1 SUCCESS WITH 2012 IECC DELAWARE Recommended Practices for Optimized Energy Savings for Builders & Trades COPYRIGHT 2015 ADVANCED ENERGY. ALL RIGHTS RESERVED VERSION

2 DELAWARE For vented attics, install wind baffles on top of all exterior walls, leaving 1. room for insulation over top plates and ventilation above. 1. For vented attics, install wind baffles on top of all exterior walls, leaving room for insulation over top plates and ventilation above. MISALIGNMENT RIGHT INSTALLATION WIND WASHING RIGHT INSTALLATION COPYRIGHT 2015 ADVANCED ENERGY. ALL RIGHTS RESERVED VERSION PAGE 2

3 DELAWARE 2. Install insulation levels to meet the 2012 IECC. a CLIMATE ZONE CEILING FRAME WALL MASS WALL C FLOOR BASEMENT WALL C CRAWL SPACE WALL C Zone 4 R-49 R-20 or 13+5 h R-8/13 R-19 R-10/13 R-10/13 10, 2 ft. SLAB a. R-values are minimums. U-factors and SHGC are maximums. When insulation is installed in a cavity which is less than the label or design thickness of the insulation, the installed R-value of the insulation shall not be less than the R-value specified in the table. c. "15/19" means R-15 continuous insulation on the interior or exterior of the home or R-19 cavity insulation at the interior of the basement wall. "15/19" shall be permitted to be met with R-13 cavity insulation on the interior of the basement wall plus R-5 continuous insulation on the interior or exterior of the home. "10/13" means R-10 continuous insulation on the interior or exterior of the home or R-13 cavity insulation at the interior of the basement wall. h. First value is cavity insulation, second is continuous insulation or insulated siding, so "13+5" means R-13 cavity insulation plus R-5 continuous insulation or insulated siding. If structural sheathing covers 40 percent or less of the exterior, continuous insulation R-value shall be permitted to be reduced by no more than R-3 in the locations where structural sheathing is used - to maintain a consistent total sheathing thickness. COPYRIGHT 2015 ADVANCED ENERGY. ALL RIGHTS RESERVED VERSION PAGE 3

4 DELAWARE GAPS NO GAPS VOIDS NO VOIDS MISALIGNMENT NO MISALIGNMENT COMPRESSION NO COMPRESSION COPYRIGHT 2015 ADVANCED ENERGY. ALL RIGHTS RESERVED VERSION PAGE 4

5 DELAWARE 4. Cut and split insulation around blocking, plumbing, HVAC and electrical components. COMPRESSION 5. NO COMPRESSION Install insulation to completely fill floor and/or cantilever framing or to maintain permanent contact with the subfloor. VOIDS NO VOIDS 4. Cut and split insulation around blocking, plumbing, HVAC and electrical components. MISALIGNMENT 5. NO MISALIGNMENT Install insulation to completely fill floor and/or cantilever framing or to maintain permanent contact with the subfloor. GAPS COPYRIGHT 2015 ADVANCED ENERGY. ALL RIGHTS RESERVED VERSION PAGE 5 NO GAPS

6 DELAWARE 6. Air seal around windows and doors using backer rod, caulk or low expansion foam. 7. SEAL Insulate the attic access to the same level as surroundings and install weather stripping around the perimeter. NO 7. Insulate the attic access and install weather stripping around the perimeter. NO 8. For attics with loose fill insulation, install baffles around the attic access opening. NO BAFFLES COPYRIGHT 2015 ADVANCED ENERGY. ALL RIGHTS RESERVED VERSION PAGE 6 RIGHT INSTALLATION