OPTIMIZATION OF PLANNING, SCHEDULING, AND CONTROL OF HIGH RISE CONSTRUCTION PROJECTS
|
|
- Helen Parsons
- 6 years ago
- Views:
Transcription
1 International Journal of Civil Engineering and Technology (IJCIET) Volume 9, Issue 4, April 2018, pp , Article ID: IJCIET_09_04_102 Available online at ISSN Print: and ISSN Online: IAEME Publication Scopus Indexed OPTIMIZATION OF PLANNING, SCHEDULING, AND CONTROL OF HIGH RISE CONSTRUCTION PROJECTS S.M.B.Jaswanth, P.G Student, Department of Civil Engineering, Koneru Lakshmaiah Educational Foundation, Vaddeswaram, Guntur, Andhra Pradesh, India. P. Sundara Kumar Professor, Department of Civil Engineering, Koneru Lakshmaiah Educational Foundation, Vaddeswaram, Guntur, Andhra Pradesh, India. ABSTRACT Nowadays in the construction industry is delaying due to inappropriate planning and scheduling with the help of P6 software it can achieve the appropriate planning and scheduling still many construction companies are following the traditional way of planning but few companies are using P6software. In olden days planning takes more time and with the help of P6 software, time is minimized during the planning stage. This study deals with the optimization of planning and scheduling method can be explained and how much time can be saved. The main objective of the research is to detect the scheduling technique followed by the organization, to develop the critical path method and to investigate the errors in planning and scheduling. KEY WORDS: Planning, Scheduling, P6 software, Optimization, Critical path method. Cite this Article: S.M.B.Jaswanth and P. Sundara Kumar, Optimization of Planning, Scheduling, and Control of High Rise Construction Projects, International Journal of Civil Engineering and Technology, 9(4), 2018, pp INTRODUCTION In construction industries, all construction projects are time bound and directed achieve the project objectives with respect to time and quality. Project management is the procedure of collection of data, recording the data and reporting the data allowing to the performance of the project. Planning and scheduling aim at the suitable execution of work according to project plan schedule and can apply remedial measures in the event of any several deviations occur. Monitoring the progress of the project with respect to the time, Performance, scheduling and resources throughout the actual implementation of the project and can identify the delay area which requires timely proceedings to be taken. The task of finishing off a construction site editor@iaeme.com
2 Optimization of Planning, Scheduling, and Control of High Rise Construction Projects within an estimated time is the most crucial task among the project managers. Unavoidable delays and cost in projects may happen due to improper coordination and communication between the line managers. These constrain make project management makes a difficult task.(unmesh 2015) said that in his project by using P6 software and accomplished by data collection of three main aspects such as by taking a day to day reports, labor-work output, activities are running agreeing to their planned duration. (EsakkiThanga 2016) explains that p6 software that develops the quality and the construction management with effective cost and time within the sequences and minimum resources. (Subramanian 2015) says that IBS (Industrial building system) is best time-saving technique and this method does not have enough popular and compares with the conventional method. And with the help of Primavera software many industries got helpful for their planning and scheduling. (Siva Nagaraju 2016) said that performance of Primavera software for metro rail projects to reduce the delays in the project. In past days it required more paper work at the planning stage itself. So, at the present globalization scenario by using P6 software delays can be minimizing by planning and scheduling stage. (Satish Chandra 2017) said that M.S.P software will consider every aspect of planning stage itself and scheduling and take accountability for every activity which can be easily analyzed. (Vijay 2016) states that project delays may occur due to the inadequate and timely supply of resources this can be overcome by proper planning and scheduling techniques by using the P6 software. (Rajendra 2016) said that with the help of P6 software multiple projects can be managed easily and resource optimization can be done for each project and can be compared so that the postponements can be recognized. (Hammed Ziaiadoostan 2013) said that based on personal or political factors strategic management is not implemented resources are assigned to some of the organizations. So by using resource distribution primavera software can be done, resources can be allocated in an effective manner. (Patil 2013) said that to achieve the profit with in limited time and funds some construction activities can be managed. In 1970' s some of the management methods, for instance, PERT, CPM has implemented in various projects. (Uma 2016) said that planning and scheduling plays an important role in various projects due to increasing in complexities in the construction field for scheduling and planning the huge amount of paperwork will take, to reduce these problems primavera software can be used. 2. NEED FOR STUDY Using P6 software scheduling is done, delays can be identified and optimization is done for each activity. Corrective events have been suggested. 3. OBJECTIVES 1. To identify scheduling method used by the organization in developing plan and schedule. 2. To develop a schedule and determine the CPM using Primavera software. 3. To investigate faults in the planning and scheduling procedure. 4. To follow and optimize the project and estimation is done. 4. RESEARCH METHODOLOGY This research methodology gives a guide to achieve the objectives of the study and discuss the detail procedure. The research methodology helps to understand the problems that are a time constraint, objectives of the study. A literature analysis is collected from several journals, articles, books. A G+6 building is selected as a study area and detail schedules are collected from the site and with the help of P6 software analysis is done. With the aid of critical path method scheduling is prepared. Finally, optimization is done and budget is prepared editor@iaeme.com
3 S.M.B.Jaswanth and P. Sundara Kumar Literature review Selection of study area Data collection and data analysis Study primavera software Define work break down structure List out all the activities in detail With the help of critical path method prepare detail planning and scheduling Develop scheduling by primavera software Optimiztion of duration Budget is prepared Figure 1 Flowchart proposed a research methodology 4.1. Steps involved in the Primavera software 1) Creating the schedule To form a schedule for a project first, we have to gather the data for the project. The next steps to follow in P6 software. 2) Enterprise Structure (EPS) Create a complete arrangement of a company with its subdivisions, which is executed in Primavera software. This is known enterprise structure. 3) Organization Breakdown Structure (OBS) In this structure, it represents the entire management responsibilities of the project editor@iaeme.com
4 Optimization of Planning, Scheduling, and Control of High Rise Construction Projects 4) Creating calendar In this step, we have to create our own calendar in these working hours to be given. 5) Creating a new project In this step, we have to form a new project. In this, we will give the project details and we will give the relation between the EPS and OBS. 6) Work break down structure (WBS) In this step the works of the project to break down into a stepwise step structure in detail of the project. 7) Define activities In this step activities are the fundamental key work of the project. Project activity contains some characteristics like activity calendar, activity name, activity type, activity code, activity ID etc. 8) Define the relationship between the activities There are four relations. They are Finish-start relationship(fs) Start-start relationship(ss) Finish-finish relationship(fs) Start-finish relationship(sf) 9) Activity duration In this step time of each activity is calculated in the project. 10) Activity cost The total expenditure of each activity is calculated and given in the project. 5. RESULTS AND DISCUSSION At present scenario of all construction companies main aim is to achieve the project within the stipulated time and with the available resources helps financial and accomplish the project with profitably. To come across the schedule quality of the project is done by using various techniques established in the recent developments in the construction field. Improvising the project with critical path method using the Primavera software. Reducing the wastage of resources and budget. Fig. 2 explains the overall structure of the project detailly. Fig. 3 to Fig.5 gives the details of each activity with there duration and estimation is done in this duration is not optimized.fig. 6 to Fig. 8 gives the details of each activity with there duration and estimation is done optimization technique is done and finally, the duration is decreased editor@iaeme.com
5 S.M.B.Jaswanth and P. Sundara Kumar Figure 2 Work break down the structure Figure 3 Scheduling without optimization editor@iaeme.com
6 Optimization of Planning, Scheduling, and Control of High Rise Construction Projects Figure 4 scheduling without optimization Figure 5 scheduling without optimization editor@iaeme.com
7 S.M.B.Jaswanth and P. Sundara Kumar Figure 6 Scheduling with optimization Figure 7 Scheduling with optimization editor@iaeme.com
8 Optimization of Planning, Scheduling, and Control of High Rise Construction Projects Figure 8 Scheduling with optimization 6. CONCLUSION Based on the study approved the best features of Primavera software in schedule controller techniques, it is concluded that primavera software can be used to schedule the project and reduce project duration in the construction project. This research helps to identify the defects in planning, scheduling process of the organization. A perfectly planned project helps in reducing the loss of cost and time. Primavera software is a user-friendly which provides user to perform any type of task, the cost of any individual work break down a structure can be known along with duration. With help of Primavera software, 6% of the schedule has been optimized compared to the originally planned schedule. After optimization of cost, there is a variance of 2.9% in the cost compared to the originally planned budget. REFERENCES [1] Unmesh. Y. Polekar(2015),"Planning, Scheduling, and Tracking of a residential Project using Primavera Software", International Journal of advanced research in computer science and management studies, 3(5), pp: [2] P. EssakiThangam(2016),"Planning, Scheduling and Time management of six lanes road construction work at V.O.C port trust using primavera", International Journal of Science Technology and Engineering, 2(11), pp: editor@iaeme.com
9 S.M.B.Jaswanth and P. Sundara Kumar [3] T.Subramani, (2015), "Construction Management and Scheduling of residential building using primavera", International Journal of application in engineering and management, 4(5), pp: [4] T. SivaNagaraju, (2016), "Schedule and Resources Optimization using primavera in Metro Rail Project", International Journal of Mechanical and Production Engineering, 4(7), pp: [5] SatishChandra, (2017), "Optimal Planning and scheduling of high rise buildings", International Journal of civil engineering and technology, 8(1), pp: [6] Vijay. K, (2016), "Planning, Scheduling and Resource optimization of multiple projects using Oracle Primavera", International Journal of research in engineering and technology, 5(6), pp: [7] Ragendra, (2016), "Schedule Control of an Apartment Building using Primavera Techniques", International Journal of engineering research and technology, 5(6), pp: [8] HamedZiaidoostan, (2013), "Using Primavera software in resource allocation and project evaluation of construction projects", Interdisciplinary Journal of contemporary research in business, 4(12), pp: [9] Patil, (2013), "Resource Scheduling of construction project: a case study", International Journal of science and research, 4(5), pp: [10] Uma, (2016), "Review of project management software's- Msproject and primavera", International research journal of engineering and technology, 3(11), pp: [11] B. Sasikala and Dr. V.P. Eswaramurthy Ant Based Multi Attribute Job Shop Scheduling of Identical Machines, International Journal of Mechanical Engineering and Technology 8(12), 2017, pp [12] Dr. R. Dillibabu and Suresh. K, Development of Multi-Agent Systems Based Intelligent Fleet Maintenance Scheduling International Journal of Industrial Engineering Research and Development (IJIERD), Number 1, May - June (2010), pp [13] Dr. Sridhar K and Prakash T. Lazarus, Experimental Design of Constraint Satisfaction Adaptive Neural Network for Generalized Job-Shop Scheduling International Journal of Industrial Engineering Research and Development (IJIERD), Volume 5, Issue 3, May - June (2014), pp [14] S. K. Gupta, Dr. V. K. Mahna, Dr. R. V. Singh and Rajender Kumar, Optimizing the Unevenness in Production Scheduling Through Mathematical Approach: A Case Study International Journal of Industrial Engineering Research and Development (IJIERD), Volume 3, Issue 1, January- June (2012), pp [15] K. Mallikarjuna, V. Veeranna and K. Hemachandra Reddy, Performance of Metaheuristic Methods for Loop Layout Design in Flexible Manufacturing System with Integrated Scheduling International Journal of Production Technology and Management (IJPTM), Volume 4, Issue 1, January - April (2013), pp editor@iaeme.com
Construction Project Scheduling of MK Apartment Using MS Project 2013
Construction Project Scheduling of MK Apartment Using MS Project 2013 Monish Kumar K 1, Maheshwar S Maregoudru 2, Sparsha B.P 3 1,2 PG Student, Dept. of Civil Engineering, KVGCE, Sullia, Karnataka, India
More informationRESOURCE OPTIMIZATION IN CONSTRUCTION OF A RESIDENTIAL APARTMENT USING PRIMAVERA P-6 SOFTWARE
RESOURCE OPTIMIZATION IN CONSTRUCTION OF A RESIDENTIAL APARTMENT USING PRIMAVERA P-6 SOFTWARE BHAJANTHRI THIRUMALESHA 1, RAJANI V.AKKI 2,BASAVARAJ BAVI 3 1 P.G. Student, Civil Engineering Department, Shree
More informationOPTIMAL RESOURCES UTILIZATION IN CONSTRUCTION INDUSTRY
International Journal of Civil Engineering and Technology (IJCIET) Volume 8, Issue 1, January 2017, pp. 273 280, Article ID: IJCIET_08_01_029 Available online at http://www.iaeme.com/ijciet/issues.asp?jtype=ijciet&vtype=8&itype=1
More informationProgram Evaluation and Review Technique (PERT)
Program Evaluation and Review Technique (PERT) PERT Bar charts and CPM networks assume all activity durations are constant or deterministic. The assumption of constant durations may not be realistic because
More informationPrimavera P6 R8.3 Professional Fundamentals Training Course Outline
Course Overview Prescience Technology is an Oracle Platinum Partner and specialist provider of Primavera Services. This Prescience course introduces the user to Oracle Primavera P6 version 8.3 Professional
More informationPLANNING, SCHEDULING, TRACKING OF RESIDENTIAL BUILDING USING PRIMAVERA SOFTWARE P6
PLANNING, SCHEDULING, TRACKING OF RESIDENTIAL BUILDING USING PRIMAVERA SOFTWARE P6 Mrs. SANGEETHA H M 1,Mr. RAJEEVA S J 2,Dr. G.NARAYANA 3 1 PG STUDENT, Department of Civil Engineering, SJCIT Chickballapur,
More informationPrimavera Training - P6 Basic Course (102)
Primavera Training - P6 Basic Course (102) This training session provides hands-on training for Primavera s client/server-based solution, leading participants through the entire project life cycle, from
More informationA CASE STUDY ON REQUIREMENTS OF QUALITY WORKMANSHIP IN CONSTRUCTION PROJECTS
International Journal of Civil Engineering and Technology (IJCIET) Volume 8, Issue 4, April 2017, pp. 1061 1067, Article ID: IJCIET_08_04_119 Available online at http://www.iaeme.com/ijciet/issues.asp?jtype=ijciet&vtype=8&itype=4
More information3-Day Oracle Primavera P6 Professional Fundamentals - Training Outline -
3-Day Oracle Primavera P6 Professional Fundamentals - Training Outline - PREPARED BY: Jessica Summers Virtual Training Coordinator PPM Global Services, Inc. P: 1-800-746-4029 x 310 F: 1-800-746-4029 E:
More informationProject Planning and Control Using Oracle Primavera P6 : P8.3, 8.4, 15.2
Primavera Essential Course Contents: 1. Overview Describe the Primavera modules Explain the difference between global and project-specific data Project Portfolio Management Defining the Enterprise Project
More informationProject Planning, Scheduling and Preparation of Quality Assurance Control Documents
Project Planning, Scheduling and Preparation of Quality Assurance Control Documents J.SHARANYASREENIVAS 1, G.GAJALAKSHMI 2, K.RAVI THEJA 3 1P.G Student M.Tech (Structural Engg. and construction managment),
More informationFor the PMP Exam using PMBOK Guide 5 th Edition. PMI, PMP, PMBOK Guide are registered trade marks of Project Management Institute, Inc.
For the PMP Exam using PMBOK Guide 5 th Edition PMI, PMP, PMBOK Guide are registered trade marks of Project Management Institute, Inc. 1 Contacts Name: Khaled El-Nakib, MSc, PMP, PMI-RMP URL: http://www.khaledelnakib.com
More informationBLAST ANALYSIS AND BLAST RESISTANT DESIGN OF R.C.C RESIDENTIAL BUILDING
International Journal of Civil Engineering and Technology (IJCIET) Volume 8, Issue 3, March 17, pp. 761 770 Article ID: IJCIET_08_03_076 Available online at http://www.iaeme.com/ijciet/issues.asp?jtype=ijciet&vtype=8&itype=3
More informationEstimating Project Schedule-Time and Cost
Estimating Project Schedule-Time and Cost Chapter 5 5 1 Where We Are Now 5 2 1 Overview Seminar Agenda What is involved in schedule and cost management? In-depth Determining the sequence of activities
More informationANALYSIS OF MULTISTORIED BUILDING WITH AND WITHOUT FLOATING COLUMN USING ETABS
International Journal of Civil Engineering and Technology (IJCIET) Volume 8, Issue 6, June 2017, pp. 91 98, Article ID: IJCIET_08_06_011 Available online at http://www.iaeme.com/ijciet/issues.asp?jtype=ijciet&vtype=8&itype=6
More informationWATER QUALITY SCENARIO OF URBAN POLLUTED LAKES A MODEL STUDY
International Journal of Civil Engineering and Technology (IJCIET) Volume 8, Issue 5, May 2017, pp. 297 302, Article ID: IJCIET_08_05_033 Available online at http://www.iaeme.com/ijciet/issues.asp?jtype=ijciet&vtype=8&itype=5
More informationCOMPARATIVE STUDY ON REGULAR & IRREGULAR STRUCTURES USING EQUIVALENT STATIC AND RESPONSE SPECTRUM METHODS
International Journal of Civil Engineering and Technology (IJCIET) Volume 8, Issue 1, January 2017, pp. 615 622 Article ID: IJCIET_08_01_071 Available online at http://www.iaeme.com/ijciet/issues.asp?jtype=ijciet&vtype=8&itype=1
More informationLessons Learned Schedule Updating and Maintenance using Primavera P6 Hannah Schumacher, PSP, PMI-SP, LEED AP Hill International
Schedule Updating and Maintenance using Primavera P6 Hannah Schumacher, PSP, PMI-SP, LEED AP Hill International Charlie Jackson, PSP, Primavera Certified Trainer Hill International Construction CPM Conference
More informationStructured Approach to Project Execution, Monitoring and Control at Operational Level
MANAGEMENT SCIENCE AND ENGINEERING Vol. 5, No. 1,, pp. 10-18 www.cscanada.org ISSN 1913-0341 [Print] ISSN 1913-035X [Online] www.cscanada.net Structured Approach to Project Execution, Monitoring and Control
More informationDESIGN AND OPTIMISATION OF ROLLER CONVEYOR SYSTEM
International Journal of Mechanical Engineering and Technology (IJMET) Volume 9, Issue 4, April 2018, pp. 116 125, Article ID: IJMET_09_04_014 Available online at http://www.iaeme.com/ijmet/issues.asp?jtype=ijmet&vtype=9&itype=4
More informationDEVELOPMENT OF RISK-BASED STANDARDIZED WBS (WORK BREAKDOWN STRUCTURE) FOR COST ESTIMATION OF APARTMENT S PROJECT
International Journal of Civil Engineering and Technology (IJCIET) Volume 8, Issue 10, October 2017, pp. 822 833, Article ID: IJCIET_08_10_087 Available online at http://http://www.iaeme.com/ijciet/issues.asp?jtype=ijciet&vtype=8&itype=10
More informationJust like QUALITY Good Project Management Practices start with an Internal Kick-Off Meeting. It is the Project Managers job to communicate:
Just like QUALITY Good Project Management Practices start with an Internal Kick-Off Meeting It is the Project Managers job to communicate: What is the team trying to accomplish? How the team is going to
More informationIJSRD - International Journal for Scientific Research & Development Vol. 5, Issue 06, 2017 ISSN (online):
IJSRD - International Journal for Scientific Research & Development Vol. 5, Issue 06, 2017 ISSN (online): 2321-0613 Integrated Approach of Planning, Scheduling & Resource Management of a G+2 Residential
More informationPlanning & Scheduling CSTM 102
Planning & Scheduling CSTM 102 Items Big A Project on Website Thursday Discuss Big A Project next Tuesday April 18, 2011 CPM Scheduling You were the successful bidder! What s next? Procurement/Buy
More informationPERFORMANCE MEASUREMENT OF RESIDENTIAL PROJECTS IN INDIA: A BALANCED SCORECARD APPROACH
International Journal of Civil Engineering and Technology (IJCIET) Volume 7, Issue 6, November-December 2016, pp. 698 706, Article ID: IJCIET_07_06_077 Available online at http://www.iaeme.com/ijciet/issues.asp?jtype=ijciet&vtype=7&itype=6
More informationPMP Sample Questions Click here for PMP Questions. Question No : 1 Which of the following is an output of Define Scope?
PMP Sample Questions www.techfaq360.com Click here for 1600+ PMP Questions Question No : 1 Which of the following is an output of Define Scope? A. Accepted deliverables B. Change Requests C. Project document
More informationROLE OF EFFECTIVE LEADERSHIP ON PERFORMANCE MANAGEMENT SYSTEM-A STUDY IN BANKING SECTOR IN KRISHNA DISTRICT
International Journal of Civil Engineering and Technology (IJCIET) Volume 9, Issue 4, April 2018, pp. 308 319, Article ID: IJCIET_09_04_034 Available online at http://www.iaeme.com/ijciet/issues.asp?jtype=ijciet&vtype=9&itype=4
More informationJOB CREATION AND TRANSFORMATION OF UNSKILLED WOMEN FORCE -A CASE STUDY IN MANUFACTURING INDUSTRY
International Journal of Mechanical Engineering and Technology (IJMET) Volume 9, Issue 1, January 2018, pp. 655 660 Article ID: IJMET_09_01_071 Available online at http://www.iaeme.com/ijmet/issues.asp?jtype=ijmet&vtype=9&itype=1
More informationJOB SEQUENCING & WIP LEVEL DETERMINATION IN A CYCLIC CONWIP FLOWSHOP WITH BLOCKING
International Journal of Mechanical Engineering and Technology (IJMET) Volume 8, Issue 9, September 2017, pp. 274 280, Article ID: IJMET_08_09_029 Available online at http://www.iaeme.com/ijmet/issues.asp?jtype=ijmet&vtype=8&itype=9
More informationSTRUCTURAL BEHAVIOUR OF HOLLOW STEEL SECTIONS UNDER COMBINED AXIAL COMPRESSION AND BENDING
International Journal of Civil Engineering and Technology (IJCIET) Volume 8, Issue 3, March 2017, pp. 868 877 Article ID: IJCIET_08_03_087 Available online at http://www.iaeme.com/ijciet/issues.asp?jtype=ijciet&vtype=8&itype=3
More informationWelcome to the Eastwood Harris Pty Ltd Primavera P6 Versions 8.2 EPPM Web Tool 2 day training course Enterprise Portfolio Project Management
Welcome to the Eastwood Harris Pty Ltd Primavera P6 Versions 8.2 EPPM Web Tool 2 day training course Enterprise Portfolio Project Management Page 2 Copyright Eastwood Harris Pty Ltd IMPORTANT POINTS FOR
More informationUnderstanding Import & Export with NetPoint 4.2
Understanding Import & Export with NetPoint 4.2 Eric Lowther PMA Consultants 1 Primary Differences Regarding Import/ Export CPM Tools F9 and Early/Late Dates Float & Total Float Gantt Charts (Waterfall
More informationBEHAVIOUR OF M20 GRADE CONCRETE AT DIFFERENT TEMPERATURES
International Journal of Civil Engineering and Technology (IJCIET) Volume 8, Issue 3, March 2017, pp. 1043 1048 Article ID: IJCIET_08_03_106 Available online at http://www.iaeme.com/ijciet/issues.asp?jtype=ijciet&vtype=8&itype=3
More informationCLASSIFICATION OF PRODUCTION SYSTEMS
CLASSIFICATION OF PRODUCTION SYSTEMS Assistant Professor Industrial Engineering Branch Department of Production Engineering and Metallurgy University of Technology Baghdad - Iraq dr.mahmoudalnaimi@uotechnology.edu.iq
More informationMEASURING CUSTOMER SATISFACTION TOWARDS ATM SERVICES - A COMPARATIVE STUDY OF UNION BANK OF INDIA AND YES BANK
Volume 3, Issue 7 (July, 2014) Online ISSN-2277-1166 Published by: Abhinav Publication Abhinav National Monthly Refereed Journal of Research in MEASURING CUSTOMER SATISFACTION TOWARDS ATM SERVICES - A
More informationAnalyzing the Various Factors Affecting Lobour Productivity in Construction Industry
Volume-7, Issue-2, March-April 2017 International Journal of Engineering and Management Research Page Number: 143-148 Analyzing the Various Factors Affecting Lobour Productivity in Construction Industry
More informationAACE Planning and Scheduling Professional (PSP) Certification Preparation Training Course Brochure and Competency Matrix
AACE Planning and Scheduling Professional (PSP) Certification Preparation Training Course Brochure and Competency Matrix INDEX: 1. Course Description 2. Course Development 3. Certifications offered by
More informationAnalysis on the Logistics Cost Control of Self-Logistics System in the Electric Business Enterprise
American Journal of Industrial and Business Management, 2016, 6, 1113-1121 http://www.scirp.org/journal/ajibm ISSN Online: 2164-5175 ISSN Print: 2164-5167 Analysis on the Logistics Cost Control of Self-Logistics
More informationGuten Tag. (good day)
Guten Tag (good day) Project Management Process Groups Project 4. Integration Management Knowledge Areas 13. Stakeholder Initiating Planning Executing 5. Scope 6. Time 7. Cost 8. Quality 9. Human Resources
More informationPMI Scheduling Professional (PMI-SP)
PMI Scheduling Professional (PMI-SP) E X A M I N AT I O N CO N T E N T O U T L I N E Project Management Institute PMI Scheduling Professional (PMI-SP) Exam Content Outline Published by: Project Management
More informationSession 5 - MECHANICAL ENGINEERING PROFILE, ITS IMPORTANCE AND APPLICATION
INTRO TO INDUSTRIAL ENGINEERING SESSION 5 1 Session 5 - MECHANICAL ENGINEERING PROFILE, ITS IMPORTANCE AND APPLICATION Definition of Industrial Engineering The formal definition of industrial engineering
More informationApplication & Management of CPM Schedules
Application & Management of CPM Schedules Matthew Milliet James Construction Group, LLC 2009 Louisiana Transportation Conference Session 60 Project Scheduling DISCLAIMER The following is intended to outline
More informationISSN: (Online) Volume 3, Issue 6, June 2015 International Journal of Advance Research in Computer Science and Management Studies
ISSN: 2321-7782 (Online) Volume 3, Issue 6, June 2015 International Journal of Advance Research in Computer Science and Management Studies Research Article / Survey Paper / Case Study Available online
More informationCauses and Effects of Cost Overrun On Construction Projects in Madhya Pradesh
Causes and Effects of Cost Overrun On Construction Projects in Madhya Pradesh Santosh kumar prajapati, Rakesh Gupta, Mukesh Pandey M. Tech Student, Assistant Professor, Head of civil Engineering department
More informationΑππλιχατιονσ βασεδ ον Σουρχε οφ Αππλιχατιον
Applications based on Nature of Processing This is the way an application updates data, say in batch processing, there is a time delay in occurrence and recording of transaction. On the other hand in online
More informationDEADLOCK AVOIDANCE AND RE-ROUTING OF AUTOMATED GUIDED VEHICLES (AGVS) IN FLEXIBLE MANUFACTURING SYSTEMS (FMS)
DEADLOCK AVOIDANCE AND RE-ROUTING OF AUTOMATED GUIDED VEHICLES (AGVS) IN FLEXIBLE MANUFACTURING SYSTEMS (FMS) MD. Saddam Hussain 1, B. Satish Kumar 2, Dr. G.Janardhana Raju 3 Email: 1 Saddam.mohd321@gmail.com,
More informationScope Management 3/11/2015. Chapter 5 Learning Objectives. Project Scope. 1) Conceptual development. Problem Statements. Statement of Work (SOW)
Chapter 5 Learning Objectives Scope Management 05-01 Project Scope 05-02 Conceptual Development The process that addresses project objectives by finding the best ways to meet them. Project scope is everything
More informationCHAPTER 1. Basic Concepts on Planning and Scheduling
CHAPTER 1 Basic Concepts on Planning and Scheduling Eugénio Oliveira Scheduling, FEUP/PRODEI /MIEIC 1 Planning and Scheduling: Processes of Decision Making regarding the and ordering of activities as well
More informationCOST LOADED CONSTRUCTION SCHEDULES PART 1 - GENERAL
SECTION 01310 COST LOADED CONSTRUCTION SCHEDULES PART 1 - GENERAL 1.01 SCOPE: A. COST LOADED CONSTRUCTION SCHEDULE (Construction Schedule): The WORK under this Contract shall be planned, scheduled, executed,
More informationP6 Instructors Sample Presentation
Welcome to the Eastwood Harris Pty Ltd Primavera P6 Versions 8.1 to 8.4 Professional and Optional Client 3 day training course PMI REP No 3001 Course Number PP6 Page 2 Page 4 Administration Evacuation
More informationINTERIOR DESIGN AND CONSTRUCTION PROJECT MANAGEMENT: PERFORMANCE AND PRODUCTIVITY IN MALAYSIAN BUILDING INDUSTRY
JOURNAL OF ARCHITCTURE, PLANNING & CONSTRUCTION MANAGEMENT Volume 6 Issue 1, 2016 INTERIOR DESIGN AND CONSTRUCTION PROJECT MANAGEMENT: PERFORMANCE AND PRODUCTIVITY IN MALAYSIAN BUILDING INDUSTRY International
More informationCourse Outline. TEC D 205 Engineering Tech Project Planning Olympic College Bremerton, WA. Week 1 Chapter 4: DEFINING THE PROJECT
Course Outline TEC D 205 Engineering Tech Project Planning Week 1 Chapter 4: DEFINING THE PROJECT 1. Step one: Defining the Project Scope A. Employing a Project Scope Checklist 1. Project objective 2.
More informationBIG DATA ANALYTICS: WHAT IT IS AND WHAT IT ISN T, CHARACTERISTICS, CLASSIFICATION, CHALLENGES AND IMPORTANCE
International Journal of Computer Engineering & Technology (IJCET) Volume 8, Issue 6, Nov-Dec 2017, pp. 60 66, Article ID: IJCET_08_06_007 Available online at http://www.iaeme.com/ijcet/issues.asp?jtype=ijcet&vtype=8&itype=6
More informationEFFECTS OF PRICE AND ECONOMIC FACTORS ON THE DEMAND OF PRIVATE CARS IN JAKARTA INDONESIA
International Journal of Civil Engineering and Technology (IJCIET) Volume 8, Issue 8, August 2017, pp. 724 730, Article ID: IJCIET_08_08_073 Available online at http://http://www.iaeme.com/ijciet/issues.asp?jtype=ijciet&vtype=8&itype=8
More informationViews and Layouts for Program Management
MnDOT Project Management Office Presents: Views and Layouts for Program Management Presenter: Jonathan McNatty Senior Schedule Consultant DRMcNatty & Associates, Inc. Housekeeping Items Lines will be muted
More informationP6 Version 8.2 to 8.4 EPPM Web Power Sample Point Slide Show
THIS SLIDE REQUIRES NEW PICTURE Welcome to the Eastwood Harris Pty Ltd Primavera P6 Version 8.4 EPPM Web Tool 2 day training course Enterprise Portfolio Project Management Page 2 Administration Evacuation
More informationWelcome to the Eastwood Harris Pty Ltd Primavera P6 Version 7 and Earlier Versions 3 day training course
Welcome to the Eastwood Harris Pty Ltd Primavera P6 Version 7 and Earlier Versions 3 day training course PMI REP No 3001 Course Number PP6 Administration Evacuation Timings and meals Facilities Mobile
More informationRole of Civil Engineering for Smart City Development: A Review
International Journal of Innovations in Engineering Sciences and Technology: Civil, volume. 2, issue.1 http://www.civil.ijiest.org ISSN: 2455-2933 Role of Civil Engineering for Smart City Development:
More informationDEVELOPMENT OF FUZZY RATING MODEL FOR RESIDENTIAL GREEN BUILDINGS BASED ON PRE-OCCUPANCY & POST-OCCUPANCY PARAMETERS
International Journal of Civil Engineering and Technology (IJCIET) Volume 8, Issue 10, October 2017, pp. 1821 1828, Article ID: IJCIET_08_10_183 Available online at http://http://www.iaeme.com/ijciet/issues.asp?jtype=ijciet&vtype=8&itype=10
More informationA CRITICAL SWOT ANALYSIS FOR SMART CITY PLANNING: A MODEL STUDY ELURU CITY
International Journal of Civil Engineering and Technology (IJCIET) Volume 8, Issue 4, April 2017, pp. 1506 1513 Article ID: IJCIET_08_04_169 Available online at http://www.ia aeme.com/ijciet/issues.asp?jtype=ijciet&vtyp
More informationAnalysis of Improper Material Management Affecting Cost in Construction Projects
Analysis of Improper Material Management Affecting Cost in Construction Projects P.Lenin *, L.Krishnaraj *, D.Narendra Prasad *, V.R Prasath Kumar *, Assistant Professor, Civil Engineering Department,
More informationSchedule % Complete in Primavera P6
Schedule % Complete in Primavera P6 Schedule % Complete is one of the many percent completes you have in Primavera P6 and we re going to have a complete look at what it is and how it is calculated. Two
More informationResource Optimization of Construction Project Using Primavera P6
IOSR Journal of Mechanical and Civil Engineering (IOSR-JMCE) e-issn: 2278-1684,p-ISSN: 2320-334X, Volume 14, Issue 1 Ver. V (Jan. - Feb. 2017), PP 01-08 www.iosrjournals.org Resource Optimization of Construction
More informationPMBOK Guide Fifth Edition Pre Release Version October 10, 2012
5.3.1 Define Scope: Inputs PMBOK Guide Fifth Edition 5.3.1.1 Scope Management Plan Described in Section 5.1.3.1.The scope management plan is a component of the project management plan that establishes
More informationProductivity Improvement by Using Quality Control Tools A Case Study of Chartered Rubber Products
IOSR Journal of Mechanical and Civil Engineering (IOSR-JMCE) e-issn: 2278-1684,p-ISSN: 2320-334X, Volume 12, Issue 1 Ver. IV (Jan- Feb. 2015), PP 45-51 www.iosrjournals.org Productivity Improvement by
More informationISE480 Sequencing and Scheduling
ISE480 Sequencing and Scheduling INTRODUCTION ISE480 Sequencing and Scheduling 2012 2013 Spring term What is Scheduling About? Planning (deciding what to do) and scheduling (setting an order and time for
More informationMICRO AND MACRO LEVEL ANALYSIS OF LABOR PRODUCTIVITY
International Journal of Civil Engineering and Technology (IJCIET) Volume 8, Issue 8, August 2017, pp. 500 507, Article ID: IJCIET_08_08_052 Available online at http://http://ww www.iaeme.com/ijciet/issues.asp?jtype=ijciet&v
More informationRetained Logic and Progress Override in Primavera P6
By Pat Hendricks TEPCO, LLC www.tepco.us Retained Logic and Progress Override The retained logic and progress override setting can drastically affect a schedule depending on which is used, so understanding
More informationDeliverable Factors of Manpower Requirement Plan: An Evidence from Indian EPC Company
Deliverable Factors of Manpower Requirement Plan: An Evidence from Indian EPC Company Amruth Gurudev S #1, Srinivasa Rao Potti *2, Shiva Prasad H.C #3 # 1 PG Research Scholar, Humanities and Management,
More informationCommon Tool for Intelligent Scheduling / Critical Chain Project Management for US Navy & Contractor Shipyards
Common Tool for Intelligent Scheduling / Critical Chain Project Management for US Navy & Contractor Shipyards Rob Richards, Ph.D. April 20, 2016 Planning, Production Processes & Facilities Panel (PPP&F)
More informationCambridge International AS & A Level Computer Science
Topic Support Guide Cambridge International AS & A Level Computer Science 9608 For examination from 2017 Topic 4.4.3 Project management PERT and GANTT charts Cambridge International Examinations retains
More informationSOCIAL ENTREPRENEURSHIP AND CRM: LINKING THROUGH COMMON FACTORS
International Journal of Mechanical Engineering and Technology (IJMET) Volume 9, Issue 4, April 2018, pp. 733 740, Article ID: IJMET_09_04_081 Available online at http://www.iaeme.com/ijmet/issues.asp?jtype=ijmet&vtype=9&itype=4
More informationAvailable online at ScienceDirect. Procedia Engineering 123 (2015 ) Creative Construction Conference 2015 (CCC2015)
Available online at www.sciencedirect.com ScienceDirect Procedia Engineering 123 (2015 ) 308 315 Creative Construction Conference 2015 (CCC2015) Application of Relationship Diagramming Method (RDM) for
More informationEnergy Aware Resource Allocation for Data Center
Advances in Computational Sciences and Technology ISSN 0973-6107 Volume 10, Number 1 (2017) pp. 1-9 Research India Publications http://www.ripublication.com Energy Aware Resource Allocation for Data Center
More informationClassical Approach to Solve Economic Load Dispatch Problem of Thermal Generating Unit in MATLAB Programming
Classical Approach to Solve Economic Load Dispatch Problem of Thermal Generating Unit in MATLAB Programming Arunesh Dutt 1, Ashish Dhamanda 2 1 Assistant Professor (EEE), SGIET, NGBU, Allahabad, U.P, India
More informationProblemsofMicroManufacturingEntrepreneursin ChittoorDistrict
Global Journal of Management and Business Research: A Administration and Management Volume Issue 0 Version.0 Year 0 Type: Double Blind Peer Reviewed International Research Journal Publisher: Global Journals
More informationMarket Analysis and a Detailed Study of a Leading Cloud Telephony and SMS Gateway Company Pawan Kumar Naik 1 Praveen Kumar 2 Dr.S.A.
IJSRD - International Journal for Scientific Research & Development Vol. 3, Issue 10, 2015 ISSN (online): 2321-0613 Market Analysis and a Detailed Study of a Leading Cloud Telephony and SMS Gateway Company
More informationPrimavera Curriculum. For the individual
Primavera Curriculum Training is crucial to realizing the full value of your Primavera application. Training is available in different formats to suit the needs of each individual and the organization:
More informationProject Time Management
Project Time Management Understand the importance of project schedules and good project time management. Define activities as the basis for developing project schedules. Describe how project managers use
More informationProject Management CSC 310 Spring 2017 Howard Rosenthal
Project Management CSC 310 Spring 2017 Howard Rosenthal 1 No?ce This course is based on and includes material from the text: Effective Project Management - Traditional, Agile, Extreme 7TH Edition Authors:
More informationCHAPTER 1 INTRODUCTION
1 CHAPTER 1 INTRODUCTION 1.1 MANUFACTURING SYSTEM Manufacturing, a branch of industry, is the application of tools and processes for the transformation of raw materials into finished products. The manufacturing
More informationA STUDY ON INFLUENCE OF EMPLOYEE S FACTORS ON PERFORMANCE OF TEXTILE INDUSTRIAL UNITS
International Journal of Mechanical Engineering and Technology (IJMET) Volume 8, Issue 10, October 2017, pp. 903 909, Article ID: IJMET_08_10_098 Available online at http://www.iaeme.com/ijmet/issues.asp?jtype=ijmet&vtype=8&itype=10
More informationPARAMETRIC STUDY OF PORTABLE RESS (RAPID ERECTION SUN SHELTERS) WITH NCEL
International Journal of Civil Engineering and Technology (IJCIET) Volume 8, Issue 4, April 17, pp. 121 13 Article ID: IJCIET_8_4_17 Available online at http://www.iaeme.com/ijciet/issues.asp?jtype=ijciet&vtype=8&itype=4
More informationCEMENT DUST EXTRACTION TOOL WITH FOGGING METHOD
International Journal of Civil Engineering and Technology (IJCIET) Volume 8, Issue 10, October 2017, pp. 781 786, Article ID: IJCIET_08_10_082 Available online at http://http://www.iaeme.com/ijciet/issues.asp?jtype=ijciet&vtype=8&itype=10
More informationLONG INTERNATIONAL. Andrew Avalon, P.E., PSP and Curtis W. Foster
Andrew Avalon, P.E., PSP and Curtis W. Foster LONG INTERNATIONAL Long International, Inc. 5265 Skytrail Drive Littleton, Colorado 80123-1566 USA Telephone: (303) 972-2443 Fax: (303) 200-7180 www.long-intl.com
More informationCA Clarity Project & Portfolio Manager
CA Clarity Project & Portfolio Manager Business Objects Universes for CA Clarity PPM Reference Guide v12.1.0 This documentation and any related computer software help programs (hereinafter referred to
More informationArtificial Intelligence
Artificial Intelligence Combinatorial Optimization G. Guérard Department of Nouvelles Energies Ecole Supérieur d Ingénieurs Léonard de Vinci Lecture 4 Outline 1 2 Decisions about Resource Allocation Which
More informationIntroduction to Project Management 1Day Seminar
LB0010 Introduction to Project Management 1Day Seminar Program Notes This manual, its contents and layout and all its inclusions are the intellectual property of ProjectWare, and may not be reproduced
More informationPS.08. Let s Scrap the Precedence Diagramming Method
2004 AACE International Transactions PS.08 Let s Scrap the Precedence Diagramming Method Earl T. Glenwright Jr. THE STATE OF CONSTRUCTION SCHEDULING PRACTICES AND SCHEDULES WHY PRECEDENCE DIAGRAMMING WAS
More informationA STUDY OF DIGITAL BANKING FACILITIES: WITH REFERENCE TO GUWAHATI IN KAMRUP (METRO) DISTRICT OF ASSAM
Journal of Management (JOM) Volume 5, Issue 1, Jan Feb 2018, pp. 6 13, Article ID: JOM_05_01_002 Available online at http://www.iaeme.com/jom/issues.asp?jtype=jom&vtype=5&itype=1 Journal Impact Factor
More informationResource-constrained project scheduling using Relationship Diagramming Method (RDM)
Creative Construction Conference 2015 Resource-constrained proect scheduling using Relationship Diagramming Method (RDM) J. Uma Maheswari 1, Purva Muumdar 2, Anshul Goyal 3 & V. Paul C. Charlesra 4 * 1,2,3
More informationFlowshop Scheduling Problem for 10-Jobs, 10-Machines By Heuristics Models Using Makespan Criterion
Flowshop Scheduling Problem for 10-Jobs, 10-Machines By Heuristics Models Using Makespan Criterion Ajay Kumar Agarwal Assistant Professor, Mechanical Engineering Department RIMT, Chidana, Sonipat, Haryana,
More informationBEHAVIOR OF REINFORCED CEMENT CONCRETE BEAM WITH BAMBOO AS PARTIAL REPLACEMENT FOR REINFORCEMENT
International Journal of Civil Engineering and Technology (IJCIET) Volume 8, Issue 9, September 2017, pp. 580 587, Article ID: IJCIET_08_09_066 Available online at http://http://www.iaeme.com/ijciet/issues.asp?jtype=ijciet&vtype=8&itype=9
More information(Assignment) Master of Business Administration (MBA) PGDPM Subject : Management Subject Code : PGDPM
(Assignment) 2017-2018 Master of Business Administration (MBA) PGDPM Subject : Management Subject Code : PGDPM Subject Title : Operation Research Course Code : PGDPM-01 Maximum Marks: 30 Note: Long Answer
More informationOperations Management
17-1 Project Management Operations Management William J. Stevenson 8 th edition 17-2 Project Management CHAPTER 17 Project Management McGraw-Hill/Irwin Operations Management, Eighth Edition, by William
More informationSEISMIC ANALYSIS ON MEZZANINE FLOORING SYSTEM
International Journal of Civil Engineering and Technology (IJCIET) Volume 8, Issue 4, April 2017, pp. 689 702 Article ID: IJCIET_08_04_080 Available online at http://www.iaeme.com/ijciet/issues.asp?jtype=ijciet&vtype=8&itype=4
More informationSOFTWARE QUALITY IMPROVEMENT THROUGH DEFECT PREDICTION
SOFTWARE QUALITY IMPROVEMENT THROUGH DEFECT PREDICTION DR. DEEPAK KUMAR VERMA ASSISTANT PROFESSOR DEPARTMENT OF COMPUTER SCIENCE & INFORMATION TECHNOLOGY BABASAHEB BHIMRAO AMBEDKAR UNIVERSITY, (A CENTRAL
More informationProject Management. Learning Objectives. What are Projects? Dr. Richard Jerz. Describe or Explain:
Project Management Dr. Richard Jerz 1 Learning Objectives Describe or Explain: What are projects The role of the project manager Work breakdown structure Project management tools (Gantt, PERT, & CPM) The
More information[Ganesh S* et al., 5(7): July, 2016] ISSN: IC Value: 3.00 Impact Factor: 4.116
IJESRT INTERNATIONAL JOURNAL OF ENGINEERING SCIENCES & RESEARCH TECHNOLOGY POOR QUALITY IN BUILDING PROJECTS Mahajan Ganesh S* * Post graduate student, Department of Civil Engineering, Maharashtra Institute
More informationDEPARTMENT OF MCA CLASS / YEAR : III MCA SUB. CODE & NAME: MC9252, SOFTWARE PROJECT MANAGEMENT. UNIT I 2 MARKS QUESTIONS & ANSWERS 1. What is software project management? Software project management is
More information