Schedule Module Exploration Systems Engineering, version 1.0

Size: px
Start display at page:

Download "Schedule Module Exploration Systems Engineering, version 1.0"

Transcription

1 Schedule Module Exploration Systems Engineering, version.0 Exploration Systems Engineering: Schedule Module

2 Module Purpose: Schedule To understand the different types of schedules: Gantt chart, milestone chart, network schedules. To recognize their advantages and disadvantages. To introduce the key concepts of critical path and float as applied to network scheduling. To show how to prepare a schedule and estimate activity durations. To introduce schedule margin recommendations. To discuss example schedule performance measures and reporting formats. Exploration Systems Engineering: Schedule Module 2

3 The When: Project Schedule Provides a framework of timephased and coordinated activities which represent the plan for completing the project within established constraints. Used: To integrate all elements of a project as a function of time and flow As a communication tool across the project team As a basis for assessing project status For project management control Key inputs: The work breakdown structure (WBS) External constraints (such as imposed launch date) Required milestones (such as technical reviews) Major deliverables Imposed funding profiles (can only get so much done for $X) Exploration Systems Engineering: Schedule Module 3

4 Scheduling Approaches Gantt chart: A graphic portrayal of a project which shows the activities to be completed and the time to complete represented by horizontal lines drawn in proportion to the duration of the activity. Milestone chart: A graphic portrayal of a project that shows the events to be completed on a timeline. Network scheduling Critical Path Method (CPM): A graphical technique that aids understanding of the dependency of events in a project and the time required to complete them. Program Evaluation and Review Technique (PERT): A technique based on constructing a network model of integrated activities and events. Difference from CPM: uses statistical theory and probability to make a determination of duration time for each task and the likelihood of an event being on schedule. Exploration Systems Engineering: Schedule Module 4

5 Gantt Chart Format aka Bar Charts Gantt and milestone charts are best used for displaying the planned activities and events of a project and the progress in meeting them. This makes them very useful for presenting schedule and program status information in a concise simple format at such things as program or activity reviews. Because of its simplicity and ease of interpretation, it is a particularly good tool for communicating to higher management when information must be presented quickly and efficiently. Exploration Systems Engineering: Schedule Module 5

6 Example Milestone Chart Preformulation Phase A Phase B Phase C/D NonTraditional = 0% Complete = 00% Complete FY05 FY06 FY07 FY08 FY09 FY0 FY FY2 FY3 Flight Test/ Mission Milestones LAS LAS2 LAS3 RRF RRF2 RRF3 LAS4 ISS ISS2 UCM PC PC2 ISS3 Program Integration L Req Baseline Review PreNAR Kickoff L2 SRR Complete PreNAR Complete L2 SDR NAR PDR Complete CDR Complete CEV Delivery of Crew & Service Module ATP CEV SRR Contractor &2 SRR SDR PDR CDR LAS LAS2 LAS3 RRF RRF2 RRF3 LAS4 ISS PC Unpressurized payload structure Delivery of Launch Abort System LAS LAS2 LAS3 RRF RRF2 LAS4 RRF3 ISS CLV System Engineering & Integration Gov t Lead SRR Jun PDR Feb CDR Jul First Stage ATP SRR PDR CDR RRF RRF2 RRF3 Del ISS to KSC Upper Stage Gov t Lead SRR PDR CDR MPTA Fab, Integ & Test Jul Nov Apr Del for RRF2 RRF3 US ISS to KSC Upper Stage Engine (RS25d/e) ATP SRR PDR CDR Dev Eng Needed MPTA RRF3 Del for RRF2 ISS Exploration Systems Engineering: Schedule Module 6

7 Milestone or Event Charts Key features: Displays activity milestones against time. Lines represent duration of a single activity with appropriate start and stop milestones. Open triangles indicate milestones planned. Closed triangles indicate milestones completed. Example Symbols Used on Milestone Charts Exploration Systems Engineering: Schedule Module 7

8 Gantt & Milestone Charts ADVANTAGES ) Simple to prepare and update, 2) Information portrayed in easily understood format, 3) Relatively inexpensive to prepare using software tools, 4) Relate activities and calendar dates, 5) Easy to roll up information into summary form, 6) Useful first step for preparation of more complex type schedules 7) Reliable estimates can be developed when the work is repetitive and when the product is easy to measure quantitatively. DISADVANTAGES ) Difficult to use for detailed schedule analysis 2) Do not show the effects of late or early activity starts, 3) Do not represent dependencies among activities as well as other scheduling methods 4) Do not reflect the uncertainty in the planned activity duration or event date 5) Only as reliable as the estimates on which they are based; looking at the chart doesn t indicate which estimates are the most reliable 6) Do not allow quick or easy exploration of the consequences of alternative actions. Exploration Systems Engineering: Schedule Module 8

9 Example: Network Schedule for Computer Installation Program Network schedule data consists of: Activities Dependencies between activities Milestones that occur as a result of one or more activities Duration of each activity Activity Legend: A Build raised floor B Build air conditioning vents C Bring special power source to computer room D : 5 days D Install wiring and connect to power source E Install air conditioning F Await delivery of computer G Install computer F : 4 days G : 6 days Program Start Program Complete Exploration Systems Engineering: Schedule Module 9

10 Example: Critical Path and Float Critical Path is the sequence of activities that will take the longest to accomplish. Any delay on this path will delay the project. Example: 4 days, Activities that are not on the critical path have a certain amount of time that they can be delayed until they, too are on the critical path. This time is called float (or slack). Example, Path : 9 days => 5 days of float + Example, Path 2: 3 days => day of float + D : 5 days F : 4 days G : 6 days Program Start Program Complete Exploration Systems Engineering: Schedule Module 0

11 Time Estimates Used in PERT Using PERT, it is possible to determine an expected time for completion of a project and the likelihood (probability) that this expected completion time will be met. Projects best suited for PERT are oneofakind complex programs that involve new technology or processes and research and development. Three estimates are required: Most Likely, m Optimistic, a Pessimistic, b Expected completion time, or mean time a m b t e = a+4m+b 6 Beta Probability Distribution Exploration Systems Engineering: Schedule Module

12 Network Schedules ADVANTAGES ) Provide graphical portrayal of project activities and relationships/constraints 2) Force communications among team members in identifying activities 3) Organize what would otherwise be confusing material, making it easier for managers to make tradeoffs and develop alternative plans 4) Give managers more control over activities/events and schedules 5) Facilitate what if exercises 6) Provide the basis for Gantt and milestone chart information DISADVANTAGES ) Network construction can be difficult and time consuming. 2) Only as sound as the activity time and resource estimates. 3) Sometimes difficult to portray graphically too many lines, nodes and intersections. 4) Not particularly good for conveying information in briefings/reviews. 5) Complex networks, once sketched out on a large wall chart, tend to become the focus of management attention when, in fact, a manager should be paying attention to factors not on the chart, such as management/ labor relations. Exploration Systems Engineering: Schedule Module 2

13 Schedule Preparation A fivestep process for schedule preparation that is commonly used in project management includes:. Activity definition what has to be accomplished? 2. Activity sequencing what has to occur first, second? 3. Activity duration estimation how long does activity take? 4. Schedule development what are realistic start & finish dates? 5. Schedule control how to manage changes & track performance? Risk is inherent in all programs, and scheduling is one element of risk. Uncertainty introduced in estimating the duration of each activity causes most schedule risk. Project managers must assess the likelihood of failing to meet schedule plans and the impact of that failure. Probabilistic techniques have proven to be very useful in conducting these assessments. Exploration Systems Engineering: Schedule Module 3

14 Activity Duration Estimating Activity duration estimating is the determination of the time required to complete the activities that make up the project. This is one of the most difficult aspects of schedule development and should be performed by people who are most familiar with the activity. Two key inputs to the estimation process. the resources/workforce required and assigned for the activity 2. the capabilities of the resources assigned. The following techniques are commonly used in estimating activity durations: Expert judgment guided by historical information, Analogous estimating based on experience of similar programs, Parametric estimating based on formulas describing relationships among project parameters and time, and Use of simulation to develop distributions of probable duration of each activity. Note: If probability distributions not used, then estimates should include a range of possible values, e.g., 3 weeks ± week, and a clear statement of the assumptions made in the estimation process. Exploration Systems Engineering: Schedule Module 4

15 Schedule Margin Schedule Margin Rate month/year 2 months/year week/month (2.8 months/year) Flight Missions/ Flight Experiment Projects Implementation Start to Delivery to Assembly & Test/ Instrument I&T Assembly & Test Start To Ship to Launch Site/ Instrument I&T Start to Delivery To ATLO Delivery to Launch Site to Launch Definitions: Total Schedule = Critical Path (i.e., Planned Activities) + Schedule Margin Schedule Margin = No Planned Activities, but Funded Schedule Schedule Margin Rate = Schedule Margin/(Planned Activity + Schedule Margin) Exploration Systems Engineering: Schedule Module 5

16 Additional Schedule Materials Next few slides: Technical Performance Measures: ü Schedule examples for James Webb Space Telescope (JWST) Resource Loaded Schedules Exploration Systems Engineering: Schedule Module

17 James Webb Space Telescope Cumulative Milestones Tracking Chart Cumulative number of milestones * Tracking start point = / Mar07 A pr07 May07 Jun07 Jul07 A ug07 Sep07 Oct07 Nov07 Dec07 Jan08 Feb08 Baseline (JWST Rev E) A ctuals Forecast Exploration Systems Engineering: Schedule Module 7

18 PROJECT TREND ANALYSIS 0 JWST Total Mission Slack (June 203 LRD) 8 Months of Slack Jan07 Feb07 Mar07 Apr07 May07 Jun07 Jul07 Aug07 Sep07 Oct07 Nov07 Dec07 Jan08 Mission Total Slack Desired Total Slack (one month per year) LRD = Launch Readiness Date Exploration Systems Engineering: Schedule Module 8

19 Exploration Systems Engineering: Schedule Module Resource Loaded Schedules Important to do: Assure no resource conflicts Staff being assigned efficiently Minimize gaps for engineering personnel (EPs) Schedule ) Eng EPs Act A Act B Act C Act D Act E Act F Act G Act H 2) Mfg/Test EPs Act A Act B Act C Act D Act E Act F Act G Act H 3) Test Facilities Act A Act B Act C Act D Act E Act F Act G Act H E D H C G A F B Project Complete Months Resources Required Number of resources required defined for each activity, each month Activity C requires: 2 Eng EPs 7 Mfg/Test EPs 0 Test Facilities

20 Module Summary: Schedule There are different methods for displaying project schedule information. Gantt and Milestone charts relate activities to calendar dates in an easily understood format. Network schedules show the dependencies between activities in a graphical portrayal with activity durations. Critical Path is the sequence of activities that will take the longest to accomplish. Any delay on this path will delay the project. Activities that are not on the critical path have a certain amount of time that they can be delayed until they, too are on the critical path. This time is called float (or slack). There is inherent risk in developing schedules. Probabilistic techniques can be used to assess the risk. For space missions, guidelines exist for determining schedule margin. Schedule information, such as the accomplishment of milestones or the amount of schedule slack, can be used to report project status/progress (as a form of technical performance measures). Exploration Systems Engineering: Schedule Module 20

21 Exploration Systems Engineering: Schedule Module Backup Slides for Schedule Module

22 Additional Schedule Topics Additional topics if you are interested in adding to the lecture: Earned Value Management (EVM) A tool for measuring and assessing project performance through the integration of technical scope with schedule and cost objectives during the execution of the project. EVM provides quantification of technical progress, enabling management to gain insight into project status and project completion costs and schedules. Two essential characteristics of successful EVM are EVM system data integrity and carefully targeted monthly EVM data analyses (i.e., risky WBS elements). One can dedicate an entire lecture just on EVM. Note that many contractors and government agencies have entire courses devoted to teaching EVM. Schedule Software Tools, such as Microsoft Project Primavera Exploration Systems Engineering: Schedule Module 22

23 Network Schedule Example Network schedule data consists of: Activities Dependencies between activities Milestones that occur as a result of one or more activities Duration of each activity H In this example, the lines represent project activities A through H; the nodes represent the events associated with the beginning and end of the activities. The network shows the following constraints among the activities: activity A must be completed before activities B, C, or D can begin; B must be completed before E can begin; F cannot begin until D is completed; G cannot begin until C and E are done, and H cannot begin until F and G are completed. In addition to showing this type of sequencing constraints, network schedules can also show the time and resources planned for each activity and thus provide managers with a mechanism to monitor and control the project. Exploration Systems Engineering: Schedule Module 23

Project Management. Learning Objectives. What are Projects? Dr. Richard Jerz. Describe or Explain:

Project Management. Learning Objectives. What are Projects? Dr. Richard Jerz. Describe or Explain: Project Management Dr. Richard Jerz 1 Learning Objectives Describe or Explain: What are projects The role of the project manager Work breakdown structure Project management tools (Gantt, PERT, & CPM) The

More information

Estimating Project Schedule-Time and Cost

Estimating Project Schedule-Time and Cost Estimating Project Schedule-Time and Cost Chapter 5 5 1 Where We Are Now 5 2 1 Overview Seminar Agenda What is involved in schedule and cost management? In-depth Determining the sequence of activities

More information

PMP Exam Preparation Course Project Time Management

PMP Exam Preparation Course Project Time Management Project Time Management 1 Project Time Management Processes Define Activities Sequence Activities Estimate Activity Resources Estimate Activity duration Develop Schedule Control Schedule In some projects,

More information

Operations Management

Operations Management 17-1 Project Management Operations Management William J. Stevenson 8 th edition 17-2 Project Management CHAPTER 17 Project Management McGraw-Hill/Irwin Operations Management, Eighth Edition, by William

More information

For the PMP Exam using PMBOK Guide 5 th Edition. PMI, PMP, PMBOK Guide are registered trade marks of Project Management Institute, Inc.

For the PMP Exam using PMBOK Guide 5 th Edition. PMI, PMP, PMBOK Guide are registered trade marks of Project Management Institute, Inc. For the PMP Exam using PMBOK Guide 5 th Edition PMI, PMP, PMBOK Guide are registered trade marks of Project Management Institute, Inc. 1 Contacts Name: Khaled El-Nakib, MSc, PMP, PMI-RMP URL: http://www.khaledelnakib.com

More information

Project Time Management

Project Time Management Project Time Management Understand the importance of project schedules and good project time management. Define activities as the basis for developing project schedules. Describe how project managers use

More information

Project Management Concepts, Tools & Techniques

Project Management Concepts, Tools & Techniques Project Management Concepts, Tools & Techniques Course ISI-1438 5 Days Instructor-led, Hands on Introduction This highly interactive 5 day, instructor-led workshop is designed to give participants a solid

More information

Cambridge International AS & A Level Computer Science

Cambridge International AS & A Level Computer Science Topic Support Guide Cambridge International AS & A Level Computer Science 9608 For examination from 2017 Topic 4.4.3 Project management PERT and GANTT charts Cambridge International Examinations retains

More information

Software Project Management

Software Project Management Software Project Management Dr. M.E. Fayad, Professor Computer Engineering Department College of Engineering, San José State University One Washington Square, San José, CA 95192-0180 E-mail: m.fayad@sjsu.edu

More information

Plan Your Work, Work Your Plan. Dr. R. Rockland Chair and Professor, Department of Engineering Technology New Jersey Institute of Technology

Plan Your Work, Work Your Plan. Dr. R. Rockland Chair and Professor, Department of Engineering Technology New Jersey Institute of Technology Plan Your Work, Work Your Plan Dr. R. Rockland Chair and Professor, Department of Engineering Technology New Jersey Institute of Technology Agenda Understand what a project is Understand the basics of

More information

Program Evaluation and Review Technique (PERT)

Program Evaluation and Review Technique (PERT) Program Evaluation and Review Technique (PERT) PERT Bar charts and CPM networks assume all activity durations are constant or deterministic. The assumption of constant durations may not be realistic because

More information

Electric Forward Market Report

Electric Forward Market Report Mar-01 Mar-02 Jun-02 Sep-02 Dec-02 Mar-03 Jun-03 Sep-03 Dec-03 Mar-04 Jun-04 Sep-04 Dec-04 Mar-05 May-05 Aug-05 Nov-05 Feb-06 Jun-06 Sep-06 Dec-06 Mar-07 Jun-07 Sep-07 Dec-07 Apr-08 Jun-08 Sep-08 Dec-08

More information

Schedule Guidance Document

Schedule Guidance Document Schedule Guidance Document Version: 1.2 Effective Date: August 20, 2013 Contents 1. Purpose... 1 2. Applicability and Basic Requirements... 2 3. Baseline Schedule... 3 3.1. General... 3 3.2. Schedule Work

More information

Administration Division Public Works Department Anchorage: Performance. Value. Results.

Administration Division Public Works Department Anchorage: Performance. Value. Results. Administration Division Anchorage: Performance. Value. Results. Mission Provide administrative, budgetary, fiscal, and personnel support to ensure departmental compliance with Municipal policies and procedures,

More information

STO Navigator Canada Best-Practices Manual

STO Navigator Canada Best-Practices Manual Page 1 / 5 24.1- SCHEDULING METHODOLOGY 24.1.1. PURPOSE The following best-practice guideline provides the STO Project Controls Team with a defined methodology for scheduling, to accurately identify the

More information

Introduction. Project Scheduling. Morgan State University ARCH 738: REAL ESTATE PROJECT MANAGEMENT. Jason E. Charalambides, PhD, M.

Introduction. Project Scheduling. Morgan State University ARCH 738: REAL ESTATE PROJECT MANAGEMENT. Jason E. Charalambides, PhD, M. Project Scheduling ARCH 738: REAL ESTATE PROJECT MANAGEMENT Morgan State University Jason E. Charalambides, PhD, M.ASCE, AIA, ENV_SP (This material has been prepared for educational purposes) Introduction

More information

1.Which of the items listed below is not one of the software engineering layers?

1.Which of the items listed below is not one of the software engineering layers? 1.Which of the items listed below is not one of the software engineering layers? Process Manufacturing Methods Tools 2.The software quality assurance activity which is performed to check errors in logic,

More information

Course Outline. TEC D 205 Engineering Tech Project Planning Olympic College Bremerton, WA. Week 1 Chapter 4: DEFINING THE PROJECT

Course Outline. TEC D 205 Engineering Tech Project Planning Olympic College Bremerton, WA. Week 1 Chapter 4: DEFINING THE PROJECT Course Outline TEC D 205 Engineering Tech Project Planning Week 1 Chapter 4: DEFINING THE PROJECT 1. Step one: Defining the Project Scope A. Employing a Project Scope Checklist 1. Project objective 2.

More information

Developing and Delivering Complex Projects using Quantitative Risk Analysis Colin Cropley BE(Chem), PMP, Cert PRINCE2 Practitioner Managing Director,

Developing and Delivering Complex Projects using Quantitative Risk Analysis Colin Cropley BE(Chem), PMP, Cert PRINCE2 Practitioner Managing Director, Developing and Delivering Complex Projects using Quantitative Risk Analysis Colin Cropley BE(Chem), PMP, Cert PRINCE2 Practitioner Managing Director, Risk Integration Management Pty Ltd Presentation Outline

More information

COST LOADED CONSTRUCTION SCHEDULES PART 1 - GENERAL

COST LOADED CONSTRUCTION SCHEDULES PART 1 - GENERAL SECTION 01310 COST LOADED CONSTRUCTION SCHEDULES PART 1 - GENERAL 1.01 SCOPE: A. COST LOADED CONSTRUCTION SCHEDULE (Construction Schedule): The WORK under this Contract shall be planned, scheduled, executed,

More information

Scheduling. Why Schedule? Scheduling will: Delivering On Your Promises

Scheduling. Why Schedule? Scheduling will: Delivering On Your Promises Scheduling Delivering On Your Promises Why Schedule? Don t need to, I ve done this before. I have the schedule in my head. Nobody will pay attention to it. Why bother, it just changes. I m on the line

More information

Planning & Scheduling CSTM 102

Planning & Scheduling CSTM 102 Planning & Scheduling CSTM 102 Items Big A Project on Website Thursday Discuss Big A Project next Tuesday April 18, 2011 CPM Scheduling You were the successful bidder! What s next? Procurement/Buy

More information

12/26/2013. Sharif University of Technology. Session#11. Instructor. Class time. Course evaluation. International Campus Kish

12/26/2013. Sharif University of Technology. Session#11. Instructor. Class time. Course evaluation. International Campus Kish International Campus Kish Sharif University of Technology Session#11 Instructor Omid Fatahi Valilai, Ph.D. Industrial Engineering Department, Sharif University of Technology Email: Fvalilai@Sharif.edu,

More information

Microsoft Project Tips & Tricks. Project Solutions Group, Inc.

Microsoft Project Tips & Tricks. Project Solutions Group, Inc. Microsoft Project Tips & Tricks Project Solutions Group, Inc. Objectives Formatting & Printing Gantt Charts Leveling Resources Calculating Costs & Pricing Information Collecting & Entering Project Actuals

More information

MANAGING CONSTRUCTION SCHEDULES. Kelly Selman, P.E. Dallas District. Date. Dallas District October 10, 2017

MANAGING CONSTRUCTION SCHEDULES. Kelly Selman, P.E. Dallas District. Date. Dallas District October 10, 2017 MANAGING CONSTRUCTION SCHEDULES Kelly Selman, P.E. Dallas District Dallas District October 10, 2017 Date Types of Schedules Contract Time Schedule A+B Bidding Lane Rental Preliminary Schedule Project Baseline

More information

Test your Understanding-The Answers

Test your Understanding-The Answers Table of Contents Module 1 Project management methodology... 2 A. Introduction to Project Management... 2 B. The Phases of Project Management... 2 C. Project Management Methodology questions... 2 Module

More information

Chapter 3 Managing the Information Systems Project

Chapter 3 Managing the Information Systems Project Princess Noura University Computer Science and Information Faculty Information Systems Department IS321 Chapter 3 Managing the Information Systems Project Learning Objectives Discuss skills required to

More information

Project Planning and Estimating DJ

Project Planning and Estimating DJ Project Planning and Estimating DJ201 0807 Copyright ESI International August 2007 All rights reserved. No part of this publication may be reproduced, stored in a retrieval system, or transmitted, in any

More information

Traffic Division Public Works Department Anchorage: Performance. Value. Results.

Traffic Division Public Works Department Anchorage: Performance. Value. Results. Mission Promote safe and efficient area-wide transportation that meets the needs of the community and the Anchorage Municipal Traffic Code requirements. Direct Services Design, operate and maintain the

More information

Views and Layouts for Program Management

Views and Layouts for Program Management MnDOT Project Management Office Presents: Views and Layouts for Program Management Presenter: Jonathan McNatty Senior Schedule Consultant DRMcNatty & Associates, Inc. Housekeeping Items Lines will be muted

More information

Today s Lecture. Fall 2004 SE 101 Introduction to Software Engineering 2

Today s Lecture. Fall 2004 SE 101 Introduction to Software Engineering 2 Project Planning Today s Lecture 1. Intro to Software Engineering 2. Inexact quantities 3. Error propagation 4. Floating-point numbers 5. Design process 6. Teamwork - no web review 7. Project planning

More information

SUPPLY CHAIN EXCELLENCE IN WIDEX. June 2016

SUPPLY CHAIN EXCELLENCE IN WIDEX. June 2016 SUPPLY CHAIN EXCELLENCE IN WIDEX June 2016 AGENDA 1. Presentation of Widex 2. The first year Creating a solid base 3. The second year Stabilizing the performance 4. The next steps Unleashing the competitive

More information

SPECIFICATIONS - DETAILED PROVISIONS Section Project Control Schedule C O N T E N T S

SPECIFICATIONS - DETAILED PROVISIONS Section Project Control Schedule C O N T E N T S SPECIFICATIONS - DETAILED PROVISIONS Section 01310 - Project Control Schedule C O N T E N T S PART 1 - SCHEDULE REQUIREMENTS PROGRESS SCHEDULE... 1 PART 2 - SUBMITTAL PROCEDURES... 2 PART 3 - DEFINITIONS...

More information

Project Management CSC 310 Spring 2017 Howard Rosenthal

Project Management CSC 310 Spring 2017 Howard Rosenthal Project Management CSC 310 Spring 2017 Howard Rosenthal 1 No?ce This course is based on and includes material from the text: Effective Project Management - Traditional, Agile, Extreme 7TH Edition Authors:

More information

LONG INTERNATIONAL. Richard J. Long, P.E., Andrew Avalon, P.E., PSP and Ronald J. Rider, MBA

LONG INTERNATIONAL. Richard J. Long, P.E., Andrew Avalon, P.E., PSP and Ronald J. Rider, MBA Richard J. Long, P.E., Andrew Avalon, P.E., PSP and Ronald J. Rider, MBA LONG INTERNATIONAL Long International, Inc. 5265 Skytrail Drive Littleton, Colorado 80123-1566 USA Telephone: (303) 972-2443 Fax:

More information

PROJECT TITLE PROJECT NO: CONTRACT TITLE UNIVERSITY OF CALIFORNIA, DAVIS CITY, CALIFORNIA

PROJECT TITLE PROJECT NO: CONTRACT TITLE UNIVERSITY OF CALIFORNIA, DAVIS CITY, CALIFORNIA This section is used for projects under $1,000,000 use other section if more than $1M SECTION 01 32 00 CONSTRUCTION PROGRESS DOCUMENTATION PART 1 - GENERAL 1.1 SCOPE A. Preliminary Contract Schedule, Contract

More information

Project management tools and techniques assist project managers and their teams in various aspects of project management Some specific ones include

Project management tools and techniques assist project managers and their teams in various aspects of project management Some specific ones include Abeer Bin Humaid Project management is the application of knowledge, skills, tools, and techniques to project activities in order to meet project requirements Triple constraints of project management Every

More information

Objectives of Project Management Framework. What are the Characteristics Of Project. Activities involved Project Management

Objectives of Project Management Framework. What are the Characteristics Of Project. Activities involved Project Management PMP Training Training Topics Chapter 1 Introduction to PMP Objectives of PMP Requirements for PMP Exam About PMP Exam PMP Exam Syllabus Chapter 2 Objectives of Project Management Framework What is Project

More information

P6 Instructors Sample Presentation

P6 Instructors Sample Presentation Welcome to the Eastwood Harris Pty Ltd Primavera P6 Versions 8.1 to 8.4 Professional and Optional Client 3 day training course PMI REP No 3001 Course Number PP6 Page 2 Page 4 Administration Evacuation

More information

Guten Tag. (good day)

Guten Tag. (good day) Guten Tag (good day) Project Management Process Groups Project 4. Integration Management Knowledge Areas 13. Stakeholder Initiating Planning Executing 5. Scope 6. Time 7. Cost 8. Quality 9. Human Resources

More information

Topic # 12. CIS Project Management: an overview

Topic # 12. CIS Project Management: an overview Topic # 12 CIS Project Management: an overview Project Planning Major Activities during Project Planning: 1) describing project scope, alternatives, and feasibility; 2) dividing the project into manageable

More information

Operations Management, 11e (Heizer/Render) Chapter 3 Project Management. Section 1 The Importance of Project Management

Operations Management, 11e (Heizer/Render) Chapter 3 Project Management. Section 1 The Importance of Project Management Instant download and all chapters Test Bank Operations Management 11th Edition Jay Heizer, Barry Render https://testbankdata.com/download/test-bank-operations-management-11thedition-jay-heizer-barry-render/

More information

PMP Sample Questions Click here for PMP Questions. Question No : 1 Which of the following is an output of Define Scope?

PMP Sample Questions  Click here for PMP Questions. Question No : 1 Which of the following is an output of Define Scope? PMP Sample Questions www.techfaq360.com Click here for 1600+ PMP Questions Question No : 1 Which of the following is an output of Define Scope? A. Accepted deliverables B. Change Requests C. Project document

More information

Planning & Scheduling

Planning & Scheduling Planning & Scheduling Dr. Nabil I. El Sawalhi Assistant Professor of Construction Management Chapter 3 1 Planning Successful Project Management depends on continues planning. The activities of Designers,

More information

Welcome to the Eastwood Harris Pty Ltd PRINCE2 TM Revised 2009 and Microsoft Project 2010 training course

Welcome to the Eastwood Harris Pty Ltd PRINCE2 TM Revised 2009 and Microsoft Project 2010 training course Welcome to the Eastwood Harris Pty Ltd PRINCE2 TM Revised 2009 and Microsoft Project 2010 training course Administration Evacuation Timings, meals and facilities Mobile phones and emails Introductions

More information

Certificate IV in Project Management Student Assessment Guide

Certificate IV in Project Management Student Assessment Guide Overview The assessment for the Certificate IV in Project Management comprises Assessment Task Description Percentage Individual Assignment Unit Tests Development of a detailed Project Management Plan

More information

PowerPoint. presentation

PowerPoint. presentation presentation PowerPoint Unit 308: Monitor information systems Understand how information systems are used 2015 City and Guilds of London Institute. All rights reserved. 1 of 27 Lesson objectives Be able

More information

PROJECT TIME MANAGEMENT

PROJECT TIME MANAGEMENT PROJECT TIME MANAGEMENT ESTIMATE ACTIVITY DURATION PLANNING MONITORING & CONTROLLING 6.1 Plan Schedule Mgt 6.7 Control Schedule 6.2 Define Activities 6.3 Sequence Activities 6.4 Estimate Activity Resources

More information

S O Seminar Objective

S O Seminar Objective Introduction to Project Management Welcome! Presenter: Bob Hull CalACT Conference September 202 S O Seminar Objective To provide an overview of project management processes and provide some skills, tools

More information

Microsoft Office Project 2010 Basic Course 01: Getting Started

Microsoft Office Project 2010 Basic Course 01: Getting Started Microsoft Office Project 2010 Basic Course 01: Getting Started Slide 1 Topic A Project Management Concepts Slide 2 Project Constraints Slide 3 Phases of Project Management The initial Phase Initiating

More information

PMBOK Guide Fifth Edition Pre Release Version October 10, 2012

PMBOK Guide Fifth Edition Pre Release Version October 10, 2012 5.3.1 Define Scope: Inputs PMBOK Guide Fifth Edition 5.3.1.1 Scope Management Plan Described in Section 5.1.3.1.The scope management plan is a component of the project management plan that establishes

More information

PMI Scheduling Professional (PMI-SP)

PMI Scheduling Professional (PMI-SP) PMI Scheduling Professional (PMI-SP) E X A M I N AT I O N CO N T E N T O U T L I N E Project Management Institute PMI Scheduling Professional (PMI-SP) Exam Content Outline Published by: Project Management

More information

MODULE 15 OPERATIONAL PLANNING TECHNIQUES (USE OF PLANNING TOOLS LIKE GANTT CHART, PERT/CPM)

MODULE 15 OPERATIONAL PLANNING TECHNIQUES (USE OF PLANNING TOOLS LIKE GANTT CHART, PERT/CPM) MODULE 15 OPERATIONAL PLANNING TECHNIQUES (USE OF PLANNING TOOLS LIKE GANTT CHART, PERT/CPM) Content Writer/Author: Email id: Mrs. RENU ARORA renu214@gmail.com Structure of Module/Syllabus of module(define

More information

Leading Indicators for Systems Engineering Effectiveness Presentation for NDIA SE Conference October 28, 2009

Leading Indicators for Systems Engineering Effectiveness Presentation for NDIA SE Conference October 28, 2009 Leading Indicators for Systems Engineering Effectiveness Presentation for NDIA SE Conference October 28, 2009 Garry Roedler Lockheed Martin 1 Growing Interest in SE Effectiveness Questions about the effectiveness

More information

Welcome to the Eastwood Harris Pty Ltd Primavera P6 Versions 8.2 EPPM Web Tool 2 day training course Enterprise Portfolio Project Management

Welcome to the Eastwood Harris Pty Ltd Primavera P6 Versions 8.2 EPPM Web Tool 2 day training course Enterprise Portfolio Project Management Welcome to the Eastwood Harris Pty Ltd Primavera P6 Versions 8.2 EPPM Web Tool 2 day training course Enterprise Portfolio Project Management Page 2 Copyright Eastwood Harris Pty Ltd IMPORTANT POINTS FOR

More information

PORTFOLIO OPTIMIZATION MODEL FOR ELECTRICITY PURCHASE IN LIBERALIZED ENERGY MARKETS

PORTFOLIO OPTIMIZATION MODEL FOR ELECTRICITY PURCHASE IN LIBERALIZED ENERGY MARKETS PORTFOLIO OPTIMIZATION MODEL FOR ELECTRICITY PURCHASE IN LIBERALIZED ENERGY MARKETS Edwin Castro CNEE Guatemala Viena, september 2009 What is the reason to develop this model? In our own electricity market

More information

Epicor Selection and Implementation

Epicor Selection and Implementation Epicor Selection and Implementation Keith Cote UFP Technologies 1 Company Background UFP Technologies is a producer of innovative custom-engineered components, specialty packaging, and end products. Founded

More information

Primavera P6 R8.3 Professional Fundamentals Training Course Outline

Primavera P6 R8.3 Professional Fundamentals Training Course Outline Course Overview Prescience Technology is an Oracle Platinum Partner and specialist provider of Primavera Services. This Prescience course introduces the user to Oracle Primavera P6 version 8.3 Professional

More information

Meter Data Management System (MDMS) Sharing. Ricky Ip CLP Project Manager

Meter Data Management System (MDMS) Sharing. Ricky Ip CLP Project Manager Meter Data Management System (MDMS) Sharing Ricky Ip CLP Manager Agenda Introduction Objectives Critical Success Factors Change Management Lessons Learned 2 CLP Power Hong Kong Limited (CLP Power) is the

More information

Agricultural Projects

Agricultural Projects Development and Management of Agricultural Projects Introduction Communicate Product Quality and Risk Developing a Project Ten (10) Steps To Creating a Project Plan March 11 th 2017 Facilitated by Arnold

More information

Extreme Agile Implementation and Creating a Value Delivery Office

Extreme Agile Implementation and Creating a Value Delivery Office Extreme Agile Implementation and Creating a Value Delivery Office Anup Deshpande Sr. Leader of Agile Portfolio Management 1 COPYRIGHT 2017 Anup Deshpande. ALL RIGHTS RESERVED For Informational Purposes

More information

GLOSSARY AND INDEX. Glossary Index Project Management Institute, 130 South State Road, Upper Darby, PA USA 155

GLOSSARY AND INDEX. Glossary Index Project Management Institute, 130 South State Road, Upper Darby, PA USA 155 GLOSSARY AND INDEX Glossary Index iv 1996 Project Management Institute, 130 South State Road, Upper Darby, PA 19082 USA 155 156 NOTES GLOSSARY 1. Inclusions and Exclusions This glossary includes terms

More information

Asta Powerproject NEW FEATURES IN VERSION elecosoft.com. Asta Powerproject: The power behind successful projects

Asta Powerproject NEW FEATURES IN VERSION elecosoft.com. Asta Powerproject: The power behind successful projects Asta Powerproject NEW FEATURES IN VERSION 14.0.01 elecosoft.com Assess and identify risks within projects with Risk Analysis Asta Powerproject now includes Risk Analysis, which was previously available

More information

IAF Advisors Energy Market Outlook Kyle Cooper, (713) , October 31, 2014

IAF Advisors Energy Market Outlook Kyle Cooper, (713) , October 31, 2014 IAF Advisors Energy Market Outlook Kyle Cooper, (713) 722 7171, Kyle.Cooper@IAFAdvisors.com October 31, 2014 Price Action: The December contract rose 17.5 cents (4.7%) to $3.873 on a 33.3 cent range. Price

More information

Air Force Acquisition Excellence & Change Office (AQXC) Schedule Risk Assessment (SRA) Process

Air Force Acquisition Excellence & Change Office (AQXC) Schedule Risk Assessment (SRA) Process Air Force Acquisition Excellence & Change Office (AQXC) Schedule Risk Assessment (SRA) Process Version: 2.0, 18 JAN 2012 Configuration Management Log & Draft Version Status Document Configuration Management

More information

Air Force Acquisition Excellence & Change Office (AQXC) Schedule Risk Assessment (SRA) Process

Air Force Acquisition Excellence & Change Office (AQXC) Schedule Risk Assessment (SRA) Process Air Force Acquisition Excellence & Change Office (AQXC) Schedule Risk Assessment (SRA) Process Version: 2.0, 18 JAN 2012 Configuration Management Log & Draft Version Status Document Configuration Management

More information

Project Planning and Control Using Oracle Primavera P6 : P8.3, 8.4, 15.2

Project Planning and Control Using Oracle Primavera P6 : P8.3, 8.4, 15.2 Primavera Essential Course Contents: 1. Overview Describe the Primavera modules Explain the difference between global and project-specific data Project Portfolio Management Defining the Enterprise Project

More information

The Confluence Model. Presentation to Modeling and Forecasting Working Group January 21, 2015

The Confluence Model. Presentation to Modeling and Forecasting Working Group January 21, 2015 The Confluence Model Presentation to Modeling and Forecasting Working Group January 21, 2015 Introductions Presenter: Gary Fiske Working Group Water Department staff Objective: Penetrate the Black Box

More information

Designing Incentives and Rewards

Designing Incentives and Rewards Total Rewards instructor s Manual Designing Incentives and Rewards By Dale Dwyer, Ph.D. Project Team Author: SHRM project contributor: External contributor: Copy editing: Design: Dale Dwyer, Ph.D. Nancy

More information

Lehman Brothers T Conference San Francisco. Craig DeYoung, Vice President Investor Relations December 9, 2004

Lehman Brothers T Conference San Francisco. Craig DeYoung, Vice President Investor Relations December 9, 2004 Lehman Brothers T4 2004 Conference San Francisco Craig DeYoung, Vice President Investor Relations December 9, 2004 Safe Harbor Safe Harbor Statement under the U.S. Private Securities Litigation Reform

More information

Facilities Management. FM Key Performance Indicators

Facilities Management. FM Key Performance Indicators Facilities Management FM Key Performance Indicators September 21, 2017 Facilities Management Key Volume Indicators Key Volume FM Change Evanston Chicago Full Time Equivalent (FTE) 369 +5 304 65 Acres 296

More information

Welcome to the Eastwood Harris Pty Ltd Primavera P6 Versions 8.1 & 8.2 Professional and Optional Client 3 day training course SAMPLE SLIDE SHOW

Welcome to the Eastwood Harris Pty Ltd Primavera P6 Versions 8.1 & 8.2 Professional and Optional Client 3 day training course SAMPLE SLIDE SHOW Welcome to the Eastwood Harris Pty Ltd Primavera P6 Versions 8.1 & 8.2 Professional and Optional Client 3 day training course SAMPLE SLIDE SHOW PMI REP No 3001 Course Number PP6 Page 2 Page 4 Administration

More information

Facilities Management. FM Key Performance Indicators

Facilities Management. FM Key Performance Indicators Facilities Management FM Key Performance Indicators August 15, 2017 Facilities Management Key Volume Indicators Key Volume FM Change Evanston Chicago Full Time Equivalent (FTE) 364 +11 299 65 Acres 296

More information

Construction Formwork Inventory Control Tracking System

Construction Formwork Inventory Control Tracking System Construction Formwork Inventory Control Tracking System 1 P age CASE STUDY OVERVIEW Supertech was first engaged by the subject formwork and concrete construction contractor to transition their planning,

More information

Comparing PMBOK Guide 4 th Edition, PMBOK Guide 5 th Edition, and ISO 21500

Comparing PMBOK Guide 4 th Edition, PMBOK Guide 5 th Edition, and ISO 21500 Comparing PMBOK Guide 4 th Edition, PMBOK Guide 5 th Edition, and ISO 21500 Thierry Labriet, STS STS SA, Lausanne, Switzerland +41 21 510 11 50 office@sts.ch www.sts.ch 1 Contents 1 Foreword... 3 2 Executive

More information

MINGGU Ke 2 Analisa dan Perancangan Sistem Informasi

MINGGU Ke 2 Analisa dan Perancangan Sistem Informasi MINGGU Ke 2 Analisa dan Perancangan Sistem Informasi Pokok Bahasan: Project Management Tujuan Instruksional Khusus: Learing to Choose and Manage System Information Project Referensi: (1) Hoffer, J.A.,

More information

Project Scheduling and Tracking. CIS 375 Bruce R. Maxim UM-Dearborn

Project Scheduling and Tracking. CIS 375 Bruce R. Maxim UM-Dearborn Project Scheduling and Tracking CIS 375 Bruce R. Maxim UM-Dearborn 1 What does the customer want to know? Do you understand my needs? Can you design a system to help me? How long will it take? How much

More information

CPM in Construction Management transition from 7 th to 8 th Edition. James J. O Brien Fredric L. Plotnick

CPM in Construction Management transition from 7 th to 8 th Edition. James J. O Brien Fredric L. Plotnick CPM in Construction Management transition from 7 th to 8 th Edition James J. O Brien Fredric L. Plotnick Introduction to CPM is Still Required Chapter 1. Introduction to CPM Planning and Scheduling 3 1.1

More information

Delivering End-to-End Supply Chain Excellence

Delivering End-to-End Supply Chain Excellence Delivering End-to-End Supply Chain Excellence -The DCMA Perspective- Ms. Marie A. Greening Director, Operations and Aeronautical Systems Divisions 19 March 2009 DCMA Mission We provide Contract Administration

More information

Watts Bar Nuclear Plant Unit 2 Completion Project

Watts Bar Nuclear Plant Unit 2 Completion Project Watts Bar Nuclear Plant Unit 2 Completion Project Fifth Quarterly Update to the Estimate to Complete May 2013 - July 2013 Published October 2013 Table of Contents Section 1 - Executive Summary... 3 Quarterly

More information

Primavera Training - P6 Basic Course (102)

Primavera Training - P6 Basic Course (102) Primavera Training - P6 Basic Course (102) This training session provides hands-on training for Primavera s client/server-based solution, leading participants through the entire project life cycle, from

More information

Project Forecast Survey Results Good Scheduling Practices June 2016

Project Forecast Survey Results Good Scheduling Practices June 2016 Good Scheduling Practices 5 June 6 Good Scheduling Practices 5 June 6 Executive Summary There is a saying failing to plan is planning to fail, but what if the plan itself is a failure? The scheduling of

More information

New Specialty Crops for California

New Specialty Crops for California New Specialty Crops for California Mark Gaskell, Farm Advisor UC Cooperative Extension - Santa Maria UC Statewide Small Farm Program California Offers A Special Mix Diverse growing environments Large,

More information

Downloaded from Integrated Master Plan and Integrated Master Schedule Preparation and Use Guide

Downloaded from  Integrated Master Plan and Integrated Master Schedule Preparation and Use Guide Integrated Master Plan and Integrated Master Schedule Preparation and Use Guide Version 0.9 October 21, 2005 TABLE OF CONTENTS SECTION PAGE List of Figures... ii 1. Introduction...1 1.1 Purpose of the

More information

PMI-001 Questions & Answers

PMI-001 Questions & Answers PMI-001 Questions & Answers Number: PMI-001 Passing Score: 700 Time Limit: 137 min File Version: 21.2 http://www.gratisexam.com/ PMI-001 Questions & Answers Exam Name: Project Management Professional v5

More information

SECTION NETWORK ANALYSIS SCHEDULES (NCA)

SECTION NETWORK ANALYSIS SCHEDULES (NCA) PART 1- GENERAL 1.1 DESCRIPTION: SECTION 01 32 16.13 NETWORK ANALYSIS SCHEDULES (NCA) SPEC WRITER NOTES: 1. Use this section only for NCA projects. 2. Coordinate this section with the paragraphs of FAR

More information

Introduction to IT Project Management

Introduction to IT Project Management Adapted from Managing Information Technology Projects, Chapter 1, Schwalbe Introduction to IT Project Management Prof. Dr. Daning Hu Department of Informatics University of Zurich Sep 22th, 2016 Outline

More information

Sensitivity and Risk Path Analysis John Owen, Vice President Barbecana, Inc.

Sensitivity and Risk Path Analysis John Owen, Vice President Barbecana, Inc. Sensitivity and Risk Path Analysis John Owen, Vice President Barbecana, Inc. Sensitivity Analysis Sensitivity Analysis shows us which tasks are creating uncertainty in a selected outcome. The outcome might

More information

Integration Mgmt / Initiating Process Group 4.1 Develop Project Charter

Integration Mgmt / Initiating Process Group 4.1 Develop Project Charter 1 Mgmt / Initiating Process Group 4.1 Develop Project Charter Project statement of work Business Case Contract Enterprise environmental factors Project charter Expert judgement 26/02/2013 18:22:56 1 2

More information

Review: Simple schedule risk modelling with Safran Risk

Review: Simple schedule risk modelling with Safran Risk Creating value from uncertainty Broadleaf Capital International Pty Ltd ABN 24 054 021 117 www.broadleaf.com.au Review: Simple schedule risk modelling with Safran Risk With a view to exploring alternative

More information

Systems Engineering Affordability Tracking (SEAT) System

Systems Engineering Affordability Tracking (SEAT) System Systems Engineering Affordability Tracking (SEAT) System SP&A Affordability Phantom Works January 2008 Karen Mourikas AMSE Experimentation - Integrated Defense Systems BOEING is a trademark of Boeing Management

More information

Analysis of Productivity by Comparing Mivan and Conventional Formwork

Analysis of Productivity by Comparing Mivan and Conventional Formwork Analysis of Productivity by Comparing Mivan and Conventional Formwork 1 Prathul U, 2 Leeladhar Pammar 1 PG student, 2 Assistant Professor 1, 2 Department of Civil Engineering, NMAMIT, Nitte Abstract Productivity

More information

Just like QUALITY Good Project Management Practices start with an Internal Kick-Off Meeting. It is the Project Managers job to communicate:

Just like QUALITY Good Project Management Practices start with an Internal Kick-Off Meeting. It is the Project Managers job to communicate: Just like QUALITY Good Project Management Practices start with an Internal Kick-Off Meeting It is the Project Managers job to communicate: What is the team trying to accomplish? How the team is going to

More information

Welcome to the Eastwood Harris Pty Ltd Primavera P6 Version 7 and Earlier Versions 3 day training course

Welcome to the Eastwood Harris Pty Ltd Primavera P6 Version 7 and Earlier Versions 3 day training course Welcome to the Eastwood Harris Pty Ltd Primavera P6 Version 7 and Earlier Versions 3 day training course PMI REP No 3001 Course Number PP6 Administration Evacuation Timings and meals Facilities Mobile

More information

QUICK START GUIDE. SQF Implementation. for.

QUICK START GUIDE. SQF Implementation. for. QUICK START GUIDE for SQF Implementation www.22000-tools.com CONTENTS WHAT IS SQF? BENEFITS OF SQF SQF LEVELS SQF MODULES IMPLEMENTING SQF AND PREPARING FOR CERTIFICATION ASSIGN YOUR PEOPLE RESOURCES

More information

Schedule Margin. Contingency for Schedulers. John Owen, Product Manager Schedule and Risk, Deltek

Schedule Margin. Contingency for Schedulers. John Owen, Product Manager Schedule and Risk, Deltek Schedule Margin Contingency for Schedulers John Owen, Product Manager Schedule and Risk, Deltek Contingency / Management Reserve Let s start with a question Have you ever seen a project without any Contingency

More information

Okaloosa RESTORE Advisory Committee (ORAC) January 8, :30 PM 4:30 PM Emerald Coast Convention Center

Okaloosa RESTORE Advisory Committee (ORAC) January 8, :30 PM 4:30 PM Emerald Coast Convention Center Okaloosa RESTORE Advisory Committee (ORAC) January 8, 2014 2:30 PM 4:30 PM Emerald Coast Convention Center Agenda Minutes Approval Consultant s Administrative Report Scheduled Presentations - None Regional

More information

3.1 Edition APMP Syllabus APMP

3.1 Edition APMP Syllabus APMP 3.1 Edition APMP Syllabus APMP 2 APMP 3rd Edition 3.1 Edition APMP Syllabus All of the syllabus elements should be taken within the context of a project, and project. The syllabus assumes that candidates

More information

REDUCING MANUFACTURING CYCLE TIME OF WAFER FAB WITH SIMULATION

REDUCING MANUFACTURING CYCLE TIME OF WAFER FAB WITH SIMULATION Computer Integrated Manufacturing. J. Winsor, AI Sivakumar and R Gay, eds. World Scientific, (July 1995), pp 889-896. REDUCING MANUFACTURING CYCLE TIME OF WAFER FAB WITH SIMULATION Giam Kim Toh, Ui Wei

More information

Forecasting for Short-Lived Products

Forecasting for Short-Lived Products HP Strategic Planning and Modeling Group Forecasting for Short-Lived Products Jim Burruss Dorothea Kuettner Hewlett-Packard, Inc. July, 22 Revision 2 About the Authors Jim Burruss is a Process Technology

More information