1 Market Simulation Fall 2014 Release Christopher McIntosh Lead Market Simulation Coordinator Fall 2014 Release August 18 th, 2014

2 Agenda Fall 2014 Market Simulation Initiatives and Timelines Fall 2014 MAP Stage Availability FNM Expansion with EIM OMS FRAC MOO and M2M Next Steps Reference Slides Page 2

3 Fall 2014 Release Market Simulation Initiatives and Timelines Full Network Model Expansion with Energy Imbalance Market - July 28 th, 2014 September 12 th, 2014 (Structured and Unstructured) Outage Management System Replacement - July 28 th, 2014 September 30 th, 2014 (Unstructured) Many to Many: Standard Capacity Payment (SCP) Availability Calculations with Flexible Resource Adequacy Criteria and Must Offer Obligation (FRAC-MOO) - August 25 th, 2014 September 12 th, 2014 (Structured and Unstructured) All initiatives Regression Testing - September 12 th, 2014 September 30 th, 2014 Page 3

4 Fall 2014 Release MAP Stage Availability MAP Stage Scheduled Maintenance - August, 22 nd, 09:00 MAP Stage Fall Release Daily Maintenance Window - 16:00-20:00 MAP Stage Weekly Maintenance Window - Friday s, 09:00 - Monday s 09:00 Page 4

5 FNM Expansion with EIM The Full Network Model Expansion with Energy Imbalance Market Simulation timeline FNM Expansion with EIM: July 28 th - September 30 th, 2014 (Structured and Unstructured) FNM Expansion with EIM: July 28 th - September 1 st, 2014 (Structured) FNM Expansion with EIM: September 2 nd, September 30 th, 2014 (Unstructured) Structured Scenarios - FullNetworkModeExpansionStructuredScenarios.pdf Week 1 - Scenario #1 TD 7/30 and # 2 TD 7/31 Bid to Market Output, Completed Successfully Week 2 - Scenario #5 TD 8/6 and #4 8/7 Successful executed, Statements posting this week, one day delay in 8/7 statement posting Week 3 No Scenarios Week 4 TD 8/19 12, 13, 14 and 15 - TD 8/20 7, 18 and 19 - TD 8/21 6 and 8 Page 5

6 FNM Expansion with EIM Known Issue List # Application Severity (H/M/L) New or Existing Variance Variance Description Resolution Expectations 1 SIBR M Closed EIM Entity BSC can t submit To be resolved 8/18 RT Base Schedules for future hours (when no Base Schedule is there) 2 SIBR M Open ETCC Limit data showing on UI for Ind Viewer To be resolved 8/25 3 SIBR M Closed Cancel of Base Schedule does To be resolved 8/18 not work. 4 SIBR M Closed Rule does not fire To be resolved 8/18 when it should for BSC after 2nd cutoff. Base Schedule RT timing of submit based on Entity Y/N did not recognize flag. 5 SIBR M Closed Rule fired level 5 it should be level 6 for good match). Wheeling Bid special processing does not see a valid match. To be resolved 8/18 6 SIBR M Closed Rule ( registered WHL ) To be resolved 8/18 Registered resource with WHL not recognized as a WHL 7 SIBR H Closed Balance viewer is not showing To be resolved 8/18 full aggregation of BAA. 8 SIBR M Closed F14 Wheel API (advanced To be resolved 8/18 submit) not recognizing Trans counter resource 9 SIBR L Open SIBR UI is not user friendly with Summary or Component screen To be resolved 8/25 Page 6

7 FNM Expansion with EIM Known Issue List # Application Severity (H/M/L) New or Existing Variance Variance Description Resolution Expectations 10 OASIS M Open OASIS -The Energy Type drop-down menu in the Expected Energy report does not have the BASE and MDE options 11 OASIS M Open OASIS - Exceptional Dispatch Group Zip APIs not providing data To be resolved 8/25 To be resolved 8/25 12 OASIS M Open OASIS - Node column is duplicated in To be resolved 8/25 CSV API download file for Contingency Dispatch Locational Marginal Prices (LMP) Report in Prices section. 13 OASIS M Open OASIS Price Ticker not working To be resolved 8/25 14 OASIS M Open OASIS CAISO Demand Forecast To be resolved 8/25 Report not showing EIM TAC Entries 15 OASIS M Open OASIS - GHG Report not populating To be resolved 8/25 16 OASIS M Open OASIS EIM NSI Reports XML APIs showing incorrect 3600 second interval for RTD & RTPD To be resolved 8/25 17 OASIS M Open OASIS - The EIM footprint total (the sum of all ISO and EIM TACs) and EIM entity total ( the sum of all EIM BAA TAC associated with EIM entity) are NOT available in the System Load and Resource Schedules report To be resolved 8/25 18 OASIS M Open OASIS - The System Load & Resource To be resolved 8/25 Schedules API queries with the TAC Zone Name equal to TAC_PAC is returning data for CAISO_Totals as well. 19 OASIS M Open OASIS - Contingency Dispatch Locational Marginal Prices Data is not populated To be resolved 08/25 Page 7

8 FNM Expansion with EIM Known Issue List # Application Severity (H/M/L) New or Existing Variance Variance Description Resolution Expectations 20 CMRI H Open Retrieve Market schedules v1 To be resolved 8/25 is giving APPL0014 IO Read time out in map stage for execution type RTUC 21 CMRI H Open MarketSchedules_CMRIv2 To be resolved 8/25 when run for one Trade Date gives APPL0014: IO Exception: Read timed out error. 22 CMRI M Open MMD_Transmission Limit -- Generated MPP (HASP) File has Empty Columns. To be resolved 8/25 23 CMRI H Open MarketAwards_CMRIv3 fails To be resolved 8/25 XSD validation when TiePointUsedforFlow is populated in response. 24 CMRI H Open Day Ahead Import Export To be resolved 8/25 Schedules report does not display Scheduling Point for Transaction ID's. 25 CMRI H Open RTUC Advisory Schedules is To be resolved 08/25 not displaying data for Trade Hr = 1 received in RTUC Advisory Schedules Payload. 26 Tag Test Bed H Closed Tagging Test bed connection issue in to Market Simulation To be resolved 8/18 Page 8

9 Outage Management System The Outage Management System Market Simulation Outage Management System: July 28 th - September 30 th, 2014 (Unstructured) Beginning July 28 th, 2014 ISO will approve outages with no ISO operations review; this will last until August 1 st, ISO will be approving outages throughout the day for outages submitted prior to 16:00, for immediate outage approval please MarketSim@caiso.com. Beginning August 4 th, 2014 ISO operations will review submitted outages prior to 16:00 daily, this support will end August 15 th, The time period from August 18 th, 2014 through the end of unstructured market simulation September 30 th, ISO will be approving outages throughout the day for outages submitted prior to 16:00, for immediate outage approval please MarketSim@caiso.com. Page 9

10 OMS UI and APIs are available in MAP Stage RetrieveAvailability_OMSv1 RetrieveAvailability_OMSv1_DocAttach RetrieveFacilityOutageDefinition_OMSv1 RetrieveFacilityOutageDefinition_OMSv1_DocAttach RetrieveResourceOutage_OMSv1 RetrieveResourceOutage_OMSv1_DocAttach RetrieveResourceOutageChangeRequest_OMSv1 RetrieveResourceOutageChangeRequest_OMSv1_DocAttach RetrieveTransmissionOutage_OMSv1 RetrieveTransmissionOutage_OMSv1_DocAttach RetrieveTransmissionOutageChangeRequest_OMSv1 RetrieveTransmissionOutageChangeRequest_OMSv1_DocAttach AcknowledgeOutageWarning_OMSv1 SubmitResourceOutage_OMSv1 SubmitResourceOutage_OMSv1_DocAttach SubmitResourceOutageChangeRequest_OMSv1 SubmitResourceOutageChangeRequest_OMSv1_DocAttach SubmitTransmissionOutage_OMSv1 SubmitTransmissionOutage_OMSv1_DocAttach SubmitTransmissionOutageChangeRequest_OMSv1 SubmitTransmissionOutageChangeRequest_OMSv1_DocAttach WithdrawOutageChangeRequest_OMSv1 Page 10

11 Outage Management System Known Issues List # Application Severity (H/M/L) New or Existing Variance Variance Description Resolution Expectations 1 OMS H Existing SubmitResourceOutage - No validation on stated availability for Pmin against MasterFile 2 OMS H Existing RetrieveAvailability - Response is failing when validating with XSD and one datetimepoint incorrect CAISO is validating fix Next maintenance window 3 OMS M Existing RetrieveTransmissionOutage - Retrieve Transmission outage returns incorrect status for the equipment (switch) CAISO is validating fix 4 OMS M Existing SubmitTransmissionOutage - Submit status is showing CAISO is validating fix as ACCEPTED instead of REJECTED even though batch is actually rejected 5 OMS H Existing SubmitResourceOutageChangeRequest - Allowing to CANCEL Outage with updated dates CAISO is investigating 6 OMS H Existing RetrieveAvailability Expected to be available today with variance that it returns responses inline instead of attached for responses that are < =768B, returning an error to the requestor. Current workaround is to increase query size to get the response > 768B. 7 OMS H Existing Market participants associated with sub BAs cannot currently access new OMS 8 OMS M Existing For market participants having problems with access, please clear browser cache 9 OMS M New Some market participants are having issues with accessing OMS help 10 OMS M Existing Some market participants are having issues with missing resources Next maintenance window CAISO is investigating CAISO is investigating if there is a pervasive issue here since one user had this issue CAISO is investigating CAISO is investigating Page 11

12 FRAC MOO and Many to Many The Many to Many: Standard Capacity Payment (SCP) Availability Calculations with Flexible Resource Adequacy Criteria and Must Offer Obligation (FRAC-MOO) Simulation timeline Many to Many: Standard Capacity Payment (SCP) Availability Calculations with Flexible Resource Adequacy Criteria and Must Offer Obligation (FRAC-MOO): August 25 th, 2014 September 12 th, 2014 (Structured and Unstructured) Week 1 Unstructured, Week 2 Structured and Week 3 Unstructured Week 2 FRAC-MOO Unstructured Schedule Date Scenario Steps 9/2/2014 Upload RA and Supply Plans that contain Flex RA showings 9/3/2014 ISO to run Flex Cross Validation by 11:00 AM and market participants to review results 9/4/2014 Market participants to correct errors by 11:00 AM. ISO to run Flex deficiency analysis and data will be published by close of business 9/5/2014 Cure period - Market participants to cure deficiency by close of business - 9/8 and 9/8/2014 9/15/2014 ISO to issue flex CPM and allocate cost to deficient LSEs by close of business 9/15 Structured Scenarios Link - Page 12

13 Next Steps The next teleconference will take 13:00 PPT on Thursday, August 21 st, Page 13

14 Reference Slides Reference Slides Page 14

15 Fall 2014 Release Market Simulation Plan etsimulationplan.pdf Page 15

16 ISO System Access Documentation ion_marketparticipants.pdf Page 16

17 ISO Market Simulation Support Hours - 09:00-18:00, PST (Monday through Friday) Mkt Sim Coordinator Phone - (530) ISO s 24X7 Help Desk - (916) (Connectivity - GUI or API) - MarketSim@caiso.com Page 17

18 Market Simulation Issue Management Submit all issues to the CIDI case management system. CIDI tickets will need to have Functional Environment = Market Simulation Fall 2014 to be reviewed by ISO SME s. Page 18

19 Fall 2014 Release Communication Plan ISO will host Bi-weekly call on Mondays and Thursdays starting July 28 th, 2014 Date July August September 28 Kick Off Call, 31 4, 7, 11,14, 18, 21, 25, 28 4, 8, 11, 15, 18, 22, 25, 29 Please refer to the California ISO public calendar at for current login information relevant for each meeting. Time 1:00 p.m. to 2:30 p.m. (Pacific Time) Page 19