1 Supporting ADE-3 At the end of the Obtain Phase, the program office prepares for Acquisition Decision Event 3 (ADE-3). ADE-3 is the production decision to advance to the Produce/Deploy/Support/Dispose Phase of the DHS Acquisition Lifecycle Framework (ALF). As discussed in earlier lessons, ADEs are oversight reviews conducted at the end of each phase of the ALF. These senior management reviews determine whether a program has adequately completed the objectives of the current phase and is mature enough to advance into the next phase. They are designed to ensure that the risk of proceeding to the next phase of the acquisition is acceptable. In this lesson, we will describe the information and documents needed to support a production decision to begin the Produce/Deploy/Support/Dispose Phase of an acquisition. You may print the Full Rate Production ADE-3 lesson or save it for future reference. D Page 1 of 12

2 Graphic representation of the ALF highlighting Acquisition Decision Event 3. The Need Phase begins with ADE-0 and ends with ADE-1. The Analyze Select Phase ends with ADE-2A. The Obtain Phase includes ADE-2B and 2C, and ends with ADE-3 just before the Produce/Deploy/Support/Dispose Phase.

3 Objectives Upon completion of this lesson, you should be able to: List the key documents generated/updated during the Obtain Phase of the Acquisition Lifecycle Framework (ALF) Identify the information required for a decision to proceed to the Produce/Deploy/Support/Dispose Phase of the ALF Page 2 of 12

4 Key Activities of the Obtain Phase During the Obtain Phase, the program office takes the selected alternative, and then designs, develops, tests, and evaluates a system to provide capability to the user. They prepare for the upcoming Produce/Deploy/Support/Dispose Phase, start preliminary production efforts, and plan for deployment and sustainment of the system. For capital investments, the program office may conduct limited or low rate initial production (LRIP) to prove out the production process, ramp up to continuous production, and provide test articles for operational testing. They also revise the Life Cycle Cost Estimate (LCCE) and Acquisition Program Baseline (APB) to include refined logistics and funding parameters from the evolving Integrated Logistics Support Plan (ILSP). Based on successful demonstration of the capability through testing and evaluation, an independent assessment of system supportability and sustainment capability, and the preparation of all required documentation, the program may proceed to ADE-3. Page 3 of 12

5 Documents of the Obtain Phase These products of the Obtain Phase are documents that continue to evolve to reflect trade space decisions and fact-of-life changes in requirements and available resources. Note that some of these documents were first prepared in earlier phases. Select each product below to review. DHS Headquarters Approved: Acquisition Program Baseline (APB) Acquisition Plan (AP) Life Cycle Cost Estimate (LCCE) Integrated Logistics Support Plan (ILSP) Component Approved: Cost Estimating Baseline Document (CEBD) Integrated Master Schedule (IMS) Program Management Plan (PMP) Risk Management Plan (RMP) Test and Evaluation Master Plan (TEMP) Test and Evaluation Reports Systems Engineering Life Cycle (SELC) Review Results Page 4 of 12 Acquisition Program Baseline (APB) The APB documents the fundamental agreement on critical program cost, schedule, and performance parameters between the program manager (PM), the Component Head/Component Acquisition Executive (CAE) and the DHS Acquisition Decision Authority (ADA). The APB provides what will be delivered, how it will perform, when it will be delivered, and what it will cost and contains the intermediate markers to measure progress. The APB establishes the baseline cost, schedule, and performance parameters for the program and related projects. Acquisition Plan (AP) The AP is a living document that spans the life of the acquisition. As such, it is progressively elaborated over time, and requires the involvement of the Component Head of Contracting Activities (HCA) as it is developed. It provides a top-level plan for the overall acquisition approach and types of acquisition (e.g., asset acquisitions, services acquisitions, etc.) and a plan for acquiring future sustainment and support. The plan should describe why the solution is in the Government's best interest and why it is most likely to succeed in delivering capabilities to users. Life Cycle Cost Estimate (LCCE) A LCCE provides an exhaustive and structured accounting of all past (or sunk), present, and future resources and associated cost elements required to develop, produce, deploy, sustain and dispose of a particular system (program) regardless of

6 funding sources. The LCCE should represent the objective design, performance, and schedule of the system/program being estimated. Integrated Logistics Support Plan (ILSP) The ILSP defines the strategy for ensuring the supportability, sustainment, and eventual retirement/disposal of a future capability. Properly planned, it provides critical insight into the acquisition approach, schedule, and funding requirements for integrating supportability and sustainability requirements into the systems engineering process. Cost Estimating Baseline Document (CEBD) A CEBD is a single, comprehensive document that defines the technical, programmatic, and schedule description of an acquisition program. It provides information on development, testing, procurement, integration, program security and protection, installation and replacement, operations and maintenance, planned upgrades, and disposal. Integrated Master Schedule (IMS) Defines the program oversight and management systems and tools used to monitor, oversee, and integrate cost, schedule, and technical performance goals, metrics, and resources. Establishes the relationship among the work breakdown structure (WBS), the proposed product(s), requirements, and schedule; and, identifies the functional leads, stakeholders, and personnel who develop and maintain the WBS and all of its elements. Defines the relationship between the program's IMS and the contractor's schedule, and how the schedules are linked or interfaced. Program Management Plan (PMP) The objective of a PMP is to describe the establishment and coordination of tasks, resources, milestones, and finances necessary to successfully complete the program. It describes the program scope, objectives, and management methodology, and addresses the tasks, personnel, and stakeholder management, as well as cost and project controls. Risk Management Plan (RMP) An RMP details the process used to identify, analyze, mitigate, and report project risk. It clearly defines the criteria used to define consequence and likelihood. An RMP does not list specific project risks, but rather defines the method and process for managing risks. Test and Evaluation Master Plan (TEMP) The approved Operational Requirements Document (ORD) provides the key performance parameters (KPPs), source data for Critical Operational Issues (COIs), and derived technical parameters for developing a TEMP. A TEMP is finalized to describe the program's Test and Evaluation (T&E) strategy in terms of the Developmental Test and Evaluation (DT&E) and Operational Test and Evaluation (OT&E) needed to determine system technical performance; and, the strategy for evaluating the system's operational effectiveness and suitability through an integrated assessment of that developmental and operational testing. A preliminary version may be prepared prior to ADE-2A. Test and Evaluation Reports Developmental testing and operational assessments/tests are conducted in accordance with the TEMP and test plans. The results are used to ensure that the system meets all technical performance specifications and will be operationally effective and suitable. Systems Engineering Life Cycle (SELC) Review Results A series of technical reviews are conducted to control technical risk as the system evolves. The SELC provides for the following reviews during the Obtain Phase: Project Planning Review (PPR) System Definition Review (SDR) Preliminary Design Review (PDR) Critical Design Review (CDR)

7 Integration & Test Readiness Review (IRR) Production Readiness Review (PRR) Operational Test Readiness Review (OTRR) Operational Readiness Review (ORR)

8 Knowledge Review Which of the following is a key document that is updated during the Obtain Phase in preparation for ADE-3? A. Mission Need Statement (MNS) B. Capabilities Development Plan (CDP) C. Integrated Logistics Support Plan (ILSP) D. Concept of Operations (CONOPS) Correct! Integrated Logistics Support Plan (ILSP). The ILSP is listed in DHS Acquisition Management Instruction as one of the primary documents updated during the Obtain Phase, and is required to support the ADE-3 decision to proceed into the Produce/Deploy/Support/Dispose Phase. Page 5 of 12

9 Preparing for ADE-3: Coordination The coordination process is the same for every ADE, with the Office of Program Accountability and Risk Management (PARM) serving as the DHS Headquarters focal point for coordination between the Acquisition Review Team (ART) and the Component. Select the D-link to read a detailed explanation of the graphic D Page 6 of 12 The DHS ART is the staffing body that supports the ARB by reviewing the status of acquisitions scheduled for ARBs, and by assisting with the preparation of the decisions and issues placed before the ARB. The ART is comprised of action officers representing the DHS lines of business and key stakeholders who are ARB members. These include: CIO: Chief Information Officer CFO: Chief Financial Officer CPO: Chief Procurement Officer CRSO: Chief Readiness Support Officer A/S Policy: Assistant Secretary for Policy DOT&E: Director, Operational Test and Evaluation Representative from Joint Requirements Council (JRC) Other members as necessary A flow chart illustrates the notional coordination process leading up to ADE-1. It begins with a PM interacting with the Component acquisition team. The Component acquisition team provides input to PARM, who then provides input to the acquisition review team. The acquisition review team is composed of the CIO, CFO, CPO, CRSO, A/S Policy, DOTE, JRC representative, and others members as necessary. For IT programs, the Component acquisition team also provides input to the enterprise architecture board (EAB). The EAB provides input to the acquisition review team.

10 Conducting ADE-3: The Acquisition Review Board (ARB) Meeting The Acquisition Decision Authority (ADA) serves as the chair of the Acquisition Review Board (ARB). Based on successful testing, production readiness, sustainment reviews, and verification of sufficient production and operational resources (staffing and funding), the ARB may recommend that the ADA authorize entry into the Produce/Deploy/Support/Dispose Phase at ADE-3. The ADA's decision is documented in an Acquisition Decision Memorandum (ADM). For hardware intensive systems, this is a Full Rate Production decision For information technology, this decision grants the authority to deploy the system to the enterprise If the system is not ready for deployment, the ADA determines what actions are required to make it ready and documents those actions in an ADM. Page 7 of 12 Acquisition Decision Memorandum (ADM) - A documented record of decisions, exit criteria, and assigned actions for a specific type of acquisition as determined by the ADA.

11 Conducting ADE-3: ARB Considerations Questions to be answered at the ADE-3 decision point include: Has the system been tested in a relevant environment? Have the requirements been met? Have the shortfalls been addressed? Is the system operationally effective and suitable? Are the intended users trained and ready to accept the capability? Are the production processes mature? Are transition plans (if required) adequate? Is the capability/system supportable? Is sustainment and support planning adequate (as certified by the Component Acquisition Executive or equivalent)? Are sufficient resources available to support plans for production and deployment? Page 8 of 12

12 Conducting ADE-3: After the ARB The post-arb actions for all ADEs are the same: PARM drafts an ADM with program manager input, and submits it to the ADA for signature The ADM is signed by the ADA (with ARBassigned action items and due dates) The decision process is complete when the ADM is signed ADM actions/due dates are entered into the departmental periodic reporting system and are tracked by PARM on behalf of the Chief Acquisition Officer (CAO) Page 9 of 12

13 Knowledge Review Which of these is a question that should be answered at ADE-3? A. Does the Mission Need Statement identify any relationship to other DHS programs/systems? B. Are operational requirements (as described in the Operational Requirements Document) valid, complete, testable, and measurable? C. What resources are required for operational testing? D. Has the system been tested in a relevant environment? Correct! ADE-3 is the time to determine that the system has been tested in a relevant environment. Page 10 of 12

14 Review of the Obtain Phase Here is an illustration of what takes place during the Obtain Phase. You have learned about each of these elements and can now see how they fit in the "big" picture as they support ADE-3. Rollover each acronym in the graphic to see it expanded. Select the D-link to read a detailed explanation of the graphic D Page 11 of 12 Graphic reviewing all the documents and oversight groups between ADE-2B and ADE-3. Headquarters approved documents include the Acquisition Program Baseline (APB), Acquisition Plan (AP), Life Cycle Cost Estimate (LCCE), and Integrated Logistics Support Plan (ILSP). Component approved documents include the Cost Estimating Baseline Document (CEBD), Integrated Master Schedule (IMS), Program Management Plan (PMP), Risk Management Plan (RMP), and Test and Evaluation Master Plan (TEMP). Technical reviews include the PPR (Project Planning Review), System Definition Review (SDR), Preliminary Design Review (PDR), Critical Design Review (CDR), Integration & Test Readiness Review (IRR), Production Readiness Review (PRR), Operational Test Readiness Review (OTRR), and Operational Readiness Review (ORR). Oversight and review of the entire process is done by the Office of Program Accountability and Risk Management (PARM), then by the Acquisition Review Team (ART), and finally by the Acquisition Review Board (ARB). Meanwhile, the Enterprise Architecture Board (EAB) guides program decision makers toward alignment with the Homeland Security Enterprise Architecture (HLS EA). The ARB issues an Acquisition Decision Memo (ADM) prior to ADE-3. ADE-2B Acquisition Decision Event 2B APB Acquisition Program Baseline

15 AP Acquisition Plan LCCE Life Cycle Cost Estimate ILSP Integrated Logistics Support Plan CEBD Cost Estimating Baseline Document IMS Integrated Master Schedule PMP Program Management Plan RMP Risk Management Plan PPR Project Planning Review (Includes the SELC Tailoring Plan) PDR Preliminary Design Review IRR Integration Readiness Review OTRR Operational Test Readiness Review SDR System Definition Review CDR Critical Design Review PRR Production Readiness Review ORR Operational Readiness Review PARM Office of Program Accountability and Risk Management EAB

16 Enterprise Architecture Board ART Acquisition Review Team ARB Acquisition Review Board ADM Acquisition Decision Memo ADE-3 Acquisition Decision Event 3 TEMP Test and Evaluation Master Plan

17 Summary ADE-3 is the gateway to the Produce/Deploy/Support/Dispose Phase of the Acquisition Lifecycle Framework (ALF). The major activities of the Obtain Phase are design, development, and testing of the system. A series of technical reviews and tests are conducted to monitor system development. Plans, such as the Test and Evaluation Master Plan (TEMP) and Integrated Logistics Support Plan (ILSP), and other program documents, such as the Acquisition Program Baseline (APB) and Life Cycle Cost Estimate (LCCE), are developed and updated to reflect knowledge gained during the phase. As with other acquisition decision events, DHS follows an established process for conducting ADE-3, the production decision, with reviews and feedback from the Office of Program Accountability and Risk Management (PARM) and the Acquisition Review Team (ART) before the Acquisition Review Board (ARB) meeting. The Acquisition Decision Authority (ADA) summarizes the decision in an acquisition decision memorandum (ADM) that spells out any required follow-on activities. You may print the Full Rate Production ADE-3 lesson or save it for future reference. D Page 12 of 12 Repeat of the graphic representation of the ALF highlighting Acquisition Decision Event 3. The Need Phase begins with ADE-0 and ends with ADE-1. The Analyze Select Phase ends with ADE-2A. The Obtain Phase includes ADE-2B and 2C, and ends with ADE-3 just before the Produce/Deploy/Support/Dispose Phase.

Department of Homeland Security. DHS Directives System Directive Number: 1 02~1 Revision Number: 01 Issue Date: ACQUISITION MANAGEMENT DIRECTIVE

Department of Homeland Security. DHS Directives System Directive Number: 1 02~1 Revision Number: 01 Issue Date: ACQUISITION MANAGEMENT DIRECTIVE I. Purpose Department of Homeland Security. DHS Directives System Directive Number: 1 02~1 Revision Number: 01 Issue Date: ACQUISITION MANAGEMENT DIRECTIVE A. This Directive provides the overall policy

More information

The Analyze/Select Phase

The Analyze/Select Phase D page 1 of 32 Long Description Title screen for Module 1, Lesson 3: System Acquisition Life Cycle, with three photos: three people meeting at a conference table, a stoplight, and a group of people meeting.

More information

TECHNICAL REVIEWS AND AUDITS

TECHNICAL REVIEWS AND AUDITS Chapter 11 Technical Reviews and Audits CHAPTER 11 TECHNICAL REVIEWS AND AUDITS 11.1 PROGRESS MEASUREMENT The Systems Engineer measures design progress and maturity by assessing its development at key

More information

Operational Requirements Document (ORD)

Operational Requirements Document (ORD) Operational Requirements Document (ORD) A. Purpose This Appendix sets the requirements and establishes procedures for preparation of an Operational Requirements Document (ORD). It also prescribes procedures

More information

The Produce/Deploy/Support Phase. The Produce/Deploy/Support Phase. Long Description

The Produce/Deploy/Support Phase. The Produce/Deploy/Support Phase. Long Description D page 1 of 13 Long Description Title screen for Module 1, Lesson 5: System Acquisition Life Cycle with three images: A person looking at a clipboard in a large warehouse, a Coast Guard ship on the ocean,

More information

System Safety in Systems Engineering V-Charts

System Safety in Systems Engineering V-Charts System Safety in Systems Engineering V-Charts System Safety is an integral part of the systems engineering (SE) process, providing specific inputs by activity and phase as illustrated in the five V-Charts

More information

3 PART THREE: WORK PLAN AND IV&V METHODOLOGY (SECTION 5.3.3)

3 PART THREE: WORK PLAN AND IV&V METHODOLOGY (SECTION 5.3.3) 3 PART THREE: WORK PLAN AND IV&V METHODOLOGY (SECTION 5.3.3) Emagine IT s approach to Independent Verification and Validation (IV&V) has been shaped over the years by hands-on experience and contributions

More information

WORK PLAN AND IV&V METHODOLOGY Information Technology - Independent Verification and Validation RFP No IVV-B

WORK PLAN AND IV&V METHODOLOGY Information Technology - Independent Verification and Validation RFP No IVV-B 1. Work Plan & IV&V Methodology 1.1 Compass Solutions IV&V Approach The Compass Solutions Independent Verification and Validation approach is based on the Enterprise Performance Life Cycle (EPLC) framework

More information

Life Cycle Cost Estimate (LCCE)

Life Cycle Cost Estimate (LCCE) Life Cycle Cost Estimate (LCCE) Assessments 2013 ICEAA Annual Conference New Orleans, Louisiana June 17-21, 2013 Casey D. Trail Colleen Craig David Brown Motivation A particular program support and cost

More information

Given design trade studies, interpret the results to recommend the most cost-effective concept for development.

Given design trade studies, interpret the results to recommend the most cost-effective concept for development. 1 Summarize the Planning, Programming, Budgeting and Execution (PPBE) process. Analyze the financial structure and the movement of funds within the PPBE. 2 Given a scenario, develop an appropriate PMO

More information

Passit4Sure.OG Questions. TOGAF 9 Combined Part 1 and Part 2

Passit4Sure.OG Questions. TOGAF 9 Combined Part 1 and Part 2 Passit4Sure.OG0-093.221Questions Number: OG0-093 Passing Score: 800 Time Limit: 120 min File Version: 7.1 TOGAF 9 Combined Part 1 and Part 2 One of the great thing about pass4sure is that is saves our

More information

Intermediate Systems Acquisitions Course. Commercial and Non-Developmental Items

Intermediate Systems Acquisitions Course. Commercial and Non-Developmental Items Commercial and Non-Developmental Items Many systems acquired by DHS are not completely new developments; instead, they use existing products. These products may be used just as they are, or they may be

More information

DEFENSE ACQUISITION UNIVERSITY ISA 101 BASIC INFORMATION SYSTEM ACQUISITION

DEFENSE ACQUISITION UNIVERSITY ISA 101 BASIC INFORMATION SYSTEM ACQUISITION 1 Identify applicable United States laws, federal regulations and DoD directives that govern management of IT/SW systems. Identify key statutes related to the acquisition of Information Technology (IT)

More information

Project Plan. CxOne Guide

Project Plan. CxOne Guide Project Plan CxOne Guide CxGuide_ProjectPlan.doc November 5, 2002 Advancing the Art and Science of Commercial Software Engineering Contents 1 INTRODUCTION... 1 1.1 DELIVERABLE PURPOSE... 1 1.2 LIFECYCLE...

More information

Incorporating Test and Evaluation into Department of Defense Acquisition Contracts

Incorporating Test and Evaluation into Department of Defense Acquisition Contracts DEPARTMENT OF DEFENSE UNITED STATES OF AMERICA Incorporating Test and Evaluation into Department of Defense Acquisition Contracts CLEARED For Open Publication OCT 24, 2011 Office of Security Review Department

More information

CMMI-DEV V1.3 CMMI for Development Version 1.3 Quick Reference Guide

CMMI-DEV V1.3 CMMI for Development Version 1.3 Quick Reference Guide processlabs CMMI-DEV V1.3 CMMI for Development Version 1.3 Quick Reference Guide CMMI-DEV V1.3 Process Areas Alphabetically by Process Area Acronym processlabs CAR - Causal Analysis and Resolution...

More information

Report of the Reliability Improvement Working Group Table of Contents

Report of the Reliability Improvement Working Group Table of Contents Report of the Reliability Improvement Working Group 1942 poster commissioned by US Office for Emergency Management, Office of War Information Courtesy of the National Archives September 2008 Report of

More information

NASA Systems Engineering Processes and Requirements

NASA Systems Engineering Processes and Requirements NASA NPR 7123.1B Procedural Effective Date: April 18, 2013 Requirements Expiration Date: April 18, 2018 RESPONSIBLE OFFICE: Office of the Chief Engineer COMPLIANCE IS MANDATORY NASA Systems Engineering

More information

This resource is associated with the following paper: Assessing the maturity of software testing services using CMMI-SVC: an industrial case study

This resource is associated with the following paper: Assessing the maturity of software testing services using CMMI-SVC: an industrial case study RESOURCE: MATURITY LEVELS OF THE CUSTOMIZED CMMI-SVC FOR TESTING SERVICES AND THEIR PROCESS AREAS This resource is associated with the following paper: Assessing the maturity of software testing services

More information

The SAM Optimization Model. Control. Optimize. Grow SAM SOFTWARE ASSET MANAGEMENT

The SAM Optimization Model. Control. Optimize. Grow SAM SOFTWARE ASSET MANAGEMENT The Optimization Model Control. Optimize. Grow The Optimization Model In an ever-changing global marketplace, your company is looking for every opportunity to gain a competitive advantage and simultaneously

More information

Program Management. PREFERRED: o Level II or III Certification in a second DAWIA career field.

Program Management. PREFERRED: o Level II or III Certification in a second DAWIA career field. Program Management Specific Functional Requirements for Key Leadership Positions (Attributes and Demonstrated Experience Beyond Level III Certification) Education: PREFERRED: o Advanced Degree Preferably

More information

CMMI Project Management Refresher Training

CMMI Project Management Refresher Training CMMI Project Management Refresher Training Classifica(on 2: Foxhole Technology Employees Only RMD 032 Project Management Refresher Training Course September 21, 2017 Version 1.0 The Process Approach The

More information

Work Breakdown Structures

Work Breakdown Structures D page 1 of 19 Long Description Title page for Module 2, Lesson 5: Program Management and Acquisition Concepts, containing three photos: two professionals consulting paperwork, a professional in an office,

More information

Engineering and Manufacturing Development YOU ARE HERE. As homework, you read the SPAW MS B TEMP and wrote down any mistakes you noticed.

Engineering and Manufacturing Development YOU ARE HERE. As homework, you read the SPAW MS B TEMP and wrote down any mistakes you noticed. TEMP Review Exercise CDD Validation Dev. RFP Release MDD A B C FRP IOC FOC Materiel Solution Analysis Tech Maturation & Risk Reduction Engineering and Manufacturing Development Production & Deployment

More information

Applying Systems Engineering to ITS Projects: Advancing Beyond Federal Rule 940. INCOSE IW Transportation Working Group January 27, 2015

Applying Systems Engineering to ITS Projects: Advancing Beyond Federal Rule 940. INCOSE IW Transportation Working Group January 27, 2015 Applying Systems Engineering to ITS Projects: Advancing Beyond Federal Rule 940 William Gleckler Deputy Systems Engineering Officer, NYCT Capital Program Management Vincent Cavataio, CCM Deputy Systems

More information

Top 10 Signs You're Ready (or Not)

Top 10 Signs You're Ready (or Not) Top 10 Signs You're Ready (or Not) For an Appraisal Gary Natwick Harris Corporation Gary Natwick - 1 Government Communications Systems Division DoD s Strategic and Business Development CMMI Technology

More information

System Under Development Review of the Departmental Financial Management System Renewal Project

System Under Development Review of the Departmental Financial Management System Renewal Project System Under Development Review of the Departmental Financial Management System Renewal Project Audit and Evaluation Branch In collaboration with Deloitte LLP December 2015 List of Acronyms AAFC ADM AEB

More information

Rigor and Objectivity in T&E

Rigor and Objectivity in T&E Guest Editorial ITEA Journal 2010; 31: 161 164 Rigor and Objectivity in T&E J. Michael Gilmore, Ph.D. Director, Operational Test and Evaluation, Office of the Secretary of Defense, Washington, DC The Director

More information

Key Leadership Position Joint Qualification Board Application

Key Leadership Position Joint Qualification Board Application Key Leadership Position Joint Qualification Board Application The information collected in this application will be used by the Key Leadership Position (KLP) Qualification Board to identify personnel with

More information

CMMI-SVC V1.3 CMMI for Services Version 1.3 Quick Reference Guide

CMMI-SVC V1.3 CMMI for Services Version 1.3 Quick Reference Guide processlabs CMMI-SVC V1.3 CMMI for Services Version 1.3 Quick Reference Guide CMMI-SVC V1.3 Process Areas Alphabetically by Process Area Acronym processlabs CAM - Capacity and Availability Management...

More information

KEY SUCCESS FACTORS FOR MAJOR PROGRAMS THAT LEVERAGE IT. The 7-S for Success Framework

KEY SUCCESS FACTORS FOR MAJOR PROGRAMS THAT LEVERAGE IT. The 7-S for Success Framework KEY SUCCESS FACTORS FOR MAJOR PROGRAMS THAT LEVERAGE IT The 7-S for Success Framework May 2014 This document sets forth a framework of critical success factors for large scale government IT projects. ACT-IAC

More information

Report of the Reliability Improvement Working Group (RIWG) Volume II - Appendices

Report of the Reliability Improvement Working Group (RIWG) Volume II - Appendices Report of the Reliability Improvement Working Group (RIWG) Volume II - Appendices Appendix 1 Formulate Programs with a RAM Growth Program II-1 1.1 Reliability Improvement Policy II-3 1.2 Sample Reliability

More information

SYSTEMS ENGINEERING REQUIREMENTS AND PRODUCTS

SYSTEMS ENGINEERING REQUIREMENTS AND PRODUCTS BY ORDER OF THE COMMANDER SMC Standard SMC-S-001 12 July 2010 ------------------------ Supersedes: SMC-S-001 (2008) Air Force Space Command SPACE AND MISSILE SYSTEMS CENTER STANDARD SYSTEMS ENGINEERING

More information

Mission-Level Systems Engineering

Mission-Level Systems Engineering 6 th Annual DoD Enterprise Architecture Conference Mission-Level Systems Engineering Mr. Ricardo Cabrera ASN (RD&A) CHSENG Hampton, VA 13 Apr 2011 DISTRIBUTION STATEMENT A. Approved for public release;

More information

Project Management Institute (PMI) Practice Standard for Configuration Management

Project Management Institute (PMI) Practice Standard for Configuration Management Project Configuration Management Project Management Institute (PMI) Practice Standard for Configuration Management Project Configuration Management What we will cover: Introduction Relationship with other

More information

UNCLASSIFIED. Exhibit R-2, RDT&E Budget Item Justification Date: February 2005 APPROPRIATION/BUDGET ACTIVITY DEFENSE WIDE RDT&E BA 6

UNCLASSIFIED. Exhibit R-2, RDT&E Budget Item Justification Date: February 2005 APPROPRIATION/BUDGET ACTIVITY DEFENSE WIDE RDT&E BA 6 Exhibit R-2, RDT&E Budget Item Justification Date: February 2005 APPROPRIATION/BUDGET ACTIVITY DEFENSE WIDE RDT&E BA 6 R-1 ITEM NOMENCLATURE Capital Asset Management Systems -Military Equipment Evaluation

More information

PART THREE: Work Plan and IV&V Methodology (RFP 5.3.3)

PART THREE: Work Plan and IV&V Methodology (RFP 5.3.3) PART THREE: Work Plan and IV&V Methodology (RFP 5.3.3) 3.1 IV&V Methodology and Work Plan 3.1.1 NTT DATA IV&V Framework We believe that successful IV&V is more than just verification that the processes

More information

TOGAF 9.1 in Pictures

TOGAF 9.1 in Pictures TOGAF 9. in Pictures The TOGAF ADM Cycle Stage Set up an EA team and make sure it can do its work The ADM is about understanding existing architectures and working out the best way to change and improve

More information

USING PILOTS TO ASSESS THE VALUE AND APPROACH OF CMMI IMPLEMENTATION. Goddard Space Flight Center (GSFC)

USING PILOTS TO ASSESS THE VALUE AND APPROACH OF CMMI IMPLEMENTATION. Goddard Space Flight Center (GSFC) USING PILOTS TO ASSESS THE VALUE AND APPROACH OF CMMI IMPLEMENTATION Goddard Space Flight Center (GSFC) Sally Godfrey, James Andary, Linda Rosenberg SEPG 2003 2/03 Slide 1 Agenda! Background " NASA Improvement

More information

Available online at ScienceDirect. Procedia Computer Science 61 (2015 )

Available online at  ScienceDirect. Procedia Computer Science 61 (2015 ) Available online at www.sciencedirect.com ScienceDirect Procedia Computer Science 61 (2015 ) 293 300 Complex Adaptive Systems, Publication 5 Cihan H. Dagli, Editor in Chief Conference Organized by Missouri

More information

Alan F. Estevez. Principal Deputy Assistant Secretary of Defense for Logistics and Materiel Readiness

Alan F. Estevez. Principal Deputy Assistant Secretary of Defense for Logistics and Materiel Readiness FOREWORD The DoD Weapon Systems Acquisition Reform Product Support Assessment (WSAR-PSA) identified eight principle areas to improve product support effectiveness. One of those areas, Governance, included

More information

Implementation of the Reliability & Maintainability (R&M) Engineering Body of Knowledge (BoK)

Implementation of the Reliability & Maintainability (R&M) Engineering Body of Knowledge (BoK) Implementation of the Reliability & Maintainability (R&M) Engineering Body of Knowledge (BoK) Andrew Monje Office of the Deputy Assistant Secretary of Defense for Systems Engineering 20th Annual NDIA Systems

More information

Objective (c.f., p.58)

Objective (c.f., p.58) TOGAF 9.1 CIS 8090 Session #4 Chapter 6 Preliminary Phase Chapter 7 Phase 4 Architecture Vision Part III Chapter 18 Introduction to ADM Guidelines and Techniques Sources: 1. Primary Slide Deck By: Samuel

More information

Human Systems Integration (HSI) in Acquisition

Human Systems Integration (HSI) in Acquisition Human Systems Integration (HSI) in Acquisition Integrating Human Concerns into Life Cycle Systems Engineering Management Guide HSI Domain and Acquisition Phase Guides also Available Report Documentation

More information

Space project management

Space project management ECSS-M-ST-10C Rev. 1 Space project management Project planning and implementation ECSS Secretariat ESA-ESTEC Requirements & Standards Division Noordwijk, The Netherlands Foreword This Standard is one of

More information

PRACTICE NO. PD-ED RELIABILITY February 1996 PRACTICES PAGE 1 OF 7 COMMON REVIEW METHODS FOR ENGINEERING PRODUCTS

PRACTICE NO. PD-ED RELIABILITY February 1996 PRACTICES PAGE 1 OF 7 COMMON REVIEW METHODS FOR ENGINEERING PRODUCTS PREFERRED PRACTICE NO. PD-ED-1215.4 RELIABILITY PRACTICES PAGE 1 OF 7 COMMON REVIEW METHODS FOR Practice: Conduct technical reviews to validate engineering designs using a common, consistent approach which

More information

CHAPTER 2: IMPLEMENTATION PHASES AND OFFERINGS

CHAPTER 2: IMPLEMENTATION PHASES AND OFFERINGS CHAPTER 2: IMPLEMENTATION PHASES AND OFFERINGS Objectives Introduction The objectives are: Describe the purpose of the phase planning activity, preconditions, and deliverables in the implementation methodology.

More information

Factors to Consider When Implementing Automated Software Testing

Factors to Consider When Implementing Automated Software Testing Factors to Consider When Implementing Automated Software Testing By Larry Yang, MBA, SSCP, Security+, Oracle DBA OCA, ASTQB CTFL, ITIL V3 ITM Testing is a major component of the Software Development Lifecycle

More information

PRINCESS NOURA UNIVESRSITY. Project Management BUS 302. Reem Al-Qahtani

PRINCESS NOURA UNIVESRSITY. Project Management BUS 302. Reem Al-Qahtani PRINCESS NOURA UNIVESRSITY Project BUS 302 Reem Al-Qahtani This is only for helping reading the PMBOK it has our notes for focusing on the book Project Framework What is PMBOK? o PMBOK= Project Body of

More information

Net-Ready Key Performance Parameter (NR-KPP) Implementation Guidebook

Net-Ready Key Performance Parameter (NR-KPP) Implementation Guidebook Net-Ready Key Performance Parameter (NR-KPP) Implementation Guidebook Version 1.0 1 October 2009 Assistant Secretary of the Navy (Research, Development, and Acquisition) Chief Systems Engineer Department

More information

Market Systems Enhancement

Market Systems Enhancement Market Systems Enhancement Update for the Technology Committee MISO Board of Directors November 28, 2017 Executive Summary Market System Enhancement Program is refining its seven-year plan, including key

More information

MBA BADM559 Enterprise IT Governance 12/15/2008. Enterprise Architecture is a holistic view of an enterprise s processes, information and

MBA BADM559 Enterprise IT Governance 12/15/2008. Enterprise Architecture is a holistic view of an enterprise s processes, information and Enterprise Architecture is a holistic view of an enterprise s processes, information and information technology assets as a vehicle for aligning business and IT in a structured, more efficient and sustainable

More information

Course Title: Progressive Concepts in Program Management Course #: 6894 Duration: 4 days Delivery Method: Instructor-led live classroom

Course Title: Progressive Concepts in Program Management Course #: 6894 Duration: 4 days Delivery Method: Instructor-led live classroom Course Title: Progressive Concepts in Program Management Course #: 6894 Duration: 4 days Delivery Method: Instructor-led live classroom 1. What business or organizational need does this course address?

More information

Session 11E Adopting Agile Ground Software Development. Supannika Mobasser The Aerospace Corporation

Session 11E Adopting Agile Ground Software Development. Supannika Mobasser The Aerospace Corporation Session 11E Adopting Agile Ground Software Development Supannika Mobasser The Aerospace Corporation The Aerospace Corporation 2017 Overview To look beyond the horizon and to embrace the rapid rate of change

More information

COMPLIANCE WITH THIS PUBLICATION IS MANDATORY

COMPLIANCE WITH THIS PUBLICATION IS MANDATORY Template modified: 27 May 1997 14:30 BY ORDER OF THE SECRETARY OF THE AIR FORCE AIR FORCE INSTRUCTION 63-501 31 MAY 1994 Certified Current 4 November 2009 Acquisition AIR FORCE ACQUISITION QUALITY PROGRAM

More information

National Aeronautics and Space Administration Washington, DC 20546

National Aeronautics and Space Administration Washington, DC 20546 Technical Standards Division Publication NASA-STD-2100-91 NASA Software Documentation Standard Software Engineering Program NASA-STD-2100-91 -91 Approved: July 29, 1991 National Aeronautics and Space Administration

More information

SYSTEMS ENGINEERING REQUIREMENTS AND PRODUCTS

SYSTEMS ENGINEERING REQUIREMENTS AND PRODUCTS SMC Standard SMC-S-001 1 July 2013 ------------------------ Supersedes: SMC-S-001 (2010) Air Force Space Command SPACE AND MISSILE SYSTEMS CENTER STANDARD SYSTEMS ENGINEERING REQUIREMENTS AND PRODUCTS

More information

NDIA Systems Engineering Conference 2013 M&S Applied to Improved Test Planning & Analysis Methods in the DT & OT Execution Phase

NDIA Systems Engineering Conference 2013 M&S Applied to Improved Test Planning & Analysis Methods in the DT & OT Execution Phase Joe Murphy Analytical Graphics, Inc. jmurphy@agi.com 610 457 5002 NDIA Systems Engineering Conference 2013 M&S Applied to Improved Test Planning & Analysis Methods in the DT & OT Execution Phase Oct 30,

More information

Project Charter For Florida PALM

Project Charter For Florida PALM For Florida PALM Department of Financial Services Date: 09/15/2017 Version: 4.1 Table of Contents Project Overview... 3 Implementation Approach... 7 Project Organization Structure... 8 Assumptions...13

More information

DATA ITEM DESCRIPTION TITLE: TRAINING SITUATION DOCUMENT Number: DI-SESS-81517C Approval Date:

DATA ITEM DESCRIPTION TITLE: TRAINING SITUATION DOCUMENT Number: DI-SESS-81517C Approval Date: DATA ITEM DESCRIPTION TITLE: TRAINING SITUATION DOCUMENT Number: DI-SESS-81517C Approval Date: 20130524 AMSC Number: N9379 Limitation: N/A DTIC Applicable: N/A GIDEP Applicable: N/A Office of Primary Responsibility:

More information

Audit and Advisory Services Integrity, Innovation and Quality

Audit and Advisory Services Integrity, Innovation and Quality Audit and Advisory Services Integrity, Innovation and Quality Follow-up Progress Assessment of the Audit of IM/IT Project Life Cycle Controls 1577-13/14-101 Table of Contents EXECUTIVE SUMMARY 1 1. Introduction

More information

COMPLIANCE WITH THIS PUBLICATION IS MANDATORY

COMPLIANCE WITH THIS PUBLICATION IS MANDATORY BY ORDER OF THE COMMANDER AIR FORCE RESEARCH LABORATORY AIR FORCE RESEARCH LABORATORY INSTRUCTION 33-401 13 MARCH 2014 Communications and Information ENTERPRISE BUSINESS INFORMATION TECHNOLOGY REQUIREMENTS

More information

COMPLIANCE WITH THIS PUBLICATION IS MANDATORY

COMPLIANCE WITH THIS PUBLICATION IS MANDATORY BY ORDER OF THE SECRETARY OF THE AIR FORCE AIR FORCE MANUAL 63-119 20 JUNE 2008 SPACE AND MISSILE SYSTEMS CENTER Supplement 24 JUNE 2014 Acquisition CERTIFICATION OF SYSTEM READINESS FOR DEDICATED OPERATIONAL

More information

IT PROJECT ANALYST/MANAGER

IT PROJECT ANALYST/MANAGER IT PROJECT ANALYST/MANAGER I. DESCRIPTION OF WORK Positions in this banded class are responsible for project management work involving planning and coordination of information technology projects. To ensure

More information

SECTION C - DESCRIPTION / SPECIFICATIONS / STATEMENT OF WORK

SECTION C - DESCRIPTION / SPECIFICATIONS / STATEMENT OF WORK SECTION C - DESCRIPTION / SPECIFICATIONS / STATEMENT OF WORK C.1. OBJECTIVE The objective of OASIS is to provide Government agencies with total integrated solutions for a multitude of professional service

More information

Washington Headquarters Services ADMINISTRATIVE INSTRUCTION

Washington Headquarters Services ADMINISTRATIVE INSTRUCTION Washington Headquarters Services ADMINISTRATIVE INSTRUCTION NUMBER 94 October 19, 2007 Incorporating Change 2, July 17, 2017 DFD FSD SUBJECT: Personal Property Management and Accountability References:

More information

CMMI FOR SERVICES, THE PREFERRED CONSTELLATION WITHIN THE SOFTWARE TESTING FUNCTION OF A SOFTWARE ENGINEERING ORGANIZATION

CMMI FOR SERVICES, THE PREFERRED CONSTELLATION WITHIN THE SOFTWARE TESTING FUNCTION OF A SOFTWARE ENGINEERING ORGANIZATION CMMI FOR SERVICES, THE PREFERRED CONSTELLATION WITHIN THE SOFTWARE TESTING FUNCTION OF A SOFTWARE ENGINEERING ORGANIZATION NAME: Nestor K. Ovalle, PhD TITLE: Leadership & Corporate Change Consultant; CMMI

More information

Independent Verification and Validation (IV&V)

Independent Verification and Validation (IV&V) Independent Verification and Validation (IV&V) 12 th Annual NDIA CMMI Conference November 2012 - Denver, CO The MITRE Corporation The author s affiliation with The MITRE Corporation is provided for identification

More information

GAIA. GAIA Software Product Assurance Requirements for Subcontractors. Name and Function Date Signature 15/09/05 15/09/05 15/09/05 15/09/05 15/09/05

GAIA. GAIA Software Product Assurance Requirements for Subcontractors. Name and Function Date Signature 15/09/05 15/09/05 15/09/05 15/09/05 15/09/05 Title Page : i Software Product Assurance Requirements for Subcontractors Name and Function Date Signature Prepared by D.MUNCH Prime Contractor SPA Manager 15/09/05 Verified by D.PERKINS E-SVM PA Manager

More information

Sawdey Solution Services

Sawdey Solution Services Sawdey Solution Services I n c o r p o r a t e d COMMERCIAL PRICE LIST 2016 1430 Oak Court, Suite 304 Beavercreek, OH 45430 Office Phone: (937) 490-4060 Fax: (937) 490-4086 www.sawdeysolut ionservices.com

More information

SYSTEMS ENGINEERING PLAN (SEP) OUTLINE

SYSTEMS ENGINEERING PLAN (SEP) OUTLINE SYSTEMS ENGINEERING PLAN (SEP) OUTLINE June 2, 2015 Version 2.0 1 2 MANDATED FORMAT FOR ALL SYSTEMS ENGINEERING PLANS PROGRAM NAME ACAT LEVEL SYSTEMS ENGINEERING PLAN VERSION SUPPORTING MILESTONE _ AND

More information

ISACA. The recognized global leader in IT governance, control, security and assurance

ISACA. The recognized global leader in IT governance, control, security and assurance ISACA The recognized global leader in IT governance, control, security and assurance High-level session overview 1. CRISC background information 2. Part I The Big Picture CRISC Background information About

More information

It s about your success

It s about your success Business-IT alignment assessment Proposed approach and methodology OCTANT 1 Introduction The domain of IT Governance, business-it alignment and process optimization is one of the cornerstones of BUSINESS

More information

Latest Reliability Growth Policies, Practices, and Theories for Improved Execution

Latest Reliability Growth Policies, Practices, and Theories for Improved Execution Latest Reliability Growth Policies, Practices, and Theories for Improved Execution Lou Gullo Raytheon Missile Systems Senior Principal Engineer March 14, 2012 Copyright 2012 Raytheon Company. All rights

More information

Logistics Community of Interest 0346 Logistics Management Series Competency-Based Learning Map and Training Strategy. Page 1

Logistics Community of Interest 0346 Logistics Management Series Competency-Based Learning Map and Training Strategy. Page 1 Page 1 Competency-Based Learning Map Overview The United States Marine Corp (USMC) Logistics Community of Interest (COI) developed this competency-based learning map to support 0346 logistics management

More information

Project Management Manual Prepared by: Project Support Office, Major Projects Department

Project Management Manual Prepared by: Project Support Office, Major Projects Department Project Management Manual Prepared by: Project Support Office, Major Projects Department Version: 2015 Project Support Office Project Management Manual Version: November 2015 This manual is a living document

More information

The 9 knowledge Areas and the 42 Processes Based on the PMBoK 4th

The 9 knowledge Areas and the 42 Processes Based on the PMBoK 4th The 9 knowledge Areas and the 42 Processes Based on the PMBoK 4th www.pmlead.net PMI, PMP, CAPM and PMBOK Guide are trademarks of the Project Management Institute, Inc. PMI has not endorsed and did not

More information

Enterprise Architectures

Enterprise Architectures Enterprise Architectures A Just-in-Time Approach for Decision-Making Carlos E. Martinez The MITRE Corporation 7515 Colshire Drive McLean, Virginia 22102 March 24, 2014 Approved for Public Release; Distribution

More information

PMI - Minnesota August 14, Oh no - PMO. Presented by: Michael Vinje - PMP.

PMI - Minnesota August 14, Oh no - PMO. Presented by: Michael Vinje - PMP. PMI - Minnesota August 14, 2007 Oh no - PMO Presented by: Michael Vinje - PMP 1 mvinje@trissential.com 2005 All Rights Reserved. Agenda Presentation Objective PMO Background & Survey What The Experts Said

More information

Concept of Operations. Disaster Cycle Services Program Essentials DCS WC OPS PE

Concept of Operations. Disaster Cycle Services Program Essentials DCS WC OPS PE Concept of Operations Disaster Cycle Services Program Essentials DCS WC OPS PE October 2014 Change Log Date Page(s) Section Change Owner: Disaster Cycle Services 2 Change Log... 2 Introduction... 4 Purpose...

More information

The USDA Enterprise Architecture Program

The USDA Enterprise Architecture Program The USDA Enterprise Architecture Program Niles E Hewlett, PMP CEA Enterprise Architecture Team USDA-OCIO January 25, 2006 1 We have an Enterprise Architecture -- We just can t show it, explain it, share

More information

7/26/2016 ARETE-ZOE, LLC 1

7/26/2016 ARETE-ZOE, LLC 1 Registered address: 1334 E Chandler Blvd 5 A-19, Phoenix 85048 Arizona, USA T: +1-480-409-0778 Skype: arete-zoe veronikav@arete-zoe.com Website SlideShare 7/26/2016 ARETE-ZOE, LLC 1 RISK MANAGEMENT PROCESS

More information

Internal Audit of ICT Governance in WFP. Office of the Inspector General Internal Audit Report AR/15/11

Internal Audit of ICT Governance in WFP. Office of the Inspector General Internal Audit Report AR/15/11 Fighting Hunger Worldwide Internal Audit of ICT Governance in WFP Office of the Inspector General Internal Audit Report AR/15/11 Contents Page I. Executive summary 3 II. Context and scope 5 III. Results

More information

Organization Name: Rockwell Collins Program Name: KC-46 Tanker. Sub-System R&D/SDD program or project

Organization Name: Rockwell Collins Program Name: KC-46 Tanker. Sub-System R&D/SDD program or project I. Program Overview Organization Name/Program Name: Program Leader Name/ Position/Contact information E-mail, Phone Program Category Organization Name: Rockwell Collins Program Name: KC-46 Tanker Program

More information

Advantages and Disadvantages of. Independent Tests. Advantages. Disadvantages

Advantages and Disadvantages of. Independent Tests. Advantages. Disadvantages 8.0 Test Management Outline 8.1 Test organisation 8.2 Test planning and estimation 8.3 Test program monitoring and control 8.4 Configuration management 8.5 Risk and testing 8.6 Summary Independent Testing

More information

Aeronautical Systems Center

Aeronautical Systems Center Aeronautical Systems Center Emerging Policy 12 May 09 John Brannan Dave Pressler ASC/AQ john.brannan@wpafb.af.mil david.pressler@wpafb.af.mil Report Documentation Page Form Approved OMB No. 0704-0188 Public

More information

ACQ202 Intermediate Systems Acquisitions Course (ISAC)

ACQ202 Intermediate Systems Acquisitions Course (ISAC) Intro ductio n ~ I Page l of 33 I ~ Introduction Closed captioning In this lesson we will follow IPPD tenets and use an IPT to assist in formulating the acquisition strategy for the Firebird program. This

More information

Leveraging Your Service Quality Using ITIL V3, ISO and CMMI-SVC. Monday Half-Day Tutorial

Leveraging Your Service Quality Using ITIL V3, ISO and CMMI-SVC. Monday Half-Day Tutorial Leveraging Your Service Quality Using ITIL V3, ISO 20000 and CMMI-SVC Monday Half-Day Tutorial Definitions Service - Employment in duties or work for another The Challenge This situation where organization

More information

Development, Validation and Implementation Considerations of a Decision Support System for Unmanned & Autonomous System of Systems Test & Evaluation

Development, Validation and Implementation Considerations of a Decision Support System for Unmanned & Autonomous System of Systems Test & Evaluation Development, Validation and Implementation Considerations of a Decision Support System for Unmanned & Autonomous System of Systems Test & Evaluation Test Week 2010 Kris Cowart, Maj, USAF Ricardo Valerdi,

More information

Improving Our Leaders Ability to Understand and Manage Risks, Issues, and Opportunities

Improving Our Leaders Ability to Understand and Manage Risks, Issues, and Opportunities Improving Our Leaders Ability to Understand and Manage Risks, Issues, and Opportunities Mr. Chris DeLuca Office of the Deputy Assistant Secretary of Defense for Systems Engineering 18th Annual NDIA Systems

More information

ISO/IEC JTC1/SC7 N2683

ISO/IEC JTC1/SC7 N2683 ISO/IEC JTC1/SC7 Software & System Engineering Secretariat: CANADA (SCC) ISO/IEC JTC1/SC7 N2683 2002-07-25 Document Type PDTR Ballot Title PDTR 19760 Systems Engineering Guide for ISO/IEC 15288 (System

More information

DATA ITEM DESCRIPTION

DATA ITEM DESCRIPTION DATA ITEM DESCRIPTION Title: HUMAN SYSTEMS INTEGRATION PROGRAM PLAN Number: Approval Date: 20070404 AMSC Number: N7716 Limitation: N/A DTIC Applicable: N/A GIDEP Applicable: N/A Office of Primary Responsibility:

More information

Project Scope Management

Project Scope Management Assalam-o-alaikum Project Management Process Groups Project Integration Management Knowledge Areas Initiating Planning Executing Scope Time Cost Quality Human Resources Communications Monitoring & Controlling

More information

Open Government Implementation Plan (OGIP)

Open Government Implementation Plan (OGIP) Transportation Safety Board of Canada Bureau de la sécurité des transports du Canada Open Government Implementation Plan (OGIP) October 2015 Table of Contents 1. Purpose... 3 2. Approval... 3 3. Context...

More information

Oregon Department of Transportation. Geographic Information Systems. Implementation Plan

Oregon Department of Transportation. Geographic Information Systems. Implementation Plan Oregon Department of Transportation Systems Implementation Plan January Introduction Access to information is the key component driving ODOT s GIS goals. Most forms of information can be related to a geographic

More information

Information Technology Services Project Management Office Operations Guide

Information Technology Services Project Management Office Operations Guide Information Technology Services Project Management Office Operations Guide Revised 3/31/2015 Table of Contents ABOUT US... 4 WORKFLOW... 5 PROJECT LIFECYCLE... 6 PROJECT INITIATION... 6 PROJECT PLANNING...

More information

DoD DMSMS Conference: Lifecycle Management Panel

DoD DMSMS Conference: Lifecycle Management Panel DoD DMSMS Conference: Lifecycle Management Panel RADM Charles Hamilton, PEO Ships 11 July 2006 Distribution Statement A: Approved for Public Release; Distribution Unlimited. (7/13/2006). This Brief is

More information

NATIONAL EXPORT STRATEGY

NATIONAL EXPORT STRATEGY NATIONAL EXPORT STRATEGY BUILDING AN EXPORT CULTURE This document is for discussion purposes only and does not imply any engagement or liability on the part of the International Trade Centre (ITC). Copyright

More information

RESEARCH REPORT. Includes complete survey data. Project Management Maturity & Value Benchmark

RESEARCH REPORT. Includes complete survey data. Project Management Maturity & Value Benchmark RESEARCH REPORT Includes complete survey data Project Management Maturity & Value Benchmark 2014 2 Project Management Maturity & Value Benchmark 2014 Introduction PM Solutions Research first surveyed organizations

More information

Document Revision History

Document Revision History Document Revision History Version Date Author Change Description 1.0 July 2015 Capt. Christina Felkins Initial creation 2.0 November 2015 Diana Lamonica 1 st Revision Strategic Goals and Communication

More information