Buildings Construction Procurement Strategy

Size: px
Start display at page:

Download "Buildings Construction Procurement Strategy"

Transcription

1 Buildings Construction Procurement Strategy Update Q Disclaimer: This presentation is given for information only and cannot be considered as binding Ref. F4E_D_2ABES6 v4.7 1

2 Table of Contents 1. Overview of the ITER Buildings 2. Packaging Strategy 3. Overview of the Procurement Packages 4. Description of remaining Procurement Packages I. Scope II. Procurement process III. Key dates IV. Criteria 2

3 1. Overview of the ITER Buildings NB power supplies Hot Cells Control building Magnet Power Conversion Tokamak Complex Cooling Towers Emergency distribution Electrical Distribution Cryoplant Fast discharge Assembly Hall Site services 3

4 2. Packaging Strategy Procurement of large packages Scope of supply Buildings & associated services Scope in line with design complexity: Industrial buildings and services: Design & Build Main Nuclear structures: Build from Construction Design Buildings with technical specificities: Build from Tender Design Schedule driven by need dates: Preliminary Works: Foundation Tokamak & Site Adaptation Works Works ongoing: Infrastructure, Tokamak Complex and surrounding buildings Next Phase: Neutral Beam Power and Fast Discharge (34, 37,75), Control building (71), Emergency distribution buildings (44-47) Future Phase: Hot Cell complex (21,23,24), Safety Diesel Generators (57-60) 4

5 3. Overview of the Procurement Packages Next phase Future phase Ongoing works 5

6 3. Overview of the Procurement Packages Preparatory Phase: TB00 - Construction of the Tokamak Complex Seismic Isolation Pit, Supply and Installation of Anti-Seismic Bearings Contracts signed/completed TB01 - Site Adaptation Contract signed/completed Completed and ongoing: TBAlpha Galleries and drainage works Contract signed/completed TB02 Long Lead Mechanical Handling Contract signed TB03 Main Civil & Finishing Contract signed TB04 Main M&E/Services Contract signed TB05 D&B Package Contract signed TB06 HV Electrical Equipment Contract signed TB07 D&B Package Contract signed TB08 Site Infrastructure Works Contract terminated TB11 Completion contract Contract signed TB16 Site Infrastructure Works (re-launch of part of the TB08 scope) Contract signed 6

7 3. Overview of the Procurement Packages Next Phases: Ongoing 2018 TB12 Buildings 34, 37 (baseline), 71 non PIC, 75, bridges (options) TB13 Electrical equipment and Buildings 44, 45, 46, 47 New! TB19 Painting, coating for Tokamak complex Procurement planned as of 2019 onward New! Engineering Contract for Hot Cell (21), Radwaste (23) & Personal Access Control Building (24) Procurement in 2019 New! TB18- Civil Works and finishings for B14 tritium building above L2 Procurement in 2019 New! Architect Engineer and Support to the Owner services Procurement in 2019 TB09 (including former TB10 scope) Construction of Hot Cell (21), Radwaste (23) & Personal Access Control Building (24) and 71 PIC Procurement postponed until 2023 TB17 Electrical Diesel Generators, Fuel Tanks and buildings 42, 43, Procurement in

8 4. Description of remaining Procurement Packages The procurement packages listed below are described in the subsequent pages: TB12 Buildings 34, 37 (baseline), 71 non PIC, 75, bridges (options) Call for Expression of Interest launched Q TB13 Electrical equipment and Buildings Call for Tender launched Q TB 19 Painting, coating for Tokamak complex Call for Expression of Interest launched for Q

9 TB12 - Design & Build of Buildings 34, 37, 71, 75 and bridges Scope of Supply: between 50m and 100m Design and Build of Buildings: - 34 (NB Power Supply Building) and 37 (NB High Voltage Power Supply Building), - 71 (Control Building non PIC ) and 75 (Fast Discharge Building). - Plant bridges - Infrastructures works (e.g. deep service trenches in reinforced concrete). 9

10 TB12 - Design & Build of Buildings 34, 37, 71, 75 and bridges Procurement Process: competitive procedure with negotiation Type of contract: FIDIC 10

11 TB12 - Design & Build of Buildings 34, 37, 71, 75 and bridges Key Dates: TB 12 Issue call for Expression Interest Q Receipt Expression of Interest Q Issue of Call For Tender Q Site Visit and information session Q Receipt of Tenders Q Contract Award Q Contract Signature Q

12 TB13 Electrical equipment and Buildings Scope of Supply: < 100m Design and Build of Buildings 44, 45, 46 & 47: Emergency Power Supply Buildings. Design, Supply and installation of emergency power supply electrical components in above mentioned buildings. Foreseen options: Supply and installation of all of the PBS43 cables going out of the B44, B45, B46 and B47 Operation and maintenance from hand over, Integrated commissioning, Off-loading and pre-assembly of all the IP equipment provided by US DA. Procurement Process: Open procedure Input: Tender Design Type of contract: FIDIC 12

13 TB13 Electrical equipment and Buildings 13

14 TB13 Electrical equipment and Buildings Key Dates: TB13 Issue of Pre Information Notice Q Issue of Call For Tender Q Receipt of Tenders Q Contract Award Q Contract Signature Q

15 TB 19 Painting and Coating for Tokamak complex Painting and Coating for Buildings Tokamak Complex [ ] : Baseline Contract: Tokamak building except: Drain Tank Room, SU1 Tank Room, Crane Hall, PF4 penetration. Bioshield internal walls B2 slab out of central pit, B2M level internal walls and slabs Tritium building: Levels B2, B1, L1 15

16 TB 19 Painting and Coating for Tokamak complex Contract Option 1: Tritium building from L2 up to the roof both included. Contract Option 2: Building 74 from B1 up to the roof both included Contract Option 3: Crane Hall in tokamak bldg. Contract Option 4: Bioshield walls Contract Option 5: Concrete reparation considering either injections on cracks or surface treatment for all baseline contract and options. 16

17 TB 19 Painting and Coating for Tokamak complex Key Dates: TB 19 Issue of Pre Information Notice Q Issue call for Expression Interest Q Receipt Expression of Interest Q Issue of Call For Tender Q Receipt of Tenders Q Contract Award Q Contract Signature Q