1 Fichtner GmbH & Co. KG Windpower Owner s Engineering during construction phase of a WPP Marios Papageorgiou Senior Mechanical Engineer Fichtner GmbH & Co. KG Merkezi Almanya Türkiye Istanbul Şubesi Büyükdere Cad. Polat Han No:87/ Mecidiyeköy/Istanbul, Turkey info@fichtner.com.tr

2 Owner s Engineering in Construction Phase of WPP Contents FICHTNER Independent Engineering and Consulting Wind Teams Turkey Office Turkey Wind Power References as of Nov 2014 Turkey Wind Power Owner s Engineering Services Life of a Wind Power Plant Project Why is Technical Consultancy Necessary for WPP Construction? Most Common Problems During WPP Construction How Does Owner s Engineer Help Lower the Risks Created Typical Interface and Internal Organization 2

3 FICHTNER Independent Engineering and Consulting Founded in 1922 and 100% family owned since then Germany s biggest independent engineering and consultancy company Staff strength: Home office (Stuttgart) ca. 500 Total ca. 1,800 Home office: Total: Turn-over 2013: 170 million EUR 242 million EUR On a global level FICHTNER takes part in approximately 1,200 projects with an overall investment volume of around 86 billion EUR. FICHTNER is represented in more than 50 countries worldwide. 3

4 FICHTNER Wind Teams Red: FICHTNER Offices Green: FICHTNER Wind Teams 4

5 FICHTNER Turkey Office FICHTNER group has been working in Turkey for more than 40 years FICHTNER Turkey was established as a branch of FICHTNER GmbH & Co. KG in Istanbul in July 2008 Completed numerous projects mainly in private sector Brought together experienced international experts with local engineers/ consultants to work on the most important projects of Turkey Vision of FICHTNER Turkey: Becoming indispensable in energy sector by providing optimum solutions through complete services to its customers Providing state-of-the art engineering and technical services to meet our customer's needs in growing energy market Permanent training of our personnel to keep our leading position on an international level 5

6 FICHTNER Turkey Wind Power References as of Nov

7 FICHTNER Turkey Wind Power FICHTNER Turkey Wind Power Services includes: Owner s Engineering Services Lender s Engineering Services Technical Due Diligence Services Inspection Services Energy Yield Assessment Services With engineering and consultancy services, in the role of Owner s Engineering we support our clients in their wind energy projects over the entire value added chain from the earliest project stage up to project operation monitoring and end of warranties 7

8 Wind project s life and our contribution DEVELOPMENT PHASE CONSTRUCTION PHASE OPERATION PHASE 8

9 Wind project s life and our contribution DEVELOPMENT PHASE CONSTRUCTION PHASE OPERATION PHASE 8

10 Why is Technical Consultancy Necessary for WPP Construction? For new project owners, it can ensure that the optimum, cost effective and most productive plan will be realized For experienced project owners, independent technical consultancy will be added strength to the owner s existing team and will also be a valuable tool in front of lenders, insurers and subcontractors In all cases, it is added value to any project, providing consultancy, on site services and documentation of a trusted, established name in the sector, not only improving a project s life cycle, but making it more trustworthy in the operational time 10

11 Time schedule Quality Design - Implementation Inconsistencies Communication and Interfaces Accidents 11

12 Time schedule Weather conditions especially in wind sector are causing most delays Faulty planning sometimes resulting to technically impossible targets to meet Often authorities are causing further delay due to bureaucracy The result is delays in payments, extra costs, disputes, loss of production 12

13 Quality Quality is an important factor connected to the life of the plant Often owners focus their efforts more in the main parts and less in secondary issues, resulting to future (short or long term) problems Subcontractors might undertake projects outside their expertise, in order to achieve a better contact, with immediate result to quality of work Possibility of accidents, time delays, poor turbine performance, even outages during operating period 13

14 Examples of Quality problems 14

15 Examples of Quality problems 14

16 Examples of Quality problems 14

17 Examples of Quality problems 14

18 Examples of Quality problems 14

19 Design - implementation inconsistencies In the designing period best solution might have been planned, but on site, things can be different. Equipment on site might not meet the contractual criteria Equipment might be damaged or used Transporting, storing or installation equipment and methods can be unsuitable for the specific project Wrong installation, inadequate or faulty equipment may cause reduced efficiency to the project, or even worse, a possible accident 21

20 Examples of Design - implementation inconsistencies 23

21 Examples of Design - implementation inconsistencies 23

22 Examples of Design - implementation inconsistencies 23

23 Examples of Design - implementation inconsistencies 23

24 Communication and interfaces In a complete construction with multiple teams and subcontractors, everyone can blame it on the other, when something will go wrong It is a very common fight, what are the limits of each specific work, either it is installation or procurement Often missing or misleading communication during construction can stall work for days Lack of clear boundaries as well as communication method and skills, causes negative conditions, arguments and delays 24

25 Accidents Accidents happen and they affect equipment in the easy cases, or people in the worst cases Health and safety on and off site is something often neglected, mostly by smaller contractors There is a way of handling all equipment and actions on and off site, in a safe and fast way but it is often unknown Safety is often considered as a legal necessity and thus is underestimated, causing loss in time and money even if no one is hurt 26

26 Examples of accidents or incidents 32

27 Examples of accidents or incidents 32

28 Examples of accidents or incidents 32

29 Examples of accidents or incidents 32

30 Examples of accidents or incidents 32

31 Examples of accidents or incidents 32

32 How does OE Services support and mitigate problems during construction phase? Technical advisor works for the owner but technically works for the project Everyone wants to have the best of their project: Owner wants a productive, low cost power plant that will work for years Supplier wants to provide a fast and efficient service in order to get a good reference and move to the next project Lender wants to know what s going on and if he will get his money back All subcontractors want to get more work 32

33 How does OE Services support and mitigate problems during construction phase? A consultant may help by Planning a feasible time schedule and monitoring it; dynamic process Providing consultancy in all fields by bringing in experts from a big pool around the world Being on site and supporting site management at all times Preparing reports to keep track and recording all activities Adding experience to project and project owner 33

34 Typical Interface with Project Owner Contractual Scheme for Turnkey Contract 34

35 Typical Internal Interface Organizational Diagram for Technical Consultant 35

36 Consultancy 1% Civil and ground work Electrical 11% and control 11% Financial cost 1% Turbines 76% Cost Structure of medium sized wind turbine Source: The Economics of Wind Energy; a Report by European Wind Energy Association

37 Thank you for your attention FICHTNER TURKEY Fichtner GmbH & Co. KG Merkezi Almanya Türkiye İstanbul Şubesi Büyükdere Cad. Polat Han No:87/ Mecidiyeköy/İstanbul, Turkey Phone Fichtner GmbH & Co. KG Ufuk Üniversitesi Cad. Ambrosia Plaza No:18 Kat:8/ Cankaya - Ankara, Turkey Phone