NYC Department of Education

Size: px
Start display at page:

Download "NYC Department of Education"

Transcription

1 Architectural Inspection Building Assessment Survey Asset: P.S BROOKLYN, 46 MCKEEVER PLACE, New York, Inspection Id Inspection Type Time In Last Edited SA : Architectural - Senior :52 AM :49 AM AA : Architectural - Associate :57 AM :08 PM Asset Data Was the building fully accessible for inspection Inspection Access Comment Principal(s) Information Answer No The Shower Rooms are being used for storage and the door from the Basement to the Sidewalk Elevator has been sealed - the vault slab and foundation walls were inaccessible for inspection. Principal Name Organization Did you meet with this Principal? Did this Principal provide feedback? Summary of Principal's Feedback Principal Name Organization Did you meet with this Principal? Did this Principal provide feedback? Schwanna Ellman Jackie Robinson Elementary - Brooklyn Yes Yes The Principal's comments are as follows: 1. The freight elevator does not work. 2. The school's electrical service is insufficient for normal school functions. 3. Telephones do not receive calls during rain and snow. 4. Internet service works intermittently. 5. The PA system breaks frequently and does not work in the auditorium, cafeteria, and several classrooms. Geannene Rowe Ebbets Field Middle School - Brooklyn No No Principal Name Maureen Ferry Organization Exceed Charter School - Brooklyn Did you meet with this Principal? No Did this Principal provide feedback? No Custodian Andre Bayne Fireman Quintin McMillan Building Square Footage Comments on the Area None Comments on the Stories (Floors) plus Basements 4+B Comments on the Number of Classrooms 70 Comments on the Year Built 1968 Student Population 713 Staff Population 150 Weather Fair PB/A&W Page 1 of 64

2 Facade Photo Building Assessment Survey Main Entrance Photo Corner of McKeever Place and Sullivan Place - Northeast View Roof Photo Facade A - McKeever Place Roof 1 - Southwest View PB/A&W Page 2 of 64

3 Building Assessment Survey Have any Systems/Major Building Components been upgraded? Have there been any New Building Additions? Tandem Schools? Leased Space? Yes Systems: Coping repairs; Exterior Walls waterproofing Year: 2016 Systems: Limited Structural repairs in Gas Meter Room; limited Toilet Room Partition replacement Year: 2013 Systems: Limited Roofing, Coping, Exterior Doors and Stair repairs; Areaway Gratings replacement; Foundation and Exterior Walls flood elimination program. Year: 2012 Systems: New Windows and Guards; limited Exterior Doors replacement; Exterior Masonry and Parapet repairs Year: 2008 Systems: New Roofing throughout Year: 1995 No No No Priority Priority Exist Last Year? Priority Category Description Component Affected Location Description Person(s) Notified Person(s) Title PhotoImage Yes Tripping Hazard Severely heaving DOT Sidewalk is a potential tripping hazard. SITE PAVING DOT Sidewalk Concrete Franklin Avenue Andre Blayne Custodian Structural Engineer Required Structural Type Description Component Affected Location Description Person(s) Notified Person(s) Title PhotoImage No condition recorded Accessibility Accessibility Status Is the primary or secondary entrance on an accessible route? Is the building a multi-story building? Are all floors of the building accessible through compliant means? Are SOME floors other than the 1st floor and basement accessible through compliant means? Do any of the following spaces exist on the First floor? Classroom, Art Room, Auditorium, Cafeteria, Computer, Gymnasiums, Library, Multipurpose Room, Science Labs For the rooms that do exist, are SOME of them accessible on the 1st floor? Boys and Girls or Unisex accessible toilets exist on the 1st floor? Yes Yes No No Yes Yes No Physical Breakdown Structure Exists Complies Required FUNCTIONAL ACCESSIBILITY Exterior Routes Exterior Entrances & Exits Yes Exterior H/C Lifts No No Exterior Ramps and Railings Yes Yes Interior Routes Corridor and Lobby H/C Lifts No No PB/A&W Page 3 of 64

4 Building Assessment Survey Physical Breakdown Structure Exists Complies Required Interior Routes Interior Corridor Doors and Hardware Yes Yes Interior Corridors and Lobbies Interior Elevators Interior Lobby Doors and Hardware No Interior Ramps Yes No Railing Height < 34 or > 38 Inches Rooms & Spaces Art Rooms Room 319 No Not on Accessible Route Auditorium Basement No No Stage Access Not on Accessible Route Wheelchair Parking Cafeteria 1st Floor - Students, 1st Floor - Staff Yes Classrooms 1st Floor Yes Computer Rooms Rooms 222, 322, 404 No Not on Accessible Route Gymnasium 1st Floor Yes Library Room 224 No Not on Accessible Route Main Office Room 102 Yes Multi-purpose Room Rooms 301A, 434 No Not on Accessible Route Nurse's Room Room 110 No Not on Accessible Route Pool Science Lab Room 312 (In Use), Rooms 305, 310, 314, 319, 323 (Alternate Use) No No Yes Yes No Not on Accessible Route Toilet Rooms (Boys) 1st Floor No Clear opening < 32" Turning Radius Toilet Rooms (Girls) 1st Floor No Clear opening < 32" Turning Radius Toilet Rooms (Staff) 1st Floor Men's No Clear opening < 32" No Lever-type Hardware Urinal Arrangement Water Closet Arrangement 1st Floor Women's No Clear opening < 32" No Lever-type Hardware Water Closet Arrangement PB/A&W Page 4 of 64

5 Building Template Building Assessment Survey Inspection Architectural EXTERIOR AREAWAY Instance on AW1-AW2 Instance Instance Quantity 2 Instance EACH AWNINGS AND CANOPIES CHIMNEY Material Type(s) Masonry 3 - Fair BRICK: DETERIORATED LADDER Roof Plan reference Quantity 1 EACH PB/A&W Page 5 of 64

6 EXTERIOR CHIMNEY Photo1 Building Assessment Survey Roof Plan reference Chimney BRICK: DETERIORATED CAP Quantity 10 L.F. Urgency of Action PRIORITY 4 Photo1 Chimney BRICK: MINOR CRACKS AND SPALLING PB/A&W Page 6 of 64

7 EXTERIOR CHIMNEY Roof Plan reference Building Assessment Survey Quantity 40 RESTITCH Photo1 COPING Roof Plan reference Chimney 4 - Between Fair and Poor METAL: LIFTED OFF Quantity 125 L.F. -IN-KIND PB/A&W Page 7 of 64

8 EXTERIOR COPING Photo1 Building Assessment Survey Roof Plan reference Roof 3 METAL: DETERIORATED Quantity 70 L.F. -IN-KIND Urgency of Action PRIORITY 4 Photo1 CORNICE DOORS DOORS AND FRAMES Roof 1 METAL CLAD: DETERIORATED DOOR AND FRAME - MAJOR DETERIORATION PB/A&W Page 8 of 64

9 EXTERIOR DOORS DOORS AND FRAMES Roof Plan reference Building Assessment Survey Quantity 1 EACH Urgency of Action PRIORITY 4 Photo1 Facade C DOOR HARDWARE LINTELS TRANSOM/SIDE LIGHT EXTERIOR WALLS Material Type(s) Masonry Replacement Quantity 50,000 Replacement Uom Instance on All Facades Instance 3 - Fair Instance Quantity 50,000 Instance BRICK: EFFLORESCENCE PB/A&W Page 9 of 64

10 EXTERIOR EXTERIOR WALLS Roof Plan reference Building Assessment Survey Elevation Quantity 45 MAINTENANCE Urgency of Action PRIORITY 1 Purpose of Action LEVEL 1 Photo1 No photo recorded Roof Plan reference BRICK: OPEN JOINTS Elevation Quantity 270 PB/A&W Page 10 of 64

11 Building Assessment Survey Architectural Inspection EXTERIOR EXTERIOR WALLS REPOINT Photo1 Roof Plan reference Facade C BRICK: CRACKS/DISPLACED/SPALLED BRICK AT BUILDING CORNERS Elevation Quantity 25 REMOVE AND REBUILD Urgency of Action PRIORITY 4 PB/A&W Page 11 of 64

12 EXTERIOR EXTERIOR WALLS Photo1 Building Assessment Survey Facade M Roof Plan reference BRICK: RELIEVING ANGLES - MINOR DETERIORATION Elevation Quantity 80 L.F. MAINTENANCE Photo1 No photo recorded BRICK: MASONRY SILLS - OPEN JOINTS PB/A&W Page 12 of 64

13 EXTERIOR EXTERIOR WALLS Roof Plan reference Building Assessment Survey Elevation Quantity 70 L.F. REPOINT Photo1 Roof Plan reference Facade H1 BRICK: MAJOR / THRU CRACKS PB/A&W Page 13 of 64

14 EXTERIOR EXTERIOR WALLS Elevation Building Assessment Survey Quantity 10 REMOVE AND REBUILD Urgency of Action PRIORITY 4 Photo1 Roof Plan reference Facade H1 STUCCO CEMENT SURFACE: CRACKS, SPALLING Elevation Quantity 115 PB/A&W Page 14 of 64

15 Building Assessment Survey Architectural Inspection EXTERIOR EXTERIOR WALLS Photo1 Roof Plan reference Facade E BRICK: WATER INFILTRATION IN INSTRUCTIONAL SPACE Elevation Quantity 40 REPAIR Urgency of Action PRIORITY 5 Photo1 Facade P - Room 222 (Facade Q - Room 214 similar) PB/A&W Page 15 of 64

16 EXTERIOR EXTERIOR WALLS EXTERIOR SOFFITS Roof Plan reference Building Assessment Survey STUCCO/PLASTER: MAJOR CRACKS/SPALLING Elevation Quantity 20 Urgency of Action PRIORITY 4 Photo1 Facade S LOADING DOCK LOUVER PARAPETS Material Type(s) Concrete Replacement Quantity 12,000 Replacement Uom Instance on All Roofs C.F. PB/A&W Page 16 of 64

17 Building Assessment Survey Architectural Inspection EXTERIOR PARAPETS Instance Instance Quantity 12,000 Instance C.F. CONCRETE: MINOR CRACKS, SPALLING Roof Plan reference Quantity 20 REPAIR Photo1 Roof 1 PLAZA DECK ROOF Roofing Replacement Quantity 60,000 Replacement Uom ROOF HATCH/SMOKE HATCH LEADERS, GUTTERS, DOWNSPOUTS, SCUPPERS ROOF BARRIER 3 - Fair BEAR CLAW/METAL BAR: MINOR RUSTING PB/A&W Page 17 of 64

18 EXTERIOR ROOF Roofing ROOF BARRIER Roof Plan reference Building Assessment Survey Quantity 290 MAINTENANCE Photo1 No photo recorded Roof Plan reference BEAR CLAW/METAL BAR: DETERIORATED, MAJOR RUSTING Quantity 10 Urgency of Action PRIORITY 4 Photo1 ROOF CAGE ROOF FENCE Facade M PB/A&W Page 18 of 64

19 EXTERIOR ROOF Roofing ROOFING Instance on IRMA: Roof 1 Instance 3 - Fair Instance Quantity 30,000 Instance Does the roof have major mechanical equipment sitting on Dunnage Steel less than 18" above the Roofing? Installation Year 1995 Source of Installation Instance on Built-Up: Roof 2-8 Instance No Custodial Staff 3 - Fair Instance Quantity 30,000 Instance Does the roof have major mechanical equipment sitting on Dunnage Steel less than 18" above the Roofing? Installation Year 1995 Source of Installation Roof Plan reference Building Assessment Survey No Custodial Staff BUILT-UP: ROOFING: MAJOR ACTIVE ROOF LEAKS IN INSTRUCTIONAL SPACE Quantity 80 Urgency of Action PRIORITY 5 Photo1 ROOFING WITHOUT MAJOR EQUIPMENT REMOVAL Roof 5 - Student and Staff Cafeteria BUILT-UP: FLASHING: BASE FLASHING DETERIORATED PB/A&W Page 19 of 64

20 EXTERIOR ROOF Roofing ROOFING Roof Plan reference Building Assessment Survey Quantity 20 REPAIR Urgency of Action PRIORITY 4 Photo1 Roof 4 BUILT-UP: ROOFING: BEYOND USEFUL LIFE Location/Instance Built-Up: Roof 2-8 Quantity 30,000 Urgency of Action PRIORITY 1 Photo1 No photo recorded ROOFING DRAINS 3 - Fair DETERIORATED PB/A&W Page 20 of 64

21 EXTERIOR ROOF Roofing ROOFING DRAINS Roof Plan reference Building Assessment Survey Quantity 1 EACH Urgency of Action PRIORITY 4 Photo1 Specialties BULKHEAD/PENTHOUSE Roof Plan reference Roof Between Fair and Poor BULKHEAD/PENTHOUSE WALLS/INTERIOR: CMU CRACKS/SPALLING Quantity 40 MAINTENANCE Photo1 No photo recorded PB/A&W Page 21 of 64

22 EXTERIOR ROOF Specialties BULKHEAD/PENTHOUSE Roof Plan reference Building Assessment Survey BULKHEAD/PENTHOUSE WALLS/EXTERIOR: CRACKS/SPALLING - MINOR Quantity 45 REPAIR Photo1 Roof Plan reference BH2 BULKHEAD/PENTHOUSE DOORS: DETERIORATED DOOR AND FRAME Quantity 4 EACH DOOR AND FRAME Urgency of Action PRIORITY 4 PB/A&W Page 22 of 64

23 EXTERIOR ROOF Specialties BULKHEAD/PENTHOUSE Photo1 Building Assessment Survey CUPOLA/ SPIRES/ TOWERS DORMER DUNNAGE STEEL SKYLIGHT/ROOF VENT Material Type(s) Roof Plan reference BH3 Glass 3 - Fair DAMAGED GUARDS Quantity 20 MAINTENANCE Photo1 No photo recorded ROOF/GRAVITY TANK STAIRS/RAMPS: EXTERIOR BUILDING CHEEK/FLANK WALLS 5 - Poor CAST IN PLACE CONCRETE: DETERIORATED EXPANSION JOINT PB/A&W Page 23 of 64

24 Building Assessment Survey Architectural Inspection EXTERIOR STAIRS/RAMPS: EXTERIOR BUILDING CHEEK/FLANK WALLS Roof Plan reference Quantity 10 L.F. Photo1 Roof Plan reference Main Entrance - HC Ramp CAST IN PLACE CONCRETE: CRACKS/SPALLING - MAJOR Quantity 40 Urgency of Action PRIORITY 4 PB/A&W Page 24 of 64

25 Building Assessment Survey Architectural Inspection EXTERIOR STAIRS/RAMPS: EXTERIOR BUILDING CHEEK/FLANK WALLS Photo1 RAILINGS STAIRS/RAMPS Roof Plan reference Facade A - Main Entrance 5 - Poor CONCRETE: WORN-OUT TREAD/RISER/NOSING Quantity 10 Urgency of Action PRIORITY 4 Photo1 Facade E CONCRETE: CRACKS/SPALLING - MAJOR PB/A&W Page 25 of 64

26 EXTERIOR STAIRS/RAMPS: EXTERIOR STAIRS/RAMPS Roof Plan reference Building Assessment Survey Quantity 20 Urgency of Action PRIORITY 4 Photo1 Roof Plan reference Facade L CONCRETE: CRACKS/SPALLING - MINOR Quantity 25 REPAIR PB/A&W Page 26 of 64

27 EXTERIOR STAIRS/RAMPS: EXTERIOR STAIRS/RAMPS Photo1 Building Assessment Survey Facade A - Main Entrance WINDOWS Replacement Quantity 15,000 Replacement Uom EXTERIOR GUARDS LINTELS STEEL: MINOR RUSTING Roof Plan reference Elevation Quantity 15 L.F. MAINTENANCE Photo1 WINDOWS No photo recorded PB/A&W Page 27 of 64

28 Building Assessment Survey Architectural Inspection EXTERIOR WINDOWS WINDOWS Material Type(s) Aluminum Instance on Aluminum - Other: All Facades Instance Instance Quantity 15,000 Instance Installation Year 2008 Source of Installation Custodial Staff ALUMINUM - OTHER: BROKEN PANE Roof Plan reference Elevation Quantity 70 MAINTENANCE Urgency of Action PRIORITY 5 Photo1 No photo recorded INTERIOR POOLS STRUCTURAL COLUMNS/BEAMS/BEARING WALLS FLOOR STRUCTURE 3 - Fair CONCRETE SLAB ON GRADE: MINOR CRACKS Location/Instance Basement Quantity 35 PB/A&W Page 28 of 64

29 Building Assessment Survey Architectural Inspection INTERIOR STRUCTURAL FLOOR STRUCTURE REPAIR Purpose of Action LEVEL 5 Photo1 Room C13 CONCRETE: CRACKS/SPALLED/REINFORCEMENT EXPOSED Location/Instance Basement Quantity 50 REPAIR Purpose of Action LEVEL 5 Photo1 Room C20 (similar Room C26 and Basement Corridor) FOUNDATION WALLS Material Type(s) Location/Instance Quantity 80 Concrete 3 - Fair CONCRETE: WATER INFILTRATION IN NON- INSTRUCTIONAL SPACE Basement Urgency of Action PRIORITY 5 Purpose of Action LEVEL 5 INSTALL WATERPROOFING PB/A&W Page 29 of 64

30 INTERIOR STRUCTURAL FOUNDATION WALLS Photo1 Building Assessment Survey Basement Corridor (similar Room C18) ROOF STRUCTURE VAULTS-BUNKERS Foundation Walls Slab Structure Vault/Ash Hoist Doors and Framing Location/Instance Quantity 2 Inaccessible Inaccessible 5 - Poor MINOR RUSTING Basement EACH REPAIR Photo1 AUDITORIUM Ceiling Instance on Basement Seats Instance on Basement Seats Door(s) Instance on Basement Seats Fixed H/C Lift Instance on Basement Seats Fixed Seating Instance on Basement Seats Location/Instance Quantity 10 No photo recorded DAMAGED/BROKEN/INOPERABLE Seats A/3,6, C/1, D/2, S/113, and others PB/A&W Page 30 of 64 EACH

31 Building Assessment Survey Architectural Inspection INTERIOR AUDITORIUM Fixed Seating Photo1 Seat A/6 Floor Finish Instance on Basement Seats CONCRETE: CRACKS Location/Instance Near Stage Quantity 20 Photo1 Near Stage Sliding-folding Partition Stage Stage Instance on Basement Seats Instance on Basement Seats Instance on Basement Seats Location/Instance Quantity Fair DAMAGED STEPS Stage Right PB/A&W Page 31 of 64

32 Building Assessment Survey Architectural Inspection INTERIOR AUDITORIUM Stage Stage Photo1 Stage Right DAMAGED FLOOR Location/Instance In the Middle Quantity 20 Photo1 In the Middle Stage Curtain Rigging Instance on Basement Seats Location/Instance Quantity Poor INOPERABLE Stage EACH MAINTENANCE Photo1 Stage Curtains Instance on Basement Seats No photo recorded PB/A&W Page 32 of Fair

33 Building Assessment Survey Architectural Inspection INTERIOR AUDITORIUM Stage Stage Curtains WORN/DETERIORATED Location/Instance Stage Left, Stage Right Quantity 200 Photo1 Stage Left Walls Instance on Basement Seats Window Curtains/Shades/Blinds Instance on Basement Seats CAFETERIA Instance on 1st Floor - Staff (600 SF) Instance on 1st Floor - Students Ceiling Instance on 1st Floor - Staff (600 SF) 3 - Fair ACOUSTIC TILES: DAMAGED/MISSING - ACTIVE LEAK Location/Instance Near Servery Quantity 10 Urgency of Action PRIORITY 5 Photo1 PB/A&W Page 33 of 64

34 INTERIOR CAFETERIA Ceiling Building Assessment Survey Near Servery Instance on 1st Floor - Students 4 - Between Fair and Poor ACOUSTIC TILES: DAMAGED/MISSING - ACTIVE LEAK Location/Instance Near Vending Machines Quantity 20 Urgency of Action PRIORITY 5 Photo1 Near Vending Machines Instance on 1st Floor - Staff (600 SF) 3 - Fair ACOUSTIC TILES: DAMAGED/MISSING Location/Instance Near Windows Quantity 30 Photo1 Near Windows Instance on 1st Floor - Students Location/Instance Quantity Between Fair and Poor ACOUSTIC TILES: DAMAGED/MISSING Near Entrance, in the Middle PB/A&W Page 34 of 64

35 Building Assessment Survey Architectural Inspection INTERIOR CAFETERIA Ceiling Photo1 Near Entrance Door(s) Instance on 1st Floor - Students 4 - Between Fair and Poor WOOD: DETERIORATED DOOR Location/Instance Entrance Quantity 2 EACH MAINTENANCE Photo1 Fixed Equipment Instance on 1st Floor - Staff (600 SF) Instance on 1st Floor - Students Floor Finish Instance on 1st Floor - Staff (600 SF) Instance on 1st Floor - Students Sliding-folding Partition Entrance PB/A&W Page 35 of 64

36 Building Assessment Survey Architectural Inspection INTERIOR CAFETERIA Sliding-folding Partition Instance on 1st Floor - Staff (600 SF) Instance on 1st Floor - Students Stage Instance on 1st Floor - Staff (600 SF) Instance on 1st Floor - Students Walls Instance on 1st Floor - Students Instance on 1st Floor - Staff (600 SF) Window Curtains/Shades/Blinds Instance on 1st Floor - Staff (600 SF) Instance on 1st Floor - Students CLASSROOMS/CORRIDORS/ADMIN SPACES Ceiling GYPSUM BOARD: DAMAGED/DETERIORATED Location/Instance Room 305 Quantity 40 Photo1 Room 305 PLASTER: CRACKS/SPALLING Location/Instance Exit 9 Vestibule Quantity 20 PB/A&W Page 36 of 64

37 Building Assessment Survey Architectural Inspection INTERIOR CLASSROOMS/CORRIDORS/ADMIN SPACES Ceiling Photo1 Exit 9 Vestibule ACOUSTIC TILES: DAMAGED/MISSING Location/Instance Main Entrance Lobby, Corridor near Rooms Quantity 1,800 Photo1 Corridor near Room 117 Door(s) 5 - Poor METAL: DETERIORATED DOOR Location/Instance Rooms 312, 327 Quantity 2 EACH MAINTENANCE Photo1 PB/A&W Page 37 of 64

38 Building Assessment Survey Architectural Inspection INTERIOR CLASSROOMS/CORRIDORS/ADMIN SPACES Door(s) Room 312 WOOD: DETERIORATED DOOR Location/Instance Rooms 208, 225, 322, 403, 410, and others Quantity 9 EACH MAINTENANCE Photo1 Room 208 Floor Finish VINYL TILES: TRIPPING HAZARD - ELECTRICAL OUTLET Location/Instance Room 226 Quantity 10 Urgency of Action PRIORITY 5 Purpose of Action LEVEL 6 Photo1 Room 226 VINYL TILES: BROKEN/DETERIORATED/MISSING TILES Location/Instance Corridor near Stair F/1,3, Corridor near Room 120, Room 214, Corridor near Gymnasium Quantity 60 PB/A&W Page 38 of 64

39 Building Assessment Survey Architectural Inspection INTERIOR CLASSROOMS/CORRIDORS/ADMIN SPACES Floor Finish Photo1 Corridor near Stair F/1 VINYL TILES: DETERIORATED SUBSTRATE Location/Instance Corridor near Room 122, Corridor near Stair D/1 Quantity 50 Photo1 Corridor near Stair D/1 TERRAZZO: CRACKS Location/Instance Corridor near Room 112, Exit 9 Vestibule Quantity 40 Photo1 Corridor near Room 112 PB/A&W Page 39 of 64

40 Building Assessment Survey Architectural Inspection INTERIOR CLASSROOMS/CORRIDORS/ADMIN SPACES Floor Finish Walls PLASTER: CRACKS/SPALLING Location/Instance Room 222 Quantity 10 Photo1 Room 222 PLASTER: CRACKS/SPALLING - ACTIVE LEAK Location/Instance Rooms 214, 222 Quantity 20 Urgency of Action PRIORITY 5 Photo1 Room 222 GYPSUM BOARD: DETERIORATED Location/Instance Room 305 Quantity 10 PB/A&W Page 40 of 64

41 Building Assessment Survey Architectural Inspection INTERIOR CLASSROOMS/CORRIDORS/ADMIN SPACES Walls Photo1 Room 305 MASONRY: CRACKS/SPALLING Location/Instance Exit 9 Vestibule Quantity 20 Photo1 Exit 9 Vestibule Specialties Classroom Locker(s) Fixed Seating GYMNASIUM Instance on 1st Floor Ceiling Instance on 1st Floor ACOUSTIC TILES: DAMAGED/MISSING Location/Instance Office Quantity 10 PB/A&W Page 41 of 64

42 INTERIOR GYMNASIUM Ceiling Photo1 Building Assessment Survey Office Door(s) Instance on 1st Floor 3 - Fair WOOD: DETERIORATED DOOR Location/Instance Office Quantity 1 EACH MAINTENANCE Photo1 Office Fixed Equipment Instance on 1st Floor Floor Finish Instance on 1st Floor WOOD: DAMAGED/DETERIORATED Location/Instance Near Entrance Quantity 20 PB/A&W Page 42 of 64

43 INTERIOR GYMNASIUM Floor Finish Photo1 Building Assessment Survey Near Entrance Seating Instance on 1st Floor Sliding-folding Partition Instance on 1st Floor 5 - Poor MOTOR: INOPERABLE Location/Instance In the Middle Quantity 1 EACH Photo1 No photo recorded Stage Instance on 1st Floor Walls Instance on 1st Floor Window Curtains/Shades/Blinds Instance on 1st Floor INTERIOR DOOR HARDWARE 3 - Fair INTERIOR GUARDS DETERIORATED/TORN-OUT/MISSING Location/Instance Room 409 Quantity 10 PB/A&W Page 43 of 64

44 INTERIOR INTERIOR GUARDS Photo1 Building Assessment Survey Room 409 KITCHEN Instance on 1st Floor Ceiling Instance on 1st Floor 5 - Poor METAL PAN: DAMAGED/MISSING Location/Instance Servery, Preparation Area Quantity 150 Photo1 Servery Door(s) Instance on 1st Floor Floor Finish Instance on 1st Floor Location/Instance Quantity 30 CERAMIC TILE: BROKEN/MISSING TILES Servery, near Ovens, near Preparation Area PB/A&W Page 44 of 64

45 INTERIOR KITCHEN Floor Finish Photo1 Building Assessment Survey Near Ovens Walls Instance on 1st Floor LIBRARY Instance on Room 224 Built-in Furnishing Instance on Room 224 Ceiling Instance on Room 224 Door(s) Instance on Room Fair WOOD: DETERIORATED DOOR Location/Instance Entrance Quantity 1 EACH MAINTENANCE Photo1 No photo recorded Floor Finish Instance on Room 224 Walls Instance on Room 224 LOCKER ROOM Instance on 1st Floor - Boys PB/A&W Page 45 of 64

46 Building Assessment Survey Architectural Inspection INTERIOR LOCKER ROOM Alternative use Yes Instance on 1st Floor - Girls Alternative use Yes Ceiling Instance on 1st Floor - Boys Instance on 1st Floor - Girls Door(s) Instance on 1st Floor - Girls Instance on 1st Floor - Boys Floor Finish Instance on 1st Floor - Boys Instance on 1st Floor - Girls Locker Room Lockers Instance on 1st Floor - Boys Instance on 1st Floor - Girls Walls Instance on 1st Floor - Girls MASONRY: CRACKS/SPALLING Location/Instance Near Windows Quantity 20 Photo1 Near Windows PB/A&W Page 46 of 64

47 Building Assessment Survey Architectural Inspection INTERIOR MULTI-PURPOSE ROOM SCIENCE DEMO ROOM Instance on Room 304 Alternative use Yes Fixed Equipment Instance on Room Fair DEMO TABLE: DAMAGED/DETERIORATED Location/Instance Room 304 Quantity 1 EACH Photo1 Room 304 SCIENCE LAB Instance on Rooms 314, 319, 323 Alternative use Yes Instance on Room 312 Alternative use No Instance on Rooms 305, 310 Alternative use Yes Fixed Equipment Instance on Rooms 305, Fair DEMO TABLE: DAMAGED/DETERIORATED Location/Instance Rooms 305, 310 Quantity 2 EACH PB/A&W Page 47 of 64

48 INTERIOR SCIENCE LAB Fixed Equipment Photo1 Building Assessment Survey Room 310 Instance on Room Between Fair and Poor CABINETRY: MISSING/DAMAGED Location/Instance Room 312 Quantity 20 L.F. Photo1 Room 312 Instance on Rooms 314, 319, Fair CABINETRY: MISSING/DAMAGED Location/Instance Rooms 314, 319, 323 Quantity 30 L.F. PB/A&W Page 48 of 64

49 INTERIOR SCIENCE LAB Fixed Equipment Photo1 Building Assessment Survey Room 323 SCIENCE PREP ROOM Instance on Room 303 Alternative use Yes Fixed Equipment Instance on Room 303 SHOWER ROOM Instance on 1st Floor - Boys Inaccessible Instance on 1st Floor - Girls Inaccessible STAIRS/RAMPS: INTERIOR Do Letter Stair Signs Exist? Yes Ceiling Door(s) 3 - Fair METAL: DETERIORATED DOOR Location/Instance Stair E/2,3 Quantity 2 EACH MAINTENANCE Photo1 Stair E/2 Partition PB/A&W Page 49 of 64

50 Building Assessment Survey Architectural Inspection INTERIOR STAIRS/RAMPS: INTERIOR Railings Stairs and Landings CONCRETE: CRACKS/SPALLING - MAJOR Location/Instance Stair E/Bulkhead Quantity 10 Photo1 Stair E/Bulkhead VINYL TILES: DETERIORATED SUBSTRATE Location/Instance Stairs D/1,2, F/1 Quantity 20 Photo1 Stair F/1 Location/Instance Quantity 30 METAL: RUST - MAJOR Stairs A/3, D/Basement,1,2,3,4 PB/A&W Page 50 of 64

51 INTERIOR STAIRS/RAMPS: INTERIOR Stairs and Landings Photo1 Building Assessment Survey Stair D/1 Walls TOILET ROOMS - STAFF Ceiling PLASTER: CRACKS/SPALLING Location/Instance Gymnasium Office Quantity 10 Photo1 Gymnasium Office Door(s) 5 - Poor WOOD: DETERIORATED DOOR Location/Instance Room 218, Kitchen Staff Toilet, Gymnasium Office Quantity 3 EACH MAINTENANCE PB/A&W Page 51 of 64

52 INTERIOR TOILET ROOMS - STAFF Door(s) Photo1 Building Assessment Survey Room 218 WOOD: DAMAGED LOUVER Location/Instance Room 220 Quantity 1 EACH MAINTENANCE Photo1 Room 220 Floor Finish Stalls Walls CERAMIC TILE: BROKEN/ MISSING Location/Instance Room 218 Quantity 10 PB/A&W Page 52 of 64

53 INTERIOR TOILET ROOMS - STAFF Walls Photo1 Building Assessment Survey Room 218 TOILET ROOMS - STUDENTS Ceiling Door(s) 5 - Poor WOOD: DAMAGED LOUVER Location/Instance Rooms 136, 307, 413 Quantity 3 EACH MAINTENANCE Photo1 Room 413 WOOD: DETERIORATED DOOR AND FRAME Location/Instance Room 409 Quantity 1 EACH MAINTENANCE PB/A&W Page 53 of 64

54 INTERIOR TOILET ROOMS - STUDENTS Door(s) Photo1 Building Assessment Survey Room 409 WOOD: DETERIORATED DOOR Location/Instance Rooms 211, 311, 1st Floor Boys Quantity 3 EACH MAINTENANCE Photo1 1st Floor Boys Floor Finish CERAMIC TILE: BROKEN/MISSING TILES Location/Instance Locker Room Boys Quantity 10 Photo1 PB/A&W Page 54 of 64

55 INTERIOR TOILET ROOMS - STUDENTS Floor Finish Building Assessment Survey Locker Room Boys Stalls RUST - MAJOR Location/Instance Locker Room Girls Quantity 1 EACH Photo1 Locker Room Girls Walls PLASTER: CRACKS/SPALLING Location/Instance Room 207 Quantity 10 Photo1 Room 207 Location/Instance Quantity 150 CERAMIC TILE: BROKEN/ MISSING Rooms 207, 211, 307, 311, 409, 1st Floor Girls, Locker Room Boys PB/A&W Page 55 of 64

56 Building Assessment Survey Architectural Inspection INTERIOR TOILET ROOMS - STUDENTS Walls Photo1 Room 409 LIFE SAFETY F.D. HOLDING AREA STEEL STAIRS SITE CONTAINERIZATION 5 - Poor CONTAINER DAMAGED Location/Instance Franklin Avenue Quantity 3 EACH Photo1 Drainage System for Asphalt Catch Basins/Manhole - Surrounded by asphalt Culverts - Asphalt Covering Drainage System for Concrete Catch Basins/Manhole - Surrounded by concrete Franklin Avenue PB/A&W Page 56 of 64

57 Building Assessment Survey Architectural Inspection SITE Drainage System for Concrete Culverts - Concrete Covering Drainage System for Soil Catch Basins/Manhole - Surrounded by Soil Culverts - Soil Covering DRINKING FOUNTAINS FENCES 3 - Fair CONCRETE CURB: DAMAGED/DETERIORATED Location/Instance Franklin Avenue, Sullivan Place, McKeever Place Quantity 50 Photo1 Franklin Avenue WROUGHT IRON: DAMAGED/DETERIORATED Location/Instance Franklin Avenue Quantity 40 Photo1 Franklin Avenue IRRIGATION SYSTEM PB/A&W Page 57 of 64

58 Building Assessment Survey Architectural Inspection SITE PAVING Student Non-Use Gravel Exists? No Asphalt Concrete Pavers Student Use Gravel Exists? No Asphalt 3 - Fair CRACKS - MAJOR Location/Instance Schoolyard Quantity 250 Photo1 Schoolyard Concrete Pavers Site Sidewalks & Walkways Asphalt Concrete 3 - Fair CRACKS - MAJOR Location/Instance Main Entrance, Sullivan Place Walkway, Franklin Avenue Walkway Quantity 175 PB/A&W Page 58 of 64

59 SITE PAVING Site Sidewalks & Walkways Concrete Photo1 Building Assessment Survey Main Entrance Pavers DOT Sidewalk Asphalt Concrete 4 - Between Fair and Poor HEAVING Location/Instance Franklin Avenue Quantity 75 Urgency of Action PRIORITY 5 Purpose of Action LEVEL 6 Photo1 Franklin Avenue DAMAGED/DETERIORATED/MISSING SECTIONS Location/Instance Franklin Avenue, Sullivan Place, McKeever Place Quantity 2,875 Urgency of Action PRIORITY 4 Purpose of Action LEVEL 4 PB/A&W Page 59 of 64

60 SITE PAVING DOT Sidewalk Concrete Photo1 Building Assessment Survey Franklin Avenue HEAVING Location/Instance Franklin Avenue, McKeever Place Quantity 475 Urgency of Action PRIORITY 4 Purpose of Action LEVEL 4 Photo1 Franklin Avenue Pavers HEAVING Location/Instance Franklin Avenue Quantity 20 Urgency of Action PRIORITY 4 Purpose of Action LEVEL 4 Photo1 PB/A&W Page 60 of 64

61 SITE PAVING DOT Sidewalk Pavers PLAYGROUNDS Benches Instance on Along Franklin Avenue Instance on Along McKeever Place Instance on Along McKeever Place Fence Instance on Along Franklin Avenue Instance on Along McKeever Place Pavement Instance on Along Franklin Avenue Instance on Along McKeever Place Instance on Along Franklin Avenue Play Equipment Instance on Along Franklin Avenue Instance on Along McKeever Place Safety Surfacing Instance on Along McKeever Place Instance on Along Franklin Avenue Unpaved Area Instance on Along Franklin Avenue Instance on Along McKeever Place PLAYING SURFACE RETAINING WALLS Are there any Retaining Walls 6' OR higher facing public street/sidewalk? Location/Instance Quantity 20 Building Assessment Survey Franklin Avenue No 3 - Fair CAST IN PLACE CONCRETE: CRACKS/SPALLING - MAJOR Schoolyard PB/A&W Page 61 of 64

62 Building Assessment Survey Architectural Inspection SITE RETAINING WALLS Photo1 Schoolyard Location/Instance Quantity 10 CAST IN PLACE CONCRETE: DETERIORATED EXPANSION JOINT McKeever Place L.F. Photo1 McKeever Place SEATING Benches Concrete Metal/Wood/Plastic Bleachers SITE WALLS (NOT RETAINING WALLS) Location/Instance Quantity 10 CAST IN PLACE CONCRETE: DETERIORATED EXPANSION JOINT Schoolyard L.F. PB/A&W Page 62 of 64

63 Building Assessment Survey Architectural Inspection SITE SITE WALLS (NOT RETAINING WALLS) Photo1 Schoolyard STAIRS/RAMPS: EXTERIOR Railings 4 - Between Fair and Poor MISSING Location/Instance Schoolyard Quantity 20 L.F. Urgency of Action PRIORITY 5 Purpose of Action LEVEL 6 Photo1 Schoolyard Site Cheek/flank Walls Stairs/ramps CAST IN PLACE CONCRETE: CRACKS/SPALLING - MAJOR Location/Instance Schoolyard Quantity 20 PB/A&W Page 63 of 64

64 SITE STAIRS/RAMPS: EXTERIOR Stairs/ramps Photo1 Building Assessment Survey Schoolyard PB/A&W Page 64 of 64