1 SAFETY» Total Man Hours Worked This Week: 24125» Total Man Hours on Project: » Crafts On Project This Week: 24» OSHA Recordable Rate: 0

2 CURRENT CONSTRUCTION ACTIVITIES East Zone» Continued MEP Building E.» Installed Paper Towel Bldgs G & F.» Continued Painting Buildings F & E.» Continued Lights and Building E.» Began Spreading Top East Zone.» Continued Point Building F 3rd Floor.» Continued Installing Irrigation Along East Spine.» Poured Footings For Dumpster Pad Walls.» Painted Exterior Building G.» Continued Drywall Hanging & Building E.» Continued Building G.» Placed Top Bldgs. G, E & F Bldg. G Main Lobby Light Fixtures Building E Complex Lounge Dumpster Wall Foundations SITE, HUB, & WEST ZONE» Continued Interior Bldgs. B and C.» Continued Brick Bldg. C.» Continued MEP HUB, Bldg. B, & Bldg. A.» Continued Building D.» Continued Glass HUB & Building C.» Continued Newman Rd Intersection Roadwork.» Poured Newman Road Intersection.» Continued Window Frame Building D.» Continued Finishing Building A.» Continued Hanging Building B.» Continued Sidewalk and Structural Soil Top Soil Spreading Building E Wall Tile

3 NEXT WEEK S ACTIVITIES East Zone» Continue Overhead Buildings E.» Continue Finishing Building E.» Continue Building F.» Continue Wall Building F & E.» Continue Priming Building E.» Continue Installing Lights & Bldg. E.» Continue Point Up 3rd Building F.» Continue Punch Building G.» Continue Bldg. F» Continue East Zone Building B DEFS Building D ERV Unit Building D Window Frames SITE, HUB, & WEST ZONE» Continue Curtain Wall HUB.» Continue Brick Building C.» Continue MEP Bldgs. A, B, & HUB.» Continue Interior Framing & Bldg B.» Continue Roof Building D.» Begin Trash Walls North of Building E.» Continue Framing Interior Building C.» Continue Priming Building A.» Continue Temp Building D.» Continue Newman Road Intersection Roadwork.» Continue Storm HUB & Bldg. E HUB Sunshade Infill Building D Waterproofing

4 MANPOWER Holder Construction Company General Contractor American Deep Foundation Auger Cast Piles Accessories Unlimited Bathroom Accessories Baker Roofing Sheathing and Shingles Brightview Landscape Develop- Hardscape & Landscape Cabinets By Design Millwork Carolina Fire Protection Sprinklers C&C Fence Site Fence Cowart Tree Mulch Tree Removal Davis Crane Erectors Pre-Cast Erection D.H. Griffin Tank Foundation Removal Elite Flooring Tile Feltman Brothers West - Masonry Gainesville Mechanical Ductwork Gill Plumbing Plumbing Graham Hodge Glass Gregory Electric Aboveground Electric Hutch-N-Son Early Site Work st Choice Glass Glass Johnson Controls Building Controls JBR Construction Early Site Work Johnsons Modern Electric Aboveground Electrical King Asphalt Asphalt Kone Elevators Labor Finders Labor Force Metro Power Underground Electrical Nations Roofing Roofing Old North State Masonry East - Masonry Osteen Chill Water pipe Precision Concrete

5 MANPOWER CONTINED Pro Door Doors & Hardware Pyramid Masonry Hub Masonry R.E. Mclean Tank Tank Demo Reeves Young Site Grading & Utilities Rival Construction Inc. Concrete RJ Coogan Deck Installers Ruppert Landscaping Landscape/ Hardscape Sears Contract Drywall/Metal Trusses Sentential Maintenance Construction Cleaning Silt Fence Installation Site Erosion Control Simplex Controls Southern Mechanical Inc. Electrical/Plumbing Specialty Finishes Painting Steel Toe Labor Force TG Welding Misc. Steel Tree South Arborist Upstate Curb Curb and Gutter Valley Farm Construction Tree removal/grading Waterproofing Specialties Waterproofing Total

6 WEATHER CURRENT WEEK Rain Days This Week = 0 Rain Days To Date = 63 SAFETY REVIEW LOG Douthit Hills Monthly OSHA Statistics Man-hours worked RCR/DART Cumulative Man- Hours Mar-16 Apr-16 May-16 Jun-16 Jul-16 Aug-16 Sep-16 Oct-16 Nov-16 Dec-16 Jan-17 Feb-17 Mar- Apr- May- Jun- Jul- Aug- Sep- Oct- Nov- Dec- Jan- Feb RCR DART R

7 MANPOWER CHART Douthit Hills Workforce Reeves Grading Metro Power Davis Crane Erectors Pyramid Masonry Sears Contract Gainesville Mechanical 1st Choice Glass Southern Mechanical Rival Construction Feltman Brothers JME Graham Hodge Elite Flooring Speacialty Finishes Other Holder