FIELD OBSERVATION REPORT

Size: px
Start display at page:

Download "FIELD OBSERVATION REPORT"

Transcription

1 ARCHSOL, L.L.C. FIELD OBSERVATION REPORT 8901 E. Pima Center Pkwy. Ste. 205 Scottsdale, Arizona Project: SJHMC_Gregory W. Fulton ALS and Neuromuscular Disorder Clinic Author: R. Arellano [Archsol] Date: 20 June 2013 Please reference items noted on Field Observation Report. Specific attention shall be given to items noted for GC Action. Confirm corrective action taken. Similar installations, not noted herein, are to be corrected in similar manner. [WIP: WORK IN PROGRESS] CORRECTIVE ACTION ITEMS ITEM NO DESCRIPTION_REMARKS ACTION BY 01 VARIOUS LOCATIONS THROUGHOUT FIRE ALARM CONDUIT: PROVIDE RED COLORED CONDUIT GYPSUM BOARD ATTACHMENT: 02 PANEL EDGE ATTACHMENT IS NON.EXISTENT PROVIDE MEMBER TO ALLOW FOR POSITIVE ATTACHMENT AT PANEL EDGE

2 03 TERMINAL UNITS: ENSURE PROPER PROTECTION FROM DAMAGE IS PROVIDED. DO NOT LAY ON FLOOR 04 MAIN DUCT RUN: HALL 4190 SUPPORT DOES NOT APPEAR ADEQUATE PROVIDE SUPPORT STRAPS AS REQUIRED 05 DUCTWORK COVERING SOME OPEN ENDS ARE EXPOSED COVER OPEN ENDS AS REQUIRED SHELL [4500] WAITING [4100]

3 06 SAMPLES [4309] WASTE LINE HAS BEEN OFFSET TO CLEAR FLOOR BEAM BELOW RE.ROUTE LINE WITHIN PARTITION NORTH AND WEST TO AVOID MODIFYING OF MILLWORK 07 WEST CORRIDOR [4002] ELECTRICAL CONDUIT SUPPORT ROD IS NOT INDEPENDENT PROVIDE NEW INDEPENDENT ROD

4 08 WEST CORRIDOR [4002] EXISTING VENT LINE IS NOT SUPPORTED PROPERLY PROVIDE UNI.STRUT SUPPORT AS REQUIRED 09 MEN S TOILET [4004] ROUGH.IN INSTALLED. WASTE LINE OFFSET SUPPORT IS NON.CONFORMING PROVIDE CONFORMING SUPPORT

5 GENERAL CONSTRUCTION PROGRESS ITEMS 01 TOP OF WALL CONDITION: [WIP] INSULATION INFILL IS DEEMED ACCEPTABLE AT NON.RATED PARTITIONS CONTINUE INSTALLATION FOR ALL FULL.HEIGHT WALLS 02 PENETRATIONS THROUGH PARTITIONS: [WIP] SEAL PENETRATIONS AS REQUIRED [G.001_GENERAL NOTE PLUMBING ROUGH.IN: SUPPORT STRAPS ISOLATED FROM METAL STUDS

6 04 VITALS [4118]: FLOOR SCALE: SLAB SAW CUT OPENING EXECUTED. COVERED AND SECURED W/ DANGER TAPE 05 BOTOX [4119]: BACKING STRAP FOR MILLWORK INSTALLED 06 NURSES STATION [4116]: FRAMING: IN PROGRESS INSULATION: IN PROGRESS WALL ROUGH.IN: CONDUIT INSTALLED [PULL STRING]

7 07 VARIOUS LOCATIONS: [WIP] PARTITION AT WINDOW CONDITION. PROVIDE MULLION MATE ASSEMBLY OFFSETS LONGER THAN TREATMENT ROOM [4166]: EXTERIOR WALL ROUGH.IN INSTALLED MILLWORK BACKING STRAP INSTALLED 09 TERMINAL UNIT INSTALLATION: HALL 4190 DUCTWORK OPEN ENDS COVERED SUPPORT STRAPS INSTALLED DUCTWORK CONNECTIONS SEALED

8 10 HALL [4190] CEILING HEADER FRAMED DUCTWORK RUN 11 PHYSICIAN S OFFICE [4176] PARTITION HAS BEEN RELOCATED DUCT TRANSITION AND INSTALLATION OF FIRE DAMPER IS PENDING [WIP]

9 12 MULTI.PURPOSE ROOM [4182] FRAMING IN PROGRESS DOOR RELOCATED ROUGH.IN ON NORTH WALL TO BE RELOCATED [WIP] DATA ALCOVE 13 DUCT CHASE [WEST OF THERAPY_4308] FLOOR SLAB OPENING HAS BEEN CUT FALL PROTECTION EXECUTED

10 14 WAITING [4300]] FLOOR SCALE: OPENING HAS BEEN SAW CUT [NORTH END OF ROOM] FALL PROTECTION INSTALLED 15 WEST CORRIDOR [4002] SOUTH AND NORTH VIEW SOUTH VIEW NORTH VIEW 16 ELECTRICAL ROOM [4007] PANEL CAN INSTALLED PENETRATIONS: PROVIDE FIRESTOPPING SYSTEMS [WIP] GENERAL CONSTRUCTION PROGRESS OBSERVATIONS: 1. PARTITION FRAMING APPEARS TO BE COMPLETED AND IN GENERAL CONFORMANCE. UPPER LAYER OF GYPSUM BOARD HUNG 2. MILLWORK BACKING STRAP INSTALLED 3. PARTITION INSULATION: UPPER SECTION LAYED 4. MAIN VENTILATION DUCTS AND BRANCH LINES: INSTALLATION IN PROGRESS. TRAPEZE HANGERS BEING INSTALLED. OPEN ENDS COVERED 5. OVERHEAD ELECTRICAL CONDUIT MOSTLY COMPLETE. HANGERS IN GENERAL CONFORMANCE 6. ELECTRICAL ROUGH.IN INSTALLED UP TO CEILING ELEVATION. NO WIRING PULLED 7. CEILING HEADERS FRAMED 8. OVERHEAD WATER LINES: RUN. SUPPORTS ARE IN GENERAL CONFORMANCE NOTE: Other work was in progress on this date which was not reviewed by Archsol. Notify Architect of any comments, within twenty.four hours of report receipt.