Substation Business Applications using CIM / PI AF

Size: px
Start display at page:

Download "Substation Business Applications using CIM / PI AF"

Transcription

1 December 12, 2007

2 Substation Business Applications using CIM / PI AF by Stephen Diebold Manager Real Time Systems Kansas City Power & Light

3 Agenda Overview of KCP&L CIM / PI AF Project A Convergence of Opportunities Main Goal Situation Without Project Closing the Loop Asset-Related Applications Applications Interoperability Test Project Status Questions

4 Over 810,000 customers Peak in excess of 5,660 MW Service territory across 47 counties in MO and KS covering 17,934 sq. miles Over 3,170 employees 30 office/service center locations 9 generation plant sites and 10 peaking facilities 3,309 miles transmission lines 24,466 miles of overhead distribution lines 3,400 miles of underground distribution lines 322 substations

5 CIM/PI AF Project A Convergence of Opportunities EMS comes with PI Historian Stores history of EMS real-time point data PI features for model-based access to tags Utilizes standards-based CIM model for EMS database configuration

6 CIM/PI AF Project Main Goal Transmission Engineering Interest in moving from Event-based maintenance to Condition-Based Maintenance

7 CIM/PI AF Project Situation Without Project EMS gathering 50,000+ points of real-time data CIM database where equipment and associated real-time data points defined for EMS AF PI Server Point data history stored in PI tags, but accessible only by point name. PI product (AF) able to model equipment s relationships to tags, but product not currently used.field devices CIM DE Environment EMS

8 CIM/PI AF Project Closing the Loop Export CIM model data to PI AF product Create PI equipment / asset model for retrieving historic tag data AF PI Server GDA (Utility Integration Bus). Create infrastructure for generalized retrieval of historic real-time information on equipment basis (by reference to equipment location in system) on asset basis no matter where asset has been moved in system Generalized retrieval is essential to the creation of applications.field devices CIM DE Environment Network Manager EMS

9 CIM/PI AF Project Asset-Related Applications Asset Management System Condition-Based Maintenance Applications AF PI Server GDA (Utility Integration Bus) Condition-Based Maintenance Applications for transformers and breakers PI Server. Desktop access Paging/ notification Web access First step toward dashboard access to real-time Operations data.field devices CIM DE Environment Network Manager EMS

10 PI Server Condition-Based Maintenance Applications Asset Management System CIM/PI AF Project Applications Transmission, Substation Engineering Distribution Engineering Power Sales and Services, Generation Engineering EMS Energy Management System TMS Data Acquisition Supervisory Control Alarming Real-Time Data Network Adv Apps Training Simulator Transmission/ Substation Model Market Interfaces Energy Accounting GMS Data Acquisition Supervisory Control Alarming Real-Time Data Power Adv Apps Training Simulator Generator Model Market Interfaces Energy Accounting DMS Data Acquisition Supervisory Control Alarming Real-Time Data Distr Adv Apps Distribution Model OMS Data Acquisition Supervisory Control Alarming Real-Time Data Outage Mgmt Distribution Model Distribution System Operations Transmission Operations Power Operations

11 Interoperability Test The changing business environment has increased the need for greater business and operating flexibility. Flexibility to combine, in one or more integrated platforms, software that best meets your needs. Access a range of needed information via open systems. EPRI continues to sponsor collaborative efforts to advance these integration strategies for greater information systems integration solutions.

12 Interoperability Test Demonstrate interoperability between ABB, SISCO and OSISoft s products based on the CIM and/or GDA. Verify compliance with the CIM for those CIM classes/attributes involved in the information exchanges. Demonstrate the exchange of power system models using the CIM and an RDF schema and XML representation of the model data. Demonstrate exchange between ABB and SISCO products using the services defined in the GDA Client and Server interface standard.

13 Interoperability Test Vendor Product Name Tests ABB OSISoft, LLC SISCO, Inc. Network Manager, CIM DE Toolkit PI AF PI System Explorer Part number: UIB- PIWRAP Version Beta PI Adapter Full Import using CIM XML and GDA services Incremental Import using CIM XML and GDA services Storage of the ABB model data Review and browsing of the ABB model data Full Import using CIM XML and GDA services Incremental Import using CIM XML and GDA services Provide UIB message bus for transport and communication

14 Project Status FAT completed June 4, 2010 Interoperability tests completed June 9, 2010 SAT is being scheduled

15 Questions Condition-Based Maintenance Applications AF PI Server PI Server Asset Management System GDA (Utility Integration Bus)..field devices CIM DE Environment Network Manager EMS

16 Contact information: December 15, 2007