1 Location London Date 6th May 09 Crossrail - Case study BS1192:2007 Adrian Burgess Group Collaboration Manager Scott Wilson Ltd 1

2 Agenda Introduction to Scott Wilson plc What is BS1192 BIM Building Information Modelling BS1192 on Crossrail 2

3 Scott Wilson Group plc Scott Wilson Group plc is a global integrated design and engineering consultancy for the built and natural environments. Strategic Consultancy Railways Buildings & Infrastructure Environment & Natural Resources Roads 14% 14% 30% 21% 21% 3 Note: Percentage show proportion of H1 2008/09 revenue

4 Scott Wilson Ltd Staff Approximately 6,000 staff Offices Network of 80 offices worldwide Regions UK, Asia Pacific, Europe, India and Middle East Floated The business floated in 2006 on the London Stock Exchange Doubled in size over past few years Ranked 9th largest UK owned engineering consultancy (NCE 2008) Revenue 360m 4

5 BS1192 BS1192-5:2007 is a code of practise for managing the production, distribution and quality of construction Information. Traditional Common Data Environment 5

6 BS1192. Defined Naming conventions & standard codes [ Project Ref] [Originator code] [Zones / Asset ref] [ Doc type] [ Role ] [ Number ] Standard Suitability Codes & Revision Codes [ Suitability Codes S1 S4, D1 D4, A AB] & [rev seq P1 99 C1 99 minor version for WIP] Common origins and Orientation [ Models to use common origin and orientation, use Cartesian axis, common units be at 1:1] Layer conventions [ ISO compatible, layer naming and coding strategy, to minimize the no of diff layers used ] Data exchange principals [Common interoperable format] 6

7 BS1192 Common Data Environment 7

8 BS1192 Objectives Manage disparate engineering teams & data centrally. Improve the control of information. Increase productivity and efficiency of engineering workflow Easily share data with 3rd party organisations Spatially Coordinate design information Improve the accuracy/currency and quality of AEC information Reduce the amount of re work on site. De risk projects. 8

9 Building Information Modeling (BIM) Building Information Modeling (BIM) is the process of generating and managing building information during its life cycle. 9

10 Building Information Modeling (BIM) SWG in April D 3D AIM SIM FIM BIMs BSIM BRIM CPIC AVANTI BS1192: 2007 User Guides CPIC, Avanti, BSI Bew - Richards 2008 IDM IFC ISO BIM ibim IFD Building Lifecycle Management Drawings, lines arcs text etc. Models, objects, collaboration Integrated, Interoperable Data 10

11 Building Information Modeling (BIM) BIM Tools BS

12 Crossrail - Case Study 12

13 Crossrail - Case Study Largest Infrastructure Project In Europe 16 Billion Up to 100 mph over ground Up to 60mph underground Service ready 2017 Trains carry 1500 people 24 trains per hour at peak 160,000 passengers in morning rush hour 13

14 Crossrail Case study Tools Processes People For Every One Course 1) Introductions to Bs1192 Processes Project Wise & ProjectSpace For Document Controllers : Course 2) Upload & Issue to Business Collaborator Managing TQs Managing Change Requests EWN etc For CAD Coordinators: Course 3) Spatial Coordination QA Complance Checking 14 1 Configured common data environment 2 Wrote specific Crossrail procedures 3 Designed and delivered training

15 Crossrail Tools Tools Business Collaborator Project Extranet 15 Bentley ProjectWise EDMS

16 Crossrail Tools Tools Internal Data Environment( IDE) Bentley ProjectWise Project Data Environment ( PDE) Business Collaborator 16

17 Crossrail Processes Processes Managing production, validation and Publishing of Model files Process of Managing In bound 3rd Party Models Process of Production, Validating and Publishing Drawings Process of Production, Validating and Sharing of Engineering Document Components Process of Managing In bound 3rd Party Engineering Document Components Process of Production, Validation and Publishing of Engineering Reports Wrote specific Crossrail procedures 17

18 Crossrail Case study processes 1. Automatic Notifications 2. Check download into your WIP area 1. Upload & Issue to PDE Engineering Check 2.Spatial Coordination Check 3. Remove XREFs 4. QA Check 18

19 Crossrail Training Developed and are delivering 3 courses People Introduction ( 500 people) Document controllers ( 10 ) CAD Coordinators ( 4 people ) For Every One Course 1) Introductions to Bs1192 Processes Project Wise & ProjectSpace For Document Controllers : Course 2) Upload & Issue to Business Collaborator Managing TQs Managing Change Requests EWN etc For CAD Coordinators: Course 3) Spatial Coordination QA Complance Checking 19

20 Crossrail Benefits Overall Manage disparate engineering teams & data centrally. Improve the control of information. Increase productivity and efficiency of engineering workflow Easily share data with 3rd parties Spatially Coordinate design information Improve the accuracy/currency and quality of AEC information Reduce the amount of re work on site. De risk projects. 20

21 Location London Date 6th May 09 Crossrail - Case study BS1192:2007 Adrian Burgess Group Collaboration Manager Scott Wilson Ltd 21