1 Upper East Tennessee Human Development Agency WORK ORDER INFORMATION Work Order Type: Weatherization Audit Name: 18018UE10329 CLIENT INFORMATION Address: ERWIN, TN AGENCY INFORMATION Agency: Upper East Tennessee Human Development Agency Agency Phone: (423) Address: 301 Louis Street Fax: (423) Kingsport, TN Address: Company Name & License Number: Contractor's Signature: COMMENT 672 SQUARE FOOT SINGLE WIDE MOBILE HOME MANUFACTURED AROUND ALL WORK TO BE DONE IN ACCORDANCE WITH THE TENNESSEE STANDARD WORK SPECIFICATIONS AS ADOPTED BY THE TENNESSEE HOUSING DEVELOPEMANT AGENCY. CONTRACTOR IS RESPONSIBLE TO VERIFY DIMENSIONS AND SCOPE OF WORK PRIOR TO BID. SURVEY ON 1/25/2017 BY RON CARLISLE (423) INITIAL BLOWER DOOR POST WORK TARGET MUST BE REACHED OR EXCEEDED Page 1 of 7

2 Measures Measure 1 General Air Sealing Comment Initial Blower Door Reading: Post Work Target of Must Be Met or Exceeded Suggested Best Practice of Air Infiltration Reduction is to use two part foam and appropriate materials to seal the penetrations and openings in the Subfloor (accessible in the crawl space) and in the ceilings (accessible in the attic). REPLACE THE SLIDING GLASS DOOR (D2) 71" X 80", THAT HAS BROKEN SINGLE PANES AND IS FALLING APART 1 Insulation General air sealing Each 1 (setup cost) 10 Miscellaneous Su Infiltration Reduction Each 1 Measure Sub : Sub : Page 2 of 7

3 Measure 2 DWH Pipe Insulation Comment INSULATE THE FIRST 6 FEET OF HOT AND COLD WATER PIPE OUT OF THE WATER HEATER AS PER THE TN SWS 1 Insulation DWH Pipe Insulation Each 1 2 Labor DWH Pipe Insulation Each 1 Measure Sub : Sub : Measure 3 DWH Tank Insulation Comment AS PER THE TN SWS- Wrap the 40 Gallon Electric Water Heater Located in the With R-10 or Better Insulation. Secure With Tape And Zip Ties. 1 Insulation DWH Tank Insulation Each 1 2 Labor DWH Tank Insulation Each 1 Measure Sub : Sub : Page 3 of 7

4 Measure 4 Roof Fiberglass Loose Comment MOBILE HOME ROOF INSULATION ***REQUIRES THAT REPAIRS ARE DONE TO THE CEILING- PATCH AND RE-INFORCE AS NECESSARY TO COMPLETE THE MEASURE. Mobile Home Roof cavity with loose fill Fiberglass insulation. Insulate In Progress-Cut holes in roof or ceiling to fill cavity to insert insulation machine nozzle Ensure that hole is large enough for nozzle. Ensure that each hole cut is to be patched with appropriate materials to insure no leaks. If installed from interior use proper plugs for holes cut in ceiling area. A dated receipt signed by the installer will be provided that includes: Insulation type- Must be Fiberglass Coverage area R-value Installed thickness and minimum settled thickness Number of bags installed 1 Insulation Roof Insulation - Bag 10 Fbergls,Blwn 2 Labor Roof Insulation - Bag 10 Fbergls,Blwn Measure Sub : Sub : Page 4 of 7

5 Measure 5 Fix Improper Venting (Clothes Dryer) Comment VENT THE CLOTHES DRYER TO THE OUTSIDE- AS PER THE TN SWS 1 Health and Safety Equipment Each 1 Each 1 Measure Sub : Sub : Measure 6 Fix Wiring Problems (Walls) Comment Replace Missing Electrical Switch/Receptical Plate Covers- INSTALL JUNCTION BOXES REPLACE THE MISSING 150 AMP, "SQUARE D" BREAKER BOX COVER. IT IS NOT ON SITE. 1 Health and Safety Equipment Each 2 Hour 2 Measure Sub : Sub : Page 5 of 7

6 Measure 7 Install a New TWO AND A HALF Ton Heat Pump Include New Ductwork Comment Install a New Heat Pump/Air Conditioner- Contractor Choice of Packaged unit or Split System- Complete With New Ductwork. Mechanical permits will be required for all HVAC work, as per local code. All Heat pumps installed to be 15 SEER, 8.5 HSPF. All cooling equipment, ENERGY STAR labeled and shall be sized according to the latest editions of ACCA Manuals J, S and D.Specification of any type of heating unit shall be taken to include all connections, wiring, ducting, safety switches, thermostats, pad if existing does not fit new unit and all other work to provide a complete, Tight, efficient, balanced and operational system. All wiring shall be on separate circuits, wired from panel box or disconnects to HVAC unit by contractor. If installing a split system that does not have existing line set the cost should be included in bid to provide new line set. If leaving the existing line set the line is to be flushed and pressurized to insure no leakage. If installing a package unit it is to include a four sided shroud. All work to meet current code for city or county work is being performed. Must provide all warranty information with invoice. If unit warranty needs registered with factory contractor is to do this for client. 1 Heating Equipme Install a New Heat Each 1 Pump 30 Kbtu/h 2 Labor Install a New Heat Hour 1 Pump 30 kbtu/h Measure Sub : Sub : Page 6 of 7

7 Measure 8 Install Bathroom Exhaust Fan Comment INSTALL BATH FAN WITH A NEW TWO SPEED ASHRAE COMPLIANT FAN. SET TO CFM CONTINOUS. VENT TO THE OUTSIDE WITH A TRIM KIT AS PER THE TN SWS. ************INSTALL A 6' VENT PIPE TO ENSYURE PROPER VENTILATION************* 1 Health and Safety Bathroom exhaust fan Each 1 Each 1 Measure Sub : Sub : Measure 9 Smoke Detector is Needed Comment INSTALL SMOKE DETECTORS IN ALL BEDROOMS AND COMMON AREA (HALLWAY)EACH FLOOR, 1 Health and Safety Smoke detector Each 3 Each 3 Measure Sub : Sub : Work Order Grand : Grand : Page 7 of 7