Control Plans: Ensuring the Economic Return of the Application of Statistical Thinking in Improvement Projects. Robert Mitchell 3M Corporate Quality

Size: px
Start display at page:

Download "Control Plans: Ensuring the Economic Return of the Application of Statistical Thinking in Improvement Projects. Robert Mitchell 3M Corporate Quality"

Transcription

1 Control Plans: Ensuring the Economic Return of the Application of Statistical Thinking in Improvement Projects Robert Mitchell M Corporate Quality

2 Statistical Thinking is a philosophy of learning and action based on the following fundamental principles: All work occurs in a system of interconnected processes Variation exists in all processes Understanding and reducing variation are keys to success.

3 Improvement using Statistical Thinking Process Variation Data Improvement Statistical Thinking Statistical Methods Philosophy Analysis Action

4 Process Suppliers Inputs Process Outputs Customers S I P O C A series of activities that converts inputs into outputs

5 The Bottom Line: How do we capture the benefits from the application of Statistical Thinking? Y = f(x)

6 How Projects Impact The Business - Examples Revenue Growth - Increase top line through capacity expansion and new product introduction/extension Operating Margin - Bottom-line impact of capacity expansion (growth) or cost reduction (productivity) Working Capital - Cash impact of inventory or receivable reductions or reduced thruput time (cycle time reduction - improved turns)

7 How Projects Impact The Business - Examples Revenue Preservation - Maintain volume otherwise lost (due to stockouts or lost customers, etc.) Cost Avoidance - Reduce the planned spend (that would have otherwise been incurred) Reduce NVA - Redeployment of resources (personnel, equipment, etc.) without removing their cost from the overall system - consider customer satisfaction

8 Project Selection Elements Clarify the big picture using the strategic plan and annual business plan for the business Top-down project identification Establish productivity baseline Bottom-up project identification Prioritize projects based on business metrics Select key projects with leadership support Check for accountability

9 Clarifying the Big Picture The functional goals should support the business plans. The key metrics (Critical Y s) for the business are identified and goals set for each year. Projects should support the key business directives and should be measurable through the process key metrics.

10 Project Identification Methods Two fundamental methods: Top-Down Projects are identified through association with the metrics of the company s Strategic Plan Bottom-Up Projects are identified through association with current process issues.

11 Project Selection Approaches Strategic / Operating Plan Metrics Opportunities to reach the goals Issues needing attention Problems, Defects, Dissatisfied Customers, Downtime, Pain

12 Example: Goal Tree Alignment Goals Productivity / Cost Working Capital / Cash Growth How Employee Satisfaction Metrics Better Increase Top Box Yield, RTY Faster Rate Cycle Time Cheaper Reduce Waste COPQ Projects More Valued Features Increase On-time delivery Fewer Defects Increase Capability Reduce Cycle Time Redesign Process Flow Reduce Waste Lower Inventory Reduce Rework First Time Acceptance Eliminate non-value add Why Decrease RM Cost Works Best for Operational Projects

13 Example: SIPOC Model Defectefect Suppliers Inputs x x Outputs Customers x Effectiveness of Inputs RM Consistency Intellectual Property RM Availability Mgmt Strategic Goals Market Presence Availability of Information Efficiency of Process Rolled Throughput Yield, First Pass Yield Rework, Scrap, Waste Throughput % Things Gone Right Days of Stock Days Beyond Terms Effectiveness of Outputs CTQ Performance Product Features On-Time Delivery # Warranty Claims Customer Loyalty Response Time Works Best for Transactional Projects

14 COPQ Iceberg Tip of COPQ Iceberg Customer Returns, Waste, Scrap, Rejects, Inspection Costs, Recalls, Rework, Warranty Claims Excessive Overtime, Premium Freight Costs, Expediting Costs, Excess Inventory, Consumed Capacity, Customer Allowances, More Setups, Lost Sales, Late Delivery, Long Cycle Times, Engineering Change Orders, Lost Customer Loyalty Lost Opportunity Hidden Factory Traditional Quality Costs, 4-5% of Sales Tangible, easier to measure Full COPQ, 15-25% of Sales Intangible, more difficult to measure Average COPQ Approximately 20% of Sales

15 Entitlement Defines what s possible - a vision Provides a performance level for which to aim Tells you how your process performance relates to perfection Provides an internal benchmark

16 Entitlement Best Possible Performance Rolled Throughput Yield = 100% Cost of Poor Quality = $0 Speed: Best observed performance over a short period of time Predicted by business process design Predicted by should map Capacity: Performance specified by equipment manufacturer Predicted by engineering & scientific fundamentals Best observed performance over a short period of time Best performance predicted by empirical relationships developed from process data

17 Improvement Methodology PDCA Control Define DMAIC ACT PLAN Measure CHECK DO Improve Analyze

18 Control Plans / Methods Importance to the improvement process Documented control methods for all critical Process Output Variables and Process Input Variables in the process drives sustained gains Effective control methods maintain the level of performance over the long term Provides a complete critical to operation list of variables and their associated measurement systems / control methods Identifies the Reaction Plan for the Process Owners to resolve any out-of-control occurrences

19 Outputs Control Plans / Methods Updated Control Plans and methods for all critical Process Output Variables and Process Input Variables Completed Reaction Plan for each Process Input Variable / Process Output Variable Sampling methods and measurement system controls in place for each Critical Process Input Variable and Process Output Variable Procedures and appropriate documentation Identified and completed training for all pertinent personnel / functions affected by changes in the process

20 ISO 9001:2000 Management Responsibility Resource Management Measurement, analysis, improvement Input Product Realization Output

21 Three Diamonds of ISO Management Review (5.6.1) Corrective/Preventive Action (8.5) Internal Auditing (8.2.2)

22 Benefits That Can Be Maintained/ Gained With ISO 9001:2000 Improved consistency of products and services through documentation of standards and specifications Organizational retention and transfer of process knowledge through improved documentation. Current and accurate raw material specifications Improved calibration and accuracy of measuring devices

23 Benefits That Can Be Maintained/ Gained With ISO 9001:2000 Discipline to follow documented processes Established requirements for training and record keeping Improved system performance Provides a process to reliably deliver what you promise to customers

24 Benefits That Can Be Maintained/ Gained With ISO 9001:2000 Identifies improvement project opportunities with supporting information about: Current performance levels Measures and Processes used Provides a framework to sustain the gains of continuous improvement projects

25 Case Study Adhesive Corporate Critical Y: Growth Cost Cash Performance Business Unit Critical Y Project Y Financial Impact

26 Adhesion Performance Improvement Initial Capability KPOV out of Control Mean 5 oz/inch over target of 0 PSA - Adhesion Final Capability Process in control Mean on oz/inch 50% reduction in variation Individual Value UCL=7.28 Mean=29.90 LCL=22.51 Subgroup Process Moving Range UCL=9.070 R=2.776 LCL=0

27 Adhesion Performance Control Plan Transitioned 8 of 12 identified critical X s from uncontrolled to controlled variables Documented new SOPs, implemented mistake proofing, and instituted training Critical Y s Adhesion to Glass 5-Bond Critical X s Ct Wt Profile Coating Appearance Adhesive Formulation ISO 9001:2000 Management Review Quarterly internal audits of control plan

28 Key Learnings - Control Plans Start developing the control plan as soon as possible After completion of Measure or Analyze phase Select the appropriate process owner and keep him / her informed of and involved in the Control Plan Team membership of Process Owner is crucial. If project outcome is not important to the PO, you have chosen the wrong Process Owner.

29 Key Learnings - Control Plans Keep the Control Plan as simple as needed to sustain the desired results Don t replace a complex project with an equally complex control plan. Use existing culture and SOP Simplify or mistake proof process to prevent the need for Active Control

Cost of Quality. Appendix 2B. Copyright 2006, The McGraw-Hill Companies, Inc.

Cost of Quality. Appendix 2B. Copyright 2006, The McGraw-Hill Companies, Inc. Cost of Quality Appendix 2B Copyright 2006, The McGraw-Hill Companies, Inc. Learning Objective 9 (Appendix 2B) Identify the four types of quality costs and explain how they interact. Quality of Conformance

More information

Cost of Poor Quality. BPF2123 Quality Management System

Cost of Poor Quality. BPF2123 Quality Management System Cost of Poor Quality BPF2123 Quality Management System Chapter Outline Cost of Poor Quality 1. Defining Quality Costs 2. Types of Quality Costs Prevention Costs Appraisal Costs Failure Costs Intangible

More information

Sample CPI Project Selection Criteria And Project Charter

Sample CPI Project Selection Criteria And Project Charter Sample CPI Project Selection Criteria And Project Charter Sample CPI Project Selection Criteria The most successful CPI projects are targeted at processes and value streams critical to the organization

More information

EBITDA Optimization for High Tech Manufacturing

EBITDA Optimization for High Tech Manufacturing EBITDA Optimization for High Tech Manufacturing At a Glance This paper will help High Tech Manufacturers look at industry benchmarks to compare with their own EBITDA performance, along with industry trends

More information

Due Diligence to Exit

Due Diligence to Exit Due Diligence to Exit Finding and Mining Value Hidden in Operations September, 2012 The Competition is Fierce. Change the Rules. Company Overview The ProAction Group serves private equity firms who invest

More information

Addressing ISO 9001 Risk Management Requirements

Addressing ISO 9001 Risk Management Requirements Addressing ISO 9001 Risk Management Requirements Roger Crist Quality Director, Moxtek, Inc.; and Strategic Partner, MasterControl Inc. St. Louis Section Annual Quality Conference - Nov 6, 2017 Learning

More information

Operational Excellence Methodology Continuous Improvement

Operational Excellence Methodology Continuous Improvement Operational Excellence Methodology Continuous Improvement Duvan Luong, Ph.D. Operational Excellence Networks In our everyday life, we all have objectives. Usually, the objectives are associated with obligations

More information

Quality Management Chapter 14

Quality Management Chapter 14 Quality Management Chapter 14 1 Objectives What is Quality? Total Quality Management TQM in Service Cost of Quality Quality Improvements Quality Awards and Certifications 2 What is Quality? The Meaning

More information

LEAN CERTIFICATION BODY OF KNOWLEDGE RUBRIC VERSION 3.0

LEAN CERTIFICATION BODY OF KNOWLEDGE RUBRIC VERSION 3.0 MODULE 1 LEAN CERTIFICATION BODY OF KNOWLEDGE RUBRIC VERSION 3.0 1. Cultural Enablers 15% 20% 25% 1.1. Principles of Cultural Enablers 3% 4% 5% 1.1.1. Respect for the individual 1.1.2. Humility 1.2. Processes

More information

Value Driven Solutions The Resource for the Lean Enterprise. w w w. v d s c o n s u l t i n g g r o u p. c o m

Value Driven Solutions The Resource for the Lean Enterprise. w w w. v d s c o n s u l t i n g g r o u p. c o m By Value Driven Solutions The Resource for the Lean Enterprise w w w. v d s c o n s u l t i n g g r o u p. c o m The World Class Enterprise Through the Value Driven Approach Features of a World Class Enterprise

More information

Lean Gold Certification Blueprint

Lean Gold Certification Blueprint The Lean Certification Blueprint provides additional useful information beyond the Body of Knowledge. The Body of Knowledge specifies the competencies, topics, and subtopics required by different types

More information

Sales & Operations Planning Concepts and Practical Implications. LunterenConference, 19 th January 2012 Noud Gademann

Sales & Operations Planning Concepts and Practical Implications. LunterenConference, 19 th January 2012 Noud Gademann Sales & Operations Planning Concepts and Practical Implications LunterenConference, 19 th January 2012 Noud Gademann Contents Introduction to Sales & Operations Planning Strategy alignment and performance

More information

LEARNING TO SEE an introduction to lean thinking

LEARNING TO SEE an introduction to lean thinking LEARNING TO SEE an introduction to lean thinking 2 Why Lean? Customer satisfaction Market share Costs 3 Where did Lean come from? Henry Ford First flow production line 1960s The term Lean originated International

More information

CERTIFIED SUPPLIER QUALITY PROFESSIONAL

CERTIFIED SUPPLIER QUALITY PROFESSIONAL CSQP CERTIFIED SUPPLIER QUALITY PROFESSIONAL Quality excellence to enhance your career and boost your organization s bottom line asq.org/cert Certification from ASQ is considered a mark of quality excellence

More information

Document No.: INS Rev: B Origination Date: 10/30/2013

Document No.: INS Rev: B Origination Date: 10/30/2013 1.0 Purpose This instruction is to describe the process for Cost of Poor Quality (COPQ) calculation, along with process for Cost Recovery with supplier caused problems. This applies to all purchased materials,

More information

Using Lean Six Sigma to Accelerate CMMI Implementation

Using Lean Six Sigma to Accelerate CMMI Implementation Using Lean Six Sigma to Accelerate CMMI Implementation Briefers: Diane A. Glaser Michael D. Barnett US Army CECOM LCMC SEC CMMI Coordinator Communication Software ASQ SSGB Engineering Support Division

More information

Quality Manual Revision: C Effective: 03/01/10

Quality Manual Revision: C Effective: 03/01/10 TABLE OF CONTENTS DESCRIPTION SECTION PAGE INTRODUCTION 1.0 1 APPROVAL SIGNATURE PAGE 1.1 1 AMENDMENT RECORD 1.2 2 SCOPE 2.0 3 EXCLUSIONS 2.1 3 CORPORATE POLICY 3.0 3 QUALITY MANAGEMENT SYSTEM 4.0 4 GENERAL

More information

Sections of the Standard. Evidence / Comments. (Y) / Nonconforming (NC)

Sections of the Standard. Evidence / Comments. (Y) / Nonconforming (NC) Date: Sections of the Standard 4 Context of the Organization 4.1 Understanding the organization and its context 4.2 Understanding the needs and expectations of interested parties 4.3 Determining the scope

More information

Clause Map IATF 16949:2016 to ISO/TS 16949:2009

Clause Map IATF 16949:2016 to ISO/TS 16949:2009 Table of Contents Table of Contents Foreword Foreword + Foreword Automotive QMS Standard + History + Goal + 0.5 Goal of this Technical Specification + Remarks for Certification + Remarks for Certification

More information

Open Standards Benchmarking Measure List

Open Standards Benchmarking Measure List Cost Effectiveness Page 1 100784 Inventory carrying cost as a percentage of average inventory value 103506 Total cost to perform the logistics process logistics" per $1,000 103509 Total cost to perform

More information

Supplier Quality Manual

Supplier Quality Manual Supplier Quality Manual February 2010 Page 1 of 6 Table of Contents 1.0 Purpose 2.0 Scope 3.0 Quality System Requirements 4.0 Supplier Assessments 5.0 Advance Product Quality Planning 6.0 First Article

More information

Continuous Improvement Toolkit

Continuous Improvement Toolkit Continuous Improvement Toolkit Lean Measures Managing Risk PDPC Pros and Cons Importance-Urgency Mapping RACI Matrix Stakeholders Analysis FMEA RAID Logs Break-even Analysis Cost -Benefit Analysis PEST

More information

Correlation matrices between ISO 9001:2008 and ISO 9001:2015

Correlation matrices between ISO 9001:2008 and ISO 9001:2015 Correlation matrices between ISO 9001:2008 and ISO 9001:2015 ISO 9001:2015 ISO 9001:2008 1 Scope 1 Scope 1.1 General 4 Context of the organization 4 Quality management system 4.1 Understanding the organization

More information

Continuous Improvement Toolkit. Value Analysis

Continuous Improvement Toolkit. Value Analysis Continuous Improvement Toolkit Value Analysis VA NVA The Continuous Improvement Map Managing Risk FMEA Understanding Performance** Check Sheets Data Collection PDPC RAID Log* Risk Analysis* Benchmarking***

More information

PRINTED COPY IS NOT CONTROLLED

PRINTED COPY IS NOT CONTROLLED Quality Manual We Deliver Quality on Time Form 1217 (01.16.2018) Rev. 12 SOR Inc. sorinc.com SOR QUALITY MANUAL Page 1 of 18 Table of Contents Quality Manual 8701-001 Revision 12 Introduction....4 1.0

More information

Think ROI, Not Cost When Evaluating ERP Software

Think ROI, Not Cost When Evaluating ERP Software Think ROI, Not Cost When Evaluating ERP Software BY ADAM GRABOWSKI DIRECTOR, MARKETING AND COMMUNICATIONS We simplify your manufacturing. When considering Enterprise Resource Planning (ERP) software for

More information

Business Management System Manual Conforms to ISO 9001:2015 Table of Contents

Business Management System Manual Conforms to ISO 9001:2015 Table of Contents Table of Contents 1.0 Welcome to Crystalfontz... 3 2.0 About the Crystalfontz Business Systems Manual... 4 3.0 Terms and Conditions... 5 4.0 Context of the Organization... 6 4.1. Understanding the Organization

More information

Lean Six Sigma Black Belt Week 3

Lean Six Sigma Black Belt Week 3 Lean Six Sigma Black Belt Week 3 Chapter 3-1: Lean Re-Entry and Process Institute of Industrial Engineers 3577 Parkway Place Suite 200 Norcross, GA 30092 Lean Six Sigma Black Belt Week 3 Agenda Day 1 Day

More information

ABC Metals, Inc. NONFERROUS METALS PRECISION SLITTING

ABC Metals, Inc. NONFERROUS METALS PRECISION SLITTING SCOPE This section describes the responsibility, authority, and management structure of the facility. 1.1 QUALITY POLICY The President has the ultimate responsibility for the facility s products and services.

More information

Demystifying Cost Justification for Ergonomic Solutions

Demystifying Cost Justification for Ergonomic Solutions Demystifying Cost Justification for Ergonomic Solutions WEBINAR Ben Zavitz, CPE Chief Ergonomist brzavitz@icloud.com 207-271-ERGO ERGOHP.COM Agenda 1. An Approach to Cost Justification 2. Injury vs. Operational

More information

Supply Chain Design and Alignment

Supply Chain Design and Alignment Supply Chain Design and Alignment A supply chain let s a company move product from its source to its final consumption. Companies now use their supply chain as a competitive weapon to compete. The activities,

More information

Quality. Costs of Quality-CoQ DEG/FHC 1

Quality. Costs of Quality-CoQ DEG/FHC 1 Quality Costs of Quality-CoQ DEG/FHC 1 Cost of Quality-CoQ The concept of Cost of Quality CoQ is simple yet central to Quality. It attaches a monetary value to quality activities. Therefore, the organization

More information

Engaging All Employees to Eliminate the Eight Wastes

Engaging All Employees to Eliminate the Eight Wastes Engaging All Employees to Eliminate the Eight Wastes Abstract Charles Aubrey Vice President, Anderson Pharmaceutical Packaging, USA Kaizen means continuous improvement in Japanese. It has become closely

More information

RESURRECTING MANUFACTURING

RESURRECTING MANUFACTURING RESURRECTING MANUFACTURING by mike shipulski How DFMA can save money, industry and possibly the economy 24 Industrial Engineer For too long we have praised financial enterprises for driving economic growth

More information

Supplier Quality Manual

Supplier Quality Manual Supplier Quality Manual 1 1. Introduction Scope Purpose Application Implementation 2. Purchasing Expectations Terms and Conditions Engineering / Technical Support Customer Support Resources Pricing Consistent

More information

Continuous Improvement in Government: Applying Lean Principles

Continuous Improvement in Government: Applying Lean Principles Continuous Improvement in Government: Applying Principles To Increase Revenues and Reduce Costs. QPIC (Quality and Productivity Improvement Center), LLC 21 Apache Lane Marlborough, CT 06447 1-860-295-9134

More information

Case Study: North American TPA Achieves Success with. Management Solution

Case Study: North American TPA Achieves Success with. Management Solution Case Study: North American TPA Achieves Success with Case Study: North American TPA Reduces Claims ServicePower Spend with Warranty Claims Claims Management Technology from ServicePower Management Solution

More information

Practice at UVa. & Chief Financial Officer

Practice at UVa. & Chief Financial Officer Management Methodologies in Practice at UVa Balanced Scorecard Gary Nimax, Office of the Vice President & Chief Financial Officer Six Sigma Priscilla Shuler, Quality Performance & Improvement, Medical

More information

Quality Manual. This manual complies with the requirements of the ISO 9001:2015 International Standard. AW2 Logistics, Inc Ace Industrial Dr.

Quality Manual. This manual complies with the requirements of the ISO 9001:2015 International Standard. AW2 Logistics, Inc Ace Industrial Dr. Quality Manual This manual complies with the requirements of the ISO 9001:2015 International Standard. AW2 Logistics, Inc. 6001 Ace Industrial Dr. Cudahy, WI 53210 Quality Manual Rev 3 Page 1 of 30 Table

More information

Target Management through Hour by Hour reporting for a Continuous Coating Environment

Target Management through Hour by Hour reporting for a Continuous Coating Environment Target Management through Hour by Hour reporting for a Continuous Coating Environment 2013 Aimcal Web Coating & Handling Conference Charleston, South Carolina Josh Rauen Tim Buntrock Jeff Hammes Background

More information

UNIT 2 QUALITY PHILOSOPHY

UNIT 2 QUALITY PHILOSOPHY UNIT 2 QUALITY PHILOSOPHY 1 Quality What is quality? It is a relative word It lies in the eyes of the perceiver According to ISO 9000:2000, it is defined as the degree to which a set of inherent characteristics

More information

Business processes and information systems

Business processes and information systems T-86.300 Information and Communication Technology (ICT) Enabled Commerce Business processes and information systems Jari Talvinen Ph.D.(Econ), Docent, Business Development Executive, Agenda Business Processes

More information

Quality Management (PQM01) Chapter 04 - Quality Control

Quality Management (PQM01) Chapter 04 - Quality Control Quality Management (PQM01) Chapter 04 - Quality Control Slide 1 Slide 2 Involves monitoring specific project results to determine if they comply with relevant quality standards, and identifying ways to

More information

The SAM Optimization Model. Control. Optimize. Grow SAM SOFTWARE ASSET MANAGEMENT

The SAM Optimization Model. Control. Optimize. Grow SAM SOFTWARE ASSET MANAGEMENT The Optimization Model Control. Optimize. Grow The Optimization Model In an ever-changing global marketplace, your company is looking for every opportunity to gain a competitive advantage and simultaneously

More information

Supplier Quality Manual

Supplier Quality Manual Supplier Quality Manual Document No. F-PM010 Rev 3 Owner Supplier Quality Page 1 OF 11 TABLE OF CONTENTS 1.0 Purpose 3 2.0 Scope... 3 3.0 Quality System Requirements... 3 4.0 Approved Supplier List (ASL).

More information

Union Pacific Railroad. Supplier Excellence Manual. Contents

Union Pacific Railroad. Supplier Excellence Manual. Contents Union Pacific Railroad Supplier Excellence Manual Contents Union Pacific Railroad... 1 Supplier Excellence Manual... 1 1.0 Doing Business with Union Pacific... 4 1.1 About Union Pacific... 4 1.2 Purpose

More information

A beginners guide to moving to an ERP

A beginners guide to moving to an ERP A beginners guide to moving to an ERP 2 Contents This paper is for companies considering an ERP and looking to justify the investment in new technology. This paper will provide methods to identify and

More information

Technology Consulting Analytics solutions for manufacturing and industrial products

Technology Consulting Analytics solutions for manufacturing and industrial products www.pwc.in Technology Consulting Analytics solutions for manufacturing and industrial products Overview Technological and digital innovations are transforming the manufacturing and industrial products

More information

4/26. Analytics Strategy

4/26. Analytics Strategy 1/26 Qlik Advisory As a part of Qlik Consulting, Qlik Advisory works with Customers to assist in shaping strategic elements related to analytics to ensure adoption and success throughout their analytics

More information

Luminus Devices, Inc Quality Management Systems Manual ISO 9001:2008

Luminus Devices, Inc Quality Management Systems Manual ISO 9001:2008 Luminus Devices, Inc Quality Management Systems Manual ISO 9001:2008 This document belongs to Luminus Devices, Inc. It cannot be reproduced without authorized authority. Area: Quality System Document Page

More information

Sales & Operations Planning Key Lessons Learned NFPA Chicago Regional Conference. December 7, 2016

Sales & Operations Planning Key Lessons Learned NFPA Chicago Regional Conference. December 7, 2016 Sales & Operations Planning Key Lessons Learned NFPA Chicago Regional Conference December 7, 2016 Keystone Overview Presenters Brad Terry, Principal Joined Keystone in 2009 Bradʹs areas of focus include

More information

Lean Means Speed. Alessandro Anzalone, Ph.D Hillsborough Community College, Brandon Campus

Lean Means Speed. Alessandro Anzalone, Ph.D Hillsborough Community College, Brandon Campus Lean Means Speed Alessandro Anzalone, Ph.D Hillsborough Community College, Brandon Campus 1. Is This Lean? 2. The Essentials of Lean 3. The Lean Metric: Cycle Efficiency 4. Velocity of Any Process 5. Knowing

More information

Six Sigma Black Belt Study Guides

Six Sigma Black Belt Study Guides Six Sigma Black Belt Study Guides 1 www.pmtutor.org Powered by POeT Solvers Limited. Overview of Six Sigma DMAIC Define Define the project targets and customer (internal and external) deliverables. Measure

More information

Make the difference with Lean Finance

Make the difference with Lean Finance KPMG Lean Finance Make the difference with Lean Finance Our vision and approach for successful change in your finance function www.kpmg.com Lean Finance is the transformation key towards a world class

More information

P. 1. Identify the Differences between ISO9001:2000 與 ISO9001:2008 ISO9001:2008 ISO9001:2000 版本的異同. 5 January 2009 ISO 9000 SERIES

P. 1. Identify the Differences between ISO9001:2000 與 ISO9001:2008 ISO9001:2008 ISO9001:2000 版本的異同. 5 January 2009 ISO 9000 SERIES Identify the Differences between ISO9001:2000 and ISO 9001:2008 審視 ISO9001:2000 與 ISO9001:2008 版本的異同 ISO 9000 SERIES ISO 19011 ISO9000 5 January 2009 ISO9001 ISO9004 2 ISO 9000 SERIES ISO 9001 ISO 9000

More information

Webster - Hoff Corporation. Quality Manual

Webster - Hoff Corporation. Quality Manual Registered to ISO 9001:2008 ANSI/ISO/ASQ Q9001-2008 QM-1 Page 2 of 35 TABLE OF CONTENTS Section Name Page Management Approval Of / List of Exclusions 3 Corporate Quality Policy 4 Webster-Hoff Corporation,

More information

SUPPLY CHAIN DEFINITIONS AND KEY MEASURES

SUPPLY CHAIN DEFINITIONS AND KEY MEASURES SUPPLY CHAIN DEFINITIONS AND KEY MEASURES Version 2.0.0 THE FRAMEWORK FOR PROCESS IMPROVEMENT Experience shows that benchmarking s potential to drive dramatic improvement lies squarely in making out-of-the-box

More information

Comparison ISO/TS (1999) to QS 9000, 3 rd edition (1998)

Comparison ISO/TS (1999) to QS 9000, 3 rd edition (1998) 1 SCOPE QS 9000: new: Introduction, applicability In addition to the applicability for supplier sites for production and services and their subcontractors for: - parts or materials, or - services like

More information

Reducing the Cost of Quality with Real-Time SPC

Reducing the Cost of Quality with Real-Time SPC Reducing the Cost of Quality with Real-Time SPC The level of global competition faced by today s organizations has put more pressure on the bottom line than ever before. To realize market-leading performance,

More information

4 The balanced scorecard

4 The balanced scorecard SUPPLEMENT TO THE APRIL 2009 EDITION Three topics that appeared in the 2007 syllabus have been removed from the revised syllabus examinable from November 2009. If you have the April 2009 edition of the

More information

Streamline: Progressions in Product Compliance (Part 1 of 4)

Streamline: Progressions in Product Compliance (Part 1 of 4) Intertek 70 Codman Hill Road Boxborough, MA 01719 icenter@intertek.com 1-800-WORLDLAB www.intertek.com Chapter 1: Faster, Better, More Now Faced with adversity, resourceful manufacturers often find or

More information

Cage Code First Edition. A guide to AQS continuous improvement expectations

Cage Code First Edition. A guide to AQS continuous improvement expectations Cage Code 81205 First Edition AQS Guidelines A guide to AQS continuous improvement expectations The custodian for this document is: Boeing Commercial Airplane Group, Supply Management and Procurement Division,

More information

At the end of the programme, the participants should be able to:- Understand the real meaning and importance of KPIs and KRAs to the organisation

At the end of the programme, the participants should be able to:- Understand the real meaning and importance of KPIs and KRAs to the organisation PROGRAMME OBJECTIVES At the end of the programme, the participants should be able to:- Understand the real meaning and importance of KPIs and KRAs to the organisation Link PMS to KPIs and KRAs by having

More information

Online Student Guide Types of Control Charts

Online Student Guide Types of Control Charts Online Student Guide Types of Control Charts OpusWorks 2016, All Rights Reserved 1 Table of Contents LEARNING OBJECTIVES... 4 INTRODUCTION... 4 DETECTION VS. PREVENTION... 5 CONTROL CHART UTILIZATION...

More information

"Value Stream Mapping How does Reliability play a role in making Lean Manufacturing a Success " Presented by Larry Akre May 17, 2007

Value Stream Mapping How does Reliability play a role in making Lean Manufacturing a Success  Presented by Larry Akre May 17, 2007 "Value Stream Mapping How does Reliability play a role in making Lean Manufacturing a Success " Presented by Larry Akre May 17, 2007 LAKRE 2007 1 Lean Manufacturing What is Lean Manufacturing? A philosophy

More information

9001:2015. Quality Manual 9001:2015. Engineering Value through Quality and Innovation.

9001:2015. Quality Manual 9001:2015. Engineering Value through Quality and Innovation. Quality Manual 9001:2015 9001:2015 Suburban Manufacturing, Inc. encourages comments from customers, suppliers, employees and friends in order to improve our business and its performance. Information contained

More information

CHAPTER 2. Theoretical Foundation. Scorecard is a new approach to strategic management. They proposed the concept of a

CHAPTER 2. Theoretical Foundation. Scorecard is a new approach to strategic management. They proposed the concept of a CHAPTER 2 Theoretical Foundation 2.1 Balanced Scorecard Drs.Robert Kaplan (Harvard Business School) and David Norton has developed Balanced Scorecard (BSC) in the beginning of year 1990s, they explained

More information

BALANCE SCORECARD. Introduction. What is Balance Scorecard?

BALANCE SCORECARD. Introduction. What is Balance Scorecard? BALANCE SCORECARD Introduction In this completive world where techniques are change in nights, it s very hard for an organization to stay on one technique to grow business. To maintain the business performance

More information

Debra J. Perry Harris Corporation. How Do We Get On The Road To Maturity?

Debra J. Perry Harris Corporation. How Do We Get On The Road To Maturity? How Do We Get On The Road To Maturity? Debra J. Perry Harris Corporation NDIA Conference - 1 What do we want? From this To this But how? NDIA Conference - 2 Where Do We Start? NDIA Conference - 3 Government

More information

FEC QUALITY MANUAL. Federal Equipment Company River Rd. Cincinnati, Ohio

FEC QUALITY MANUAL. Federal Equipment Company River Rd. Cincinnati, Ohio QMS-20 2016 FEC QUALITY MANUAL Federal Equipment Company 5298 River Rd Cincinnati, Ohio 45233 www.federalequipment.com www.fecheliports.com www.usdrillhead.com www.orionseals.com www.tkf.com REVISION:

More information

ANCHOR ISO9001:2008 RPR-004 MARINE SERVICES REQUIRED PROCEDURE NON-CONFORMING PRODUCTS

ANCHOR ISO9001:2008 RPR-004 MARINE SERVICES REQUIRED PROCEDURE NON-CONFORMING PRODUCTS CONTROL OF NON-CONFORMING PRODUCTS (8.3) Document Control Revision History PAGE REASON FOR CHANGE REV. REVIEWER / AUTHORISED BY: ALL ALL RELEASE DATE: Revision Approval: J.BENTINK Signature: Date: 20/02/17

More information

ISO 9001:2008 Quality Manual

ISO 9001:2008 Quality Manual Quality Manual 1785 Ellsworth Industrial Drive, N.W. Atlanta, GA 30318 Toll Free: 800-241-8990 Phone: 404-351-2600 Fax: 404-355-2046 Doc. No. 0.0 Document Title: Index Page 2 of 40 Revision History Rev

More information

Lean Distribution. Mark Kushner, COO Lloyed Lobo, Director Business Development

Lean Distribution. Mark Kushner, COO Lloyed Lobo, Director Business Development Lean Distribution Mark Kushner, COO Lloyed Lobo, Director Business Development Agenda Brief Company Overview What is Lean? Lean in the Extended Supply Chain Benefits of Lean Distribution Can Lean Help

More information

PRECISION SENSORS QUALITY ASSURANCE MANUAL THIS DOCUMENT IS CONTROLLED ONLY IF COPY IS STAMPED CONTROLLED IN RED INK

PRECISION SENSORS QUALITY ASSURANCE MANUAL THIS DOCUMENT IS CONTROLLED ONLY IF COPY IS STAMPED CONTROLLED IN RED INK SAE AS9100 DOCUMENT PRECISION SENSORS QUALITY ASSURANCE MANUAL THIS DOCUMENT IS CONTROLLED ONLY IF COPY IS STAMPED CONTROLLED IN RED INK REV. 005 10/27/10 Page 2 Page 4 Page 5 Page 6 Page 7 Page 8 Page

More information

CORPORATE QUALITY MANUAL

CORPORATE QUALITY MANUAL Corporate Quality Manual Preface The following Corporate Quality Manual is written within the framework of the ISO 9001:2008 Quality System by the employees of CyberOptics. CyberOptics recognizes the importance

More information

Lean Thinking. Continuous improvement is about removing stuff that get in the way of your things working well.

Lean Thinking. Continuous improvement is about removing stuff that get in the way of your things working well. Lean Thinking Continuous improvement is about removing stuff that get in the way of your things working well. What is LEAN Maximize customer value Minimizing waste. More value fewer resources. Understands

More information

SANDVIK MACHINING SOLUTIONS TO ACQUIRE SOFTWARE COMPANY METROLOGIC GROUP 27 APRIL 2018

SANDVIK MACHINING SOLUTIONS TO ACQUIRE SOFTWARE COMPANY METROLOGIC GROUP 27 APRIL 2018 SANDVIK MACHINING SOLUTIONS TO ACQUIRE SOFTWARE COMPANY METROLOGIC GROUP 27 APRIL 2018 INTRODUCTION 2 CAPITAL MARKETS DAY, NOVEMBER 2017 From a world leading player in the niche industry of metal cutting,

More information

Best practices in demand and inventory planning

Best practices in demand and inventory planning whitepaper Best practices in demand and inventory planning WHITEPAPER Best Practices in Demand and Inventory Planning 2 about In support of its present and future customers, Aptean sponsored this white

More information

Process Mapping. You cannot improve a process until everyone agrees on what the process is.

Process Mapping. You cannot improve a process until everyone agrees on what the process is. Process Mapping You cannot improve a process until everyone agrees on what the process is. 1 Topics I. What is a Process Map? II. III. IV. Types of Process Maps A. Process Flow Chart B. SIPOC Diagram C.

More information

Philips Healthcare Accelerate! Transformation. Greg Sebasky, Executive Vice President Business Transformation, Philips Healthcare

Philips Healthcare Accelerate! Transformation. Greg Sebasky, Executive Vice President Business Transformation, Philips Healthcare Philips Healthcare Accelerate! Transformation Greg Sebasky, Executive Vice President Business Transformation, Philips Healthcare 1 Key takeaways Accelerate! is a comprehensive program impacting all of

More information

ABB ServicePro 4.0 Service Management System

ABB ServicePro 4.0 Service Management System ABB ServicePro 4.0 Service Management System Presented by Paul Radcliffe PS Service June 6, 2014 Slide 1 Questions customers ask How successful is my maintenance program? - Am I performing the right PM

More information

INTEGRATING ISO 9000 METHODOLOGIES WITH PROJECT QUALITY MANAGEMENT

INTEGRATING ISO 9000 METHODOLOGIES WITH PROJECT QUALITY MANAGEMENT INTEGRATING ISO 9000 METHODOLOGIES WITH PROJECT QUALITY MANAGEMENT M a r ch 2015 OBJECTIVE ISO and Project Quality Management Process Are they different or the same? ISO 9000 QMS FAMILY ISO 9000:2005 Vocabulary

More information

Quality management systems

Quality management systems L E C T U R E 9 Quality management systems LECTURE 9 - OVERVIEW Quality management system based on ISO 9000 WHAT IS QMS (QUALITY MANAGEMENT SYSTEM) Goal: Meet customer needs Quality management system includes

More information

Creating Value in Key Accounts

Creating Value in Key Accounts Creating Value in Key Accounts Mark Lubkeman and Vikas Taneja July 2010 Creating Value in Key Accounts Key account management (KAM) is falling short of its potential because of four common mistakes. One,

More information

A PMO Value Model. For Strategic Execution and Value Delivery P M. Robert Frost PMP, PMOC. 4/19/2016 PMO Value Model 2016 Robert Frost 1

A PMO Value Model. For Strategic Execution and Value Delivery P M. Robert Frost PMP, PMOC. 4/19/2016 PMO Value Model 2016 Robert Frost 1 A PMO Value Model For Strategic Execution and Value Delivery P M Robert Frost PMP, PMOC O 4/19/2016 PMO Value Model 2016 Robert Frost 1 Why we need a PMO Value Model Why Capabilities Needed The Challenges*

More information

Mastio & Company s. LTL Carrier Customer Value & Loyalty Benchmarking Study. Metrics to Manage the Shipper Experience

Mastio & Company s. LTL Carrier Customer Value & Loyalty Benchmarking Study. Metrics to Manage the Shipper Experience Mastio & Company s LTL Carrier Customer Value & Loyalty Benchmarking Study 11 th Edition 2015 Metrics to Manage the Shipper Experience Tel: 816-364-6200 Fax: 816-364-3606 www.mastio.com OVERVIEW MASTIO

More information

TOTAL QUALITY MANAGEMENT UNIT I INTRODUCTION

TOTAL QUALITY MANAGEMENT UNIT I INTRODUCTION TOTAL QUALITY MANAGEMENT UNIT I INTRODUCTION 1.Define quality. (i) Quality is defined as the predictable degree of uniformity and dependability, at low cost suited to the market.(deming). (ii) Quality

More information

Supplier Partnership. BPF 2123 Quality Management System

Supplier Partnership. BPF 2123 Quality Management System Supplier Partnership BPF 2123 Quality Management System 1 Chapter Outline Introduction Principles of Supplier Partnership Sourcing Supplier Selection Supplier Certification Supplier Rating Relationship

More information

FAIRFIELD GLOBAL SUPPLIER QUALITY PROGRAM

FAIRFIELD GLOBAL SUPPLIER QUALITY PROGRAM FAIRFIELD GLOBAL SUPPLIER QUALITY PROGRAM 1 QA.101 rev. 3-2012 PURPOSE OF THIS STANDARD Fairfield is committed to continuous product quality improvement. Our management team is convinced that only with

More information

BALANCED SCORECARD (BSC) Ratapol Wudhikarn, Ph.d. Knowledge management College of Arts, Media and Technology

BALANCED SCORECARD (BSC) Ratapol Wudhikarn, Ph.d. Knowledge management College of Arts, Media and Technology BALANCED SCORECARD (BSC) Ratapol Wudhikarn, Ph.d. Knowledge management College of Arts, Media and Technology Contents IC and BSC A concept of BSC The BSC as a management system Why does business need a

More information

SECURITY METRICS MANAGEMENT

SECURITY METRICS MANAGEMENT SECURITY METRICS MANAGEMENT Presenters: Ray Bernard, PSP Bernard J. Scaglione, CPP September 26, 2007 The Basics of Security Metrics Management The Corporate Management and Shareholder View of Security

More information

Supplier Quality Manual

Supplier Quality Manual including subsidiaries of Mexico and Canada Supplier Quality Manual Issue date: March 1, 2010 Revised: April 7, 2011 Page 1 of 14 Corporate Quality Statement Quality plays a vital role in SCHOTT Gemtron

More information

BAITY SCREW MACHINE PRODUCTS QUALITY MANUAL

BAITY SCREW MACHINE PRODUCTS QUALITY MANUAL BAITY SCREW MACHINE PRODUCTS QUALITY MANUAL Page 1 of 33 TABLE OF CONTENTS SECTION TITLE PAGE 0 Company Introduction... 4 0 Organizational Chart.. 5 1 Scope.. 6 2 Related Documents... 6 3 Terminology...

More information

Boost Your Digital Journey with SAP MaxAttention

Boost Your Digital Journey with SAP MaxAttention SAP Service and Support Boost Your Digital Journey with SAP MaxAttention Today s economy is a digital economy where nearly everything and everyone is connected. For businesses like yours, the opportunities

More information

Agilent Technologies

Agilent Technologies Η Supplier Performance Agilent Technologies Supplier Performance Technology Quality Responsiveness Delivery Cost Environment Agilent Restricted 2000 TABLE OF CONTENTS Introduction... 3 Technology... 4

More information

Operations Management

Operations Management 9-1 Management of Quality Operations Management William J. Stevenson 8 th edition 9-2 Management of Quality CHAPTER 9 Management of Quality McGraw-Hill/Irwin Operations Management, Eighth Edition, by William

More information

DevOps. Changing the way you deliver software

DevOps. Changing the way you deliver software DevOps Changing the way you deliver software Who is this guy? John O Bryant Director of Application Development at HealtheSystems IT and Test Automation for over 17 years Focus on building automated test

More information

Document Number: QSP-06-01

Document Number: QSP-06-01 Page 1 of 1 Introduction to the Fluke Biomedical Supplier Handbook Dear Fluke Supplier, The Fluke Biomedical Supplier Handbook was written for you to better understand Fluke and Fluke s engagement with

More information

Continuous Improvement Toolkit. Traffic Light Assessment. Continuous Improvement Toolkit.

Continuous Improvement Toolkit. Traffic Light Assessment. Continuous Improvement Toolkit. Continuous Improvement Toolkit Traffic Light Assessment The Continuous Improvement Map Managing Risk FMEA Understanding Performance Check Sheets Data Collection PDPC RAID Log* Risk Assessment* Fault Tree

More information

Promoting Quality OINDP Components- A Supplier Perspective

Promoting Quality OINDP Components- A Supplier Perspective Promoting Quality OINDP Components- A Supplier Perspective Tom Gaspar Vice President Quality Assurance, Manufacturing and Development Support West Pharmaceutical Services IPAC-RS Conference November 2006

More information