROJECT PLANNING...

More information

Sustainable Sites (SS): where the building is located matters. SSc1 Site Selection

Sustainable Sites (SS): where the building is located matters. SSc1 Site Selection The 425 Cherry Street, SE, Grand Rapids, MI location of Planned Parenthood is seeking LEED certification. The USGBC created the LEED rating systems to support the choice to build green and to provide third

More information

USGBC & LEED. A Summary of the LEED Development as a primer for LEED ND

USGBC & LEED. A Summary of the LEED Development as a primer for LEED ND USGBC & LEED A Summary of the LEED Development as a primer for LEED ND US Green Building Council USGBC Basic USGBC information LEED (Leadership in Energy and Environmental Design GBCI (Green Building Certification

More information

RURAL ELECTRIFICATION AGENCY ENERGY FOR RURAL TRANSFORMATION PHASE III. Credit No.: 5653, Project ID.: P133312

RURAL ELECTRIFICATION AGENCY ENERGY FOR RURAL TRANSFORMATION PHASE III. Credit No.: 5653, Project ID.: P133312 RURAL ELECTRIFICATION AGENCY ENERGY FOR RURAL TRANSFORMATION PHASE III Credit No.: 5653, Project ID.: P133312 Procurement Reference No.: REA-ERTIII/SRVCS/17-18/00007 Terms of Reference for Senior Project

More information

Sustainability and Energy Use

Sustainability and Energy Use AIA Provider #: 40108008 Sustainability and Energy Use AIA Course #: SUS101 Presented by: Jason Borowski, PE LEED AP BD+C, Vice President jborowski@centuryeng.com 1 Sustainability and Energy Use Credit(s)

More information

Does This Come With Instructions?

Does This Come With Instructions? Does This Come With Instructions? Creating A Manual for Your Organization s Project Culture Russell Rivenbark M.P.M. RCDD, PMP New Hanover County Schools First, have a definite, clear practical ideal;

More information

LEED Reference Guide for Green Building Operations and Maintenance For the Operations and Maintenance of Commercial and Institutional Buildings 2009

LEED Reference Guide for Green Building Operations and Maintenance For the Operations and Maintenance of Commercial and Institutional Buildings 2009 LEED Reference Guide for Green Building Operations and Maintenance For the Operations and Maintenance of Commercial and Institutional Buildings 2009 Edition COPYRIGHT DISCLAIMER ii LEED REFERENCE GUIDE

More information

Program Lifecycle Methodology Version 1.7

Program Lifecycle Methodology Version 1.7 Version 1.7 March 30, 2011 REVISION HISTORY VERSION NO. DATE DESCRIPTION AUTHOR 1.0 Initial Draft Hkelley 1.2 10/22/08 Updated with feedback Hkelley 1.3 1/7/2009 Copy edited Kevans 1.4 4/22/2010 Updated

More information

Manage Deliverables - Construction Step 6 February 2015

Manage Deliverables - Construction Step 6 February 2015 Manage Deliverables - Construction Step 6 February 2015 1 Construction Phase Step 1: Needs Development Step 2: Scope Development Step 3: Selection of Design Team Step 4: Design Phase Step 5: Selection

More information

JGBNov_a01Muse.qxd 12/19/05 5:43 PM Page 1 I INDUSTRY CORNER

JGBNov_a01Muse.qxd 12/19/05 5:43 PM Page 1 I INDUSTRY CORNER I INDUSTRY CORNER AN INSIDE LOOK AT LEED: EXPERIENCED PRACTITIONERS REVEAL THE INNER WORKINGS OF LEED Ashley Muse, LEED AP 1 Josette M. Plaut, LEED AP 2 INTRODUCTION LEED is leading the building industry

More information

UCF FAIRWINDS Alumni Center Achieves LEED Gold Certification Evaluating the Return on Investment for LEED in an Existing Building

UCF FAIRWINDS Alumni Center Achieves LEED Gold Certification Evaluating the Return on Investment for LEED in an Existing Building UCF FAIRWINDS Alumni Center Achieves LEED Gold Certification Evaluating the Return on Investment for LEED in an Existing Building Prepared for: University of Central Florida Case Study Prepared by: UCF

More information

Water System Sustainability Symposium

Water System Sustainability Symposium Presentation by: Richard N. Davee, P.E. Senior Vice President Wright-Pierce Water System Sustainability Symposium Sponsored by: Sustainable Design Sustainable design is the philosophy of designing physical

More information

Crawford House Office Building

Crawford House Office Building Page of 4 LEED Certification Review Report This report contains the results of the technical review of an application for LEED certification submitted for the specified project. LEED certification is an

More information

CMMI Project Management Refresher Training

CMMI Project Management Refresher Training CMMI Project Management Refresher Training Classifica(on 2: Foxhole Technology Employees Only RMD 032 Project Management Refresher Training Course September 21, 2017 Version 1.0 The Process Approach The

More information

DIRECTIVE 1B-7 Issue date: October Energy, Sustainability, LEED and Executive Orders

DIRECTIVE 1B-7 Issue date: October Energy, Sustainability, LEED and Executive Orders DIRECTIVE 1B-7 Issue date: October 2017 Energy, Sustainability, LEED and Executive Orders As of December 28, 2012, Executive Order No. 88 (E.O. 88) replaced E.O.111 ( Green and Clean State Buildings and

More information

SECTION CONSTRUCTION PROGRESS DOCUMENTATION

SECTION CONSTRUCTION PROGRESS DOCUMENTATION SECTION 01 32 00 CONSTRUCTION PROGRESS DOCUMENTATION PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other

More information

Allowance Table for: General:

Allowance Table for: General: Allowance Table for: Adopting Credits from LEED Canada for New Construction and Major Renovations (NC) 2009 and LEED Canada for Core and Shell Development (CS) 2009 for LEED Canada-NC v1.0 (with or without

More information

ENERGY AND ENVIRONMENT DESIGN AND CONSTRUCTION STANDARDS ENERGY AND ENVIRONMENT

ENERGY AND ENVIRONMENT DESIGN AND CONSTRUCTION STANDARDS ENERGY AND ENVIRONMENT ENERGY AND ENVIRONMENT The University has committed to approaching new building construction and major renovations with an emphasis on Life Cycle Cost (LCC). Part of this approach is a focus on maximizing

More information

Devon Tower: From Brown to Gold Larry Nichols May 23, Site Selection

Devon Tower: From Brown to Gold Larry Nichols May 23, Site Selection Devon Tower: From Brown to Gold Larry Nichols May 23, 2012 Site Selection 1 Previous site uses Several automobile fueling and service operations were established and operated for numerous years Operations

More information

LEED BD+C Integrative Process. Lori A. Brown, LEED AP BD+C Power Jam Study! Lorisweb.com 1

LEED BD+C Integrative Process. Lori A. Brown, LEED AP BD+C Power Jam Study! Lorisweb.com 1 LEED BD+C Integrative Process Lori A. Brown, LEED AP BD+C Power Jam Study! Lorisweb.com 1 IP Prerequisite Integrative Project Planning and Design HC Intent Maximize opportunities for integrated, cost-effective

More information

What s New in LEED O+M v4: Get Ready for the Future! A Presentation by The Sustainability Experts Leonardo Academy At NFMT Las Vegas

What s New in LEED O+M v4: Get Ready for the Future! A Presentation by The Sustainability Experts Leonardo Academy At NFMT Las Vegas What s New in LEED O+M v4: Get Ready for the Future! A Presentation by The Sustainability Experts Leonardo Academy At NFMT Las Vegas Today s Speakers Michael Arny, P.E., LEED AP President & Director of

More information

Chapter 4 State Requirements for Educational Facilities Section 4.1

Chapter 4 State Requirements for Educational Facilities Section 4.1 providential cause, other impending danger to life safety, or pursuant to Section 1013.46(1)(b), F.S., the board can declare an emergency, can negotiate a contract with a design-build firm, design professional,

More information

SECTION SUSTAINABILITY CERTIFICATION REQUIREMENTS LEED NC V3

SECTION SUSTAINABILITY CERTIFICATION REQUIREMENTS LEED NC V3 PART 1 - GENERAL 1.1 DESCRIPTION SECTION 01 81 13.01 SUSTAINABILITY CERTIFICATION REQUIREMENTS LEED NC V3 A. This section describes requirements and procedures which are additive to and compatible with

More information

Table of Contents Green Associate Study Guide LEED v4 First Edition

Table of Contents Green Associate Study Guide LEED v4 First Edition CHAPTER 1 1 Introductory conversations into sustainable design and construction and the associated benefits of the roles of the LEED AP and LEED rating systems Introduction 1 About the Studio4 LEED Green

More information

LEED Application Guide for Multiple Buildings and On-Campus Building Projects

LEED Application Guide for Multiple Buildings and On-Campus Building Projects LEED Application Guide for Multiple Buildings and On-Campus Building Projects For Use with 2009 LEED Rating Systems for Design and Construction and Operations and Maintenance Released October 31, 2011

More information

LEED -Existing Buildings. Crescent Ridge Corporate Center I

LEED -Existing Buildings. Crescent Ridge Corporate Center I LEED -Existing Buildings Crescent Ridge Corporate Center I LEED Leadership in Energy and Environmental Design The U.S. Green Building Council is a coalition of leaders in the building industry promoting

More information

ASC New Building 400 Masthead Street Albuquerque, NM

ASC New Building 400 Masthead Street Albuquerque, NM September 13, 2011 Prepared by: Angela F. Núñez Matos + Freddy Marquez-Moreno in collaboration with Halcom Consulting LLC + Titan Development LLC ASC New Building 400 Masthead Street Albuquerque, NM Not

More information

601 C O P Y R I G H T 2 O 1 7

601 C O P Y R I G H T 2 O 1 7 Pennsylvania Avenue NW Sustainable Approaches Overview This project has been mandated to be environmentally responsible and to be certified using the United States Green Building Council (USGBC) Leadership

More information

Delmarva Power C&I Energy Savings Program. Retro-Commissioning for Existing Buildings and Enhanced Commissioning for New Construction

Delmarva Power C&I Energy Savings Program. Retro-Commissioning for Existing Buildings and Enhanced Commissioning for New Construction Delmarva Power C&I Energy Savings Program Retro-Commissioning for Existing Buildings and Enhanced Commissioning for New Construction Technical Resource Manual January 19, 2010 Page 1 of 16 Lockheed Martin

More information

Course ID October 2015 COURSE OUTLINE. Business Administration 210 Foundations of Project Management

Course ID October 2015 COURSE OUTLINE. Business Administration 210 Foundations of Project Management Page 1 of 5 Degree Applicable Glendale Community College Course ID 010247 October 2015 I. Catalog Statement COURSE OUTLINE Business Administration 210 Foundations of Project Management BUSAD 210 covers

More information

County of Ventura General Services Agency Maintenance Division Energy Action Plan April Policy

County of Ventura General Services Agency Maintenance Division Energy Action Plan April Policy Policy This Energy Action Plan is relevant to all (GSA) maintained buildings. GSA shall strive to: 1. Minimize the energy intensity in GSA maintained buildings through the identification and implementation

More information

A PRACTICAL GUIDE TO SAN FRANCISCO'S GREEN BUILDING ORDINANCE

A PRACTICAL GUIDE TO SAN FRANCISCO'S GREEN BUILDING ORDINANCE A PRACTICAL GUIDE TO SAN FRANCISCO'S GREEN BUILDING ORDINANCE San Francisco's new Green Building Requirements Ordinance ("Ordinance") went into effect on November 3, 2008. 1 It affects most new construction

More information

IFMA's How-To Guide Highlight: Getting Started on the Path to Sustainable Facility Management. Facility Engineering Associates

IFMA's How-To Guide Highlight: Getting Started on the Path to Sustainable Facility Management. Facility Engineering Associates IFMA's How-To Guide Highlight: g Getting Started on the Path to Sustainable Facility Management Christopher P. Hodges, P.E., CFM, LEED-AP, IFMA Fellow Christopher P. Hodges, P.E., CFM, LEED AP, IFMA Fellow

More information

The USGBC booklet, LEED for Existing Buildings: Operations

The USGBC booklet, LEED for Existing Buildings: Operations SPATIALOPERATIONS Is Your Campus ACHIEVING SUSTAINABILITY? We Can Help You Keep Your LEED Certification The USGBC booklet, LEED for Existing Buildings: Operations & Maintenance Recertification Guidance,

More information

WDVA EMR Project Readiness Assessment Report

WDVA EMR Project Readiness Assessment Report WDVA EMR Project Readiness Assessment Report 1 Prepared by: Marcus Bailey Project QA Assurance Consultant New Compass Consulting, LLC marcus@newcompassconsulting.com Tele: 360-239-4607 Transformation Leadership

More information

Guidance on portfolio, programme and project management

Guidance on portfolio, programme and project management Guidance on portfolio, programme and project management The Standard for Infrastructure Procurement and Delivery Management (SIPDM) defines the following two generic terms: Portfolio: collection of projects

More information

Green Building Ordinance Overview

Green Building Ordinance Overview Green Building Ordinance Overview September, 2013 City of Dallas Sustainable Development and Construction Dallas Green Ordinance 2008 Task Force Recommendations Two-phase implementation strategy Solution

More information

Project Charter Date 4/16/08

Project Charter Date 4/16/08 ! " " # $% &''( ) " I. Project Charter II. III. IV. Scope Statement Team Contract MS Project Gantt chart V. Cost Estimate VI. VII. VIII. IX. Quality Management Plan Project Organizational Chart Communications

More information

Reference B Project Management Requirements

Reference B Project Management Requirements Reference B State of Alaska TABLE OF CONTENTS 1... 2 1.1 Project Life Cycle Methodology... 2 1.2 Preliminary Project Management Narrative and Work Plan... 2 2 Master Project Management Plan and Master

More information

LEED for Operations and Maintenance

LEED for Operations and Maintenance LEED for Operations and Maintenance Bill Green PE, LEED AP Jessie Jones, EIT, LEED AP O+M The RMH Group September 16, 2010 Topics of Discussion Overview of USGBC s LEED Rating System(s) Benefits of LEED

More information

Lessons Learned for Better LEED Submissions

Lessons Learned for Better LEED Submissions Lessons Learned for Better LEED Submissions October 2009 Purpose of Presentation Understanding the LEED documentation process Understanding how and when to collect information. Understanding how to track

More information

Integrated Pest Management Policy

Integrated Pest Management Policy Integrated Pest Management Policy Summary This standard provides guidelines for general best management practices for interior and exterior pest control management practices at this building. This plan

More information

Cornerstones Unified Database Implementation Project (CUDIP)

Cornerstones Unified Database Implementation Project (CUDIP) Cornerstones Unified Database Implementation Project (CUDIP) SYST 699 Spring 2015 Brian Burke Dheeraj Kankanala Project Proposal 1.0 Introduction Cornerstones is a nonprofit organization that promotes

More information

CE Option 1 and 2 - Provide the pre-development site run -off rate (cfs) CE Option 1 and 2 - Provide the pre-development site run -off quantity (cf)

CE Option 1 and 2 - Provide the pre-development site run -off rate (cfs) CE Option 1 and 2 - Provide the pre-development site run -off quantity (cf) LEED - 2009 for Retail - New and Major Renovations HINESBURG, VERMONT DPM Des.Proj.Mngr Mech., Elect., Plumbing Issued: 12-17-2010 Civil Eng. GC-S General Contractor - Site Revised: 4-9-12 Tasklist for

More information

1) MERV (Minimum Efficiency Reporting Value) is relevant to which ASHRAE standards in LEED v4? (Choose 2)

1) MERV (Minimum Efficiency Reporting Value) is relevant to which ASHRAE standards in LEED v4? (Choose 2) 1) MERV (Minimum Efficiency Reporting Value) is relevant to which ASHRAE standards in LEED v4? (Choose 2) A. 52.2-2007 B. 55-2010 C. 62.1-2010 D. 90.1-2010 E. 189.1 Answer A and C. 52.2-2007 - ASHRAE Standard

More information

Facility Management Professional

Facility Management Professional Facility Management Professional Expert Trainer Michel Theriault With 25 years in Facility Management delivering facility services in-house and with an FM outsourcing provider, Michel has deep practical

More information

PROPOSED SAN FRANCISCO GREEN BUILDING CODE AMENDMENTS 2016 Edition

PROPOSED SAN FRANCISCO GREEN BUILDING CODE AMENDMENTS 2016 Edition PROPOSED SAN FRANCISCO GREEN BUILDING CODE AMENDMENTS 2016 Edition Chapter 1 GENERAL SECTION 101 GENERAL 101.1 Title. These regulations shall be known as the California San Francisco Green Building Standards

More information

Green Assistance Program Orientation Meeting March 22, August 5, 2010

Green Assistance Program Orientation Meeting March 22, August 5, 2010 Green Assistance Program Orientation Meeting March 22, 2013 August 5, 2010 Agenda I. What is the Green Assistance Program? II. Who is Balboa Park Cultural Partnership? III. LEED EB O+M IV. How will we

More information

City of Galax BUILDING PERMIT APPLICATION

City of Galax BUILDING PERMIT APPLICATION Building Official,, 111 E. Grayson Street, Galax, VA 24333 --- Telephone 276-236-7297 Property Owner Information Property Owner: Address: Telephone Number: Contractor or Owner s Agent Information Contractor

More information

Energy Efficiency & LEED v4 Certification at the O Connell Center. FEFPA Summer 2017

Energy Efficiency & LEED v4 Certification at the O Connell Center. FEFPA Summer 2017 Energy Efficiency & LEED v4 Certification at the O Connell Center FEFPA Summer 2017 Course Number: Credit Designation: TLC Engineering for Architecture Presenters KRISTY M. WALSON PE, LEED AP BD+C, BEMP

More information

How to Interpret this Report

How to Interpret this Report How to Interpret this Report Purpose The Leadership in Energy and Environmental Design (LEED) Rating System was designed by the US Green Building Council to encourage and facilitate the development of

More information

Project Execution Plan For

Project Execution Plan For Project Execution Plan For [Insert Name Here] Project Document Revision History Revision Date Project Manager Project Sponsor Page 1 of 24 About This Project Execution Plan Template: This template is intended

More information

Genentech Building 20 Office LEED-CI Gold XL CONSTRUCTION

Genentech Building 20 Office LEED-CI Gold XL CONSTRUCTION Genentech Building 20 Office LEED-CI Gold Above and Beyond A LEED Gold 50,00 s.f. tenant improvement, the space was originally designed with a goal to achieve LEED silver certification. Innovative approaches

More information

SOUTHERN CALIFORNIA EDISON DATA CENTER GREEN BUILDING EDUCATION: VIRTUAL TOUR

SOUTHERN CALIFORNIA EDISON DATA CENTER GREEN BUILDING EDUCATION: VIRTUAL TOUR SOUTHERN CALIFORNIA EDISON DATA CENTER GREEN BUILDING EDUCATION: VIRTUAL TOUR Owner s Visions and Goals Energy efficient and environmentally intelligent facility Owner s Visions and Goals Create an environmental

More information

Sugen Building 3 LEED-CI Pilot Project

Sugen Building 3 LEED-CI Pilot Project Sugen Building 3 LEED-CI Pilot Project Winner San Mateo County Sustainability Award 2006 SAMCEDA Award of Excellence, Environmental Action Category 2005 LEEDing Lab Completed in 2003, Sugen s Building

More information

Statement of Qualifications

Statement of Qualifications Statement of Qualifications Philosophy We don t carry an exceptional taste for aesthetics; rather we mature it through our ingenuity of experience, professionalism, reliability, conceptuality, and trust.

More information

Continued reiteration of best practices delivered in 2010 training sessions. Signage posted in driver areas and on school property

Continued reiteration of best practices delivered in 2010 training sessions. Signage posted in driver areas and on school property Actions Towards Carbon Neutrality The actions listed below contribute to a reduction in greenhouse gas emissions from sources for which public sector organizations are responsible under the carbon neutral

More information

Uzbekenergo: Talimarjan Thermal Power Plant 2, Uzbekistan Environmental and Social Action Plan (ESAP)

Uzbekenergo: Talimarjan Thermal Power Plant 2, Uzbekistan Environmental and Social Action Plan (ESAP) Uzbekenergo: Talimarjan Thermal Power Plant 2, Uzbekistan Environmental and Social Action Plan (ESAP) No Action Environmental Risks, Liability/ Benefits Legislative Requirement / EBRD Performance Requirement

More information

30 LEED O+M Documentation Mistakes to Avoid

30 LEED O+M Documentation Mistakes to Avoid 30 LEED O+M Documentation Mistakes to Avoid Copyright The content of this course is the copyrighted property of Green Building Education Services, LLC. Reproduction or distribution of this presentation

More information

Identification Selection Definition Execution. Schedule.

Identification Selection Definition Execution. Schedule. SCHEDULE DEVELOPMENT Schedule development is the identification, definition and sequencing of activities that are required to be performed for successful completion of the project scope. Identification

More information

E W ENTRANCE E W ATRIUM E W N S LOBBY N S PARKING N S RETAIL BLOCK SECTION - NORTH/SOUTH 0' 16' 32' 64' Seal/Signature OFFICE. Date.

E W ENTRANCE E W ATRIUM E W N S LOBBY N S PARKING N S RETAIL BLOCK SECTION - NORTH/SOUTH 0' 16' 32' 64' Seal/Signature OFFICE. Date. LOBBY LAFAYETTE HALL I ST I STREET FITNESS PARKING AVENUE AVENUE INTERNATIONAL 90' RIGHT-OF-WAY E W ENTRANCE E W ATRIUM E W 130'-0" RIGHT-OF-WAY FINANCE CORPORATION BLOCK SECTION - NORTH/SOUTH A-500 N

More information

CxA Gap Session. April 25, :00 p.m. 4:30 p.m. Instructors: Derek De Jesús, CxA, LEED AP Darren Draper, PE, CxA, LEED AP

CxA Gap Session. April 25, :00 p.m. 4:30 p.m. Instructors: Derek De Jesús, CxA, LEED AP Darren Draper, PE, CxA, LEED AP CxA Gap Session April 25, 2017 2:00 p.m. 4:30 p.m. Instructors: Derek De Jesús, CxA, LEED AP Darren Draper, PE, CxA, LEED AP AIA Provider Number 50111116 Course Description This session and short quiz,

More information

PgMP Exam Prep Training - 4 Days

PgMP Exam Prep Training - 4 Days PgMP Exam Prep Training - 4 Days Course Length: 4 Days Course ID: PgMP Credits: 21 PDUs Course Duration: 3 or 4 days (Live in person or online class) Course Level: Advanced Day workshop- PgMP Boot Camp

More information

LEED-CERTIFIED GREEN FACILITY PANDORA PRODUCTION CO.LTD. LAMPHUN

LEED-CERTIFIED GREEN FACILITY PANDORA PRODUCTION CO.LTD. LAMPHUN LEED-CERTIFIED GREEN FACILITY PANDORA PRODUCTION CO.LTD. LAMPHUN Welcome to PANDORA Production Co., Ltd. (Lamphun Branch). This is a green facility in Northern Thailand. We strive to minimise environmental

More information

TD CANADA TRUSTCREDIT VALLEY TOWN PLAZA

TD CANADA TRUSTCREDIT VALLEY TOWN PLAZA TD CANADA TRUSTCREDIT VALLEY TOWN PLAZA 6051 CREDITVIEW RD, MISSISSAUGA, ON 2016 CANADIAN CONSULTING ENGINEERING AWARD SUBMISSION Submitted by: Integral Group 1 PROJECT INFORMATION Project Name: TD Canada

More information

3,740. Demonstrating Competent Performance SIX EXPERIENCE AREAS. INTRODUCTION What is the Architectural Experience Program?

3,740. Demonstrating Competent Performance SIX EXPERIENCE AREAS. INTRODUCTION What is the Architectural Experience Program? What is the Architectural Experience Program? The Architectural Experience Program (AXP ) is an essential step in the path to becoming an architect. Through the AXP, you will learn about the daily realities

More information

500 WEST PUTNAM AVENUE GREENWICH, CT

500 WEST PUTNAM AVENUE GREENWICH, CT LEED-CI ANALYSIS June 2015 500 WEST PUTNAM AVENUE GREENWICH, CT To learn more please visit the sustainability section of our website: www.slgreen.com or contact Jay Black, SL Green s director of sustainability

More information

Subject: Statement of Qualifications for Public Safety Building Design

Subject: Statement of Qualifications for Public Safety Building Design March 5, 2010 Subject: Statement of Qualifications for Public Safety Building Design The City of Porterville seeks Statements of Qualification (SOQ) from qualified architectural and engineering firms for

More information

RETROFITTING OF EXISTING BUILDING AS PER IGBC EXISTING BUILDING NORMS A REVIEW

RETROFITTING OF EXISTING BUILDING AS PER IGBC EXISTING BUILDING NORMS A REVIEW RETROFITTING OF EXISTING BUILDING AS PER IGBC EXISTING BUILDING NORMS A REVIEW P Dilip Asst Professor Department of Civil, Siddhartha Institute of technology & Sciences, Narapalli, TS, India Abstract:

More information

ELG4126 Sustainable Development for Electrical Engineers

ELG4126 Sustainable Development for Electrical Engineers ELG4126 Sustainable Development for Electrical Engineers Case Study of A Case Study on Renewable Energy and Smart Grid of Three Phases Phase Three Sustainable Development for Electrical Engineers Conduct

More information

Fresh Air Ideas SUPPORTING GREEN INITIATIVES WITH INNOVATION

Fresh Air Ideas SUPPORTING GREEN INITIATIVES WITH INNOVATION Fresh Air Ideas SUPPORTING GREEN INITIATIVES WITH INNOVATION SUPPORTING GREEN INITIATIVES WITH INNOVATION As one of the first manufacturers of air movement and control equipment to join the U.S. Green

More information

LEED And Your Indoor Environment

LEED And Your Indoor Environment LEED And Your Indoor Environment An overview of LEED v3 and Indoor Air Quality David McCauley, CIE Council Certified Indoor Environmentalist ACAC CIE #1008005 USGBC's Mission To transform the way buildings

More information

International Diploma in Project Management. (Level 4) Course Structure & Contents

International Diploma in Project Management. (Level 4) Course Structure & Contents Brentwood Open Learning College (Level 4) Page 1 Unit 1 Overview of Project Management The unit 1 covers the following topics: What is A Project? What is Project Management? Project Constraints Tools and

More information

KITCHEN RENOVATION PROJECT PLAN 1

KITCHEN RENOVATION PROJECT PLAN 1 KITCHEN RENOVATION PROJECT PLAN 1 Human Resource Management Plan 9.1 Plan Human Resource Management Process Benjamin Srock Embry-Riddle Aeronautical University Worldwide Campus Capstone Project PMGT-69

More information

Project Manager Regional Projects Manager Department Division/Region Community Location

Project Manager Regional Projects Manager Department Division/Region Community Location 1. IDENTIFICATION Position No. Job Title Supervisor s Fin. Code Position 14-01693 Project Manager Regional Projects Manager 14-03406 14740-01-02-210- 1406000-01 Department Division/Region Community Location

More information

HOW TO OBTAIN A BUILDING PERMIT

HOW TO OBTAIN A BUILDING PERMIT HOW TO OBTAIN A BUILDING PERMIT A GUIDE TO THE HOMEOWNER Copies of the Guide can be obtained from the Building Department of Highlands East or on our web site: www.highlandseast.ca Municipality of Highlands

More information

Project Management Proposal

Project Management Proposal Project Management Proposal INTRODUCTION Managing Government Projects can often be challenging. You typically need to manage internal staff, external suppliers, contractors, equipment and materials - while

More information

A Building Commissioning Overview. Presented by: Goetting & Associates Commissioning

A Building Commissioning Overview. Presented by: Goetting & Associates Commissioning A Building Commissioning Overview Presented by: Goetting & Associates Commissioning www.goettingcx.com What is the Definition of Commissioning? Building Commissioning is a Quality Assurance Process of

More information