1 ADDENDUM #2 Date: December 5, 2018 Issued By: Jordan, Gilbert & Bain Landscape Architects, Inc. 459 North Ventura Avenue, Ventura, California (805) Phone; (805) Fax Project: Freedom Park Baseball Fields Phase 2 Issued To: Bob Cerasuolo, PVRPD Project Manager For Distribution to Bidders This Addendum forms a part of the Contract Documents and modifies the original Contract Documents as noted below. Acknowledge receipt of this Addendum in the space provided on the Bid Schedule. Changes are indicated as Delta 2, dated December 5, This Addendum consists of five (5) pages. A. Pleasant Valley Recreation and Park District will now be hiring Musco Lighting directly under separate contract to perform all work described in Contract Bid Specifications Section , Part 4.2 Musco Lighting Scope of Work. Contractors bidding this project will not be hiring Musco Lighting as a Subcontractor for this project. Specification Section is revised to clarify the remaining Scope of Work required by Contractors bidding this project involving field light work that will be part of the base bid work. These identified items will be listed by Bidding Contractors on the Field Lights line item within the Bid Schedule of Values.

2 SECTION FIELD LIGHTS PART 1 GENERAL 1.1 SECTION INCLUDES Furnish all labor, materials and equipment required to complete specific work excluded by Musco Lighting as well as Contractor and Electrical Contractor responsibilities identified in Part 4 Musco Lighting Section. 1.2 SUBMITTALS Submittal for new light poles and light fixtures are not in Contract. 1.3 QUALITY ASSURANCE Light poles and fixtures to be installed by Musco Lighting and is not in Contract. 1.4 RELATED SECTIONS Comply with requirements of all electrical sections of these Specifications. 1.5 DELIVERY OF MATERIAL Musco Lighting will be responsible for all light pole and fixture deliveries. This scope of work is not in Contract. 1.6 MEASUREMENT AND PAYMENT Measurement and payment for sports field lighting, excluded by Musco Lighting as well as Contractor and Electrical Contractor responsibilities identified in Section 4, will be made as contract lump sum price bid and shall include full compensation for all items in the Contract Documents. Provide the lump sum price in the space provided on Bid Schedule of Work and prices. PART 2 PRODUCTS 2.1 MANUFACTURER Musco Light-Structure system is the selected product for the field light pole and fixture. No known equals as this project requires the matching of existing field lights. Musco Sports Lighting; 3002 Dow Avenue, Suite 504, Tustin, CA 92780; Phone (949) x6111. Musco Representative is Mike Marchetti. Page 1 of 4

3 2.2 FIELD LIGHT FIXTURE COMPONENTS Field light fixture components shall be as manufactured by Musco Lighting. These include, but not limited to, new base, new pole, new pole top fitter, additional ballast and ballast enclosures, and new wire harness. Additional fixtures as specified. 2.3 EXISTING FIXTURES Existing light fixtures shall be repositioned and adjusted on light poles by Musco Lighting. This work is not in Contract. 2.4 UL LISTING 2.5 BASE All system components shall be UL Listed for the appropriate application. Base (rock base) for new pole installation shall be crush rock base material. All materials required to install light poles shall be purchased and installed by Musco Lighting and is not in Contract. PART 3 EXECUTION 3.1 REMOVAL OF EXISTING POLES Removal of existing light poles shall be performed by Musco Lighting and is not part of this Contract. PART 4 SUBCONTRACT WITH MUSCO LIGHTING 4.1 WORK TO BE INCLUDED BY CONTRACTORS BIDDING PROJECT The Musco Lighting Scope of Work includes Exclusions and Contractor/Electrical Contractor Responsibilities. All Contractors bidding this project shall provide all electrical work and other work specifically excluded from the Musco Lighting Scope of Work. These costs shall be identified on the Schedule of Values on the field lighting line item. Include all existing turf and finish grade repair estimated to be damaged during the new pole/demolition of existing pole Scope of Work. Page 2 of 4

4 4.2 MUSCO LIGHTING SCOPE OF WORK A. Musco Responsibilities 1. Provide required poles, fixtures, and foundations. 2. Provide layout of pole locations and aiming diagram. 3. Provide equipment and materials to off load equipment at jobsite per scheduled delivery. 4. Provide storage containers for material, (including electrical components enclosures), as necessary and waste disposal. 5. Provide adequate security to protect Musco delivered products from theft, vandalism or damage during the installation. 6. Confirm the existing underground utilities and irrigation systems have been located and are clearly marked so as to avoid damage from construction equipment. 7. Demolition and disposal of (2) poles and foundations, poles S1 and S3, as defined by demolition note 1 on sheet E-3 of the project plans. Light fixtures and remote electrical components enclosure (ECE) on these two poles to be removed and protected for re-installation on other poles. Foundations to be removed to 24 below grade and debris from foundation excavation to be removed from site, ground restorations at removed foundations to be done by others. 8. Provide materials and equipment to install (4) Light Structure System foundations as specified on layout and per Musco foundation design, for poles A7, A8, A9, and C10. High water table/ground water encountered during foundation excavation will be pumped onto field/turf adjacent to pole/foundation location. Spoils from augured foundations to be removed from the site by others. 9. Provide equipment and materials to assemble and erect (4) Light Structure System Poles (A7, A8, A9, and C10). 10. Provide materials and equipment to assemble (9) new HID fixtures on (2) of the new poles, A7 and A Re-install existing light fixtures, remote ECE and new wire harness (from ECE to fixtures) from demolished pole S1 onto new pole C Remove fixtures, ECE, and wire harness from existing pole S4 and install on new pole A Re-install existing light fixtures, remote ECE, and new wire harness (from ECE to fixtures) from demolished pole S3 onto existing pole S Re-aim existing fixtures on poles as needed to meet specified light levels. 15. Re-lamp all existing fixtures. B. Exclusions 1. All items associated with the electrical system infrastructure including all conduit, conductors, pull boxes, contactors, final termination of conductors at pole, etc., to be provided and installed by others. We will coordinate with the electrical contractor so conduit sweeps can be installed in the pole bases prior to backfilling with concrete. Page 3 of 4

5 2. Removal of excavated spoils from the (4) new pole foundations 3. Permits 4. Ground/turf protection from construction vehicles 5. Ground/turf restoration after installation 6. Bonding for any new electrical installation work required to provide electrical power to new light poles. C. Contractor/Electrical Contractor Responsibilities 1. Complete access to the site and pole locations for construction using standard two-wheel drive rubber tire equipment. 2. Locate existing underground utilities not covered by One Call or Dig Alert and mark all irrigation systems and sprinkler heads. Musco or Subcontractor will not be responsible for repairs to unmarked utilities. 3. Survey, locate and mark field reference points (home plate and foul poles) and new pole locations per Musco supplied layout. 4. Provide disposal of spoils from foundation excavation and ground/turf repair and restoration as needed. END OF SECTION Page 4 of 4