Safety Update Crossing study is in final review stages. Facilities Update Construction Progress

Size: px
Start display at page:

Download "Safety Update Crossing study is in final review stages. Facilities Update Construction Progress"

Transcription

1 Major Projects Update September 2017 Prepared by Business and Operations September 11, 2017 Transportation Update As of 9/6/17 we have 4,803 students registered for busing, up 643 from last month s update. Road construction in SMS area has been an issue with SMS/LHS PM routes. Under the Transportation link of the new BPS website is a Bus Delays/Changes tab. This tab shows: o Buses that are delayed, why they are delayed, and how far behind they are. o It will also show if a spare bus has been sent in place of the regular bus so students know which bus to watch for. Safety Update Crossing study is in final review stages. Facilities Update Construction Progress Bismarck High School Addition & Renovation Bid in February 2018 Century High School Phase II Bid in February

2 Century High School Addition & Renovation Phase I Foundations have been excavated and helical piers are being drilled. Framing is continuing and soon to be completed. Ductwork and heat line is being hung. Started electrical roughing in walls. Century High School Started framing walls Framing office walls Excavating foundations in area B Bathroom plumbing roughed in 2

3 Horizon Middle School Addition & Renovation Footing and foundation work continues on the west side. Progress continues on the backfill and the foundation work on the east additions. Sprinklers are reinstalled where the sewer line was put in. Sidewalk work and other concrete has also been completed in this area. Mechanical rough in is in progress on the west side. Electrical is working on the lights in the east parking lot. Horizon Middle School Progress at Area A Foundation work at area A Progress at Area B/C Excavation progress at Areas B/C 3

4 Simle Middle School Addition & Renovation Setting steel on 1 st and 2 nd floor. Steel for 3 rd story on site. Foundations insulated and backfilled. Simle Middle School Setting steel on 1 st and 2 nd floor Setting steel All steel for 3 rd story on site Foundations insulated and backfilled 4

5 Wachter Middle School Addition & Renovation Exterior stud construction has commenced at Area C East. Openings at windows and doors remain to be framed. The first floor slab at area C East has been placed and about 80% of the interior walls have been constructed. Steel roof deck has been placed on Area C East roof and is being attached. Steel roof deck is ready to commence at Area C West. The second floor slab for Area C West has been placed. Rough in plumbing for the ground floor of Area C West is in place. The foundations at area A are complete and backfill is nearly complete. Masons are laying CMU walls at Area A. Helical piers have been drilled at area D. Area D has been excavated for footings. Electrical service upgrades are complete. Wachter Middle School Metal stud construction commenced at C East Rough in plumbing at Area C West Masons are laying CMU walls at Area A Grade beams being formed at Area D 5

6

7

8 BISMARCK PUBLIC SCHOOLS Building Fund Revenues and Expenditures August 31, 2017 Beginning Fund Balance - July 1, 2017 $ (536,666) Revenue For FY-18: Property Tax Receipts $ 6,268 Misc. Property Tax Receipts School Construction Loan Revenue in Lieu of Taxes Proceeds from Sale of Bonds 34,700,500 Fundraising Interest Income - Total Revenue $ 34,706,768 34,706,768 Total Funds Available $ 34,170,102 Expenditures For FY-18: Bond Payment Bond Professional Services 80,135 Athletic Complex 1,863, Projects 2,065,944 Total Expenditures 4,009,909 4,009,909 Fund Balance as of August 31, ,160,193 Special Assessments Beginning Balance - July 1, 2017 $ 50 Revenue For FY-18: Property Tax Receipts $ 680 Total Revenue 680 Total Funds Available $ 730 Expenditures For FY-18: Minimum Payment Payment towards Balance Total Expenditures - - Balance as of August 31, 2017 $ 730 Special Assessment Balance $ 2,689, Building Fund - Summary FY18 9/7/2017

9 Project Detail Expenditures August 31, 2017 Horizon Middle School Construction Expenses 972, ,318, Fees 34, , FFE , Misc (Testing, Surveying) 27, Total $ 1,007, $ 1,723, Simle Middle School Construction Expenses 205, , Fees 685, FFE - Misc (Testing, Surveying) 32, Total $ 205, $ 1,418, Wachter Middle School Construction Expenses 738, ,523, Fees 31, , FFE - Misc (Testing, Surveying) 30, Total $ 770, $ 2,054, Bismarck High School Construction Expenses - Fees 40, , FFE - Misc (Testing, Surveying) , Total $ 40, $ 454, Century High School Construction Expenses 17, , Fees 23, ,044, FFE 1, , Misc (Testing, Surveying) 27, Total $ 41, $ 1,114, Total Bond Projects Current FY Project Total Total $ 2,065, $ 6,765, Building Fund - Back Up to FY18 9/7/2017