1 Title: Contractor Management Procedure Site Function: Ecology, Health & Safety Procedure No.: 4.03 Page: 1 of 12 Kankakee Reviewed: 08/16/2016 Effective: 08/16/2016 Supersedes: 10/2/09 Preparer: Jodie Turner TES Contractor Supervisor Owner: Judy Brinkman Site Director Approver: Travis Rollins TES Manager 1. PURPOSE To establish minimum environmental, health, and safety (EHS) requirements for the qualification and oversight of Contractors for the Kankakee Site. 2. DEFINITIONS 2.1. BASF Contractor Safety Improvement Leader This BASF employee or designee is the point person for the site for communication, performance strategy as well as the point of contact for all contractor safety concerns Competent person An individual, by way of training and/or experience; is knowledgeable of applicable standards and guidelines is capable of identifying existing and predictable hazards in the surroundings or working conditions which are hazardous to employees is designated by their employer, and has the authority to take appropriate actions 2.3. Contractor A company which will be either placing or bringing contractor(s), temporary (contract) employee(s) or contractor employee(s) onto the Kankakee site Subcontractor A subcontractor is a company that has a direct agreement or contract with a contractor hired by BASF to perform work at Kankakee Contractor employee A contractor employee is an individual engaged by or through a third party to perform services principally for the third party and whose day-to-day activities are directed by the contractor company, not BASF Contingent staff Contingent staff is an individual for whom BASF provides direct supervision in their day-to-day activities and direction as to how an activity is to be performed Temporary agency worker Is a worker providing temporary labor employed by a temporary staffing agency or directly through a managed service provider for a period of short duration, typically around one year, and typically in areas such as light industrial, administrative/clerical, laboratory or an accounting support role. Printed On 11/18/16 Printed copy is uncontrolled
2 Contracted worker Is a worker employed by a consulting firm or a temporary staffing Agency to provide service to BASF pursuant to a contract between BASF and the firm, typically for a large project and typically within areas such as IT, engineering, or maintenance and management consulting services Field Audits A process of conducting field reviews of contractor employees, to ensure that the contractor is performing to BASF expectations and to identify and mitigate hazards to ultimately eliminate or reduce injuries and illnesses Managed Service Provider (MSP) An MSP is a third party company that facilitates selection, on-boarding, oversight and off-boarding processes for temporary agency workers at BASF CSSP (also known as Contractor Screening Service Provider) Contractor Screening Service Provider (CSSP) is a service provider that maintains a qualification system and database for managing the EHS processes and systems for BASF contractors and managed service providers (MSPs) CSSP exempt list The CSSP exempt list consists of contractor companies who meet the service personnel definition PQF (pre-qualification form) A PQF is a questionnaire used to evaluate contractors to determine EHS qualification to work at BASF Pre-task plan (PTP) A PTP is a written plan such as a Job Safety Analysis (JSA) or Job Hazard Analysis (JHA) that describes job tasks in step-by-step sequence, identifies associated hazards for each step, and outlines proper hazard controls that minimize/mitigate the risk of injury or illness to the individual(s) performing that task BASF contact Sometimes referred to as a process owner, requisitioner or job representative, is a BASF employee who identifies scope of work and requests contracted services Safe work permits Safe work permits are written authorization to perform work describing tasks, associated risks, and appropriate control measures Contractor Safety Concept A contractor safety concept is a written safety plan for major projects, e.g., turnaround, shut down, plant expansion projects, etc Service personnel Service personnel provide service work that traditionally poses low EHS risk to production related processes or facilities and does not involve or introduce EHS hazards to the work area. 3. SCOPE This procedure applies to contractors at the Kankakee Site.
3 4. PROCEDURE 4.1. General Requirements Program Management A. Contractors and subcontractors working at Kankakee must meet minimum EHS qualification criteria for work that: affects or has the potential to affect the EHS of manufacturing or manufacturing-related areas, laboratories, or offices. introduces chemical or physical hazards into the work area, such as generating a hazardous chemical exposure, operating machinery or powered equipment/tools, or generating hazardous waste. Section details contractor risk classification. B. Kankakee uses a CSSP to facilitate the EHS qualification process for all contractors. C. All subcontractors must be registered with our CSSP and meet the same EHS qualification criteria. BASF Procurement is responsible for informing the managing contractor of this requirement in the contract documents. D. The EHS approval process for a contractor that provides only contingent staff is outlined in the BC corporate procedure. If the contractor provides both contingent staff employees and contractor employees, the contractor is required to obtain EHS approval per this procedure. E. Kankakee has a Contractor Safety Improvement Leader that reports through the TES organization. The Contractor Safety Improvement leader is responsible for ensuring concepts of the contractor EHS performance strategy are in place at the site Contractor Selection A BASF service purchase order, service contract, or any other formal agreement to work cannot be generated for a contractor to work at a BASF site that has not been EHS reviewed and approved. The method illustrated in Site Service Purchase Requisition Process shall be used Full EHS Approval BASF currently uses a CSSP to coordinate contractor qualification. The process is as follows. 1. BASF contact identifies scope of work and/or contractor. 2. BASF notifies contractor of BASF approval requirements. 3. Contractor contacts and registers with our CSSP. 4. CSSP assigns a risk classification to contractor based upon contractor work capability or scope. Effective Jan. 1, 2014, the classifications have changed from low, medium and high risk to the following: a. Non-Safety Sensitive (pre-2014 low risk CSSP ranking) contractors whose work has traditionally posed a minimal EHS risk. Examples typically include: office janitorial offsite/office engineering lawn care/lawn maintenance (excluding landscaping) IT(information technology, software development) office equipment repair uniform laundry
4 b. Safety Sensitive (pre-2014 medium and high risk ranking from our CSSP) - contractors whose work involves higher risk activities where there is incident potential. Examples typically include: shipping and receiving activities landscaping/weed abatement pest control abatement/remediation confined space demolition lockout/tagout elevated work mobile crane operation electrical work hazardous waste hot work work over water rigging trench and excavation work 5. CSSP reviews contractor PQFs and related EHS information according to the minimum BASF criteria: total recordable incident rate (TRIR) 3 - year average of 1.8 or less days away from work case rate (DAFWCR) 3 - year average of 1.0 or less experience modification rate (EMR) of 1.0 or less no regulatory citations within last 3 years no fatalities within last 3 years EHS programs and procedures in place to meet regulatory and BASF s requirements. 6. An initial flag color is assigned by the CSSP as stated below: Green Full EHS approval when all regulatory and BASF criteria are met. Red signifies deficiencies in meeting regulatory and or BASF requirements based off the type of work the company performs. 7. If EHS qualification and approval criteria are met (green flag status), then the contractor is eligible to participate in the selection process or may continue service to BASF as long as technical and procurement approvals are in place. 8. If subcontractors are to be used, a list of those subcontractors must be disclosed to BASF for qualification and approval before work performance. The qualification and approval process for subcontractors is the same with the exception that the managing contractor may be required to facilitate transfer of necessary documents to our CSSP for evaluation. *Refer to , Contractor EHS Approval Flowcharts and RACI, for additional guidance Conditional EHS Approval
5 1. When contractors do not meet minimum EHS performance criteria (e.g., EMR, TRIR, DAFWCR, regulatory compliance history, or EHS programs), the site may grant a conditional approval. This should be case-by-case with consultation from EHS, Procurement, Engineering, Maintenance, and Operations considering the following situations: contractor previous safety performance within BASF safety performance trends within recent years comparison with contractor industry average from the U.S. Department of Labor / Bureau of Labor and Statistics nature of any safety program deficiencies regulatory agency compliance history nature of citation and abatement scope or risk level of work to be performed presence of contractor EHS professional on site availability of alternative safer contractor companies Conditional approval (force red to yellow) allows the contractor to work at a facility under certain prescribed conditions. Only BASF may assign a conditional approval for a contractor, not the CSSP. The Kankakee site may grant full approval (force red to green) if the nature of the deficiency warrants, such as minor regulatory citations, etc. *Refer to , Contractor Conditional Approval Decision Tree, for additional guidance. 2. Once conditional approval is decided, all information shall be documented and saved with the CSSP via the Forced Flag Form ( BASF Forced Flag Form). Acceptable conditional work requirements include, but are not limited to: providing an escort increased supervision increased number of field audits additional training conducting periodic EHS meetings or safety huddles developing and implementing contractor journey roadmap developing or improving specific EHS plans, such as confined, space entry, respiratory protection, fall protection, forklift operation, etc. providing medical surveillance Emergency EHS Approval 1. A site manager or designee may grant emergency approvals for a contractor in consultation with EHS, Engineering and Maintenance, and Procurement. Emergency approvals are temporary and valid for the emergency job only. Once the emergency job is completed, the contractor is required to participate in the EHS qualification and approval process for continued work at a BASF site. Examples of emergency approvals may include: short-term remediation of spill or release unplanned repair of process-related equipment impacting production correction of high-risk unsafe workplace condition
6 2. When emergency approvals are granted, site management, EHS and/or Procurement may require additional EHS measures such as increased supervision and/or auditing of the work throughout the job. 3. Emergency approvals must be documented and retained for the purposes of performing the contractor management system review Service Personnel Designation Providers of service whose work has traditionally posed low EHS risk to production related processes or facilities and does not involve or introduce EHS hazards to the work area, can be considered service personnel. For example, performing routine interim work on nonmanufacturing equipment such as bench top laboratory equipment, vending machines, and office equipment/cleaning are service personnel tasks. The determination for the service personnel classification must be made by the EHS Specialist and must be based on knowledge of the work that the service provider is capable of performing Pre-Access to Site If it is determined that the contractor meets the service personnel designation, the BASF contact and the EHS Specialist will work with procurement to add the company to the CSSP exempt list. *A list of suggested trades that could qualify as service personnel is included in Suggested Service Personnel List Kankakee Requirements 1. A BASF contact shall be identified for each contractor job. 2. The BASF contact will be responsible for ensuring all EHS requirements are met before the contractor employee(s) begins work. 3. The BASF contact shall ensure retention of contractor job EHS performance documentation, such as, records of inspections, job observations, and incidents. 4. The BASF contact shall ensure contractor employee accidents/incidents are entered in AIMS Contractor Safety Concept For major projects involving special or complex hazards, e.g., shut-down or plant expansion projects, representatives with adequate knowledge of the process, materials, and equipment (e.g., maintenance or construction engineer, defined EHS professionals) shall develop a concept for the implementation of the contractor safety requirements. The safety concept includes: planning activities related to process and location specific hazards coordination and scheduling of work between different contractors and BASF employees (avoiding risks because of interaction of different activities) specific safety plans for high-risk contractor work (e.g., demolition activities) Contractor safety contact (safety supervisor) to contractor worker ratios established based off of risk and agreed to prior to work beginning. (e.g. construction project may have a 1 full time safety supervisor for every 25 workers ratio, 1:25) ensuring that contractors know the necessary BASF contacts (or contacts to the main contractor for turnkey projects) for possible questions or issues concerning safety
7 specific safety supervision of the construction site on a regular basis (e.g., safety tours, safety supervisions), regular consultations held to discuss critical points and ensure all employees are informed of the applicable safety requirements, and multi-contractor coordination measures necessary to avoid accidents because of potential increase risk from on-going simultaneous work activities. Before starting the work, this concept shall be discussed with the construction/ maintenance managers of the contractors and relevant BASF services. All affected contractors must sign the implementation plan. After that, the contractors must inform all their employees about the applicable safety measures. Whenever a change in the scope of the activities occurs, the concept must be changed accordingly. *Refer EHS Contractor Safety Concept Template for Construction Projects for additional guidance EHS Site Orientation 1. Before work begins, all contractors must have attended a Contractor Safety Certification training program provided by a BASF-Approved Training Provider (OSHA 10 or 40-hour course, Prairie State Council, Three Rivers Contractor Council, or Houston Area Safety Council), and shall receive the Kankakee site specific EHS orientation. All contractor employee EHS orientations shall include: practices to control the entrance, presence and exit of contractor employees means for contractor to provide the BASF site with information about hazards that the contractor employees may generate means to ensure that the contractor employee informs BASF of any chemicals brought on-site means to ensure that contractor employees are included in any BASF sponsored accident/incident investigations that involve them or their work overview of Kankakee s field auditing and DASH programs emergency plans, alarms, and evacuation procedures known or potential hazards, such as, confined spaces, chemical hazards, asbestos, lead, electrical, fire, explosion, or process hazards related to the contractor employees work or work area provisions for the right to inspect work and stop work as appropriate means to ensure effective communication and understanding with non-english speaking contractor employees *Refer to Contractor Orientation Checklist Pre-Access / Pre-Job EHS Process This process is not a site orientation, but a structured and documented dialog between the BASF contact or designee, and the contractor crew representative (supervisor, general foreman, safety representative, superintendent, etc.) responsible for executing the work. The minimum information covered in the pre-job process will be: contractor company contractor company responsible and accountable manager s name
8 foreman information responsible for the on-site work (name, phone number, etc.) direct supervisor of the foreman completing the work on site (name, phone number, etc.) the work history of the foremen completing the work on site (how long have they been foremen, what training do they have, etc.) the safety professional responsible for the work being completed on site (name, phone number, qualifications, etc.) the BASF contact information responsible for the work being completed on site the specific procedure if one of the contractor employees is injured on site (e.g., whom to call for severe medical, 911, plant security, etc.) Do they have a local medical clinic relationship established to treat non-life-threatening injuries? incident investigation process for the site pre-task planning (PTP) process requirements access to the site safety rules specific craft training requirements 4.4. Work Execution *See BASF Pre-Access Pre-Job Checklist Exposure Reduction Process The Kankakee Site HAS implemented the D.A.S.H observation process to address behavioral based safety. Participation is expected off all contractors. The nested contractors on-site participate as observers as well as observed Contractor Safety Contact to Worker Ratio It is recommended that a safety contact to worker ratios be established at the site for all work being performed by contractors. Whether it is maintenance or construction, a risk-based evaluation should be done for the work and a ratio established. This element should be part of the site written program for contractor employee oversight. For example: a ratio of one (1) full time contractor s safety contact will be on site for 25 or greater contractor employees. Less than 25 employees will be a minimum of one (1) part time contractor s safety contact unless otherwise specified by BASF Contractor Field Audit Program 1. The Kankakee Field audit program covers all phases of activities at the site. All levels of management perform audits throughout the plant utilizing the field audit booklet which uses topics such as; housekeeping, scaffolding, permitting, LOTO, tools and equipment, etc. 2. Training may be provided by EHS or another trained active auditor. 3. Feedback is given immediately to the crew being audited. 4. A copy of the audit will be sent to EHS for entry into a tracking spreadsheet. 5. The data collected in the spreadsheet should be shared with the nested contractors on a quarterly basis during their reviews scheduled by the Contractor Safety Improvement Leader. 6. The minimum frequency for conducting field audits for contractors shall be:
9 Green flagged contractors shall be audited quarterly. Yellow flagged contractors shall be audited monthly. High risk work (crane lifts, etc.) should be audited daily regardless of flags. Turnaround and large project work would require daily auditing as well. Note: The frequency and type of observations for a conditionally approved contractor may be determined during the conditional approval process with the results documented with the CSSP Pre-Task Planning (PTP) All Contractors approved to work at BASF facilities via Safe Work Permits are required to have, at minimum, a PTP process. As a minimum, all PTP s shall have the following elements: Job/Project Title Job Location Date Crew members signoff Task Description / job step Risk/Hazard Description for each job step Risk/Hazard Controls / elimination / mitigation for each recognized hazard The criteria above may be captured on and during the permitting process. However, the PTP tool is typically a separate document and must be reviewed by all members of the work crew. Individual task planning cards may be used to meet the intent of the PTP process as long as the supervisor in charge of the work reviews the individual plan. *See Section 6, Related Documents, Attachment #10, for copy of a BASF acceptable PTP form 4.5. Monitoring, Evaluation and Feedback Contractor Periodic Reviews 1. EHS performance data and insurance requirements for all contractor risk classifications shall be updated annually. 2. Contractor classified as safety sensitive will receive an audit of their safety program manual through the CSSP at least every three years. The review shall include contractor injury statistics, EMR, regulatory agency citations, and EHS programs as stated in The results and findings of the annual and/or 3 year review may be used to adjust the contractor approval status Kankakee Contractor Management System Review/Safety Performance Evaluation The CSIL shall review the effectiveness of practices at least annually to ensure that the contractor management system is properly implemented and the elements adequately support contractor performance improvement. As a minimum, the following elements of the contractor management system shall be included in the review:
10 Review this site procedure to ensure written requirements are in agreement with BC BASF Contractor EHS Management. Participation of affected stakeholder in the development and/or revision of site procedure for adequacy. Adequate understanding of contractor management roles and responsibilities among affected stakeholders (Procurement, Engineering, Maintenance, Operations, EHS, etc.). System to provide opportunity for feedback and communication with contractor employees, e.g., meetings, exchanges, forums, etc. Maintenance of contractor approval documentation. Efficiency and adequacy of conditional approval process. Efficiency and adequacy of emergency approval process. Documented contractor orientation performed in a timely manner before work. Verification mechanism in place to ensure contractor orientation was understood. Contractor field audits performed adequately, timely with appropriate follow-up. Information/data from affected stakeholders (procurement, operations, maintenance, engineering, EHS, etc.) adequate and accessible in order to conduct periodic contractor reviews or re-approvals. Safety performance review of high risk contractors. Results of annual management system review communicated to affected stakeholders. 5. RESPONSIBILITIES *Refer to Contractor EHS Management System Checklist Contractor Hours Accounting All contractor companies will turn in hours each month for the work that is completed at the BASF sites. Each site should have a means to reasonably reconcile these hours on a periodic basis. Some of these means to reconcile can be: 1. Invoicing data 2. Sign-in and out logs with site security 3. Scan-in and out systems (badging programs) Contractor Safety Forums 5.1. Site Director Kankakee will facilitate annual contractor safety forums. The purpose of the Contractor Safety Forums is to facilitate collaboration and alignment (two way dialogue) between BASF and our contractor partners. Communicate the BASF Safety Culture to our contractors. Communicate all BASF expectations regarding contractor safety including upcoming initiatives. And share best practices among various contractor companies. Desired End Result: Drive the Zero Incident Mindset within our contractor partners, thereby ultimately improving safety performance. *Refer to Contractor Safety Forum Agenda Example document for more information.
11 The Site Director of Kankakee has the primary responsibility for the implementation of this procedure TES Manager The TES Manager has the primary responsibility for the initiation, re-issuance, administration, and/or interpretation of this procedure. 6. RELATED DOCUMENTS Site Service Purchase Requisition Process Contractor EHS Approval Flowcharts and RACI Contractor Conditional Approval Decision Tree BASF Forced Flag Form Suggested Service Personnel Contractor Safety Concept Template for Construction Projects Contractor Orientation Checklist BASF Pre-Access Pre-Job Checklist PTP Form Example Contractor EHS Management System Checklist Contractor Safety Forum Agenda Example 7. REFERENCES The following documents were referenced in creating this procedure: BC BASF Contractor EHS Management 8. TRAINING Plant personnel will receive initial training regarding this procedure and additional training if significant changes are made to it.
12 9. PROCEDURE REVIEW/REVISION HISTORY Revision No. Reason Initiator Date No. 0 New Procedure D. Deighton 4/19/ Procedure Update / Revision D. Deighton 5/5/ Procedure Update / Revision D. Deighton 8/1/ Procedure Update / Revision D. Deighton 12/6/ New procedure name and number, new N. Christain 2/1/2000 manual name, minor revisions. 5 Remove Visitor and correct details K. Carrell 8/21/ Visitor portion was removed from procedure K. Carrell 3/23/2004 and placed into a new procedure. 7 Contractor plant entrance, section 5.1 was P. Snapp 3/20/2006 removed and placed into EHS procedure Updated medical treatment information. 8 Renamed Procedure Contractor Safety M. Haller 1/4/2008 Procedure ; Replaced BASF Representative with Contract Initiator; Incorporated all of PSM Chapter 8. 9 Revision history from this date forward is M. Haller 10/2/2009 being maintained in Domino.doc. 10 New procedure Contractor Management Procedure replacing Contractor Safety Procedure J. Turner 8/16/2016
McIntosh Contractor Safety Oversight. Site Function: Safety Procedure No.: MC Page: 1 of 17
Title: McIntosh Contractor Safety Oversight Site Function: Safety Procedure No.: MC032.121 Page: 1 of 17 McIntosh Site Preparer: B. Turner Owner: M. Khan Approver: J. Slinkard EHS Specialist EHS Team Leader
More informationContractor EHS Management. Supersedes: 12/2014 (Rev.11) Preparer: Owner: Approver: EHS Team Member EHS Team Member EHS Manager
Procedure No.: PA-020-0020 Page: 1 of 26 Preparer: Owner: Approver: EHS Team Member EHS Team Member EHS Manager Document Revision Change Table Revision Number Revision Description Revised By Revision Date
More informationGeismar Site Reviewed: 09/10/18 Effective: 09/10/18 Supersedes: 12/13/17 Preparer: Owner: Approver:
Procedure No.: GSS27 Page: 1 of 18 RECORD OF REVISIONS Date Details of Change 09/10/18 Removed reference to phosgene orientation. Refer to MOC #0175-EHS-18-1139. 12/3/17 Updated Job Observation and Periodic
More informationBP OIL -- TOLEDO REFINERY
BP OIL -- TOLEDO REFINERY Document Type: Program Effective Date: September 1, 2017 Owner: Robert Myak Toledo Refinery Contractor Management Program Auth. By: (Signature on file) Reference No.: Rev. No.:
More informationBASF Contractor Pre-Access Checklist
BASF Contractor Pre-Access Checklist Purpose The purpose of this document is to ensure that BASF communicates all EHS requirements and expectations to each contractor company and that each contractor company
More informationBrian Moore. All Contractors. Regarding: Contractor Safety Introduction Letter and Packet. To Whom It May Concern:
To: All Contractors Regarding: Contractor Safety Introduction Letter and Packet To Whom It May Concern: Platte River Power Authority (Platte River) and the Safety Department are pleased that you are interested
More informationIndividual Unit Function: Safety Procedure No.: SOP-0138 Page: 1 of 10
Procedure No.: SOP-0138 Page: 1 of 10 1. PURPOSE To ensure work is performed in a safe manner by: Ensuring clear communications about the work to be accomplished. Providing approval from the equipment
More informationSite Specific Safety Plans (SSSP)
1.0 SCOPE/PURPOSE 1.1 The guidelines in this document provide a minimum framework for the development of a Site- Specific Safety Plan. They are not meant to supersede or replace regulatory requirements,
More informationTAMKO s Statement of Policy on Safety
TAMKO s Statement of Policy on Safety 2006 TAMKO Building Products, Inc. Table of Contents TAMKO s Statement of Policy on Safety 4-6 INTRODUCTION 7 Management Responsibility & Leadership 8-12 Leadership
More informationSUBCONTRACTOR MANAGEMENT PLAN
SUBCONTRACTOR MANAGEMENT PLAN Purpose The purpose of this program is to improve subcontractor health, safety and environmental performance and establish a standard for pre-qualification, evaluation/selection
More informationSUBCONTRACTOR MANAGEMENT PLAN
Doc : SMP Revision. 0 Preparation: Safety Mgr Authority: President Issuing Dept: Safety Page: Page 1 of 10 Purpose The purpose of this program is to improve subcontractor health, safety and environmental
More informationSUBCONTRACTOR MANAGEMENT
Doc : Revision. 0 Preparation: Safety Mgr Authority: Director Issuing Dept: Safety Page: Page 1 of 9 Purpose The purpose of this program is to ensure that ANC Foster continues to improve subcontractor
More informationUNCONTROLLED IF PRINTED. Issued with the authority of the Chief Commissioner and General Manager of Scouts Australia NSW
PROCEDURE Contractor Safety Issued with the authority of the Chief Commissioner and General Manager of Chief Commissioner signature Chief Executive Officer signature Sponsor Head of Risk Document type
More informationSUBCONTRACTOR SAFETY PRE-QUALIFICATION FORM
SUBCONTRACTOR SAFETY PRE-QUALIFICATION FORM GENERAL INFORMATION 1. Subcontractor Information Subcontractor Name: Street Address: Telephone Number: Fax Number: City: Website Address: State: Zip Code: 2.
More informationDEPARTMENTAL PROCEDURE
Title: Contractor Safety Procedure Rev: 9 Page 1 of 14 Approvals: Don Buckman 9/11/2007 Sergio Macieira 9/11/2007 Title: EH&S Manager Date TitIe: EH&S Coordinator Date 1. PURPOSE 1.1. Kidde Aerospace recognizes
More informationECCS Information Form
ECCS Information Form Date: EXHIBIT A Company Name: Form Completed By: Address: E-Mail Address: City, State and Zip Code Federal Tax ID #: Company Contact: List Work Codes Here: (Refer to Type of Work
More informationDoc No: SUBCON Midland Engineering Co., Inc. Initial Issue Date 12/04/15 Safety Management System
Revision Preparation: Safety Mgr Authority: President Issuing Dept: Safety Page: Page 1 of 6 PURPOSE Define subcontractor responsibility for developing, implementing and adhering to their own environmental,
More informationLockheed Martin Space Systems Company (LMSSC) Contractor Environment, Safety & Health (ESH) Site Briefing - Boulder, Colorado
Lockheed Martin Space Systems Company (LMSSC) Contractor Environment, Safety & Health (ESH) Site Briefing - Boulder, Colorado The purpose of the Contractor ESH briefing is for LMSSC to provide information
More informationSubcontractor Project Management Plan
Subcontractor Project Management Plan FOR LAYTON PROJECT: COMPANY: CONTACT NAME: ACTIVITY: Signed Date Written by: Reviewed by: Accepted by: Issue Date Description of Revisions Change Introduced by Change
More informationWork Health & Safety Procedure
1 PURPOSE This procedure explains the process for qualification of Contractors at Port of Newcastle (PON). It outlines the responsibilities for PON Representatives and Contractors. It also provides a system
More information!!!!!!!!!!!!!!!!!!!!
Jefferson Energy Companies Contractor Pre-Qualification Form (PQF) Fill out this form and send to: Jefferson Energy Companies Attention: Calvin Bates 350 Pine St Edison Plaza, 10 th Floor Beaumont, TX
More informationBIDDER INFORMATION QUESTIONNAIRE:
ONE CORPORATE DRIVE, SUITE 600, SHELTON, CONNECTICUT 06484-6211 Susan M. DeLeon Legal Administrator & Compliance Specialist (203) 925-7260 (203) 926-8829 FAX e-mail: susan_deleon@iroquois.com Type of work
More informationSECTION 1: APPLICANT INFORMATION. 1. Have you contacted your local Chapter regarding their established submission process or procedure?
2018 CONSTRUCTION SAFETY EXCELLENCE AWARDS APPLICATION INSTRUCTION STEPS: 1. DOWNLOAD FORM 2. FILL OUT 3. SUBMIT DEADLINE FEBRUARY 2, 2018 SECTION 1: APPLICANT INFORMATION 1. Have you contacted your local
More informationATST Safety, Health, and Environmental Program Plan
Project Documentation Document SPEC-0086 Revision B ATST Safety, Health, and Environmental Program Plan Joseph McMullin ATST Project Manager Steve Shimko ATST Safety Manager Chuck Gessner NOAO/NSO Risk
More informationOHS Management of Contractors in Capital Works and Maintenance
OHS Management of Contractors in Capital Works and Maintenance Physical Resources/Risk, Health and Safety Prepared by: Physical Resources/Risk, Health and Safety Version: 08/04/2008 Contents Page 1. INTRODUCTION...
More informationProcess Safety Management (PSM) Program. General Company Policy
Process Safety Management (PSM) Program General Company Policy Company Name has hazardous chemicals on site that require protections defined under OSHA's Process Safety Management (PSM) regulation, found
More informationChapter 26. Tim Foster - dba MPC (Maintenance Projects & Construction) Company Policy for Subcontractor Management Plans & Management of Change
Chapter 26 Tim Foster - dba MPC (Maintenance Projects & Construction) Company Policy for Subcontractor Management Plans & Management of Change Tim Foster - dba MPC (Maintenance Projects & Construction)
More informationInjury and Illness Prevention Program
Ghilotti Construction Company Injury and Illness Prevention Program Ghilotti Construction Company has developed the following Injury and Illness Prevention Program, in compliance with Title 8 of the California
More informationSTATEMENT OF BIDDER S QUALIFICATIONS
STATEMENT OF BIDDER S QUALIFICATIONS Eastside Trail Extension This Statement is to accompany bids submitted for the project identified above. Bidders must meet the minimum qualification criteria set forth
More informationAUDITS & INSPECTIONS!!!
Sample Written Program For Your Company For AUDITS & INSPECTIONS Provided By: P.O. Box 2136 Slidell, LA 70458 Phone: 985-781-1444 Fax: 985-718-4957 Email: info@se-safety.com Safety Audits & Inspections
More informationGOLDEN TRIANGLE BUSINESS ROUNDTABLE CONTRACTOR SAFETY AWARDS PROGRAM
CONSTRUCTION CATEGORY SUBMITTAL INSTRUCTIONS AND APPLICATION REVISED 1-2-18 OWNERS: 1.0 Give a copy of the submittal instructions, application and evaluation forms to the contractor(s) you will be nominating.
More informationHS309 Corrective Action Procedure
HS309 Corrective Action Procedure Policy Hierarchy link Responsible Officer Contact Officer Superseded Documents File Number Associated Documents This procedure details s and processes pursuant to the
More informationSAMPLE PAGES. Construction Safety and Health Program. [Company name]
The safety and health of our employees is our top priority. Everyone goes home safe and healthy every day. Construction Safety and Health Program [Company name] [Date Authorized] [Version} 0 Contents Mission
More informationHazard Identification & Risk Assessment
Purpose/ Objective: Berland River Safety Inc. has established this written safety policy and implemented procedures to ensure that hazard identification and risk assessment will be part of routine safety
More informationPASO ROBLES PUBLIC SCHOOLS INJURY AND ILLNESS PREVENTION PLAN. REVVISED Approved by Safety Committee
PASO ROBLES PUBLIC SCHOOLS INJURY AND ILLNESS PREVENTION PLAN REVVISED 2-23-15 Approved by Safety Committee 5-12-15 PASO ROBLES JOINT UNIFED SCHOOL DISTRICT INJURY AND ILLNESS PREVENTION PROGRAM POLICY
More informationInspection Program. Inspection Training
General Inspection 1 Table of Contents Inspection Program... 3 Inspection Training... 3 Inspection Responsibility... 4 Management Tours and Inspection... 4 Health, Safety and Environment Tours and Inspections...
More informationUniversity of Utah Health and Safety Training Plan UNIVERSITY OF UTAH
2017 University of Utah Health and Safety Training Plan UNIVERSITY OF UTAH 2017 Purpose and Scope This plan establishes the requirements for the safety and health training program at the University of
More informationCONTRACTOR SAFETY PRE-QUALIFICATION CHECKLIST. Name of Contractor: Date: Business Address: Telephone No.:( ) Fax No.:( )
CONTRACTOR SAFETY PRE-QUALIFICATION CHECKLIST 1. CONTRACTOR INFORMATION of Contractor: Date: _ Business Address: _ Telephone No.:( ) Fax No.:( )_ Contact Person: Company SIC Code: Years in Business: Date
More informationSnelling Injury and Illness Prevention Program. (Reviewed : June 2016)
Snelling Injury and Illness Prevention Program (Reviewed : June 2016) POLICY: It is the policy of Snelling Staffing, LLC to provide its employees with a reasonably safe place to work. To this end, at the
More informationLAUSD Construction Safety Program Safety Boot Camp
LAUSD Construction Safety Program Safety Boot Camp 2018 John E. McEvoy, CHST Facilities Services Division Construction Safety Office 333 Beaudry Ave, 19 th Floor, Room 19-116, Los Angeles, CA 90017 Office:
More informationSECTION 2 SAFETY GOALS AND RESPONSIBILITIES P AGE 1
SECTION 2 SAFETY GOALS AND RESPONSIBILITIES P AGE 1 It is our company s policy to perform its work in the safest manner possible, consistent with safe work practices, and according to all governing laws
More informationContractor and Visitor Safety
Contractor and Visitor Safety Objectives The Objectives of this section are to establish minimum requirements to assure outside contractors are fully advised of requirements regarding safe work practices
More informationSafety Approach. September 2016
Safety Approach The San Francisco Public Utilities Commission (SFPUC) Construction Safety Approach applies to all personnel and companies contracted to work on any Project related to SFPUC Capital Improvement
More informationJOB SAFETY ANALYSIS PROGRAM. Owner: Risk Management Revision No: 01. Document number: Q-001 Date last revised:
Table of Contents 1.0 Applicability...2 2.0 Scope...2 3.0 Definitions...2 4.0 Core Information and Requirements...2 5.0 Roles and Responsibilities...6 6.0 Goals, Objectives and Performance Measures...7
More informationShort Service Employee Program
Page 1 of 6 Sect: 1.0 Purpose 2.0 Responsibility The management of ARDENT recognizes that all new employees face a period of transition into new surroundings and work processes. It is during this period
More informationLockheed Martin Space (LMS)
Lockheed Martin Space (LMS) Contractor Environment, Safety & Health (ESH) Site Briefing Valley Forge site, King of Prussia, PA The purpose of the Contractor ESH briefing is for LM Space to provide site
More informationE & B Oilfield Services Inc.
Chapter 1 Company Safety Policy and Procedures E & B Oilfield Services Inc. 1798 W 3250 N. Roosevelt Utah 84066 Danny Abegglen is the designated Company Safety Coordinator. Safety & Health Policy Statement
More informationThis protocol was developed to establish a process and EHS criteria for evaluating and selecting contractors.
Hierarchy Level: Procedure Document Type: Protocol Document Owner: VP, EHS Applies to: Devon US 112981136 Revision 12/13/2017 Review Cycle: Every 3 Years Effective: 03/31/2015 I. ABOUT THIS PROTOCOL Purpose
More informationHazard Communication Program. University of San Diego
Hazard Communication Program University of San Diego Effective September 30, 2013 1. Introduction and Purpose The University of San Diego is firmly committed to providing each of its employees a safe and
More informationWHS Management Plans
WHS Management Plans Disclaimer This Guide provides general information about the obligations of persons conducting a business or undertaking and/or persons in control of premises and workers under the
More informationWritten Safety and Health Program
Written Safety and Health Program For XYZ Company Required for all Hawaii Businesses with 25 or More Employees Incorporates Provisions of Hawaii Administrative Rules Title 12, Subtitle 8, Part 2, Chapter
More informationEHS Specialist, SW Hub Manager, EHS VP & General Manager REVISION HISTORY
No.: BCF020.028 Page: Page 1 of 12 REVISION HISTORY Date Rev. # Revision Details 2/2018 5 Removal of reference to safety awareness talks. Minor typographical revisions. 10/2014 4 added RMP-specific information,
More informationACCIDENT PREVENTION PLAN!
Sample Written Program For Your Company For ACCIDENT PREVENTION PLAN Provided By: P.O. Box 2136 Slidell, LA 70458 Phone: 985-781-1444 Fax: 985-718-4957 Email: info@se-safety.com Accident Prevention Plan
More informationTransport Sector Portfolio
Transport Sector Portfolio Rehabilitation of 4.476 Kms of Asphalt Road in Shindand District, Herat Province, Afghanistan. United Nations Office for Project Services ( UNOPS ) -and- Name of Contractor Site
More informationILLINOIS INSTITUTE OF TECHNOLOGY SAFETY POLICY COMMITTEE. Contractor Safety
ILLINOIS INSTITUTE OF TECHNOLOGY SAFETY POLICY COMMITTEE Contractor Safety Approved: October 10, 2005 Reviewed and Modified: October 17, 2016 1 TABLE OF CONTENTS Section Page 1. Purpose...1 2. Scope...
More informationConsider This HEALTH & SAFETY NEWSLETTER. Work Safe. Live Safe. Stay Safe. Issue 3 March March: Eye Health at Work. Chemical Labeling Facts
Consider This Elements of an Effective Safety Program OSHA 10 Hour Overview Chemical Labeling Facts March: Eye Health at Work The Toll of OSHA Violations New Hires Stand Firm on Their Training Can we agree
More informationAugust 28, 2018 QLN Conference Center North County 1
August 28, 2018 QLN Conference Center North County 1 2 3 4 5 6 7 8 9 10 Required Submissions CONTRACTOR PRE-CONSTRUCTION ORIENTATION J.6 Each contractor shall submit at the Pre-Construction meeting the
More informationHAZARD IDENTIFICATION AND RISK ASSESSMENT Revision Date: 04/2017
HAZARD IDENTIFICATION AND RISK ASSESSMENT 23.1 PURPOSE 23.1.1 The purpose of this policy is to help employees identify, analyze and apply control strategies to eliminate or reduce hazardous conditions
More informationContractor EHS Program Attachments
Contractor EHS Program Attachments Contractor Environmental Health & Safety Program Safety Work Permit Attachments Attachment 1- Contractor Safety Work Permit The Contractor Safety Work Permit Checklist
More informationWCB Safety Certified. Element Criteria. and. Sample Questions
WCB Safety Certified Element Criteria and Sample Questions WCB Safety Certified Overview, Criteria and Sample Questions 2017 The Workers Compensation Board of Nova Scotia (WCB) is committed to the reduction
More informationSafety Tips from the WorkSafe People
Location/Department: Date of Review: Reviewed by: The following safety and health checklist is designed to be used in conjunction with the Accident Fund document Developing a Safety Program Begin With
More informationEmployee Safety Training Program
Employee Safety Training Program Line of Business: Workers Compensation, General Liability Risk Control Strategy/Key Issues: Employee training to improve job safety knowledge and reduce the number and
More informationOPTUS SUPPLIER WORK HEALTH & SAFETY POLICY
OPTUS SUPPLIER WORK HEALTH & SAFETY POLICY 1. Introduction 1.1 SCOPE & PURPOSE This policy (which includes this document and the work health and safety standards, policies, procedures and safety control
More informationApache / Contractor X. Contractor/Vendor Bridging Document
Operator Contractor/Vendor Operator Apache Contractor Contractor X Address Phone 2000 Post Oak Blvd., Suite 100 Houston, TX 056 Phone: (13)296-6000 Toll free: (00)22-2434 Address Phone *** Phone: Fax:
More informationWORK HEALTH AND SAFETY AUDIT STANDARD
WORK HEALTH AND SAFETY AUDIT STANDARD FORESTRY INDUSTRY South Australia, Victoria and Tasmania Safety Standards 2017 2017 Content I. Introduction... 2 II. Audit Criteria and Indicators... 3 1 PLANNING...
More informationI. Introduction/Welcome to MAPP
I. Introduction/Welcome to MAPP II. Company Policy HSE POLICY It is the commitment of MAPP to perform ALL work in the safest manner possible, while maintaining the highest level of construction practices.
More informationOverhead Power Lines. Corporate Safety Policy Overhead Power Lines. (Cont.)
Corporate Safety Policy Overhead Power Lines Last Modified: JAN 2013 1 of 6 Overhead Power Lines I Purpose To provide procedures, for working on overhead power lines or in their vicinity on COMPANY sites,
More informationApache / Contractor X. Contractor/Vendor Bridging Document
Operator Contractor/Vendor Operator Apache Contractor Contractor X Address Phone 2000 Post Oak Drive. Suite 100 Houston, TX 056 Phone: (13)296-6000 Toll free: (00)22-2434 Address Phone *** Phone: Fax:
More informationJOB SITE FOREMAN - SAFETY RESPONSIBILITIES
- Have Makyle Electric Inc. 8/20/2012-8/26/2012 RISK CONTROL SERVICES FROM CNA talks toolbox JOB SITE FOREMAN - SAFETY RESPONSIBILITIES INTRODUCTION The key to success in any construction loss prevention
More informationSAN FRANCISCO PUBLIC UTILITIES COMMISSION S WATER SYSTEM IMPROVEMENT PROGRAM (WSIP) SAFETY APPROACH
SAN FRANCISCO PUBLIC UTILITIES COMMISSION S WATER SYSTEM IMPROVEMENT PROGRAM (WSIP) SAFETY APPROACH WSIP Safety Approach. The Water System Improvement Program (WSIP) Construction Safety Approach applies
More informationPre-Construction Meeting Minutes
Project Name Project # Project Address Tel: Fax: Gilbane Building Company Pre-Construction Meeting Date Start End Next Meeting Next Time Prepared By Company Purpose Location Next Location General Notes
More informationHealth and Safety Management System Manual
Message from the Managing Director Health and Safety Management System Manual The Blackley Group of Companies are committed to ensuring our workers and contractors have a safe place to work and strive
More informationOWA Vendor Pre-Qualification System
OWA Vendor Pre-Qualification System March 2008 Vendor s Name An OWA Vendor is defined as any individual or company hired to provide services or supplies under contract to the OWA. The steps of the OWA
More informationWORK HEALTH, SAFETY AND WELLBEING (WHS&W)
WORK HEALTH, SAFETY AND WELLBEING (WHS&W) PLANNING 2.3 WORK HEALTH SAFETY AND WELLBEING (WHS&W) TRAINING NEEDS ANALYSIS (TNA) AND TRAINING PLAN Aim To prescribe the responsibilities and actions required
More informationWork Health and Safety Management Systems and Auditing Guidelines
Work Health and Safety Management Systems and Auditing Guidelines 5th edition, September 2013 (Updated May 2014) Work Health and Safety Management Systems and Auditing Guidelines These Guidelines are a
More informationNEW EMPLOYEE SAFETY ORIENTATION
NEW EMPLOYEE SAFETY ORIENTATION Table of Contents SECTION 1. TRAINING PROGRAM INTRODUCTION..................3 Training Objectives...........................................3 Rationale for Training.........................................4
More informationMANAGING PROJECT SAFETY. Alternatives in a Changing Market
MANAGING PROJECT Alternatives in a Changing Market SHIFTING THE BURDEN Clients reduce their costs by increasing safety requirements of contractors working on their property. Clients shift the burden of
More informationFunction: EHS No.: WYN Page: 1 of 15 Reviewed: 7/18/17 (Rev. 12) Revision History
Site No.: WYN032.054 Page: 1 of 15 Reviewed: 7/18/17 Effective: 8/1/17 Supersedes: 11/14/11 Preparer: EHS Hub Team Member Owner: EHS Hub Team Member Approver: EHS Hub Manager Revision History Revision
More informationHUGHS LIMITADA- SHEQ HSE RESPONSIBILITIES
HSE RESPONSIBILITIES All levels of Management take an active interest in the development and implementation of the Health & Safety and Environmental Management System. Demonstrating Leadership in HSE Participation
More information2018 ConocoPhillips Alaska Excellence in Safety Awards
Introduction These awards are to promote and recognize excellence in safety throughout the construction industry in Alaska. Applications are reviewed by an independent panel of safety professionals with
More informationOCCUPATIONAL HEALTH & SAFETY POLICY
OCCUPATIONAL HEALTH & SAFETY POLICY A: POLICY MANUAL INTRODUCTION is situated at 6, Townsend Road, Ashford, Middlesex TW15 3PS and provides an office furniture sales and delivery/installation service.
More informationProgram Advisory Committee (PAC) process includes defining scope and identifies needed resources necessary to support upcoming experiments
Core Function #1 - Define the Scope of Work HSS CRAD 64-10 # Criteria/ s of Inquiry Item # Physics Div liance Description lia nt Corrective s 1 Criteria: management ensures that the contractors and subcontractors
More informationORM Audit. ORM Audit Results. 1 General Safety
ORM Audit Location Information Location Name Nicholls State Univ. - General Operations Location Code 4820 Mailing Address 1 906 East First Street Mailing Address 2 City, State, ZIP Thibodaux, LA 70301
More informationSafety Manual. SEMS Program
Page 1 of 5 1.0 Purpose The purpose of this program is to ensure that all employees are adequately trained and prepared to work in an offshore environment by having the necessary skills and knowledge.
More informationCover Page / Revision Status
EFFECTIVE DATE: April 4, 2011 REVISION: 1 Page 1 of 18 Cover Page / Revision Status Rev Date Description 0 4/4/11 Original Issue signed 1 4/4/14 Revisions to contractor roles and responsibilities. Revisions
More informationPAGE 1 OF 5 HEALTH, SAFETY & ENVIRONMENTAL MANUAL PROCEDURE: S085 Hazard Recognition Program REV
PAGE 1 OF 5 PURPOSE The Hazard Recognition program is geared towards pre-loss identification and treatment of potential hazard exposures than inspections and job safety analyses. It involves several layers
More informationWork Health and Safety Management System
Work Health and Safety Management System Table of Contents 1. Governing Policy 2. Purpose 3. Scope 4. Work Health and Safety Policy and Procedures 4.1. Policy 4.2. Procedures 5. Risk management and legal
More informationTitle: Transitional Work Procedure. Director, Human Resources Staff Functions (Signature on File)
Procedure No.: BC004.039 Page: 1 of 5 Preparer: Owner: Approver: Manager, Employee Benefits Director, Human Resources Staff Functions Senior Vice President, Human Resources 1. PURPOSE To establish guidelines
More informationLeading indicators workshop: Breaking the barrier to zero injuries. [Risk Engineering]
Leading indicators workshop: Breaking the barrier to zero injuries [Risk Engineering] Welcome Administrative issues Electronic devices Exits Schedule Class structure Lecture Q & A Breaks Evaluations Introductions
More informationVerify Category A Audit Content
Verify Category A Audit Content V10.0 Achilles Group Limited, 2014. All rights reserved. Objective The objective of this document is to provide suppliers who have registered for a Verify Category A (V10.0)
More informationCONTRACTOR WHS SYSTEM STANDARD RISK MANAGEMENT EXTERNAL USE ONLY
CONTRACTOR WHS SYSTEM STANDARD RISK MANAGEMENT EXTERNAL USE ONLY Principles in the Optus Contractor WHS management process CONTRACTOR MANAGEMENT STAGES PRINCIPLES THIS STANDARD REQUISITION Requisition
More informationCITY OF JOLIET, ILLINOIS FINAL
Water and Sewer Operations Efficiency Study Implementation Plan FINAL August, The implementation plan detailed on the following pages provides a path to improve efficiency in the City s Department of Public
More informationBest Practice for SSHE
(CIM) Best Practice for SSHE STEP CHANGE IN SAFETY Share Fair June 2010 Stephane A. Gri 90 80 70 60 50 40 30 EMPC Work-hour Distribution 1 EMPC TRIR Comparison 0,9 0,8 0,7 0,6 0,5 0,4 0,3 Emp TRIR Con
More informationConstruction Environmental, Health & Safety Plan (CEHSP)
Construction Environmental, Health & Safety Plan (CEHSP) INSTRUCTIONS This Construction Environmental, Health & Health Plan (CEHSP) is required of each construction project at the Sanford Underground Research
More information2014 SAFETY EXCELLENCE AWARD SAFETY SURVEY FORM FINAL EVALUATION FOR CRANE & RIGGING SUPPORT
2014 SAFETY ECELLENCE AWARD SAFETY SURVEY FORM FINAL EVALUATION FOR CRANE & RIGGING SUPPORT SCORING: For each item listed below, decide if the entry meets the criteria as follows: 0 = Below Average 1 =
More informationCONTRACTOR SAFETY PROGRAM
CONTRACTOR SAFETY PROGRAM Program Designed to Cover All Locations in the United States 30 January 2014 TE Connectivity Date 1/30/14 Revision Table of Contents Page INTRODUCTION... 3 Implementation Steps...
More informationHEALTH AND SAFETY POLICY
SECTION 1. GENERAL POLICY STATEMENT: Director Responsible for Safety: A.C. Appleton The Director responsible for safety will ensure the adoption and maintenance of proper standards of safety, health and
More informationPatrick Malloy Communities Quality Assurance System
Patrick Malloy Communities Quality Assurance System Page 1 of 83 Log of Quality Manual Revisions Version Number Revision Date Type of Revision 1 April 9, 2007 1 st release 1 April 13, 2007 Sec 1.10 removed
More informationBASF Corporation Safety & Loss Prevention Manual
TABLE OF CONTENTS Environmental Protection, Health & Safety Policy - BC032 Preface.. Page i Introduction. 2 1. Management Commitment and Support.. 2 2. Responsibility, Authority and Accountability 3 3.
More information10 minute read. Key Takeaways. How technology supports more proactive and efficient safety management
1 Key Takeaways 10 minute read Read this ebook to learn: 1 2 3 Tips on what an effective safety program should include Common shortcomings in contractor safety programs How technology supports more proactive
More information