HOLDER CONSTRUCTION COMPANY Superintendents Weekly Activity Report #91 Douthit Hills Student Community, Clemson University Project Joe Jett

Size: px
Start display at page:

Download "HOLDER CONSTRUCTION COMPANY Superintendents Weekly Activity Report #91 Douthit Hills Student Community, Clemson University Project Joe Jett"

Transcription

1 SAFETY» Total Man Hours Worked This Week: 21450» Total Man Hours on Project: » Crafts On Project This Week: 24» OSHA Recordable Rate: 0 November 7, 20 Page 1

2 CURRENT CONSTRUCTION ACTIVITIES East Zone» Elevator Building F.» Continued Overhead Buildings E & F.» Continued MEP Building E.» Continued FCU Buildings E & F.» Continued MEP Building G.» Gas Water Heaters Buildings E & F.» Complete Fire Protection Building F.» Continued Setting Building E.» Complete Building E.» Continued Hanging Buildings E & F.» Continued Finishing Building G.» Continued Priming Building G.» Continued Tile Building G. Bldg. E Interior Soffit Framing Bldg. E & F Generators Bldg. G Bathroom Tile SITE, HUB, & WEST ZONE» Continued Curtain Wall HUB.» Continued Brick HUB.» Continued MEP HUB.» Continued HUB & Building B.» Continued Glass HUB & Building B.» Began Brick Building B.» Completed Building C.» Poured Topping Building C.» Continued Interior Framing & Building A.» Continued Building A.» Continued MEP Building A.» De-Mucked Detention Pond.» Poured Fire East Courtyard. HUB Brick Masonry HUB Curtain Spine November 7, 20 Page 2

3 NEXT WEEK S ACTIVITIES East Zone» Elevator Building E.» Continue Overhead Buildings E & F.» Continue MEP Building E.» Continue FCU Buildings E & F.» Continue MEP Building G.» Continue Fire Protection Building E.» Continue Setting Building E.» Continue Hanging Buildings E & F.» Continue Finishing Building G.» Continue Priming Building G.» Continue Tile Building G.» Pour Pedestrian Sidewalk North of Building F. Bldg. A Overhead MEP Rough-In Bldg. B Brick Masonry Bldg. C Topping Slab SITE, HUB, & WEST ZONE» Begin Curtain Wall HUB.» Continue Brick HUB.» Continue MEP HUB.» Continue HUB & Building B.» Continue Glass HUB & Building B.» Continue Brick Building B.» Begin Building D.» Pour Topping Slab and Building C.» Continue Interior Framing & Building A.» Begin Interior Building B.» Continue MEP Building A.» Pour East Monumental Stair. Bldg. C Precast Finished Fire East Courtyard November 7, 20 Page 3

4 MANPOWER TRADE CONTRACTORS ON SITE Subcontractor Trade Employees Man Hours Total Man Hrs. Holder Construction Company General Contractor American Deep Foundation Auger Cast Piles Baker Roofing Sheathing and Shingles Brightview Landscape Development Hardscape & Landscape Carolina Fire Protection Sprinklers C&C Fence Site Fence Cowart Tree Mulch Tree Removal Davis Crane Erectors Pre-Cast Erection D.H. Griffin Tank Foundation Removal Elite Flooring Tile Feltman Brothers West - Masonry Gainesville Mechanical Ductwork Gill Plumbing Plumbing Graham Hodge Glass Gregory Electric Aboveground Electric Hutch-N-Son Early Site Work st Choice Glass Glass Johnson Controls Building Controls JBR Construction Early Site Work Johnsons Modern Electric Aboveground Electrical King Asphalt Asphalt Kone Elevators Labor Finders Labor Force Metro Power Underground Electrical Nations Roofing Roofing Old North State Masonry East - Masonry Osteen Chill Water pipe Precision Concrete Pyramid Masonry Hub Masonry R.E. Mclean Tank Tank Demo November 7, 20 Page 4

5 MANPOWER CONTINED TRADE CONTRACTORS ON SITE Subcontractor Trade Employees Man Hours Total Man Hrs. Reeves Young Site Grading & Utilities Rival Construction Inc. Concrete RJ Coogan Deck Installers Ruppert Landscaping Landscape/ Hardscape Sears Contract Drywall/Metal Trusses Silt Fence Installation Site Erosion Control Southern Mechanical Inc. Electrical/Plumbing Specialty Finishes Painting Steel Toe Labor Force Tree South Arborist Upstate Curb Curb and Gutter Valley Farm Construction Tree removal/grading Waterproofing Specialties Waterproofing Total November 7, 20 Page 5

6 WEATHER CURRENT WEEK Rain Days This Week = 0 Rain Days To Date = 53 SAFETY REVIEW LOG Douthit Hills Monthly OSHA Statistics Ma n-hours worked RCR/DART Cumulative Man-Hours Dec- 15 Jan- Feb- Mar - Apr- May RCR DART R Jun- Jul- Aug - Sep- Oct- Nov - November 7, 20 Page 6

7 MANPOWER CHART Douthit Hills Workforce Reeves Grading Metro Power American Deep Foundations Davis Crane Erectors Old North State Masonry Pyramid Masonry Sears Contract Gainesville Mechanical 1st Choice Glass Precision Concrete Southern Mechanical Rival Construction Feltman Brothers JME Graham Hodge Elite Flooring Speacialty Finishes Baker Roofing Holder November 7, 20 Page 7