Incorporating Risk- Based Monitoring Strategies: Challenges in Implementation Sherri Hubby, Director, U.S. Quality Assurance

Size: px
Start display at page:

Download "Incorporating Risk- Based Monitoring Strategies: Challenges in Implementation Sherri Hubby, Director, U.S. Quality Assurance"

Transcription

1 Incorporating Risk- Based Monitoring Strategies: Challenges in Implementation Sherri Hubby, Director, U.S. Quality Assurance 26th Annual EuroMeeting March 2014 ACV, Vienna Austria.

2 Disclaimer The views and opinions expressed in the following PowerPoint slides are those of the individual presenter and should not be attributed to Drug Information Association, Inc. ( DIA ), its directors, officers, employees, volunteers, members, chapters, councils, Special Interest Area Communities or affiliates, or any organization with which the presenter is employed or affiliated. These PowerPoint slides are the intellectual property of the individual presenter and are protected under the copyright laws of the United States of America and other countries. Used by permission. All rights reserved. Drug Information Association, DIA and DIA logo are registered trademarks or trademarks of Drug Information Association Inc. All other trademarks are the property of their respective owners.

3 Applying Quality Risk Management to clinical trials A systematic process for the assessment, control, communication and review of risks to the quality of the drug (medicinal product across the product lifecycle (ICH Q-9) Questions to raise on assessing quality: What might go wrong? What is the likelihood (probability) it will go wrong? What are the consequences? 3

4 Goals of Risk-Based Monitoring Provides strategy for on-site and remote monitoring Monitor the right data (Identified Risks) Addresses the risks of the study (Risk Mitigation Plan) Allows better quality of data per ALCOA principles Accurate, Legible, Contemporaneous, Original and Attributable. Allows quick identification and issue escalation in real time Results in better utilization of resources 4

5 What are the Considerations for Risk-Based Monitoring? Monitoring experience to apply a metrics driven approach to centralized monitoring? Experience/relationship in working with the investigator site? Is the Investigator site trained in GCP ICH? Does the investigator have sufficient experience in Therapeutic area and/or compound under study Experience in the patient population under study Stage of the study Critical Primary Efficacy, Outcome data and Safety Endpoints Statistical tools available monitor Sponsor/CROs experience in coordinated team approach Quantity of data size, duration, number of sites centralized monitoring tools may help Safety of the investigational product 5

6 Comparison of Traditional versus Adaptive Risk- Based Monitoring Traditional Monitoring Standard -conduct prestudy visit Risk-Based Monitoring On-site pre-study visits based on risks: No pre-study on-site visit if site utilized within the last 6 months and clean compliance history Phone interviews with site personnel could be used in lieu of on-site visit if site properly qualified Standard: Conduct face to face Investigator Meeting and on-site initiation visit On-site initiation visit based on site qualification: In the compound or therapeutic area Experience with other sponsors with similar protocols or programs Timing of their last site qualification visit Whether changes have occurred since last assessment Site indicators which may affect quality: high turnover, PI availability and responsiveness 6

7 Comparison of Traditional versus Adaptive Traditional Monitoring Risk-Based Monitoring On-Site Monitoring is the Standard 100% of ICFs, Inclusion/ Exclusion Criteria, AEs, Labs, EKGs, IMP Regulatory Binder as time permits Focused on site-level tasks Focused on one site and one variable at a time Query resolution per patient No emphasis placed on review of primary and secondary efficacy data points as compared to review of other data Risk-Based Monitoring Centralized + On-site monitoring models: 100% ICFs for all subjects Utilizes statistical monitoring concepts o 100% review of primary efficacy data and SAEs for first 2 subjects o 20% sampling for SAEs and outcome data o Targeted monitoring for sites with significant compliance issues Remote review of labs, EKGs Receives data for centralized review remotely as it is being generated and entered to spot issues early 7

8 Comparison of Traditional versus Adaptive Risk-Based Monitoring Traditional Monitoring Review of Source: 100% Source Data Verification; driven by: Monitor identifying errors at site Quality and timeliness of monitoring Issues reflected in the monitoring reports and follow-up letters to the sites Highly dependent upon escalation system for reporting to EC and regulators Risk-Based Monitoring Review of Source: Data driven by Pre-identification of metrics at start of study and by measuring site compliance regarding: Number of protocol deviations Unusual trends in data regarding AEs/SAEs and safety signals High number of queries Quality triggers data of poor quality and/or untimely corrections Lack of PI oversight/involvement Use of cross-functional teams 8

9 Comparison of Traditional versus Adaptive Risk-Based Monitoring Traditional Monitoring Rigid, on-site monitoring visits Scheduled at 4 8 week intervals All sites start out with the same plan for frequency of monitoring Risk-Based Monitoring Monitoring visits triggered by risk-specified criteria: Based on key risk metrics and risk scores used to trigger a visit such as Data quality trending issues identified: training required across sites data integrity issues unusually high or low screen failure rates lab issues indicating sample integrity issues high number of edit checks with data quality issues edit checks with high number of manual queries 9

10 What Types of Systems Fit the Centralized Monitoring Model? According to the MHRA: Eligibility checks Rates of Recruitment, Withdrawals, and losses to follow-ups by sites Checks for missing or invalid data Checks that dose adjustments, investigation and management of events are consistent with the protocol Calendar Checks Checks for unusual data patterns Assessment of AEs and Toxicity Reporting Rates CRFs completed by authorized persons External verification Reference: MRC/DH/MHRA Joint Project: Version: 10th October

11 Challenges What types of plans do I need for risk-based monitoring? Four (4) Plans you should consider: Quality Monitoring Plan as a part of the Clinical Monitoring Plan Study Level plans Site Level Plan Program Level Plan 11

12 Considerations for Quality Plans Include Risk-mitigation strategy Include metrics to address identified risks Define issue escalation triggers Include tolerance limits and corrective action required when limits are exceeded Include responsibility actions and timelines associated with identified risks Describe tracking of corrective and preventative action plans 12

13 Considerations for Risk-based Quality Plan Includes plan for on-site Monitoring Identify Paper versus Electronic source requirements ID tasks to be performed and how tasks will be performed Includes Remote and Centralized Monitoring Define how significant protocol issues will be tracked - deviations and violations Defines how different data is to be reviewed: Source Data Verification (SDV) Remote check of source data quality indicators: against protocol compliance, quality and timeliness of source completion, site delegation, training compliance 13

14 Considerations for Study Plans: Includes all aspects of study focusing on: Criteria for site selection -Suitability of site (training, experience and assessment regarding site s ability to conduct the study according to the protocol) Significant data for review -Primary efficacy -Safety endpoint data Questions to ask: What data will be reviewed centrally as opposed to on-site Direction on what is required to conduct the site close-out visits Triggers for assessment of serious and on-going non-compliance issues 14

15 Considerations for Program Level Plans Addresses overall quality and includes risks that are known or anticipated : ID of risks and Specifications of Measurement (Before the study Planning and Design) Oversight and Execution of Monitoring Define DM and Statistical Analysis Data contained in the CSR 15

16 Considerations for Site Level Plans Include Information regarding the experience of investigator site including: Therapeutic experience Experience in similar programs or protocols Previous regulatory history and personnel experience in working with site Staff turnover PI availability and involvement Potential conflicts of interest or bias 16

17 Writing the Risk Mitigation Plan Risk Identified Loss of data at site Example 1 Assessment of Risk (Probability (P) and Consequences (C ) of Occurring and Overall risk evaluation/result (R) P C R Low Mediu m High Risk Consequence if risk not managed -Possible permanent loss of data if captured electronically -Temporary loss of data causing study/data delays -Delay in payment to site and CRO/Sponsor deliverables may be affected Risk Management Strategies -Ensure adequate prestudy and qualification visits cover review of computer systems to ensure that systems are validated and have appropriate backups and audit trails -Site procedure cover Disaster Recovery Plans 17

18 Writing the Risk Mitigation Plan Example #2 Risk Identified Fraudulent data at site Assessment of Risk (Probability (P) and Consequences (C ) of Occurring and Overall risk evaluation/ result (R) P C R Low Medi um High Risk Consequence if risk not managed -Reporting to IRB/ Ethics/Regulators -Study may need to be repeated -Regulatory action for site, CRO and Sponsor possible including penalties and rejection of submission 18 Risk Management Strategies -Ensure PI/staff are adequately trained on protocol and supported by relevant training and experience -Ensure site has GCP training and other controls in place to prevent and detect fraud

19 In summary, Risk-Based Monitoring: May not fit all trials Assessed before study start lifecycle Represents one quality control tool Statistical approach recommended Risk-Based plans tailored to trial Examples provided on setting up riskbased plans quality, site-level, programlevel and risk mitigation plan 19

20 References: FDA, Guidance for Industry: Oversight of Clinical Investigations- A Risk- Based Approach to Monitoring; August 2013 TransCelerate Position Paper: Risk-Based Monitoring Methodology 2013 EMA. Reflection paper on risk-based quality management in clinical trials (EMA/INS/GCP/397194/2011) MRC/DH/MHRA Joint Project: Risk-adapted Approaches to the Management of Clinical Trials 10th October 2011 FDA: Q9 Quality Risk Management ICH Guidance for Industry: Q9 Quality Risk Management FDA Guidance for Industry; Computerized systems used in clinical trials, May