1 Retail Markets Co-Ordination Working Group Wednesday, 14 th January, 2015 CER Offices Dublin Retail Market Design Service

2 ReMCoWG Agenda Agenda Item Presenter Time Introduction J Gregory ReMCoDS 12:30 12:35 ReMCoSG Meeting Feedback J Gregory ReMCoDS 12:35 12:45 Tibco Hub/EMMA Update Carmel O Connor, ESBN 12: Smart Metering Update M Moloney, Smart Metering 13:05 13:15 Market Design Update J Gregory ReMCoDS 13:15 13:35 ReMCoWG To-Do List Review J Gregory ReMCoDS 13:35 13:45 AOB & Closing J Gregory ReMCoDS 13:45 14:00 Retail Market Design Service

3 Approval of Minutes Minutes from ReMCoWG meeting 5 th November 2014 Retail Market Design Service

4 Update from ReMCoSG Meeting There has been one ReMCoSG held since the last ReMCoWG - 19 th November 2014 Topic Detail Action Item Status Co-ordinated The document has been reviewed by both jurisdictions. A question on the definition of consensus was ReMCoDS to update the Co-ordinated Change Control 123 Strategy document to include the CoBLCR & Co-MMR pre-existing Change Control raised. One of the Supplier Reps interpreted consensus as "majority of stakeholders and not all ". There CER to revert with clarification on what consensus Strategy Document was discussion around this at the Steering group and clarification is required. CER to provide clarification on definition and present to group for agreement. means and if any change in relation to the wording is 130 needed new CER & UR to meet to discuss the Smart Metering Programme and the impact it will have on the coordinated Market 124 closed Smart Metering A meeting had been held between RA's and the outcome was that the detail of the impacts on the coordinated market were still largely unknown (123 closed). Much of the detail will be produced from the detail design workshops taking place between Feb-May A point was made that the changes to the CoBL need to be known as if significant, it may require discussion around the co-ordinated baseline being a sensible vehicle to have in place if the apporach to smart metering diverges between the jurisidtcions significiantly. All CoBL and co-ordinated market impacts need to be understood to gain a full understanding of what ROI smart metering implementation is to mean for NI and co-ordination. This lead to developing action 131. A question was raised in relation to NI & NIE engagement with the smart Incorporating Smart changes into the Co-Ordinated Retail 105 Markets ESBN to develop a high level impact assessment for 131 Smart Metering on the co-ordinated market pre-existing new TIBCO Other The current status of the TIBCO project was discussed. It was highlighted that post consultation with MPs, Option 2 (with Suppliers having the option to upgrade their EMMAs at the time of Smart Metering) was deemed the preferred solution to progress with. It was highlighted that the project is awaiting RA approval. CER has given approval in principle to the scope of the project; costs would be considered under PR4. NIAUR are determining their position on approval. There was discussion about the stability of TIBCO and the fact that although no significant issues have arisen in the recent past there is no guarantee that there isn't going to be an issue at any point into the near future. The lack of stability also prevents any further development work such as Schema Releases and may impact Programmes like Smart. NIE and NIAUR were to meet to discuss cost recovery and funding approval for the project. Retail Market Messaging Work Plan Network Operators to provide further information and detail including timelines 111 for Supplier involvement pre-existing ESBN/NIE to review feedback from Suppliers and review the Communication process to determine if fit for 126 purpose. pre-existing 14 th January 2015 Retail Market Design Service

5 ReMCoWG Action Items Updated ReMCoWG Action List issued in advance of meeting 1 Action closed since last ReMCoWG meeting. AP No. Title Org. Assigned to Date Closed Suppliers Backend Systems - Suppliers Backend Systems - ESBN/NIE to check if Suppliers systems must be scalable in time for testing or implementation. 129 ESBN/NIE provided the following response on 12th November 2014: Suppliers will not have to scale up their back end systems for Smart Metering volume testing. The scope of testing Smart Metering volumes for this project will be contained to the new TIBCO components only i.e. the Hub and EMMAs to ensure they are capable of handling the expected load. Message volumes and sizes to and from the respective backend systems will be simulated. ESBN/NIE 12/12/2014 AP No. 1 Action still open from last ReMCoWG meeting. Title Org. Assigned to Date Due Date Raised 130 Suppliers to ask/discuss at the PMIG about the possibility of improving functionality/processes with the advent of Smart Metering rather than just moving like for like. Suppliers to update WG Suppliers 14/01/ /11/ th January 2015 Retail Market Design Service

6 ReMCoWG 14 January 2015

7 AGENDA Recent Events Future Plans 7 esbnetworks.ie

8 Recent Events Maintain operational stability No major events since the last meeting There were 25 unplanned contingency events in the last 3 months but none over the Christmas period Supplier EMMA housekeeping - Suppliers are reminded to continue their EMMA housekeeping and to keep ESB/NIE updated with any possible IT impacts in advance 8 esbnetworks.ie

9 Recent Events Start Date End Date Planned Contingency Invoked Comments 31/10/ /10/2014 N Y Supplier connectivity issue Supplier 1 01/11/ /11/2014 N Y Supplier connectivity issue Supplier 9 04/11/ /11/2014 N Y Supplier connectivity issue Supplier 2 08/11/ /11/2014 N Y Supplier connectivity issue Supplier 1 10/11/ /11/2014 Y N Supplier Reboot Supplier 2 12/11/ /11/2014 N Y Supplier connectivity issue Supplier 12 12/11/ /11/2014 N Y Supplier connectivity issue Supplier 3 12/11/ /11/2014 N Y Supplier connectivity issue Supplier 3 13/11/ /11/2014 Y Y TIBCO Alerts Supplier 3 13/11/ /11/2014 N Y Supplier connectivity issue Supplier 7 14/11/ /11/2014 Y Y TIBCO Alerts Supplier 5 15/11/ /11/2014 Y Y DR Exercise Hub 16/11/ /11/2014 N Y Supplier connectivity issue Supplier 7 17/11/ /11/2014 Y Y TIBCO Alerts Supplier 14 18/11/ /11/2014 N Y Supplier connectivity issue Supplier 2 18/11/ /11/2014 Y Y TIBCO Alerts Supplier 8 18/11/ /11/2014 Y Y TIBCO Alerts Supplier 15 20/11/ /11/2014 N Y Supplier connectivity issue Supplier 15 20/11/ /11/2014 Y Y New Production Server Supplier 10 20/11/ /11/2014 N Y Supplier connectivity issue Supplier 7 24/11/ /11/2014 Y Y New Production Server Supplier 10 24/11/ /11/2014 Y Y Planned Outage Supplier 2 24/11/ /11/2014 N Y Supplier connectivity issue Supplier 7 Start Date End Date Planned Contingency Invoked Comments 25/11/ /11/2014 N Y Supplier connectivity Supplier 13 issue 25/11/ /11/2014 Y Y New Production Server Supplier 10 26/11/ /11/2014 N Y Supplier connectivity Supplier 9 issue 01/12/ /12/2014 Y Y Supplier Reboot Supplier 7 01/12/ /12/2014 N Y Supplier connectivity Supplier 9 issue 04/12/ /12/2014 N Y Supplier connectivity Supplier 10 issue 04/12/ /12/2014 N Y Supplier connectivity Supplier 2 issue 04/12/ /12/2014 N Y Supplier connectivity Supplier 7 issue 10/12/ /12/2014 Y Y TIBCO Alerts Supplier 6 11/12/ /12/2014 Y Y TIBCO Alerts Supplier 2 11/12/ /12/2014 Y Y Supplier Security Supplier 6 Patching 12/12/ /12/2014 N Y Supplier connectivity Supplier 7 issue 16/12/ /12/2014 N Y Supplier connectivity Supplier 2 issue 16/12/ /12/2014 N Y Supplier connectivity Supplier 7 issue 16/12/ /12/2014 Y Y TIBCO Alerts Supplier 9 16/12/ /12/2014 Y Y Supplier Security Supplier 11 Patching 17/12/ /12/2014 N Y Supplier connectivity Supplier 12 issue 17/12/ /12/2014 Y Y TIBCO Alerts Supplier 10 17/12/ /12/2014 Y Y TIBCO Alerts Supplier 12 22/12/ /12/2014 N Y Supplier connectivity Supplier 4 issue 22/12/ /12/2014 N Y Supplier connectivity Supplier 5 issue 05/01/ /01/2015 Y Y TIBCO Alerts Supplier 11 08/01/ /2015 Y Y TIBCO Alerts Supplier 16 9 esbnetworks.ie

10 Recent work TIBCO Application Monitoring Alerts Successfully implemented on the TIBCO Hub on 19 th October. Capita has contacted Suppliers to confirm the SMPT address and addresses for alerts. Capita have implemented the required changes for all but two MPs (one to complete today) Additional and early TIBCO alerts will benefit the Market and reduce Supplier Outages. 10 esbnetworks.ie

11 Future Plans Outage Dates: 18 th January 8am to 2pm RoI Extranet will not be impacted, suppliers requested not to issue market messages from their back-end billing systems 11 esbnetworks.ie

12 TIBCO Upgrade - Current Status Recommendation is to proceed with Option 2 while also taking account of Suppliers preference to scale EMMAs for Smart Metering as required Expected duration is weeks incorporating MCR 1111: Debt Flagging and MCR 1122: Essential Plant The project is currently suspended while approvals are being sought The RA s and Networks companies are continuing to work together to resolve the outstanding issue of apportionment of upgrade and enhancement costs to the NI and RoI markets The Network Operators will cover their own costs related to the Audit Findings The objective is still to deliver the project in esbnetworks.ie

13 Questions? 13 Footer esbnetworks.ie

14 Update on Approach to delivery of SMART Retail Market Changes REMCoWG Smart Metering Programme 14 th January, 2014

15 Objective Today To give an update on progress on the delivery of Smart Retail Market Changes 15

16 Recap High Level Overview of Approach Under Smart Metering Programme, CER has asked ESB Networks to lead industry workshops in 2014/15 to progress this deliverable Business as usual approach is not valid - First Major project where changes are required to the Coordinated Baseline Approach reviewed with RMDS Industry workshops estimated to take 6 months - High Level Design (November 14 January 15) - MPD/Schema Level (February-May) Discussion Request(s)/ Market Change Request(s) submitted to industry change control and governance mechanism in Q Exceptional Working Group Meeting to approve Smart Discussion Request(s) Status Updates for Industry Change Control & Governance Groups - Updates at ReMCoWG Dublin Meetings Output: Market Change Request(s) containing approved schema and retail market changes to the Co-ordinated Baseline supporting SMART Metering 16

17 Status Update - Industry Workshops High Level Design Workshops - Policies, Design Considerations & Programme Assumptions (Nov) Completed - Approach To Implementation (Dec) Completed - High Level Overview by MPD Process Group Scheduled for 22nd January, 2015 MPD/Schema Level Detailed Design Workshops - Scheduled by MPD Process Grouping (11th February to 6th May) 17

18 Workshop Schedule 18

19 Approach to MPD/Schema Level Detail Design Workshops - Inputs Draft DRs with details of changes etc prepared by ESBN - Material circulated 1 week in advance of the industry workshops - Expectation that all attending the workshops will have gone through the material in advance NI specific impacts - Section in DRs with NI specific impacts - NI Input requested for review of DRs - Focus on schema/message changes affecting NI - Feedback/Questions to ESBN Smart Metering - Regular meetings between ESBN & NIE 19

20 Approach to MPD/Schema Level Detail Design Workshops - Outputs Revised DRs based on all inputs and feedback from workshop 1 Baselined DRs with all amendments from workshop 2 National Smart Metering Programme issues V1.0 of DRs V1.0 of DRs presented for approval at the extraordinary WG in Q

21 Questions 21

22 Market Design Update ReMCoDS 14 January 2015 Jessica Gregory Retail Market Design Service

23 DR 1155 V1.0 Market Design Process Diagrams conversion from ARIS to document format In 2013 a decision was made to exit from ARIS as BPM for Market Design. Project involves converting all Market Documentation from ARIS platform to Visio/Word platform and publishing directly on the RMDS website. The project is being delivered in stages with a new DR for each stage. DR 1155 is for the approval of 9 of the 41 MPDs and all 89 of the Market Messages As these MPDs are being drafted and converted there are some corrections being identified these are highlighted in the DR and also recorded in the History of Changes for each MPD. At Today s Meeting: Classification as RoI Specific at ReMCoWG Recommendation for Approval as a DR and fast track to MCR requested at IGG Retail Market Design Service

24 DR 1156 V1.0 Cancellation Reason Code OS on 111A MM The Issue Cancellation reason code OS is being sent on the 111A. The code is not included in the allowable list of codes for 111A in the MM guide. Cancellation code OS means that the gaining Supplier is cancelling in response to an objection. The appearance of OS on MM 111A can only occur when OS is sent on 011MM after the 10 day objection period has lapsed. The primary cause of this issue is that the Gaining Supplier is not responding to the original Objection message (011 MM) in the allotted objection period time. At least 1 Supplier has validated against this code being received. Receipt of the OS code on the 111A causes issues for the Supplier who have validated against it. Scale of Issue 2, A MM sent March October of these had cancellation reason code OS 6 messages were sent to 3 suppliers none of which failed on their systems 4 messages were sent to one supplier which did fail and resulted in the Losing Supplier being unable to take the customer back after the gaining Supplier had cancelled Retail Market Design Service

25 DR 1156 V1.0 Cancellation Reason Code OS on 111A MM What is proposed in DR 1156 Market Design information is revised to instruct on the non use of Cancellation Reason Code OS on the 011 MM once the 10 day objection period has elapsed. This will prevent it being auto populated on the 111A. It is suggested that one of the other appropriate and allowable cancellation codes are used (such as SE) under these circumstances. Manage validation errors caused by Suppliers receiving 111A MM (where their systems cannot accept them) on a case by case basis in MRSO. Optional A technical solution was investigated. The details of which are in the DR. It is suggested that based on the number of cases identified, that the technical solution is optional for Suppliers. At Today s Meeting: Classification as RoI Specific at ReMCoWG Recommendation for Approval as a DR requested at IGG Retail Market Design Service

26 Co-MMR The next Co-MMR is scheduled for Wednesday 11 th February 2015 It will contain various small changes to the CoBL. The changes include Inclusion of all New Supplier IDs currently not populated in the CoBL Non Conformances identified during document use. The new CoBL will versioned at 2.5 All Market Message Implementation guides will be updated to version 2.5 An will be sent to participants on detailing all changes that are to be made to the CoBL. Retail Market Design Service

27 Upcoming Outages 14 th January 2015 Retail Market Design Service

28 2014 ReMCoDS Customer Satisfaction Survey ReMCoDS has extended the RMDS survey to include a specific ReMCoDS survey. This will aim to generate feedback and suggestions on the Co-ordinated services provided by ReMCoDS. The survey will be issued on 13th February 2015 Return date will be 13th March 2015 All Market Participants are encouraged to respond as we action items arising out of the survey to improve service delivery to the Market. Retail Market Design Service

29 Next Steps Diary dates for next ReMCoWG meeting: Wednesday 4 th March Belfast Dates included on Calendar of Events on RMDS website 14 th January 2015 Retail Market Design Service Page 29

30 ReMCoWG Meeting Thank You 14 th January 2015 Retail Market Design Service