HOLDER CONSTRUCTION COMPANY Superintendents Weekly Activity Report #63 Douthit Hills Student Community, Clemson University Project Joe Jett

Size: px
Start display at page:

Download "HOLDER CONSTRUCTION COMPANY Superintendents Weekly Activity Report #63 Douthit Hills Student Community, Clemson University Project Joe Jett"

Transcription

1 SAFETY» Total Man Hours Worked This Week: 9086» Total Man Hours on Project: » Crafts On Project This Week: 13» OSHA Recordable Rate: 0 April 24, 2016 Page 1

2 CURRENT CONSTRUCTION ACTIVITIES» Continued Domestic Water Building G Bathrooms.» Continued Window Frame Building E.» Continued Brick Building G.» Continued Shingles on Building F.» Began Installing Roof Building E Sequence 2.» Poured Building E 3rd Floor Topping Slab.» Continued Installing Stair Building G.» Continued Electrical Building G.» Installed Building F Water Tie Ins. Bldg. G Overhead Rough-In Bldg. E 3rd Floor Slab Bldg. F Water Tie Ins SITE, HUB, & WEST ZONE» Continued Forming Elevated Deck HUB.» Continued Building B.» Began Auger Cast HUB.» Continued Retaining HUB.» Continued Racking Manholes.» Transformer Pad Prep for Buildings E,F,& G.» Continued Medium Voltage Cable.» Installed Ductbank From MH4 to MH3. Retaining HUB Access HUB April 24, 2016 Page 2

3 NEXT WEEK S ACTIVITIES EAST ZONE» Continue Building F.» Continue Electrical Building G.» Continue Building G.» Continue Building E.» Pour Building E 2nd Floor Topping Slab. Building A Upper Level Footings SITE, HUB, & WEST ZONE» Continue Storm Line 10.» Begin Building A.» Begin Retaining Magnolia Tree.» Continue Building B.» Continue Auger Cast HUB.» Pour Elevated Deck 1st HUB.» Continue Forming HUB Elevated Deck. Building B CIP Walls April 24, 2016 Page 3

4 MANPOWER TRADE CONTRACTORS ON SITE Man Total Man Subcontractor Trade Employees Hours Hrs. Holder Construction Company General Contractor American Deep Foundation Auger cast piles Baker Roofing Sheathing and Shingles C&C Fence Site Fence Cowart Tree Mulch Tree Removal Davis Crane Erectors Pre-Cast Erection D.H. Griffin Tank Foundation Removal Gainesville Mechanical Ductwork Hutch-N-Son Early Site Work st Choice Glass Glass JBR Construction Early Site Work Johnsons Modern Electric Aboveground Electrical King Asphalt Asphalt Labor Finders Labor Force Metro Power Underground Electrical Osteen Chill Water pipe Precision Concrete R.E. Mclean Tank Tank Demo Reeves Young Site Grading & Utilities Rival Construction Inc. Concrete RJ Coogan Deck Installers Ruppert Landscaping Landscape/ Hardscape Sears Contract Drywall/Metal Trusses Silt Fence Installation Site Erosion Control Southern Mechanical Inc. Electrical/Plumbing Tree South Arborist Upstate Curb Curb and Gutter Valley Farm Construction Tree removal/grading Waterproofing Specialties Waterproofing Total April 24, 2016 Page 4

5 WEATHER CURRENT WEEK Rain Days This Week = 1 Rain Days To Date = 47 SAFETY REVIEW LOG Douthit Hills Monthly OSHA Statistics Man-hours worked RCR/DART May-15 Jun-15 Jul-15 Aug-15 Sep-15 Oct-15 Nov-15 Dec-15 Jan-16 Feb-16 Mar-16 Apr-16 0 May-15 Jun-15 Jul-15 Aug-15 Sep-15 Oct-15 Nov-15 Dec-15 Jan-16 Feb-16 Mar-16 Apr-16 Cumulative Man-Hours RCR DART R April 24, 2016 Page 5

6 MANPOWER CHART Douthit Hills Workforce Reeves Grading Metro Power American Deep Foundations Davis Crane Erectors Sears Contract Gainesville Mechanical 1st Choice Glass Precision Concrete Southern Mechanical Baker Roofing Holder April 24, 2016 Page 6