DG Interconnection Procedures Collaborative. January 20, 2017

Size: px
Start display at page:

Download "DG Interconnection Procedures Collaborative. January 20, 2017"

Transcription

1 DG Interconnection Procedures Collaborative January 20,

2 Interconnection Procedures Collaborative State Ombudsman kick-off October 2016 Goal: develop improvements to Con Edison s internal process for managing interconnections. In accordance with the New York State Public Service Commission Standard Interconnection Requirements (SIR) CE agrees to implement changes as appropriate following the discussions. Informational report filing 6 months from the initial meeting Topics discussed, recommendations developed, and actions taken. 2

3 Agenda Topics for today s meeting Future topics and Con Edison work plan Discussion: Three line diagram checklists Verification test checklist and FAQs Regular business meetings for projects SIR workflow 3

4 Future Topics and Timeline February 2017: Completion of topics from January meeting Coordination with DOB for discussion Standardizing communications to present consistent options Additional Topics for 2017 Con Edison Work plan Guides for DG technology March Company moving forward with PV and fuel cell guides as was presented New service vs DG cases coordination April Draft Informational Report on Collaborative Filing of Informational Report on Collaborative due April 24. 4

5 Draft Content for Three Line Diagram Checklists, Verification Checklists, FAQs Refer to documents 5

6 Process for regular business meetings Any DG >5MW normally have regular meetings DG Ombudsman Office and Energy Services available for meetings on request Pre-application discussions can help set realistic expectations on unusual schedule constraints Special billing considerations (RNM, CDG, Offset Tariff, etc) will meetings scheduled near commissioning for rates Developer feedback? How to find balance between transparent communications and efficient management of 111 cases under the new SIR >50kw. 6

7 SIR workflow discussion Refer to flow chart 7

8 8

9 Preliminary Screening Analysis If any of the following screens fail, applicant must request supplemental screen or CESIR to progress. Screens performed Screen A: Is the PCC on a Networked Secondary System? Screen B: Is Certified Equipment Used? Screen C: Is the Electric Power System (EPS) Rating Exceeded? Screen D: Line Configuration Compatible w/ Interconnection Type? Screen E: Simplified Penetration Test Screen F: Simplified Voltage Fluctuation Test Deliverable: Pass: Design Approval Letter and Executed Contract Fail: Preliminary Review Letter Template (w/ Options) 9

10 Supplemental Screening Analysis If any of the following screens fail, applicant must request CESIR to progress. Screen G: Supplemental Penetration Test Where 12 months of line section minimum load da ta is available, can be calculated, can be estimated from existing data, or determined from a power flow model, is the aggregate Generating Facility capacity on the Line Section less than 100% of the minimum load for all line sections bounded by automatic sectionalizing devices upstream of the Generating Facility? Screen H: Power Quality and Voltage Tests In aggregate with existing generation on the Line Section, a. Can it be determined within the Supplemental Review that the voltage regulation on the line section can be maintained in compliance with current voltage regulation requirements under all system conditions? b. Can it be determined within the Supplemental Review that the voltage fluctuation is within acceptable limits as defined by IEEE 1453 or utility practice similar to IEEE1453? c. Can it be determined within the Supplemental Review that the harmonic levels meet IEEE519 limits at the Point of Common Coupling (PCC)? Screen I: Safety and Reliability Tests Does the location of the proposed Generating Facility or the aggregate generation capacity on the Line Section create specific impacts to safety or reliability that cannot be adequately addressed without a detailed study? Deliverables: Pass: Design Approval Letter and Executed Contract Fail: Supplemental Review Letter Template (w/ Options) 10

11 Thank you January 20,

12 Appendix Slides 12

13 INTERCONNECTION TECHNICAL WORKING GROUP Flow Chart: Regular Application Process for Systems above 50 kw to 5 MW Utility Performs Preliminary/ Supplemental Screening Analysis and Develops a CESIR if required Complete Application Received Utility Performs a Preliminary Screening Analysis (i) Preliminary Analysis results meeting Need for Supplemental Analysis Identified? System Upgrade and Construction Approval (expanded in Slide 10) Screens A through F Utility provides results within 15 BDs of screens completion If applicant fails to notify next steps within 30 BDs, interconnection shall be removed Applicant notifies utility within 10 BDs whether proceed to (ii), (iii) or (iv) Applicant passed all screens and no upgrades required? Utility Sends Notification of Construction Approval and Executed Contract Within 30 BDs, interconnection shall be removed if no response received Applicant has 10 BDs to notify the utility whether proceed to: Applicants that elect to proceed to Supplemental Analysis shall provide a nonrefundable fee of $2,500 with their response. (iii) Full CESIR (expanded in Slide 12) (iv) Withdraw the Interconnection Request (ii) Utility complete Supplemental Review within 20 BDs (Screens G through I) Utility estimates construction costs on system modification in CESIR Applicant passed all the screens and no upgrades required? Applicant notifies utility within 10 BDs whether proceed to (iii), (iv) or a Supplemental Analysis Results Meeting (expanded in Slide 11) Applicant pays advanced payment of 25% of the estimated costs within 60 BDs Utility is not required to begin procurement or construction until full payment received; utility retains the right to re-assess the project s inventory position if the applicant exceeds either of these timeframes Utilities Sends Notification of Construction Approval and Executed Contract within 15 BDs Utility Sends Notification of Construction Approval and Executed Contract; Applicant has a total of 120 BDs to provide full payment upon executed contract THE JOINT UTILITIES OF NEW YORK 13

14 INTERCONNECTION TECHNICAL WORKING GROUP Flow Chart: Regular Application Process for Systems above 50 kw to 5 MW System Upgrade and Construction Approval Need for Supplemental Analysis Identified Upgrade Needed? Utilities Sends Notification of Construction Approval and Executed Contract within 15 BDs Utility provides the applicant a non-binding cost estimate within 15 BDs Applicant Requests 15BD Extension Applicant Respond? Applicant responses within 15 BDs Applicant accepted proposed upgrades Utility Sends Notification of Construction Approval and Executed Contract within 15 BDs No Timeline exceeds 15 BDs, or 30 BDs if extension provided? Applicant withdraws application Remove from queue THE JOINT UTILITIES OF NEW YORK 14

15 INTERCONNECTION TECHNICAL WORKING GROUP Flow Chart: Regular Application Process for Systems above 50 kw to 5 MW Supplemental Analysis Results meeting (iii) Full CESIR Applicant notifies utility within 10 BDs whether proceed to: (iv) Withdraw the Interconnection Request If applicant fails to notify next steps within 30 BDs, interconnection request shall be removed from the queue Supplemental Analysis Results meeting Need for CESIR Identified? Applicant notifies utility within 10 BDs whether proceed a full CESIR or withdraw Upgrades Needed? Utility Sends Notification of Construction Approval and Executed Contract within 15 BDs Utility provides the applicant a non-binding cost estimate within 15 BDs Applicant Requests 15 BDs Extension Applicant Respond? Applicant responses within 15 BDs Applicant requests withdraw application Applicant accepted proposed upgrades Utility Sends Notification of Construction Approval and Executed Contract within 15 BDs No Timeline exceeds 15 BDs, or 30 BDs if extension provided Remove from queue THE JOINT UTILITIES OF NEW YORK 15

16 INTERCONNECTION TECHNICAL WORKING GROUP Flow Chart: Regular Application Process for Systems above 50 kw to 5 MW Full CESIR Proceed to a Full CESIR Applicant notifies utility of intent to move forward with CESIR Utility provides CESIR cost estimate within 5 BDs of notification Applicant notifies decision within 10 BDs of receiving cost estimate Withdraw the Interconnection Request Applicant provides detailed interconnection design package, contact information, authorization and payment of associated costs within 30 business days? No Detailed interconnection design package complete? Utility notifies within 10 BDs and provide detailed explanantion Applicant provided authorization to proceed and paid the fees? If applicant fails to provide complete design package, authorization, CESIR fees or other information within 30 BDs, the Interconnection Request shall be removed from the queue CESIR begins upon confirmed receipt and acceptance of provided info and fees The CESIR shall be completed within 60 BDs, absent extraordinary circumstances For systems above 2 MW up to 5 MW, a mutually agreed-upon schedule for a CESIR for these systems will not exceed an additional 20 BDs, or 80 BDs in total THE JOINT UTILITIES OF NEW YORK 16

17 INTERCONNECTION TECHNICAL WORKING GROUP Flow Chart: Regular Application Process for Systems above 50 kw to 5 MW Final Acceptance and Utility Cost Reconciliation Utility witnessed the verification testing? Results submitted indicate system passed? Yes No Utility issues to the applicant a formal letter of acceptance for interconnection within 10 BDs Request to set a date and time with applicant to witness operation of the DG system within 10 BDs Utility prepares a final reconciliation invoice of actual cost minus the application fee and advance payments by applicant Utility submits invoice within 30 BDs of final approval System Passed? Utility issues a formal letter of acceptance for interconnection within 10 BDs of testing Utility provides detailed explanation of the deficiencies within 10 BDs of testing No Utility provides detailed explanation of the deficiencies within 10 BDs This witness verification must be completed within 20 BDs of request System Passed? Utility issues a formal letter of acceptance for interconnectio n within 10 BDs The applicant receives either a bill for balance or reimbursement A formal complaint interposed by the applicant? Applicant pays the utility or utility send the reimbursement to applicant within 30 BDs Utility reserves the right to lock the generating system offline. If the applicant is not satisfied, a formal complaint may be filed with PSC *Payment Not Received THE JOINT UTILITIES OF NEW YORK 17

18 INTERCONNECTION TECHNICAL WORKING GROUP Flow Chart: Regular Application Process for Systems above 50 kw to 5 MW Initial Communication from the Potential Applicant Inquiry Reviewed by Utility Applicant Files an Application ($750 Fee) 10 Business Days (BD) *Application considered in queue on date its deemed complete Applicant submits a Pre- Application report with nonrefundable $750 fee Application meets the requirements? * Utility provides Pre-application Report Results within 10 BDs If applicant applies to interconnect 15 BDs, $750 applied towards the application fee Meter Change Performed Applicant submits the additional information within 30 BDs of notification date? Application Deemed Withdrawn Utility Sends Notification of Application Acceptance to Customer within 10 BDs of receipt of info Utility Performs Preliminary/ Supplemental Screening Analysis and Develops a CESIR if required (Next Slide) CESIR - Co-ordinated Electric System Interconnection Review Utility Sends Notification of Construction Approval and Executed Contract Project Construction 10 BDs Verification Tests & Interconnection Final Acceptance and Utility Cost Reconciliation (expanded in Slide 13) The applicant shall build the facility in accordance with the utilityaccepted design; utility commence construction of system modification and metering requirements if required h Utility requested to witness the testing process? Applicant sends the utility a written Verification testing performed within notification within 5 BDs of completion of such tests 10 BDs of the system installation completion date THE JOINT UTILITIES OF NEW YORK 18