1 Photos by Susie Fitzhugh BEX IV Projects Update: Arbor Heights, Genesee Hill, Pinehurst, Thornton Creek

2 Arbor Heights Elementary School Site Plan July 1, 2015 July 10, 2015

3 Arbor Heights Elementary School Elementary School North and South Building - Metal pan-decking and steel edgeform installation is ongoing. South Building - The eastern half of the second floor concrete slab-on-deck was poured. North Building - Remaining foundation walls formed and reinforced.

4 Arbor Heights Elementary School South Building - 2 nd Floor Pan Decking with Reinforcing Mesh August 21, 2015

5 Arbor Heights Elementary School South Building - 2 nd Floor Slab-on-Deck Concrete Pour August 21, 2015

6 Arbor Heights Elementary School South Building - 2 nd Floor Finishing Concrete August 21, 2015

7 Arbor Heights Elementary School North Building - 2 nd Floor Welding Edge Form August 21, 2015

8 Arbor Heights Elementary School Looking South through North Building August 14, 2015

9 Arbor Heights Elementary School View of Arbor Heights Elementary from North West Looking South East August 21, 2015

10 Genesee Hill Elementary School Site Plan 4

11 Genesee Hill Elementary School Area 1: Exterior wall framing and installation of sheathing at levels 1 and 2 on-going; mechanical ductwork install 95% complete; plumbing and electrical rough-in is ongoing; installation of roofing system nearing completion. Area 2: Concrete footing and stem wall foundations on-going, approximately 95% complete; structural steel erection is ongoing; continued roof trusses and bracing install; continued installing metal decking at level 2, mechanical mezzanine and roof. Area 3: Continued to install ductwork at mechanical mezzanine and started at stage; exterior metal framing continues; continued installing roofing system at high roof. Area 4: Installed framing and rigid insulation at skylights; began installing roofing system at roof. Site: Civil contractor began backfilling concrete retaining walls at access stairs to the lower parking lot; concrete slab encroachment removed from NE corner of site.

12 Genesee Hill Elementary School Aerial View

13 Genesee Hill Elementary School Area 1 - North Elevation

14 Genesee Hill Elementary School Area 1 Level 3 - Ongoing Installation of Exterior Framing

15 Genesee Hill Elementary School Area 2 - Ongoing Structural Steel Erection

16 Genesee Hill Elementary School Area 3 Roof Ongoing Installation of PVC Roofing System

17 Genesee Hill Elementary School Area 4 - Ongoing CMU Veneer Installation

18 Genesee Hill Elementary School Area 4 - Roof Framing of Skylight Curbs

19 Genesee Hill Elementary School Backfill at Access Stairs to Lower Parking Lot

20 Hazel Wolf K-8 at Pinehurst Site Plan

21 Hazel Wolf K-8 at Pinehurst Area A2 Classroom Building - Below grade masonry continued, capillary break placed for the building slab on grade. Metal deck installation ongoing on the 3 rd floor. Penthouse structural steel was completed this week. Area A1 - Foundations and stem walls are being damp proofed and on-site underground utilities are continuing. Area C Gym/Special Ed Areas - Concrete pours occurred for the large retaining walls along Pinehurst Way. Foundation and stem wall rebar and concrete work continues at the Kitchen/Music Room and Gym/ Commons areas. Below grade masonry continues at the Gym.

22 Hazel Wolf K-8 at Pinehurst Aerial View from the West

23 Hazel Wolf K-8 at Pinehurst Area A2 - Main Floor Corridor Looking South August 20, 2015

24 Hazel Wolf K-8 at Pinehurst Area A2 - Electrical Room Looking North East August 20, 2015

25 Hazel Wolf K-8 at Pinehurst Area A2 - Penthouse Steel Completed Looking North West August 20, 2015

26 Hazel Wolf K-8 at Pinehurst Area A1 - Damp Proofing Looking North August 21, 2015

27 Hazel Wolf K-8 at Pinehurst Area C - Excavation and Form Work Looking East August 21, 2015

28 Hazel Wolf K-8 at Pinehurst Area C - Geowell Cap Ends (Center Picture) Looking East August 21, 2015

29 Hazel Wolf K-8 at Pinehurst Area C - Stem Wall Rebar and Forming Looking North August 21, 2015

30 Hazel Wolf K-8 at Pinehurst Area C - Placement of Capillary Break August 21, 2015

31 New Thornton Creek Building Key Plan

32 New Thornton Creek Building Area A - Excavation of footings on-going. Concrete footing forming and placement of reinforcing steel in footings on-going. Installed underground plumbing in northeast portion of Building. Area B - Completed underground plumbing and electrical. Placing gravel capillary break, vapor barrier, steel mesh and rebar in preparation for concrete slab pour. Area C - Began erection of structural steel. Site - Completed sanitary sewer from property line to grease interceptor and from Area A north to grease interceptor. Completed grading and excavation of rain garden in southwest corner of site adjacent Area B. Began utility trenching for new electrical service and communication conduits. Off-Site - Completed street crossing and sanitary sewer connection under 40 th Ave NE.

33 New Thornton Creek Building Aerial Photo

34 New Thornton Creek Building Area A - Placing Forms for Footings

35 New Thornton Creek Building Area A - Placing Rebar in Footings

36 New Thornton Creek Building Area A - Conduits for Communication Running North

37 New Thornton Creek Building Area A - Rebar Installed in Elevator Pit

38 New Thornton Creek Building Area B - Vapor Barrier Installed Over Gravel Capillary Break

39 New Thornton Creek Building Area B - Steel Mesh and Rebar Installed

40 New Thornton Creek Building Area C - Steel Erection Begins

41 New Thornton Creek Building Area C - Steel Erection