NYC Department of Education

Size: px
Start display at page:

Download "NYC Department of Education"

Transcription

1 Architectural Inspection Building Assessment Survey Asset: SOUTH BRONX HS TRANSPORTABLE - X, 701 ST. ANNS AVENUE, New York, Inspection Id Inspection Type Time In Last Edited SA : Architectural - Senior :20 AM :00 PM AA : Architectural - Associate :20 AM :47 PM Asset Data Was the building fully accessible for inspection Principal(s) Information Custodian Fireman Principal Name Organization Did you meet with this Principal? Did this Principal provide feedback? Summary of Principal's Feedback Answer Building Square Footage 2600 Comments on the Area Comments on the Stories (Floors) plus Basements Comments on the Number of Classrooms 3 Hazel Joseph Roseboro South Bronx High School - Bronx The Principal had no concerns regarding the physical conditions of the buildings at this time. Patrick Petriello Louis Tamburri ne Comments on the Year Built 1997 Student Population 75 Staff Population 4 Weather Facade Photo 1 ( Basement) Fair Rae Street - rth view PB/A&W Page 1 of 11

2 Main Entrance Photo Building Assessment Survey Roof Photo Facade A - Unit T4 Roof 1 - West view Have any Systems/Major Building Components been upgraded? Have there been any New Building Additions? Tandem Schools? Leased Space? Systems: Partial Roofing repairs Year: 2012 Systems: New Exterior Metal Stairs and Ramps Year: 2008 Priority Priority Exist Last Year? Priority Category Description Component Affected Location Description Person(s) tified Person(s) Title PhotoImage condition recorded Structural Engineer Required Structural Type Description Component Affected Location Description Person(s) tified Person(s) Title PhotoImage condition recorded PB/A&W Page 2 of 11

3 Accessibility Building Assessment Survey Accessibility Status Is the primary or secondary entrance on an accessible route? Is the building a multi-story building? Do any of the following spaces exist? Classroom, Art Room, Auditorium, Cafeteria, Computer, Gymnasiums, Library, Multipurpose Room, Science Labs For the spaces that do exist, are they ALL accessible? Is there at least one Boys and Girls or Unisex toilet accessible in the building Physical Breakdown Structure Exists Complies Required FUNCTIONAL ACCESSIBILITY Exterior Routes Exterior Entrances & Exits Exterior H/C Lifts Exterior Ramps and Railings Interior Routes Corridor and Lobby H/C Lifts Interior Corridor Doors and Hardware Interior Corridors and Lobbies Interior Elevators Interior Lobby Doors and Hardware Interior Ramps Rooms & Spaces Art Rooms Auditorium Cafeteria Classrooms Units T1 - T3 Computer Rooms Gymnasium Library Main Office Unit T4 Multi-purpose Room Nurse's Room Pool Science Lab Toilet Rooms (Boys) Unisex in Units T2, T3 Toilet Rooms (Girls) Unisex in Units T2, T3 Toilet Rooms (Staff) Unisex in Units T1, T4 PB/A&W Page 3 of 11

4 Building Template Building Assessment Survey Inspection Architectural AWNINGS AND CANOPIES DOORS DOORS AND FRAMES Roof Plan reference 5 - Poor METAL: DETERIORATED DOOR AND FRAME - MAJOR DETERIORATION Quantity 1 EACH Urgency of Action PRIORITY 4 PB/A&W Page 4 of 11

5 DOORS DOORS AND FRAMES Photo1 Building Assessment Survey Facade G Unit T1 violations recorded. DOOR HARDWARE 3 - Fair WALLS Material Type(s) Steel Replacement Quantity 3,000 Replacement Uom Instance on All Facades Instance 3 - Fair Instance Quantity 3,000 Instance METAL PANEL: MAJOR RUSTING Roof Plan reference Elevation Quantity 25 Urgency of Action PRIORITY 4 PB/A&W Page 5 of 11

6 WALLS Photo1 Building Assessment Survey Roof Plan reference Facade G violations recorded. METAL PANEL: OPEN JOINTS Elevation Quantity 50 L.F. REPAIR Urgency of Action PRIORITY 4 Photo1 Facade G violations recorded. METAL PANEL: DAMAGED TRIM PB/A&W Page 6 of 11

7 WALLS Roof Plan reference Building Assessment Survey Elevation Quantity 50 L.F. Urgency of Action PRIORITY 4 Photo1 Facade F SOFFITS LOUVER Facade G violations recorded. PB/A&W Page 7 of 11

8 LOUVER ROOF Roofing Replacement Quantity 2,600 Replacement Uom LEADERS, GUTTERS, DOWNSPOUTS, SCUPPERS ROOFING Instance on Single Ply, Fully Adhered Roof: Roof 1 and 2 Instance 3 - Fair Instance Quantity 2,600 Instance Does the roof have major mechanical equipment sitting on Dunnage Steel less than 18" above the Roofing? Installation Year 1997 Source of Installation Custodial Staff SINGLE PLY, FULLY ADHERED ROOF: ROOFING: BEYOND USEFUL LIFE Location/Instance Single Ply, Fully Adhered Roof: Roof 1 and 2 Quantity 2,600 Urgency of Action PRIORITY 1 Photo1 Building Assessment Survey photo recorded violations recorded. STAIRS/RAMPS: RAILINGS STAIRS/RAMPS Roof Plan reference 5 - Poor METAL: RUST - MAJOR Quantity 30 Urgency of Action PRIORITY 4 PB/A&W Page 8 of 11

9 STAIRS/RAMPS: STAIRS/RAMPS Photo1 Building Assessment Survey Facade A Facade G violations recorded. WINDOWS Replacement Quantity 128 Replacement Uom GUARDS WINDOWS INTERIOR Material Type(s) Instance on Aluminum - Other: Facade A and G Instance Instance Quantity 128 Instance Aluminum 3 - Fair Installation Year 1997 Source of Installation STRUCTURAL COLUMNS/BEAMS/BEARING WALLS FLOOR STRUCTURE ROOF STRUCTURE Custodial Staff PB/A&W Page 9 of 11

10 Building Assessment Survey Architectural Inspection INTERIOR CAFETERIA CLASSROOMS/CORRIDORS/ADMIN SPACES Ceiling GYPSUM BOARD: DAMAGED/DETERIORATED Location/Instance Room T2 Quantity 10 Urgency of Action PRIORITY 3 Photo1 Room T2 violations recorded. Door(s) Floor Finish VINYL TILES: DETERIORATED SUBSTRATE Location/Instance In T1,2,3,4 Quantity 160 Urgency of Action PRIORITY 3 Photo1 Walls INTERIOR DOOR HARDWARE In T4 violations recorded. PB/A&W Page 10 of 11

11 Building Assessment Survey Architectural Inspection INTERIOR INTERIOR DOOR HARDWARE 3 - Fair KITCHEN MULTI-PURPOSE ROOM TOILET ROOMS - STAFF Ceiling Door(s) Floor Finish Walls TOILET ROOMS - STUDENTS Ceiling Door(s) Floor Finish Walls GYPSUM BOARD: DETERIORATED Location/Instance Inside Room T3 Quantity 10 Urgency of Action PRIORITY 3 Photo1 Inside Room T3 violations recorded. SITE t Required PB/A&W Page 11 of 11