1 MEDFORD SCHOOL DISTRICT 549C Bond Funded Construction Projects Updated: September 4, 2007 North Medford High School: Project Summary: Renovate and add new addition based on facility evaluation and design. Addition will include new commons areas and classrooms. Renovation projects will include: HVAC upgrade, hazardous material removal, floor replacement, roofing, ADA upgrade, security upgrade, underground piping replacement, and site drainage. Project will be phased over four summers. Total estimated project budget: $34,184,608 Architect: Mahlum/ADW Architects Project Management: TBD Contractor: TBD Construction Completion: Fall Mahlum/ADW schematic design concepts are being evaluated - Gym bleachers replacement completed - Underground mechanical piping system replacement project has been awarded to Bower Construction. Work will be phased into South Medford High School: Project Summary: Build new high school at Cunningham and Columbus. Total estimated project budget: $ 82,890,092 Architect: Mahlum/ADW Architects Project Management: Milstead & Associates Contractor: TBD, to bid spring of 2008 Construction Completion: Summer of Mahlum/ADW Architects are starting the design phase 2007 Projects: Abraham Lincoln Elementary School: Project total estimated budget: $ 49,871 - Exterior painting completed, summer of 2007 Griffin Creek Elementary School: Project Summary: HVAC upgrade, asbestos removal, floor replacement, roofing, ADA upgrades, security upgrade, and connect to City water. Total estimated project budget: $ 2,837,725

2 - Waterline connection, asbestos removal, flooring, roofing, ADA upgrades, and security upgrades are all completed - Interior painting is completed, exterior will be painted in Fall 2007 Hoover Elementary School: Project Summary: Roofing, HVAC upgrades, security, asbestos removal, and flooring. Total estimated project budget: $ 2,708,966 - Asbestos removal, flooring, roofing, ADA upgrades, and security upgrades are all completed - Interior painting is completed, exterior will be painted in Fall 2007 Jefferson Elementary School: Project Summary: Enclose walkway to outer buildings, roofing, HVAC upgrades, security, hazardous material removal, flooring, and ADA upgrades. Total estimated project budget: $ 4,047,128 Architect: OPSIS/ Abell Architects Contractor: Vitus Construction - Enclosed walkway, restroom renovations, ADA upgrades, asbestos removal, flooring, roofing, painting, and security upgrades are all completed Kennedy Elementary School: Project Summary: Roofing, HVAC upgrades, security, asbestos removal, flooring, ADA upgrades, and site work. Total estimated project budget: $2,304,253 - Asbestos removal, flooring, roofing, painting, security and ADA upgrades are all completed

3 Washington Elementary School: Project Summary: The project will be completed in two phases. Phase I will include roofing, HVAC upgrades, security, asbestos removal, flooring, painting, and ADA upgrades. Phase II will include the new cafeteria construction and convert the existing cafeteria into classrooms. Total estimated project budget: $ 6,396,817 Contractor, Phase I: Batzer Inc. Contractor, Phase II: Bids open Sept. 6. Construction Completion: Winter Site under construction - Phase I will be completed by October 1, Phase II will start October 1, 2007 and be completed by February Projects: Howard Elementary School: Project Summary: HVAC, security, asbestos removal, flooring, and ADA upgrades. Total estimated project budget: $ 1,181,235 Construction Completion: Fall 2008 Jackson Elementary School: Project Summary: Renovation and new construction, full scope of work will be developed based on Architect s evaluation and design. Total estimated project budget: $ 12,977,206 Project Management: Milstead & Associates Contractor: TBD, to bid spring of 2008 Start Construction: Summer of School has been vacated due to structural concerns - K-3 relocated to Westside and 4-6 relocated to McLoughlin - Opsis/Abell has started the programming phase and continuing building evaluations

4 Jacksonville Elementary School: Project Summary: Roofing, HVAC upgrades, security, asbestos removal, flooring, parking lot, and painting. Total estimated project budget: $ 726,085 Construction Completion: Fall Sidewalk along back street completed - security upgrade completed Lone Pine Elementary School: Project Summary: Build new elementary school, evaluate existing Media Center. Total estimated project budget: $ 15,759,572 Architect: Mahlum Architects Project Management: TBD Contractor: TBD, to bid April Mahlum Architects are in the programming phase - Project will be evaluated to determine if the project can be phased starting in 2008 Oak Grove Elementary School: Project Summary: Renovation and new construction, full scope of work will be developed based on Architects evaluation and design. Total estimated project budget: $ 9,319,300 Project Management: TBD Contractor: TBD - Opsis/Abell Architects are in the programming phase Roosevelt Elementary School: Project Summary: Renovation and new construction, full scope of work will be developed based on Architect s evaluation and design. Total estimated project budget: $ 12,954,154

5 Project Management: Milstead and Associates Contractor: TBD, to bid Spring The school has been vacated due to structural concerns - K-3 relocated to Hoover and 4-6 relocated to Hedrick - Opsis/Abell Architects are in the programming phase and building evaluations Ruch Elementary School: Project Summary: Roofing, HVAC upgrades, security, asbestos removal, flooring, ADA upgrades, and seismic upgrade. Total estimated project budget: $ 1,240,136 Construction Completion: Fall 2008 Wilson Elementary School: Project Summary: Renovation to include: Roofing, HVAC upgrade, security, asbestos removal, flooring, ADA upgrades, window replacement, and seismic upgrade. Total estimated project budget: $ 2,987,734 Construction Completion: Winter Opsis/Abell Architects are evaluating design options 2009 Projects: Hedrick Middle School: Project Summary: HVAC upgrades, security, asbestos removal, flooring, ADA upgrades, and pipe repairs. Total estimated project budget: $ 1,603,137 Contractor: TBD, to bid spring of 2009

6 Start Construction: June New gym bleachers added McLoughlin Middle School: Project Summary: Roofing, HVAC upgrades, security, asbestos removal, flooring, and seismic upgrade. Total estimated project budget: $ 1,661,701 Contractor: TBD, to bid spring of 2009 Start Construction: June New gym bleachers added