1 March 20, 2018

2 Agenda 2

3 Industry Partners Thank you to the following industry partners: Alliance Geotechnical Group Austin Bridge & Road Equify Ferrovial Agroman US Corp Fluor Corporation Granite Construction Holmes Murphy HNTB Iconic Consulting Group Kiewit Infrastructure Group McCarthy Building Companies Lazer Construction Co., Inc. Reynolds, Smith & Hills, Inc. United Rentals Webber Williams Brothers Construction Co., Inc. WSP USA, Inc. Zachry Construction Corporation 3

4 Host Partners and Regional Supporters Thank you to the following host partners: Associated General Contractors of Texas Kristen Ogden Smith Director of Subcontractor and Employee Relations Regional Hispanic Contractors Association John Martinez President Ruben Landa Vice Chairman 4

5 TxDOT Points of Contact Tyler District Glenn Green, P.E. District Engineer Shane Cunningham, P.E. Director of Construction Jeffrey Harmon, P.E. Director of TP&D Stacie Holcomb Construction Records Auditor/ DBE Coordinator Kathi White Public Information Officer Northeast Civil Rights Division Michael D. Bryant Division Director Don Barwick, Ph.D. Program Specialist Sarah C. Blackburn, CTCM Special Projects Coordinator Carlton Cooper Program Specialist Construction Division Jesse Lineberger Construction and Maintenance Contract Letting Section Director 5

6 TxDOT Websites Civil Rights Division - TxDOT DBE Program - PAVED Program - Tyler District - Diversity Management System (DMS): everify: Prequalification: 6

7 FM 2493 WIDENING PROJECT March 20, 2018

8 FM 2493 CSJ

9 FM 2493 CSJ Project Limits: FM 2818 to FM 346 Project Scope Reconstruct existing 2-ln roadway to a 4-ln divided roadway Storm Sewer Signal at FM 346 August 2018 Letting Estimated Construction Cost of $15,500,000 Estimated Completion Fall

10 FM 2493 CSJ Estimated Quantities 88,500 SY Flexible Base 29,000 TON Asphalt Concrete Pavement 76,000 SY Block Sod 14,500 LF Concrete Pipe 9200 SY Sidewalk 20,000 LF Curb & Gutter 1 Signal 10

11 US 69 GRADE SEPARATION PROJECT March 20, 2018

12 US 69 CSJ

13 US 69 CSJ Project Limits: at FM 346 Project Scope MSE Retaining Walls Four-lane Bridge Bridge-Class Culvert Extension Ramps and U-Turns August 2018 Letting Estimated Construction Cost of $15,500,000 Estimated Completion Fall

14 US 69 CSJ Estimated Quantities 30,000 TON Asphalt Concrete Pavement 154,000 SY Temporary & Permanent Seeding 2500 LF Concrete Pipe 55,200 SF Bridge Deck 30,000 SF Retaining Wall 14

15 IH 20 RAMP IMPROVEMENT PROJECT March 20, 2018

16 IH 20 CSJ

17 IH 20 CSJ Project Limits: US 69 to Jim Hogg Road Project Scope Realign 4 Ramps Widen 1 Bridge Build Eastbound and Westbound Frontage Roads Retaining Walls June 2018 Letting Estimated Construction Cost of $13,500,000 Estimated Completion Spring

18 IH 20 CSJ Estimated Quantities 23,000 TON Asphalt Concrete Pavement 104,000 SY Temporary & Permanent Seeding 2000 LF Concrete Pipe 2,500 SF Bridge Deck 45,000 SF Retaining Wall 18

19 FM 2206 WIDENING PROJECT Phase I March 20, 2018

20 FM 2206 CSJ

21 FM 2206 CSJ Project Limits: Fisher Road to Loop 281 Project Scope Reconstruct existing 2-ln roadway to a 4-ln divided roadway Storm Sewer Signal at Loop 281 August 2019 Letting Estimated Construction Cost of $13,000,000 Estimated Completion Fall

22 FM 2206 CSJ Estimated Quantities 74,500 SY Flexible Base 25,000 TON Asphalt Concrete Pavement 50,000 SY Block Sod 5,100 LF Concrete Pipe 12,000 SY Sidewalk 16,500 LF Curb & Gutter 1 Signal 22

23 FM 2493 CSJ Questions?