IMPACT NOTIFICATION PLAN #57 (3/5/2018 3/25/2018)

Size: px
Start display at page:

Download "IMPACT NOTIFICATION PLAN #57 (3/5/2018 3/25/2018)"

Transcription

1 6 IMPACT NOTIFICATION PLAN #57 The following areas will be affected the greatest: ACC WP Level 2 & 3 Emergency Department SPECIAL NOTES: - Click here to watch our progress via the webcam. SCHEDULED SHUTDOWNS: - None Scheduled SPECIAL INSPECTIONS: - Thru-penetration & partition firestopping. - In-Wall inspections prior to wall close up. KEY MILESTONES: o Mobilize work in South Corridor (ACC WP3) 3/17/18 o Level 6 Miller Bldg Drywall Completion 5/11/18 General Construction Activities EMERGENCY DEPARTMENT, WP2 & WP3 Due to a water leak that occurred on 3/3/18, there will be some restoration efforts ongoing throughout the south side of ED, (Triage, Registration, Waiting, etc) and directly above the ED on WP2 and WP3. Restoration work will entail drywall patch and paint, ceiling replacement and flooring/baseboard replacement. MILLER BUILDING CONSTRUCTION SITE Construction vehicles will be using the old ED entrance driveway and ED access will utilize the new site road. A dedicated gatekeeper will be present M-F 7 AM to 4 PM to assist vehicles, EMS staff and pedestrians at this intersection. Deliveries for the south side of the project will be utilizing the ED access road and entering into the south end of construction site. Two-way radio communication will be maintained between the gatekeepers so that access priority can be granted to ED traffic. Interiors of Miller Building will have multiple operations ongoing such as in-wall MEP rough-in, priority wall tops, firestopping, elevator installation, electrical conductors and in-wall inspections prior to drywall installation. Exterior envelope is weathertight, final finishes and cladding is being installed. Roofing installation is complete on the main building, except perimeter prep and coping installation.

2 IMPACT NOTIFICATION PLAN #57 Elevator installation is wrapping up in the south hoistways. North elevator 5&6 have arrived onsite and installation will begin. RENOVATION ACC WP: West Pavilion 2 no work scheduled West Pavilion 3 Containment will be setup in South WP ACC Corridor 3C5E for demolition and corridor improvements on 3/17/18. SEE BELOW FOR MORE DETAIL ON THE ABOVE-MENTIONED ACTIVITIES The following terms will be used in this Impact Notification to convey the level at which noise and vibrations will be occurring due to work being performed. This is an approximation and cannot predict exactly what tools, work, or unexpected conditions may create more or less disturbance than what is listed on this schedule. Slight/Minor: The use of hammers, screw guns, small power tools, non-impacting large equipment such as trucks, man lifts, etc. Moderate: Work involving hammer drills, coring drills, sawcutting, impact hammers, large equipment such as concrete pumps/trucks, excavators, bulldozers, plate compactors, etc. Heavy: Vibratory compactors & rollers, dump trucks, demolition work, pile drilling/driving, cranes, jack hammers, etc. Depending on the proximity to these activities, major vibrations and noise will be present. Skybridge: o Detailed Construction Activity Expected Aerial lifts will be in operation at the north end of the site for Skybridge east wall exterior framing and sheathing, curtainwall installation and prep for masonry. Moderate / intermittent noise can be expected when lifts are in use and framing activities are ongoing. Miller Building: o MEP Rough in, homeruns and major systems will be installed. domestic water, above ceiling HVAC piping; ductwork and medical gas work is ongoing. o Drywall installation is ongoing, South to North on each floor. o Interior stairwell close-in work will continue on South stair Level 7 working topdown; all vertical circulation should use North stair when stairwell work is ongoing. o Temporary heating & weather protection measures, including steam fired heaters, temporary exterior enclosures, etc. will be active throughout the building. o Scaffolding (swing staging) will be in used at the east elevation portion of the Miller Building to allow for metal panel operations. o Curtainwall snap caps and trim details will continue on the West elevation. o Metal panel preparation including z-girts and insulation will continue on the east elevation. This will be followed by metal panel and louver installation. o Roofing will continue Level 6 roof and Skybridge roof including roof blocking, insulation and membrane installation. o Skybridge curtainwall is ongoing. o Masonry will continue on the North elevation starting with mast climber scaffold installation, insulation and clips. o North Elevator installation will continue with building platforms and connecting motors o Patient Room Headwall med gas and power connections will continue. o Patient lift supports will continue at Level 5 and 6.

3 IMPACT NOTIFICATION PLAN #57 ACC West Pavilion Level 2 Renovations o Billing Office 2455 to be completed and turned over. ACC West Pavilion Level 3 Renovations o Demo and reconstruction of corridor 3C5E (corridor at the exterior wall of ACC WP3, from Surgery Waiting to PACU/Pre-Op) will begin 3/17/18. This phase of work will involve multiple smaller phases to renovate the new corridor that will connect the ACC building to the Miller Building. Moderate / intermittent noise can be expected during the setup of phasing and temporary provision activities. Traffic in the ACC WP3 South corridor will be redirected to account for this phasing requirement. Two Week Look Ahead Schedule see next pages If you have any questions or concerns about the work planned do not hesitate to contact Dave Keelty at (802) To report immediate concerns contact UVM Medical Center Security Department at (802)

4 All EDO Office Move Out Of Level 3 Office Space S M T W T F S S M T W T F S S M T W T F S S 3/4 3/5 3/6 3/7 3/8 3/9 3/10 3/11 3/12 3/13 3/14 3/15 3/16 3/17 3/18 3/19 3/20 3/21 3/22 3/23 3/24 3/25 STAG Skybridge Set W15-5 W/ Northstars Crane Manganaro Skybridge Framing East Wall, Ceiling, Sheathing STAG Skybridge Glazing Northstars CC-BB Masonry Install STAG Skybridge Weld W15-5 VMI Skybridge CHWS&R/HWS&R Level 1 Manganaro South Shaftwall Inside Stairway Nicom North AVB Manganaro Pump Room Install Drywall Manganaro North Ceiling Framing/Sheathing VMI Pump Room Piping/Fit Up VMI Corr, Clean Hold, Soil Ductwork Install Manganaro North Connector Layout Corridor/Columns Manganaro S. Centercpre Tape Drywall Manganaro N. Patient Rooms Tape Drywall Manganaro North Kneewall Staff Lounge Manganaro North Drywall Staff lounge Manganaro South Tape Centercore Manganaro North Ceiling Framing, Corridor Soffits Manganaro North Drywall Patient Rooms McDougall EDO Roof Install Z's, Clips, Insulation Benoit North Pipe Care Stat. Greeting Area Lights VMI South Seismic Bracing VMI North Duct Tie Ins At North Shaft VMI North Misc. Piping Tie Ins N. Elev Lobby VMI North Acoustic & Fire Caulking Benoit South Fire Caulk Manganaro North Frame Patient Rm Soffits/Ceil./Sill Benoit N. Centercore Pull Lights And Make Boxes Benoit North Pull Homeruns/Branch Circuits Benoit North Pipe Micro Station And Wire VMI North Mechanical Insulation Manganaro South Tape Drwall Patient Rooms Manganaro South Tape Drwall Centercore Rooms Benoit North Complete Kneewall/Bathroom Ceiling Manganaro N. Centercore/ Corridors Soffit Framing Benoit North Rough In Care Stat Ceiling VMI South Mechanical Insulation Corridor VMI South CHW/HW Cut In Strainers Control Valves VMI North Low Pressure Condensate Piping VMI North Ductwork Install VMI South Acoustic & Fire Caulking Manganaro South Frame Corridor Sofft And Wood Ceiling VMI South Mechanical Insulation Centercore Benoit North Pipe Elec Rooms Manganaro North Centercore Shaftwall And Adjacent Walls VMI North Overhead Piping Dom./Heating VMI North Med Gas Overhead Piping And Headwall VMI North Duct Testing VMI North Hang VAV's & Tie In's Manganaro South Frame And Shaftwall South Stair Manganaro South Drywall Patient Rooms UVM MEDICAL CENTER - MILLER BUILDING PROJECT Two Week Look Ahead Schedule Company Area Construction Activity Notes Skybridge Miller Building Level 2 Level 3 Level 4 Level 5 Level 6 Page 1 3/2/2018

5 UVM MEDICAL CENTER - MILLER BUILDING PROJECT Two Week Look Ahead Schedule S M T W T F S S M T W T F S S M T W T F S S Company Area Construction Activity Notes Benoit North Pull Homeruns/Branch Circuits Benoit N.Centercore Pull Lights And Make Boxes Manganaro North Plywood IT Rm Deck Manganaro South Sheath West Plenum Benoit North Branch And Feeder Piping Manganaro North Frame EMR Room VMI North Medgas Overhead Piping VMI North Duct-Oa Testings, Duct At Elec Rms VMI North Strong Back Trapeze Hangers & Piping Manganaro South Demob Scaffold South Stair Benoit North Pull Feeders And Panels Benoit North Make Up ATS Andemer Panel Benoit North Pipe Fire Alarm VMI North Set Filter Unit On New Steel LWI North Install Grating ACH North Complete Roof/Cleaning Northstars North Elevation Masonry Install 3/4 3/5 3/6 3/7 3/8 3/9 3/10 3/11 3/12 3/13 3/14 3/15 3/16 3/17 3/18 3/19 3/20 3/21 3/22 3/23 3/24 3/25 West Elevation Northstars 1 Line, B,C,D Install Masonry At West Columns STAG W07's Pressure Plate & Cap East Elevation McDougall D-B Install Clips, Z's, Insulation McDougall D-B Install Metal Panels STAG W08's Pressure Plate & Cap McDougall East Elevation Install Louvers North Shafts Manganaro North Shaftwall At North Elevators L7 West Cars TBD Otis North Shafts Elevator Install South Shafts VMI Utility Tunnel Med Gas Future Valve Install VMI Utility Tunnel Misc, DWV City Of Burlington Miller Building Building Inspector Walkthrough 1:00 PM- 1:30 PM SWCE Level 4N, 5S Firestopping Inspection City Of Burlington Miller Building Electrical Inspector Walkthrough City Of Burlington Miller Building Fire Marshall Walkthrough Farrington West Pavilion Level 2 Final Clean E4H/ UVMMC West Pavilion Level 2 Punchlist UVMMC/Benoit Proposed Billing Office 2455 Install Furniture Farrington Proposed Billing Office 2455 Final Clean UVM MC Proposed Billing Office 2455 UVMMC Occupy Farrington WP3 Existing Nurses Lounge Demolition Farrington South Corridor 3C5E Install Containment Farrington South Corridor 3C5E Demo Walls, Ceilings & Floors VMI/Benoit South Corridor 3C5E MEP Demo and Relocates Farrington South Corridor 3C5E Framing Benoit South Corridor 3C5E Inwall MEP Rough McDougall South Gate Metal Panel Delivery VMI/Benoit South Gate Trash Out On Hoist 1-2 PM Manganaro South Gate Drywall Delivery Benoit South Gate Material Delivery McDougall South Gate West Elevation Louvers Level 7 Level 8 (Roof) North Elevation South Elevation Utility Tunnel Building & Commissioning Inspections West Pavilion Renovation Deliveries Page 2 3/2/2018