1 NORTHSIDE INDEPENDENT SCHOOL DISTRICT 2010 BOND Facilities Construction September 2015 Leroy San Miguel ASSIST. SUPERINTENDENT FOR FACILITIES & OPERATIONS Ceasar Ponce, A.I.A. EXECUTIVE DIRECTOR CONSTRUCTION & ENGINEERING Paul Megerle DIRECTOR OF FACILITIES CONSTRUCTION Harlan High School

2 HARLAN HIGH SCHOOL (Formerly KALLISON RANCH HIGH SCHOOL) Architect Garza Bomberger & Associates Project Architect Roy Lewis NISD Project Manager Jim Berg Contractor Joeris General Contractor GMP - $110,800, Construction Period October 2014 May 2017 (39% Complete) Project Scope New 2800 Student High School Building Permit and Notice to Proceed issued October 8, Site Construction began October 14, Site grading, Piers, 1 st,2 nd and 3 rd Floor framing and columns in progress. Underground utilities and Interior CMU walls, electrical, plumbing, and HVAC rough-in in progress. Roof steel erection and window installation in progress.

3 HARLAN HIGH SCHOOL (Formerly KALLISON RANCH HIGH SCHOOL) Aerial (Aug. 20, 2015)

4 HARLAN HIGH SCHOOL (Formerly KALLISON RANCH HIGH SCHOOL) Front Entrance

5 HARLAN HIGH SCHOOL (Formerly KALLISON RANCH HIGH SCHOOL) (August 4, 2015)

6 ELEMENTARY SCHOOL ISMS (Integrated Security Mgmt System) Consultant Combs Consulting Group NISD Project Manager Charles Pereira Contractor Convergint Technologies Construction Contract Award $13,422, Total Change Orders to Date - $652, Adjusted Construction Contract Amount - $14,075, Total Construction Contract Completed - $13,270, Balance to Finish Construction Contract - $804, Notice to Proceed January 23, 2013 Original Construction Completion May 31, 2015 Revised Construction Completion November 11, 2015 Contract Percentage Completion 95%

7 ELEMENTARY SCHOOL ISMS (Integrated Security Mgmt System) Project Scope Furnish and install all new interior and exterior security surveillance cameras, with access control electrified hardware and security alarm disarm keypads. Connect and integrate the existing intrusion alarm devices, motion sensors and glass break sensors at all existing campuses. 75 Elementary School Campuses have Punch List inspections completed 2 Middle School Campuses have Punch List inspections completed 75 Elementary School Campuses have equipment and software training 2 Additional Middle School Campuses have equipment and software training. 65 Elementary campuses have Substantial Completion Certificates issued. 65 Campuses have close-out documents submitted to NISD. 45 Campuses have post warranty documents completed.

8 NORTHSIDE SPORTS GYM Architect Marmon Mok Project Architect Monty Howard NISD Project Manager Thomas Curiel Contractor Bartlett Cocke General Contractor Contract Amount $26,326, Construction Period May 2015 October 2016 (9% Complete) Project Scope Provide a District-Wide Sports Gymnasium at the Farris Complex. Site work and plumbing rough-ins in progress.

9 NORTHSIDE SPORTS GYM Site Plan

10 NORTHSIDE SPORTS GYM Aerial View (August 18, 2015)

11 NORTHSIDE SPORTS GYM Entry View

12 NORTHSIDE SPORTS GYM Plaza View

13 NORTHSIDE SPORTS GYM Seating View

14 VILLAGE at WESTPOINTE EAST ELEMENTARY SCHOOL Architect Noonan Rittimann Project Architect John Rittimann NISD Project Manager Chris Parker Contractor Bartlett Cocke General Contractor Construction Amount - $25,371, Construction Period April 2015 June 30, 2016 (23% Complete) Project Scope New 800 Student Elementary School Building layout and pad construction complete. Concrete superstructure, slab work, underground utilities, permanent power installation and structural steel in progress.

15 VILLAGE at WESTPOINTE EAST ELEMENTARY SCHOOL (Front Entrance)

16 VILLAGE at WESTPOINTE EAST ELEMENTARY Aerial View (July 8, 2015)

17 VILLAGE at WESTPOINTE EAST ELEMENTARY (August 28, 2015)

18 FM 471 # 3 ELEMENTARY SCHOOL Architect O Neill Conrad Oppelt Project Architect Mark Oppelt NISD Project Manager Marilyn Sevedge Contractor Joeris General Contractor Contract Amount - $24,615, Construction Period April 2015 June 30, 2016 (24% Complete) Project Scope New 800 Student Elementary School Full building permit issued. Concrete superstructure and slabs in progress.

19 FM 471 # 3 ELEMENTARY SCHOOL Front Entrance

20 FM 471 # 3 ELEMENTARY SCHOOL Aerial View (August 20, 2015)

21 FM 471 # 3 ELEMENTARY SCHOOL Site Plan

22 FM 471 # 3 ELEMENTARY SCHOOL (September 2015)

23 FM 471 # 3 ELEMENTARY SCHOOL (September 2015)

24 ADDITIONS AND RENOVATIONS PROJECTS IN PROGRESS

25 O CONNOR HIGH SCHOOL AG UPGRADES Architect Shawn Kaarlsen & Associates Project Architect Shawn Kaarlsen NISD Project Manager Chris Parker Contractor Baron-Long Construction, LTD Contract Amount - $818, Construction Period March 2015 July 2015 (95% Complete) Project Scope - Reconfigure Barns and Shop Renovation. Final punch list in progress. Pen panels installed at R and S building.

26 SECURITY LOBBIES AT (8) CAMPUSES Architect NextGen Architects Project Architect Joel Hernandez NISD Project Manager Marilyn Sevedge Contractor Marksmen Construction Contract Amount - $1,047, Construction Period March 2015 August 3, 2015 (95% Complete) Project Scope New Security Lobby for (8) Elementary Schools. Substantial Completion issued with exception to McDermott ES.

27 SECURITY LOBBIES AT (8) CAMPUSES - McDermott Elementary (Aug. 3, 2015)

28 SECURITY LOBBIES AT (8) CAMPUSES - Linton Elementary (Aug. 4, 2015)

29 SECURITY LOBBIES AT (8) CAMPUSES - Linton Elementary (Aug. 4, 2015)

30 SECURITY LOBBIES AT (8) CAMPUSES Rhodes Elementary (Aug. 6, 2015)

31 SECURITY LOBBIES AT (8) CAMPUSES Rhodes Elementary (Aug. 6, 2015)

32 SECURITY LOBBIES AT (8) CAMPUSES Meadow Village Elementary (Aug. 6, 2015)

33 SECURITY LOBBIES AT (8) CAMPUSES Meadow Village Elementary (Aug. 6, 2015)

34 NEFF MIDDLE SCHOOL ADA / WINDOW REPLACEMENT Architect Garza Architects Project Architect Jesse Garza NISD Project Manager Thomas Curiel Contractor D.L. Bandy Construction Amount - $3,565, Construction Period May 2015 December 2015 (71% Complete) Project Scope Window Replacement, ADA Upgrade and ALE Renovation.

35 NEFF MIDDLE SCHOOL ADA / WINDOW REPLACEMENT (Site Plan)

36 NEFF MIDDLE SCHOOL ADA / WINDOW REPLACEMENT (South Elevation)

37 NEFF MIDDLE SCHOOL ADA / WINDOW REPLACEMENT (North Elevation)

38 NEFF MIDDLE SCHOOL ADA / WINDOW REPLACEMENT (East Elevation)

39 NEFF MIDDLE SCHOOL ADA / WINDOW REPLACEMENT (September 2, 2015)

40 HOLMES HS/MARSHALL HS/NEFF MS/RAYBURN MS/ FACILITY ATHLETIC UPGRADES & RENOVATIONS Architect NextGen Architects Project Architect Joel Hernandez NISD Project Manager Chris Parker Contractor STI General Contractors Contract Amount - $1,387, Construction Period July 2, 2015 August 3, 2015 (68% Complete) Project Scope Renovate Athletic/PE Areas; Flooring and lighting complete. Lockers delivered. Installation in progress, including mobile storage units.

41

42 RUDDER MIDDLE SCHOOL SCIENCE LAB ADDITION Architect Alamo Architects Project Architect Jerry Lammers NISD Project Manager Jim Berg Contractor D.L. Bandy Contract Amount - $4,782, Construction Period May 15, 2015 August 1, 2016 (17% Complete) Project Scope New Science Classroom Addition and Renovation. Site work and underground site utilities in progress. Foundation and slab is complete.

43 RUDDER MIDDLE SCHOOL SCIENCE LAB ADDITION (New Site Plan)

44 RUDDER MIDDLE SCHOOL SCIENCE LAB ADDITION (Perspective)

45 RUDDER MIDDLE SCHOOL SCIENCE LAB ADDITION (Front Entry Final Scheme)

46 RUDDER MIDDLE SCHOOL SCIENCE LAB ADDITION (1 st Floor Plan)

47 RUDDER MIDDLE SCHOOL SCIENCE LAB ADDITION (2 nd Floor Plan)

48 RUDDER MIDDLE SCHOOL SCIENCE LAB ADDITION (September 1, 2015)

49

50 LUNA MIDDLE SCHOOL CLASSROOM ADDITION Architect Garza Bomberger & Associates Project Architect Roy Lewis NISD Project Manager Thomas Curiel Contractor Guido Brothers Construction Contract Amount - $3,198, Construction Period June 2015 June 2016 (4% Complete) Project Scope New Classroom Addition Pilot holes drilled for addition foundation. Building pad to continue and piers to start in two weeks.

51 LUNA MIDDLE SCHOOL CLASSROOM ADDITION (Site Plan)

52 LUNA MIDDLE SCHOOL CLASSROOM ADDITION (1 st Floor Plan)

53 LUNA MIDDLE SCHOOL CLASSROOM ADDITION (2 nd Floor Plan)

54 LUNA MIDDLE SCHOOL CLASSROOM ADDITION (Elevation)

55 2014 BOND PROJECTS IN BID/DESIGN PHASES

56 KALLISON RANCH #2 ES (ELLISON ES PROTOTYPE) Architect Garza Bomberger Project Architect Roy Lewis NISD Project Manager Marilyn Sevedge Contractor TBD Construction Budget - $22,500, Tentative Construction Period May 7, 2016 May 26, 2017 Project Scope Construction of an 800 Student Elementary School

57 KALLISON RANCH #2 ES - (Ellison ES Prototype) Front Entrance

58 CHILD NUTRITION WAREHOUSE - Warehouse Renovation Architect Shawn Kaarlsen & Associates Project Architect Shawn Kaarlsen NISD Project Manager Marilyn Sevedge Contractor TBD Construction Budget - $3,000, Tentative Construction Period January 2016 May 2016 Project Scope Warehouse Renovation

59 ALLEN ES CLASSROOM - (ADDITION/ADA/WINDOW UPGRADES) Architect Shawn Kaarlsen & Associates Project Architect Shawn Kaarlsen NISD Project Manager Chris Parker Contractor TBD Construction Budget - $6,230, Tentative Construction Period March 2016 August 2016 Project Scope Classroom Addition/ADA/Window Upgrades

60 HOLMES HS FINE ARTS - UPGRADE Architect Alamo Architects Project Architect Jerry Lammers NISD Project Manager James Berg Contractor TBD Construction Budget - $14,000, Tentative Construction Period June 6, 2016 December 5, 2017 Project Scope Auditorium Building Replacement

61 THORNTON ES - MUSIC ROOM ADDITION Architect Pfluger Architects Project Architect Carr Hornbuckle NISD Project Manager James Berg Contractor TBD Construction Budget - $300, Tentative Construction Period June 6, 2016 August 5, 2016 Project Scope Music Room Addition

62 ZACHRY MS BUS CANOPY MODIFICATIONS Architect Alamo Architects Project Architect Jerry Lammers NISD Project Manager Jim Berg Contractor TBD Construction Budget - $1,100, Tentative Construction Period February 2016 July 2016 Project Scope Bus Canopy Modifications

63 ALE Upgrades at CLARK HS, JAY HS & PEASE MS & ESPARZA ES Library Addition Architect O Connell Robertson Project Architect Chris Narendorf NISD Project Manager Chris Parker Contractor TBD Construction Budget - $1,125, and $880, Tentative Construction Period March 4, 2016 August 5, 2016 Project Scope Upgrades of Existing ALE Classrooms and Library Addition for Esparza ES

64 GLENOAKS ELEMENTARY - Administration Upgrades Architect NextGen Architects Project Architect Joel Hernandez NISD Project Manager Marilyn Sevedge Contractor TBD Construction Budget - $3,750, Tentative Construction Period March 2016 March 2017 Project Scope Administration Upgrades

65 CODY ES & LEON VALLEY ELEMENTARY - (CAFE & KITCHEN RENOVATIONS) Architect Garza Architects Project Architect Jesse Garza NISD Project Manager Tom Curiel Contractor TBD Construction Budget - $6,500, Tentative Construction Period February 2016 August 2016 Project Scope Renovations to Cafeteria and Kitchen

66 LOCKE HILL ES, THORNTON ES, LEON VALLEY ES, POWELL ES, COON ES, MICHAEL ES, MARY HULL ES AND CABLE ES - (SECURITY LOBBIES) Architect NextGen Architects Project Architect Joel Hernandez NISD Project Manager Marilyn Sevedge Contractor TBD Construction Budget - $480, Tentative Construction Period January 2016 August 2016 Project Scope New Security Lobby for (8) Elementary Schools

67 ROOFING PROJECTS

68 BLOCK AQUATICS ROOFING PROJECT Roofing Consultant Hollon + Cannon Contractor CT Construction Contract Amount $45, Construction Period June August 14, 2015 (100% Complete) Project Scope Roof Repair & Replacement

69 CARSON ELEMENTARY ROOFING PROJECT Roofing Consultant Raba Kistner Contractor Port Enterprises Contract Amount $861, Construction Period June August 2015 (99% Complete) Project Scope Roof Repair & Replacement. Staging in progress. Substantial Completion. Punch list items.

70 CODY ELEMENTARY ROOFING PROJECT Roofing Consultant Hollon + Cannon Contractor Cram Roofing Contract Amount $289, Construction Period June August 2015 (100% Complete) Project Scope Roof Repair & Replacement.

71 JORDAN MIDDLE SCHOOL ROOFING PROJECT Roofing Consultant Austech Engineering Contractor Port Enterprises Contract Amount $1,822, Construction Period June August 21, 2015 (99% Complete) Project Scope Roof Repair & Waterproofing. Substantial completion. Working on punch list items.

72 STEVENSON AND STINSON MIDDLE SCHOOL ROOFING PROJECT Roofing Consultant Hollon + Cannon Contractor Cram Roofing Contract Amount $566, Construction Period June August 2015 (99% Complete) Project Scope Roof Repair & Waterproofing. Barrel roof left.