Building Excellence IV Capital Levy Projects Under Construction

Size: px
Start display at page:

Download "Building Excellence IV Capital Levy Projects Under Construction"

Transcription

1 Building Excellence IV Capital Levy Projects Under Construction Project Slide Number Arbor Heights Elementary School 2 Cascadia Elementary School & Robert Eagle Staff Middle School 13 Genesee Hill Elementary School 21 Hazel Wolf K-8 at Pinehurst 35 Olympic Hills Elementary School 46 Seattle New World School at TT Minor 53 New Thornton Creek Building 63 December 18, 2015

2 Building Excellence IV Capital Levy Arbor Heights Elementary School Site: Maintaining temporary erosion control. South Building: Exterior sheathing nearly complete. Light-gauge metal stud framing continues at floors 2 and 3. Mechanical, plumbing, fire-sprinkler and electrical rough-in ongoing at floors 1, 2, and 3. Arbor: Slab-on-grade placed, structural steel bridge erection is in-progress. North Building: Slab-on-grade placed at the administrative office and entry/lobby. Steel erection at entry canopy and covered play area is nearly complete. Light-gauge metal stud framing is underway at floor 3. Membrane roofing is in-progress at the east roof. Metal roof decking is completing at the cafeteria.

3 Arbor Heights Elementary School Site Plan July 1, 2015 July 10, 2015

4 Arbor Heights Elementary School Aerial View from the South November 30, 2015

5 Arbor Heights Elementary School South Building First Floor Insulated Duct December 14, 2015

6 Arbor Heights Elementary School Arbor Structural Steel Bridge December 14, 2015

7 Arbor Heights Elementary School North Building Slab-on-Grade at Admin, Arbor, and Entry December 9, 2015

8 Arbor Heights Elementary School North Building Cafeteria and Gymnasium December 14, 2015

9 Arbor Heights Elementary School North Building Interior/Exterior Wall Framing December 14, 2015

10 Arbor Heights Elementary School North Building Entry Canopy Column December 14, 2015

11 Arbor Heights Elementary School North Building Steel Canopy at Covered Play Area December 14, 2015

12 Arbor Heights Elementary School North Building Roofing December 14, 2015

13 Building Excellence IV Capital Levy Cascadia Elementary School and Robert Eagle Staff Middle School Site: Maintaining TESC measures to protect site during record setting December rains. Backfilling around footings and underground piping when weather allows. Cement treating soil as necessary. Elementary School: Steel erection continues on the main building. Concrete slab preparation and waterproofing continuing. Concrete slabs being placed dependent on weather. Middle School: Forming concrete footings and placement occurring. Waterproofing and backfilling footing stem walls. Underground utility work on-going to prepare for slabs.

14 Cascadia Elementary School & Robert Eagle Staff Middle School Site Plan

15 Cascadia Elementary School & Robert Eagle Staff Middle School Aerial Photo December 1, 2015

16 Cascadia Elementary School & Robert Eagle Staff Middle School Steel Erection at Elementary School, Looking SE December 8, 2015

17 Cascadia Elementary School & Robert Eagle Staff Middle School Murals Reinstalled at Elementary School, Looking South December 8, 2015

18 Cascadia Elementary School & Robert Eagle Staff Middle School Elementary School Steel Joists On-Site December 8, 2015

19 Cascadia Elementary School & Robert Eagle Staff Middle School Middle School Site, Looking NW December 8, 2015

20 Cascadia Elementary School & Robert Eagle Staff Middle School Curbs at Middle School South Parking Lot, Looking West December 8, 2015

21 Building Excellence IV Capital Levy Genesee Hill Elementary School Site: Forming concrete benches at west side of Area 3 at covered bus waiting area. Area 1: Gypsum Wallboard (GWB) finishing process continues, continue to install ceramic floor and wall tile in bathrooms, continue interior painting and installation of vinyl wall covering, continued installation of window frames and glazing and installed doors at end of corridors. Area 2: Continue to install flashings at window openings; continue to install window frames, plumbing, and electrical rough-in ongoing. Area 3: CMU veneer installation is ongoing; miscellaneous interior framing ongoing, installation of GWB is ongoing; mechanical, plumbing and firesprinkler rough-in ongoing and beginning installation of operable wall track at stage. Area 4: CMU veneer is ongoing, plumbing, fire-sprinkler and electrical rough-in ongoing and installed form insulation.

22 Genesee Hill Elementary School Site Plan

23 Genesee Hill Elementary School Aerial Photo

24 Genesee Hill Elementary School Area 1 North Elevation Metal Siding Substrate Installed

25 Genesee Hill Elementary School Area 1 South Elevation Installing Metal Siding Substrate

26 Genesee Hill Elementary School Area 1 Basement Continued Installation of Hydronic Piping

27 Genesee Hill Elementary School Area 1 Level 2 Installing Vinyl Wall Covering

28 Genesee Hill Elementary School Area 1 Level 2 Continued Ceramic Tile Installation

29 Genesee Hill Elementary School Area 1 Level 3 Painting Complete; Prepping Floor for Ceramic Tile

30 Genesee Hill Elementary School Area 2 Level 1 Plumbing & Electrical Rough-in Continues; Framing Complete

31 Genesee Hill Elementary School Area 2 Level 2 Installing Temp Weather Protection; Prep for GWB Staging

32 Genesee Hill Elementary School Area 3 Level 1 Installing Window Frames, Sprinkler Piping, and Wall Track

33 Genesee Hill Elementary School Area 4 East Elevation Installing CMU Veneer at Covered Play Area

34 Genesee Hill Elementary School Area 4 Level 1 Foam Insulation Installed at South Wall of Gym

35 Building Excellence IV Capital Levy Hazel Wolf K-8 at Pinehurst Site: Installing Gas, Water and Power, general clean up. Erosion measures in place and functioning properly. Building A: Area (A1) Exterior metal stud framing, Electrical equipment /conduit and HVAC installs continue. Area (A2) metal stud framing continues on 2 nd and 3 rd floors. Gypsum wallboard and exterior sheeting continue. Mechanical, plumbing, fire-sprinkler and electrical rough-in ongoing. (A3) Structural steel completed. Floor slab prepared for concrete, capillary break rock complete Final steel and welding complete. Building B: Slab on grade ready for pour pending good weather. Welding and bolting completed. Roofing to continue. Building C: Slab on grade continues to be covered and protected. Stage stairs concrete completed. Metal roof deck welding completed. Roof Insulation and roofing material to continue weather permitting.

36 Hazel Wolf K-8 at Pinehurst Site Plan

37 Hazel Wolf K-8 at Pinehurst Aerial Photo

38 Hazel Wolf K-8 at Pinehurst Area A1 Ductwork Installation December 8, 2015

39 Hazel Wolf K-8 at Pinehurst Area A2 Interior Mechanical Shaft Wall December 8, 2015

40 Hazel Wolf K-8 at Pinehurst Area A2 Exterior Sheathing December 9, 2015

41 Hazel Wolf K-8 at Pinehurst Area A2 Classroom Window December 9, 2015

42 Hazel Wolf K-8 at Pinehurst Area A2 and C Roofing Looking East December 9, 2015

43 Hazel Wolf K-8 at Pinehurst Area A3 Sloped Roof Looking South December 9, 2015

44 Hazel Wolf K-8 at Pinehurst Area C Stage Steps December 8, 2015

45 Hazel Wolf K-8 at Pinehurst Area C Exterior Canopy December 9, 2015

46 Building Excellence IV Capital Levy Olympic Hills Elementary School Site: Geothermal well drilling occurring outside building footprint. All wells have been installed within footprint (29 wells complete, 80 remaining). Forecasting well drilling to be complete in February, Maintaining TESC measures throughout site.

47 Olympic Hills Elementary School Site Plan

48 Olympic Hills Elementary School Site Looking South December 9, 2015

49 Olympic Hills Elementary School Site Looking West December 9, 2015

50 Olympic Hills Elementary School Aerial Photo November 4, 2015

51 Olympic Hills Elementary School Geothermal Well Drilling, Looking North December 9, 2015

52 Olympic Hills Elementary School Infiltration/Rain Garden for TESC, SW Corner Looking South December 9, 2015

53 Building Excellence IV Capital Levy Seattle World School at T.T. Minor Area A Administration Office, Student Services, Health Clinic and Library: Administration office addition concrete slab pour complete, structural steel installation ongoing. Health Clinic interior framing ongoing. Area A overhead mechanical, plumbing, fire-sprinkler and electrical rough-in work ongoing. Area B Multipurpose, Kitchen, Boiler Room: Steel erection ongoing, structural wood and framing of the Kitchen ongoing. Area C Classrooms: New electrical service conduit installation ongoing, underground utility complete, CMU block wall installation complete interior steel stud framing ongoing.

54 Seattle World School at T.T. Minor Site Plan C B A C A B

55 Seattle World School at T.T. Minor Site Installation of Rain Garden Storm Water Connection to City December 14, 2015

56 Seattle World School at T.T. Minor Site Rain Garden Storm Water Connection to City December 14, 2015

57 Seattle World School at T.T. Minor Area A New Administration Addition Concrete Slab Pour Protected December 14, 2015

58 Seattle World School at T.T. Minor Area A Health Clinic Interior Framing December 14, 2015

59 Seattle World School at T.T. Minor Area A Electrical and Data Rough In Ongoing December 14, 2015

60 Seattle World School at T.T. Minor Area B New Commons Framing Ongoing December 14, 2015

61 Seattle World School at T.T. Minor Area C Classroom Steel Stud Framing Ongoing December 14, 2015

62 Seattle World School at T.T. Minor Area C Classroom CMU Block Wall Installation Complete December 14, 2015

63 Building Excellence IV Capital Levy New Thornton Creek Building Site: Continued Phase II geothermal well drilling in playfield. Continued excavation of trenches for header piping and connecting piping to geothermal wells. Building A: Placed gravel capillary break, vapor barrier and steel mesh for slab on grade. Began erecting structural steel in the southwest corner of building. Building B: Completed erecting structural steel for mechanical penthouse and continued at Building A connection. Continued placing decking on library roof. Continued exterior framing and continued install HVAC ductwork for first floor. Began plumbing rough-in in west bathrooms on first floor. Building C: Continued installing interior hollow metal window frames. Continued installing gypsum wall board (GWB) above hallway ceiling. Continued install fluid applied air barrier application. Continued insulation and brick veneer on south elevation. Continued electrical, plumbing, HVAC and fire sprinkler system rough-in. Building D: Continued building forms for walls for Covered Play Area

64 New Thornton Creek Building Key Plan Building C Building B Building A D

65 New Thornton Creek Building Aerial Photo December 15, 2015

66 New Thornton Creek Building Building A Vapor Barrier and Rebar Placement for Slab-on-Grade

67 New Thornton Creek Building Building A Beginning Structural Steel Erection

68 New Thornton Creek Building Building B Exterior Framing and Steel Decking for Roof

69 New Thornton Creek Building Building B Steel Decking on Library Roof

70 New Thornton Creek Building Building C Brick Veneer Masonry

71 New Thornton Creek Building Building C Hollow Metal Frame Door and Window Relite Installation

72 New Thornton Creek Building Building C Gypsum Wall Board (GWB) Installation on Interior Walls

73 New Thornton Creek Building Building D Building Forms for Shear Walls at Covered Play Area