2941 Fairview Park Fairview Park. Eric Sobel. Pennsylvania State University Dept. of Architectural Engineering Spring 2003 Structural Option
|
|
- Dinah McDowell
- 5 years ago
- Views:
Transcription
1 Pennsylvania State University Dept. of Architectural Engineering Spring 2003 Structural Option
2
3 PROJECT TEAM Owner: Developer: Contractor: Architect: Structural: M.E.P.: Envelope: 2941 Fairview L.L.P. The David Orr Company Clark Construction Boggs & Partners Cagley & Associates Allen & Shariff PCC Consultants
4 BUILDING $38 Million 361,101 gross sq. ft 15 rentable stories Mechanical Penthouse Basement Offices Atrium Café Restaurant
5 SYSTEMS Mechanical: VAV System Chilled Water 65 Ton AC Units Electric Heating Coils Series fan VAV Units Electrical: Circuit Breaker Panelboards K-4 Rated Transformers
6 CURTAIN WALL E-W: METAL PANEL N-S: PRECAST CONCRETE
7 PLAN TYPICAL TOWER FLOOR PLAN
8 EXISTING STRUCTURE Gravity System: Composite A992 Steel 5 ¼ LW Conc. On Metal Deck Lateral System: N-S: 2 Braced Frames E-W: 5 Braced Frames & 5 Moment Frames Foundations: Typical Spread Foundations Buried Mat Foundation
9 PLAN FOURTH FLOOR PLAN
10 REDESIGN Goals: Increase Serviceability Decrease Initial Cost Decrease Construction Time Minimal Architectural Change Advantages: Quality Control Durability Material Strength Architectural Finish Quicker Erection Disadvantages: Increased Weight Transportation
11 OUTLINE Members: Building Core Gravity System Building Envelope Connections Construction: 4D CAD Schedule Estimate
12 PLAN TYPICAL TOWER FLOOR PLAN
13 HOLLOWCORE PLANKS 8 Hollowcore Planks Lightweight Concrete 6 straight ½ tendons f c = 5,000 psi
14 INVERTED TEES 20 x 30 Inverted Tees Normal Weight Concrete 4 x 10 Ledges Straight Tendons f c = 8,000 psi
15 COLUMNS Precast: 20 x 20 4 floor pieces f c ranging from 5,000-12,000 psi Upper Floors: Lightweight Corbels
16 SPANDREL Construction Reduced Members Bearing Connection Composition 3 Concrete (2) 1 ½ Insulation Metal Facing
17 WINDOWS Waussau Window System Installation Inside Simple
18 FOUNDATIONS Goals: Adequate Strength Cost Effective Rigid Support for Shearwalls Pinned Support for Columns
19 CONNECTIONS Importance: Define Structural Response Influences Construction Schedule Goals: High Repetition Relieve Induced Stresses Easy Erection Simple Formwork
20 BEAM - COLUMN Goals: Diaphragm Action Induced Stresses Quick Erection Columns Stability Description: Mastecord Bearing Pads Supporting Angle Analysis: PCI Design Guide PCHELP
21 PRECAST - SITECAST Goals: Transfer Gravity & Lateral Forces Simple Formwork Description: JVI-Inc. BSF 200/40 The Invisible Corbel Box cast in beam Knife cast in column Weld Plate Analysis: JVI Design Aids
22 CONSTRUCTION DAY 1
23 CONSTRUCTION DAY 1 DAY 2
24 CONSTRUCTION DAY 1 DAY 2 DAY 3
25 CONSTRUCTION DAY 1 DAY 2 DAY 3 DAY 4
26 CONSTRUCTION DAY 1 DAY 2 DAY 3 DAY 4 DAY 5
27 CONSTRUCTION
28 SCHEDULE COMPOSITE STEEL PRECAST
29 ESTIMATE Composite Steel: Precast: $5.95 million $6.07 million $ Million Site Cast Flooring Columns Foundations Steel Precast
30 CONCLUSIONS Drift: 30% Stiffer Initial Cost: Similar Construction Schedule: 4 Weeks Quicker Rentable Area: 650 Additional sq. ft. Plenum Depth: Varies Acoustics: 10 db STL & INR
31 THANKS Thanks to: Joe Ajello, PE Jimmy Lakey, PE All others at Cagley & Associates Mark Tayor Mike Patton Clement Enyeji Prof s: Parffit, Geschwindner, Boothby, & Burnette All other AE Faculty AE Class of 2003 Karen My Family
32 Questions? Members Connections Construction Trades Affected
33 SHEARWALLS East-West: (4) 22-8 Shearwall 24 Thick North-South: (2) Shearwall / Moment Frame Lines 20 Thick Deep Beams General: Locations matched existing braced frame locations Loadbearing => R=4.0
34 MOMENT FRAME Location: Along grid Line H Lower Portion Goals: Increase stiffness to region Free up Space Description: Site cast Spans parallel to plank
35 EXPANSION JOINT Goals: Transfer gravity loads Transfer E-W lateral loads Separate N-S lateral loads Description: Slotted Connector Teflon bearing pad
36 GROUTED KEYS Goals: Member Connectivity Diaphragm Action Description: Grouted Keys
37 PLANK INVERTED TEE Goals: Diaphragm Action Induced Stresses Quick Erection Description: Mastecord Bearing Pads Supporting Angle Analysis: PCI Design Guide
38 DAPPED BEAM Goals: Transfer Gravity & Lateral Forces Simple Connection Description: Mastecord Bearing Pad Analysis: PCI Design Method PCHELP
39 DAPPED BEAM
40 COLUMN SPLICE Goals: Aesthetically pleasing Transfer only axial and shear loads Simple erection Description: Bolted connection Grouted Splice occurs just above floor level Analysis: PCI design aids
41 FEATURES Architectural Atrium Entrance Plaza ME/TC rooms per floor Tenant Build-Out Superb Landscaping
42 SCHEDULE General: 20 columns / day 20 beams / day 40 planks / day Core: 1 level / week Windows: 1 level / week Core: 2 weeks ahead Windows: 2 weeks behind
43 DETAIL BUILDING END DETAIL
44 CRANES
45 TRANSPORTATION
46 TRADES AFFECTED
47 TRADES AFFECTED