1 496 Nevada Mesa View Colorado Springs, CO Phone: Fax: Subcontractor Schedule Update C-18J December 20, 2018 To: Subcontractors Attention: Project Managers GHP Project: Mt San Rafael Hospital-Addition and Renovation Subject: Schedule Update 3 Attached is the current schedule for the above referenced project. Please review the dates indicated for your trade and notify us in writing no later than December 28 th, 2018, if you are unable to meet the schedule requirements of the project. If we do not receive a written response from you by this time, you are acknowledging that you are in agreement with the dates and durations indicated in the attached schedule, and the same will become part of your Purchase Order/Subcontract Agreement. Ensure your submittals are approved, necessary materials are obtained and ready for delivery to the project, and the proper crew is available to meet the indicated start and finish dates. Any specific coordination should be conducted with the Project Superintendent. Contact me at or Tim.Gurule@ghphipps.com if you have any questions or require additional information. Sincerely, Tim Gurule GH Phipps Construction Co.

2 aforce Main Schedule Data Date : 19-Dec-18 Run Date: 20-Dec-18 # Activity ID Activity Name RMNG Start Jul-18 A 08-Jun-20 2 PERMITS 7 13-Jul-18 A 02-Jan-19 3 P Trinidad Building Permit Resubmittal 6 13-Jul-18 A 28-Dec-18 4 P Phase 2 Building Permit 1 02-Jan Jan-19* 5 PROCUREMENT Sep-18 A 10-Dec-19 6 P Bidding & Award Subs 3 22-Oct-18 A 21-Dec-18 7 DIVISION 03 - CONCRETE Jan Feb-19 8 REBAR Jan Feb-19 9 P GHP Submittal Review rebar 5 07-Jan-19* 11-Jan P A/E Review ---- rebar Jan Jan P Fabrication -- rebar Jan Feb DIVISION 05 - METALS Jan May STRUCTURAL STEEL Jan May P b GHP Submittal Review -- Structural Steel 5 07-Jan-19* 11-Jan P c A/E Review --Structural Steel Jan Jan P d Fabrication -- Structural Steel Jan Mar P e Ship -- Structural Steel 5 29-Apr-19* 03-May MISC METALS / EMBEDS Jan Mar P a GHP Submittal Review - Anchor Bolts / Embeds 5 07-Jan-19* 11-Jan P a10 A/E Review -- Anchor Bolts / Embeds Jan Jan P a20 Fabrication -- Anchor Bolts / Embeds Jan Feb P a30 Ship -- Anchor Bolts / Embeds 5 25-Feb Mar DIVISION 07 - THERMAL AND MOISTURE PROTECTION Nov-18 A 10-Dec EPDM Nov-18 A 16-Jul P Prepare Submittals / Shops and Submit to GHP -- EPDM 0 26-Nov-18 A 13-Dec-18 A 26 P GHP Submittal Review -- EPDM 2 14-Dec-18 A 20-Dec P A/E Review --EPDM Dec Jan P Fabrication -- EPDM Jun-19* 09-Jul P Ship -- EPDM 5 10-Jul Jul ACM PANELS Nov-18 A 10-Dec P a Prepare Submittals / Shops and Submit to GHP -- Metal Pane 0 26-Nov-18 A 17-Dec-18 A 32 P b GHP Submittal Review -- Metal Panels 4 18-Dec-18 A 26-Dec P c A/E Review --Metal Panels Dec Jan P d Fabrication -- Metal Panels Jan Apr P e Ship -- Metal Panels Apr Apr P ca Field Measure -- Metal Panels 5 14-Oct Oct A1040 Fabrication -- Metal Panels - Corner / Remainng Pieces Oct Dec A1050 Ship -- Metal Panels - Corner / Remainng Pieces 5 04-Dec Dec DIVISION 08 - OPENINGS Nov-18 A 08-Nov CURTAIN WALL Nov-18 A 21-Oct P Prepare Submittals / Shops and Submit to GHP -- Curtain Wall Nov-18 A 18-Feb P GHP Submittal Review -- Curtain Wall 5 19-Feb Feb P A/E Review --Curtain Wall Feb Mar P Fabrication -- Curtain Wall Aug-19* 14-Oct P Ship -- Curtain Wall 5 15-Oct Oct HOLLOW METAL FRAMES Jan Jul P b GHP Submittal Review -- HM Frames 5 07-Jan-19* 11-Jan P c A/E Review --HM Frames Jan Jan-19 Trinidad Building Permit Resubmittal Phase 2 Building Permit Bidding & Award Subs GHP Submittal Review rebar A/E Review ---- rebar Fabrication -- rebar GHP Submittal Review -- Structural Steel A/E Review --Structural Steel Fabrication -- Structural Steel Ship -- Structural Steel GHP Submittal Review - Anchor Bolts / Embeds A/E Review -- Anchor Bolts / Embeds Fabrication -- Anchor Bolts / Embeds Ship -- Anchor Bolts / Embeds Prepare Submittals / Shops and Submit to GHP -- EPDM GHP Submittal Review -- EPDM A/E Review --EPDM Prepare Submittals / Shops and Submit to GHP -- Metal Panels GHP Submittal Review -- Metal Panels A/E Review --Metal Panels Fabrication -- Metal Panels Ship -- Metal Panels Fabrication -- EPDM Ship -- EPDM Prepare Submittals / Shops and Submit to GHP -- Curtain Wall GHP Submittal Review -- Curtain Wall A/E Review --Curtain Wall GHP Submittal Review -- HM Frames A/E Review --HM Frames Field Measure -- Metal Panels Fabrication -- Curtain Wall Ship -- Curtain Wall Fabrication -- Metal Panels - Corner / Remainng Pieces Ship -- Metal Panels - Corner / Remainng Pieces Critical Page 1 of 13

3 49 P d Fabrication -- HM Frames Jun-19* 23-Jul P e Ship -- HM Frames 5 24-Jul Jul HOLLOW METAL DOORS Jan Nov P b GHP Submittal Review -- Doors / Hdw 5 07-Jan-19* 11-Jan P c A/E Review --Doors / Hdw Jan Jan P d Fabrication -- Doors / Hdw Sep-19* 01-Nov P e Ship -- Doors / Hdw 5 04-Nov Nov DIVISION 13 - SPECIAL CONSTRUCTION Jan Oct RF SHIELDING Jan Oct P GHP Submittal Review -- RF Shielding 5 14-Jan-19* 18-Jan P A/E Review --RF Shielding Jan Feb P Fabrication -- RF Shielding Aug-19* 30-Sep P Ship -- RF Shielding 5 01-Oct Oct DIVISION 14 - CONVEYING EQUIPMENT Nov-18 A 13-Nov ELEVATOR Nov-18 A 13-Nov P Prepare Submittals / Shops and Submit to GHP -- Elevator 0 26-Nov-18 A 12-Dec-18 A 65 P GHP Submittal Review -- Elevator Dec-18 A 11-Jan P A/E Review --Elevator Jan Jan P Fabrication -- Elevator Jun-19* 06-Nov P Ship -- Elevator 5 07-Nov Nov DIVISION 23 - HVAC Sep-18 A 28-Aug AHU's Sep-18 A 28-Aug P b10 Approval of AC1 Submittal 3 25-Sep-18 A 21-Dec P d Fabrication -- AHUs May-19* 21-Aug P e Ship -- AHUs 5 22-Aug Aug ATU's May Jul P d Fabrication -- ATUs May-19* 10-Jul P e Ship -- ATUs 5 11-Jul Jul DIVISION 26 - ELECTRICAL Nov-18 A 04-Nov GENERATOR Nov-18 A 04-Nov P A/E Review --Generator 0 26-Nov-18 A 10-Dec-18 A 80 P Revise & Resubmit 6 11-Dec-18 A 28-Dec P Final Approval A/E Review -- Generator 5 02-Jan Jan P Fabrication -- Generator Jul-19* 28-Oct P Ship -- Generator 5 29-Oct Nov SWITCH GEAR Dec-18 A 21-Oct P A/E Review --Switch Gear 0 05-Dec-18 A 11-Dec-18 A 86 P Revise & Resubmit 6 12-Dec-18 A 28-Dec P Final Approval A/E Review - Switch Gear 5 02-Jan Jan P Fabrication -- Switch Gear Jul-19* 14-Oct P Ship -- Switch Gear 5 15-Oct Oct ELECTRICAL DISTRIBUTION PANELS Dec-18 A 09-Sep P A/E Review --Panels 0 05-Dec-18 A 12-Dec-18 A 92 P Revise & Resubmit 6 12-Dec-18 A 28-Dec P Final Approval A/E Review - Panels 5 02-Jan Jan P Fabrication -- Panels Jul-19* 30-Aug P Ship -- Panels 5 03-Sep Sep LIGHT FIXTURES Jul Sep P Fabrication -- Light Fixtures Jul-19* 16-Sep P Ship -- Light Fixtures 5 17-Sep Sep-19 Fabrication -- HM Frames GHP Submittal Review -- Doors / Hdw A/E Review --Doors / Hdw GHP Submittal Review -- RF Shielding A/E Review --RF Shielding Prepare Submittals / Shops and Submit to GHP -- Elevator GHP Submittal Review -- Elevator A/E Review --Elevator Approval of AC1 Submittal A/E Review --Generator Revise & Resubmit Final Approval A/E Review -- Generator A/E Review --Switch Gear Revise & Resubmit Final Approval A/E Review - Switch Gear A/E Review --Panels Revise & Resubmit Final Approval A/E Review - Panels Ship -- HM Frames Fabrication -- ATUs Ship -- ATUs Fabrication -- AHUs Ship -- AHUs Fabrication -- Doors / Hdw Ship -- Doors / Hdw Fabrication -- RF Shielding Fabrication -- Panels Ship -- Panels Ship -- RF Shielding Fabrication -- Elevator Ship -- Elevator Fabrication -- Generator Ship -- Generator Fabrication -- Switch Gear Ship -- Switch Gear Fabrication -- Light Fixtures Ship -- Light Fixtures Critical Page 2 of 13

4 99 MILESTONES Feb May ML.1000 Foundations Start 0 25-Feb ML.1070 SOG Pour 0 08-Jul ML.1090 Steel Start 0 09-Jul ML.1050 Steel Release for Rough-ins 0 23-Aug ML.1100 Exterior Framing Start 0 30-Aug ML.1040 Steel Complete 0 30-Aug ML.1140 Interior Framing Start 0 14-Oct ML.1110 Roof Complete 0 08-Nov ML.1150 Drywall Start 0 12-Nov ML.1130 Windows Complete 0 10-Dec ML.1160 Prime / 1st Coat Start 0 12-Dec ML.1170 Acst Grid Start 0 20-Dec ML.1180 Bal of Clg Tile Complete 0 11-Mar ML.1190 Flooring Complete 0 25-Mar ML.1200 TAB / Commissioning Start 0 31-Mar ML.1210 Substantial Completion 0 22-May ML.1220 Project Completion 0 22-May CONSTRUCTION Nov-18 A 08-Jun C Phase 2A Construction Nov-18 A 18-Nov C OVERALL PHASE 2 Construction Nov-18 A 22-May C Phase 2B Construction Jan May C Phase 2A Completion 0 18-Nov C Phase 2C Construction Jan Apr C Phase 2C Completion 0 07-Apr-20* 124 C Phase 2B Completion 0 22-May-20* 125 C OVERALL PROJECT COMPLETE 0 22-May-20* 126 PC.PH OWNER - FF&E Installation / Staff and Stock May Jun PC.PH OWNER Beneficial Occupancy / First Patient 0 08-Jun PHASE 2 CONSTRUCTION Nov-18 A 22-May PH2.C Demo of Existing East Patient Wing Jan Feb IMPACTS Nov-18 A 25-Jan Update Nov-18 A 18-Jan IMPACT Nov-18 A 18-Jan IMP IMPACT RECAP - RFI EM Power Circuits in Ext. Bldg Nov-18 A 18-Jan Update Nov-18 A 10-Jan IMPACT Nov-18 A 18-Dec-18 A 136 IMP IMPACT RECAP - Professional Complex Fiber Re-route (no longer needed) 0 19-Nov-18 A 18-Dec-18 A 137 IMPACT Nov-18 A 10-Jan IMP IMPACT RECAP - Interior Building Shoring (Grid x10) Nov-18 A 10-Jan IMP Submit RFI - Did not Need 0 28-Nov-18 A 10-Dec-18 A 140 IMP Finalize Shoring Design and Pricing 0 10-Dec-18 A 18-Dec-18 A 141 IMP Selective Demo 3 11-Dec-18 A 21-Dec IMP Issue Subcontract 1 19-Dec Dec IMP Install Shoring Dec Jan Update Dec-18 A 25-Jan IMPACT Dec-18 A 25-Jan IMP IMPACT RECAP - Concrete slab mastic ACM Dec-18 A 25-Jan IMP Prepare Change Order Proposal 0 10-Dec-18 A 14-Dec-18 A 148 IMP Owner Decision to do Abatement or Approve 3 17-Dec-18 A 21-Dec-18 Foundations Start Demo of Existing East Patient Wing IMPACT RECAP - RFI EM Power Circuits in Ext. Bldg SOG Pour Steel Start IMPACT RECAP - Professional Complex Fiber Re-route (no longer needed) IMPACT RECAP - Interior Building Shoring (Grid x10) Submit RFI - Did not Need Finalize Shoring Design and Pricing Selective Demo Issue Subcontract Install Shoring IMPACT RECAP - Concrete slab mastic ACM Prepare Change Order Proposal Owner Decision to do Abatement or Approve Steel Release for Rough-ins Exterior Framing Start Steel Complete Interior Framing Start Roof Complete Drywall Start Windows Complete Prime / 1st Coat Start Acst Grid Start Phase 2A Construction Phase 2A Completion Bal of Clg Tile Complete Flooring Complete TAB / Commissioning Start Substantial Completion Project Completion Phase 2C Construction Phase 2C Completion OVERALL PHASE 2 Construction Phase 2B Construction Phase 2B Completion OVERALL PROJECT COMPLETE OWNER - FF&E Installation / Staff a OWNER Beneficial Occupancy / Firs Critical Page 3 of 13

5 149 IMP Abatement Permit Dec Jan IMP Abatement of ACM Jan Jan PHASE 2A Jan Nov LEVEL 1 - NEW IT ROOM Aug Nov IR.2A Temp Partitions 3 13-Aug Aug IR.2A Demo 3 16-Aug Aug IR.2A Conduits from MDF to New IDF Aug Aug IR.2A Framing 2 21-Aug Aug IR.2A Set HM Frame 1 21-Aug Aug IR.2A Hang Sheet Rock Outside Walls 1 23-Aug Aug IR.2A Sawcut / Core Drill 3 23-Aug Aug IR.2A Tape & / Prime & 1st Coat - Outside Walls 2 26-Aug Aug IR.2A Hang Door / Hdw 1 27-Aug Aug IR.2A Electrical / Tele Data In Wall Rough 5 28-Aug Sep IR.2A Mech Rough / Split System 5 28-Aug Sep IR.2A Remove Temp Partitions 2 28-Aug Aug IR.2A In Wall Rough Inspection 1 05-Sep Sep IR.2A Hang Sheet Rock Inside Walls 1 06-Sep Sep IR.2A Tape & / Prime & 1st Coat 2 09-Sep Sep IR.2A Flooring 2 11-Sep Sep IR.2A Cable Tray 5 13-Sep Sep IR.2A Pull Cable / Term Sep Oct IR.2A Set Racks 5 18-Oct Oct IR.2A Final Connections Oct Nov IR.2A IT Room Closeout 7 08-Nov Nov LEVEL 1 & 2 - WINDOWS & INFILL Jan Feb IR.2A Temp Partition 3 03-Jan Jan IR.2A Erect Scaffolding 3 08-Jan Jan IR.2A Demo Windows 5 11-Jan Jan IR.2A Infill 5 18-Jan Jan IR.2A es 5 25-Jan Jan IR.2A Remove Partitions 3 01-Feb Feb IR.2A Window & Infill Closeout 5 06-Feb Feb PHASE 2B Nov-18 A 22-May CHANGE ORDER - Existing EM Power Circuits Re-Feed Nov-18 A 18-Jan CO Re-Feed of Existing EM Power Circuits Nov-18 A 18-Jan SITEWORK Jan Feb SW UG Site Utilities Jan Mar SW Fine Grade Site 5 18-Feb Feb SW Hardscapes Jan Feb SW Landscapes Jan Feb A1030 Patch Hardscapes (exterior skin) 7 14-Feb Feb FOUNDATION Feb Jul FO Basement Excavation 7 25-Feb Mar FO Underpinning at Existing Building 3 04-Mar Mar FO UG Storm & Tie-in 5 06-Mar Mar FO ' Overex 3 07-Mar Mar FO Elev Pit Mat Slab & Elev Stem Walls 7 12-Mar Mar FO Damproofing at Elev Pit 1 21-Mar Mar FO CMU Walls at Elev Pit 3 21-Mar Mar-19 Abatement Permit Abatement of ACM Temp Partition Erect Scaffolding Demo Windows Infill es Remove Partitions Window & Infill Closeout Re-Feed of Existing EM Power Circuits UG Site Utilities Fine Grade Site Basement Excavation Underpinning at Existing Building UG Storm & Tie-in 3' Overex Elev Pit Mat Slab & Elev Stem Walls Damproofing at Elev Pit CMU Walls at Elev Pit Temp Partitions Demo Conduits from MDF to New IDF Framing Set HM Frame Hang Sheet Rock Outside Walls Sawcut / Core Drill Tape & / Prime & 1st Coat - Outside Walls Hang Door / Hdw Electrical / Tele Data In Wall Rough Mech Rough / Split System Remove Temp Partitions In Wall Rough Inspection Hang Sheet Rock Inside Walls Tape & / Prime & 1st Coat Flooring Cable Tray Pull Cable / Term Set Racks Final Connections IT Room Closeout Hardscapes Landscapes Patch Hardscapes (exterior skin) Critical Page 4 of 13

6 199 FO Backfill at Elev Pit 1 22-Mar Mar FO Basement 18" Slab 7 26-Mar Apr FO Basement Walls 7 04-Apr Apr FO Damproofing 3 15-Apr Apr FO Perimeter Drain 5 15-Apr Apr FO Backfill 3 18-Apr Apr FO Over Ex / Struc Fill 5 22-Apr Apr FO Form / Pour Spread / Pad Footings & walls Apr May FO Backfill for Beams 2 16-May May FO Form / Pour Beams May Jun FO MEP Sleeves for Beams 5 20-May May FO UG Plumbing May Jun FO UG Electrical May Jun FO Vapor Barrier 5 12-Jun Jun FO Backfill & Fine Grade 6 14-Jun Jun FO Form / Rebar / Pour Stuctural Slab Jun Jul STRUCTURE Apr Sep ST CMU Core Walls - Elev & West Stair Apr May ST CMU Walls CUP May Jun ST CMU Core Walls - East Stair Jun Jul ST Erect Structural Steel Jul Jul ST Metal Deck & Detail Jul Aug ST MEP Sleeves (Box outs / Depressions) 5 12-Aug Aug ST Erect Canopy 5 13-Aug Aug ST Form / Pour SOD 5 16-Aug Aug ST Erect Stairs / Landings 5 20-Aug Aug ST MEP Equipment Pads 5 23-Aug Aug ST Spray Fireproofing Perimeter Steel Aug Sep ST Erect Roof Screen Wall 4 27-Aug Aug ENCLOSURE Aug Jan ROOF Sep Nov EN.R Spray Foam Insulation 5 23-Sep Sep EN.R Roof Blocking Sep Oct EN.R Dens Deck at Parapet 5 30-Sep Oct EN.R Roof System Oct Nov EXTERIOR SKIN Aug Jan EN Exterior Framing Aug Sep EN Sheathing Sep Oct EN Fluid Applied / Vapor Barrier Oct Oct EN Z Furring / Rigid Insulation Oct Nov EN Storefront Oct Dec EN Curtain Wall Oct Nov EN Stone Veneer Nov Dec EN Metal Panels Nov Jan EN Stucco Dec Jan EN Sunshades Jan Jan EN Metal Panels - Corners / Remaining Jan Jan EMERGECY DEPARTMENT Aug May ROUGH INS Aug Dec RO.ED Layout / Hangers / Top Track 8 23-Aug Sep-19 Backfill at Elev Pit Basement 18" Slab Basement Walls Damproofing Perimeter Drain Backfill Over Ex / Struc Fill Form / Pour Spread / Pad Footings & walls Backfill for Beams Form / Pour Beams MEP Sleeves for Beams UG Plumbing UG Electrical Vapor Barrier Backfill & Fine Grade Form / Rebar / Pour Stuctural Slab CMU Core Walls - Elev & West Stair CMU Walls CUP CMU Core Walls - East Stair Erect Structural Steel Metal Deck & Detail MEP Sleeves (Box outs / Depressions) Erect Canopy Form / Pour SOD Erect Stairs / Landings MEP Equipment Pads Spray Fireproofing Perimeter Steel Erect Roof Screen Wall Spray Foam Insulation Roof Blocking Dens Deck at Parapet Exterior Framing Sheathing Roof System Fluid Applied / Vapor Barrier Z Furring / Rigid Insulation Curtain Wall Layout / Hangers / Top Track Storefront Stone Veneer Metal Panels Stucco Sunshades Metal Panels - Corners / Remaining Critical Page 5 of 13

7 249 RO.ED Med Eqpt Supports 5 23-Aug Aug RO.ED Spray Fireproofing 5 09-Sep Sep RO.ED Hang ATU's / FCUs / FTRs Sep Sep RO.ED OH Waste / Vent Rough 8 16-Sep Sep RO.ED Hang Ductwork / Branch Sep Oct RO.ED Set HM Frames 5 07-Oct Oct RO.ED OH Electrical Rough Oct Oct RO.ED Frame Walls Oct Oct RO.ED OH HVAC Piping Rough Oct Oct RO.ED OH DCW / DHW Rough Oct Oct RO.ED OH Fire Prot Main Rough 8 14-Oct Oct RO.ED OH Med Gas Rough Oct Oct RO.ED OH Fire Prot Branch Piping Rough 5 24-Oct Oct RO.ED Electrical Rough Inspection 1 28-Oct Oct RO.ED Test / Inspect HVAC Piping 2 28-Oct Oct RO.ED Final Conn - ATU's (HVAC, ELEC, TC) 5 28-Oct Nov RO.ED Plumbing Rough Walls Oct Nov RO.ED Wall Backing 5 28-Oct Nov RO.ED Sound Insulation Walls 5 28-Oct Nov RO.ED Electrical In Wall Rough Oct Nov RO.ED In Wall Med Gas Rough 8 28-Oct Nov RO.ED Insul HVAC Piping 5 30-Oct Nov RO.ED Frame D.W. Ceiling & Soffits 5 31-Oct Nov RO.ED Rough Elec to D.W. Clgs 5 07-Nov Nov RO.ED Rough GRD's to D.W. Clgs 5 07-Nov Nov RO.ED Adjust Fire Protect Heads to D.W. Clgs 5 07-Nov Nov RO.ED Med Gas Certification 2 07-Nov Nov RO.ED Rough Wall Inspections 1 11-Nov Nov RO.ED Hang Sheet Rock Nov Dec RO.ED Above Clg Rough Inspections 1 14-Nov Nov RO.ED Hang Sheet Rock Clgs / Soffits 5 05-Dec Dec FINISHES Nov Mar IN.ED Tape & Nov Dec IN.ED Prime & 1st Coat Dec Dec RO.ED OH Tele / Data / Security / Fire Alarm Rough 8 12-Dec Dec IN.ED ACT Celing Grid Dec Jan IN.ED Tile and Grout Floor & Walls Dec Jan IN.ED Wood Panel Ceiling Dec Jan IN.ED ICU / CCU Doors 5 27-Dec Jan IN.ED Install Curtain Track 5 07-Jan Jan IN.ED Lights at Grid 8 14-Jan Jan IN.ED GRD's at Grid 8 14-Jan Jan IN.ED Adj. Fire Sprinkler Heads at Grid 5 14-Jan Jan IN.ED Above Ceiling Inspection 1 24-Jan Jan IN.ED Elec / Tele Data Trim 5 24-Jan Jan IN.ED Intital Install Ceiling Tile Jan Feb IN.ED Casework / Millwork Feb Feb IN.ED Lockers 5 04-Feb Feb IN.ED LVT 2 10-Feb Feb IN.ED Sheet Vinyl - Rooms Feb Feb-20 Med Eqpt Supports Spray Fireproofing Hang ATU's / FCUs / FTRs OH Waste / Vent Rough Hang Ductwork / Branch Set HM Frames OH Electrical Rough Frame Walls OH HVAC Piping Rough OH DCW / DHW Rough OH Fire Prot Main Rough OH Med Gas Rough OH Fire Prot Branch Piping Rough Electrical Rough Inspection Test / Inspect HVAC Piping Final Conn - ATU's (HVAC, ELEC, TC) Plumbing Rough Walls Wall Backing Sound Insulation Walls Electrical In Wall Rough In Wall Med Gas Rough Insul HVAC Piping Frame D.W. Ceiling & Soffits Rough Elec to D.W. Clgs Rough GRD's to D.W. Clgs Adjust Fire Protect Heads to D.W. Clgs Med Gas Certification Rough Wall Inspections Hang Sheet Rock Above Clg Rough Inspections Hang Sheet Rock Clgs / Soffits Tape & Prime & 1st Coat OH Tele / Data / Security / Fire Alarm Rough ACT Celing Grid Tile and Grout Floor & Walls Wood Panel Ceiling ICU / CCU Doors Install Curtain Track Lights at Grid GRD's at Grid Adj. Fire Sprinkler Heads at Grid Above Ceiling Inspection Elec / Tele Data Trim Intital Install Ceiling Tile Casework / Millwork Lockers LVT Sheet Vinyl - Rooms Critical Page 6 of 13

8 299 IN.ED Carpet 3 12-Feb Feb IN.ED Hang Doors / Hdw Feb Mar IN.ED Plumbing Fixtures & Final Trim Feb Mar IN.ED Interior Glazing 5 27-Feb Mar IN.ED Sheet Vinyl - Corridors 5 03-Mar Mar IN.ED Toilet Acc Mar Mar IN.ED Final Paint 5 10-Mar Mar IN.ED Wall & Corner Guards 5 10-Mar Mar IN.ED Interior Signage 5 17-Mar Mar IN.ED Window Curtains / Blinds 5 17-Mar Mar IN.ED Install Curtain 2 17-Mar Mar IN.ED GHP Pre Punch / Clean up 5 24-Mar Mar IN.ED Balance of Ceiling Tile 5 24-Mar Mar EMERGENCY CLOSEOUT Mar May PC.ED TAB 5 31-Mar Apr PC.ED A/E Punch 2 31-Mar Apr PC.ED Fix Punchlist Apr Apr PC.ED Final Inpsections 5 07-Apr Apr PC.ED Weather Days Apr May PC.ED ED Completion 0 07-May IMAGING DEPT Sep May MAJOR MECHANICAL Nov Dec MM.IM Set & Hook up Exhaust Fans Nov Dec ROUGH INS Sep Jan RO.IM Layout / Hangers / Top Track 8 05-Sep Sep RO.IM Med Eqpt Supports 5 05-Sep Sep RO.IM Spray Fireproofing 5 28-Oct Nov RO.IM Hang ATU's / FCUs / FTRs 5 04-Nov Nov RO.IM OH Waste / Vent Rough 5 04-Nov Nov RO.IM Hang Ductwork / Branch 8 11-Nov Nov RO.IM Set HM Frames 5 14-Nov Nov RO.IM OH Electrical Rough Nov Dec RO.IM Frame Walls Nov Dec RO.IM OH HVAC Piping Rough 8 21-Nov Dec RO.IM OH DCW / DHW Rough 8 21-Nov Dec RO.IM OH Fire Prot Main Rough 8 21-Nov Dec RO.IM OH Med Gas Rough 8 21-Nov Dec RO.IM Electrical Rough Inspection 1 04-Dec Dec RO.IM Test / Inspect HVAC Piping 2 05-Dec Dec RO.IM Final Conn - ATU's (HVAC, ELEC, TC) 5 05-Dec Dec RO.IM OH Fire Prot Branch Piping Rough 5 05-Dec Dec RO.IM In Wall Med Gas Rough 8 05-Dec Dec RO.IM Insul HVAC Piping 5 09-Dec Dec RO.IM Plumbing Rough Walls 8 09-Dec Dec RO.IM Wall Backing 5 09-Dec Dec RO.IM Sound Insulation Walls 5 09-Dec Dec RO.IM Electrical In Wall Rough 8 09-Dec Dec RO.IM Frame D.W. Ceiling & Soffits 5 12-Dec Dec RO.IM Med Gas Certification 2 17-Dec Dec RO.IM Rough Wall Inspections 1 19-Dec Dec-19 Carpet Layout / Hangers / Top Track Med Eqpt Supports Spray Fireproofing Set & Hook up Exhaust Fans Hang ATU's / FCUs / FTRs OH Waste / Vent Rough Hang Ductwork / Branch Set HM Frames OH Electrical Rough Frame Walls OH HVAC Piping Rough OH DCW / DHW Rough OH Fire Prot Main Rough OH Med Gas Rough Electrical Rough Inspection Test / Inspect HVAC Piping Hang Doors / Hdw Plumbing Fixtures & Final Trim Interior Glazing Sheet Vinyl - Corridors Toilet Acc. Final Paint Wall & Corner Guards Interior Signage Window Curtains / Blinds Install Curtain GHP Pre Punch / Clean up Balance of Ceiling Tile TAB Final Conn - ATU's (HVAC, ELEC, TC) OH Fire Prot Branch Piping Rough In Wall Med Gas Rough Insul HVAC Piping Plumbing Rough Walls Wall Backing Sound Insulation Walls Electrical In Wall Rough Frame D.W. Ceiling & Soffits Med Gas Certification Rough Wall Inspections A/E Punch Fix Punchlist Final Inpsections Weather Days ED Completion Critical Page 7 of 13

9 349 RO.IM Rough Elec to D.W. Clgs 5 19-Dec Dec RO.IM Rough GRD's to D.W. Clgs 5 19-Dec Dec RO.IM Adjust Fire Protect Heads to D.W. Clgs 5 19-Dec Dec RO.IM Hang Sheet Rock Dec Jan RO.IM Above Clg Rough Inspections 1 27-Dec Dec RO.IM Hang Sheet Rock Clgs / Soffits 5 07-Jan Jan FINISHES Dec Apr IN.IM Tape & Dec Jan IN.IM Prime & 1st Coat Jan Jan IN.IM OH Tele / Data / Security / Fire Alarm Rough 8 08-Jan Jan IN.IM ACT Celing Grid Jan Jan IN.IM Tile and Grout Floor & Walls 8 22-Jan Jan IN.IM Install Curtain Track 5 23-Jan Jan IN.IM Lights at Grid 8 30-Jan Feb IN.IM GRD's at Grid 8 30-Jan Feb IN.IM Adj. Fire Sprinkler Heads at Grid 5 30-Jan Feb IN.IM Above Ceiling Inspection 1 11-Feb Feb IN.IM Elec / Tele Data Trim 5 11-Feb Feb IN.IM Intital Install Ceiling Tile Feb Feb IN.IM Casework / Millwork Feb Mar IN.IM Carpet 5 26-Feb Mar IN.IM Sheet Vinyl - Rooms Feb Mar IN.IM Hang Doors / Hdw 8 05-Mar Mar IN.IM Plumbing Fixtures & Final Trim 8 05-Mar Mar IN.IM Interior Glazing 5 12-Mar Mar IN.IM Sheet Vinyl - Corridors 5 16-Mar Mar IN.IM Toilet Acc Mar Mar IN.IM Final Paint 5 23-Mar Mar IN.IM Wall & Corner Guards 5 23-Mar Mar IN.IM Balance of Ceiling Tile 5 27-Mar Apr IN.IM Interior Signage 5 27-Mar Apr IN.IM Window Curtains / Blinds 5 27-Mar Apr IN.IM Install Curtain 2 30-Mar Mar IN.IM GHP Pre Punch / Clean up 5 03-Apr Apr RADIOLOGY / NUC MED Dec Feb IM.XR Interior Framing 2 09-Dec Dec IM.XR OH MEP Rough 4 09-Dec Dec IM.XR In Wall Rough Ins 4 11-Dec Dec IM.XR Soffit / Ceiling Framing 2 13-Dec Dec IM.XR Hang Lead Lined Sheet Rock 8 17-Dec Dec IM.XR Lead Lined Test / Inspect 2 30-Dec Dec IM.XR Tape & 8 02-Jan Jan IM.XR Prime & 1st Coat 5 14-Jan Jan IM.XR Flooring 4 21-Jan Jan IM.XR Casework / Millwork 4 21-Jan Jan IM.XR Install XRAY 1 27-Jan Jan IM.XR Install Control Equipment 8 28-Jan Feb IM.XR Final Connections 5 07-Feb Feb MRI Dec Feb IM.MRI RF Shielding Dec Dec-19 Rough Elec to D.W. Clgs Rough GRD's to D.W. Clgs Adjust Fire Protect Heads to D.W. Clgs Hang Sheet Rock Above Clg Rough Inspections Interior Framing OH MEP Rough Hang Sheet Rock Clgs / Soffits Tape & In Wall Rough Ins Prime & 1st Coat OH Tele / Data / Security / Fire Alarm Rough ACT Celing Grid Soffit / Ceiling Framing Tile and Grout Floor & Walls Install Curtain Track Lights at Grid GRD's at Grid Adj. Fire Sprinkler Heads at Grid Above Ceiling Inspection Elec / Tele Data Trim Intital Install Ceiling Tile Casework / Millwork Carpet Hang Lead Lined Sheet Rock Lead Lined Test / Inspect RF Shielding Tape & Prime & 1st Coat Flooring Casework / Millwork Install XRAY Sheet Vinyl - Rooms Hang Doors / Hdw Plumbing Fixtures & Final Trim Interior Glazing Sheet Vinyl - Corridors Toilet Acc. Final Paint Wall & Corner Guards Balance of Ceiling Tile Interior Signage Window Curtains / Blinds Install Curtain Install Control Equipment Final Connections GHP Pre Punch / Clean up Critical Page 8 of 13

10 399 IM.MRI RF Shield Testing 2 23-Dec Dec IM.MRI Interior Framing 5 26-Dec Jan IM.MRI OH MEP Rough / Cooling Piping 3 26-Dec Dec IM.MRI In Wall Rough Ins 3 03-Jan Jan IM.MRI Soffit / Ceiling Framing 2 03-Jan Jan IM.MRI Luminous Ceiling 2 03-Jan Jan IM.MRI Hang Sheet Rock 4 08-Jan Jan IM.MRI Prime & 1st Coat 2 14-Jan Jan IM.MRI Casework / Millwork 4 16-Jan Jan IM.MRI Access Floor 5 16-Jan Jan IM.MRI Flooring 4 23-Jan Jan IM.MRI Remove Knock Out Panels 5 29-Jan Feb IM.MRI Install MRI 1 05-Feb Feb IM.MRI Install MRI Equipment Feb Feb IM.MRI Install Control Equipment Feb Feb IM.MRI Reinstall Knock Out Panels 5 06-Feb Feb IM.MRI Final Connections 5 20-Feb Feb IMAGING CLOSEOUT Apr May PC.IM TAB Apr Apr PC.IM A/E Punch 5 10-Apr Apr PC.IM Final Inpsections Apr Apr PC.IM Fix Punchlist Apr Apr PC.IM Weather Days May May PC.IM Imaging Completion 0 22-May PCU Aug May MAJOR MECH Aug Mar MM.PCU Roof Curbs 5 30-Aug Sep MM.PCU Set RTUs 5 11-Nov Nov MM.PCU Final Connections Nov Dec MM.PCU Confirm Power to Units & Eqpt Dec Dec MM.PCU Control Tie Ins Dec Jan MM.PCU Factory Startup & Testing 5 17-Jan Jan MM.PCU Point to Point Connections 5 17-Mar Mar ROUGHINS Sep Feb RO.PCU Layout / Hangers / Top Track 8 17-Sep Sep RO.PCU Med Eqpt Supports 5 17-Sep Sep RO.PCU Spray Fireproofing 5 04-Nov Nov RO.PCU Hang ATU's / FCUs / FTRs Nov Nov RO.PCU OH Waste / Vent Rough 8 11-Nov Nov RO.PCU Hang Ductwork / Branch Nov Dec RO.PCU Set HM Frames 5 03-Dec Dec RO.PCU OH Electrical Rough Dec Dec RO.PCU OH Med Gas Rough Dec Dec RO.PCU Frame Walls Dec Dec RO.PCU OH HVAC Piping Rough Dec Dec RO.PCU OH DCW / DHW Rough Dec Dec RO.PCU OH Fire Prot Main Rough 8 10-Dec Dec RO.PCU Electrical Rough Inspection 1 19-Dec Dec RO.PCU Plumbing Rough Walls Dec Jan RO.PCU Electrical In Wall Rough Dec Jan-20 RF Shield Testing Roof Curbs Set RTUs Layout / Hangers / Top Track Med Eqpt Supports Spray Fireproofing Interior Framing OH MEP Rough / Cooling Piping In Wall Rough Ins Soffit / Ceiling Framing Luminous Ceiling Hang Sheet Rock Prime & 1st Coat Casework / Millwork Access Floor Flooring Final Connections Remove Knock Out Panels Install MRI Install MRI Equipment Install Control Equipment Reinstall Knock Out Panels Final Connections Confirm Power to Units & Eqpt. Control Tie Ins Hang ATU's / FCUs / FTRs OH Waste / Vent Rough Hang Ductwork / Branch Set HM Frames OH Electrical Rough OH Med Gas Rough Frame Walls Factory Startup & Testing OH HVAC Piping Rough OH DCW / DHW Rough OH Fire Prot Main Rough Electrical Rough Inspection Plumbing Rough Walls Electrical In Wall Rough TAB A/E Punch Final Inpsections Fix Punchlist Weather Days Point to Point Connections Imaging Completion Critical Page 9 of 13

11 449 RO.PCU OH Fire Prot Branch Piping Rough 5 20-Dec Dec RO.PCU In Wall Med Gas Rough 8 20-Dec Jan RO.PCU Test / Inspect HVAC Piping 2 24-Dec Dec RO.PCU Final Conn - ATU's (HVAC, ELEC, TC) 5 24-Dec Dec RO.PCU Wall Backing 5 24-Dec Dec RO.PCU Sound Insulation Walls 5 24-Dec Dec RO.PCU Insul HVAC Piping 5 27-Dec Jan RO.PCU Frame D.W. Ceiling & Soffits 5 30-Dec Jan RO.PCU Med Gas Certification 2 03-Jan Jan RO.PCU Rough Wall Inspections 1 06-Jan Jan RO.PCU Hang Sheet Rock Jan Jan RO.PCU Rough Elec to D.W. Clgs 5 07-Jan Jan RO.PCU Rough GRD's to D.W. Clgs 5 07-Jan Jan RO.PCU Adjust Fire Protect Heads to D.W. Clgs 5 07-Jan Jan RO.PCU Above Clg Rough Inspections 1 14-Jan Jan RO.PCU Hang Sheet Rock Clgs / Soffits 5 16-Jan Jan RO.PCU OH Tele / Data / Security / Fire Alarm Rough 8 24-Jan Feb FINISHES Jan Apr IN.PCU Tape & Jan Jan IN.PCU Prime & 1st Coat Jan Feb IN.PCU ACT Celing Grid Jan Feb IN.PCU Tile and Grout Floor & Walls (Shower bases) Feb Feb IN.PCU Wood Panel Ceiling Feb Feb IN.PCU ICU / CCU Doors 5 07-Feb Feb IN.PCU Install Curtain Track 5 11-Feb Feb IN.PCU Lights at Grid 8 17-Feb Feb IN.PCU GRD's at Grid 8 17-Feb Feb IN.PCU Adj. Fire Sprinkler Heads at Grid 5 18-Feb Feb IN.PCU Above Ceiling Inspection 1 27-Feb Feb IN.PCU Intital Install Ceiling Tile Feb Mar IN.PCU Elec / Tele Data Trim 5 27-Feb Mar IN.PCU Casework / Millwork Mar Mar IN.PCU Lockers 5 05-Mar Mar IN.PCU LVT 2 11-Mar Mar IN.PCU Sheet Vinyl - Rooms Mar Mar IN.PCU Carpet 3 13-Mar Mar IN.PCU Hang Doors / Hdw Mar Apr IN.PCU Plumbing Fixtures & Final Trim Mar Apr IN.PCU Interior Glazing 5 30-Mar Apr IN.PCU Sheet Vinyl - Corridors 5 31-Mar Apr IN.PCU Toilet Acc Apr Apr IN.PCU Final Paint 5 06-Apr Apr IN.PCU Window Curtains / Blinds 5 06-Apr Apr IN.PCU Wall & Corner Guards 5 07-Apr Apr IN.PCU Balance of Ceiling Tile 5 10-Apr Apr IN.PCU Interior Signage 5 13-Apr Apr IN.PCU Install Curtain 2 13-Apr Apr IN.PCU GHP Pre Punch / Clean up 5 15-Apr Apr ELEVATOR Nov Dec SP.PCU Install Elevator - Rails, Entrances, Infill Nov Dec-19 OH Fire Prot Branch Piping Rough In Wall Med Gas Rough Test / Inspect HVAC Piping Final Conn - ATU's (HVAC, ELEC, TC) Wall Backing Sound Insulation Walls Insul HVAC Piping Frame D.W. Ceiling & Soffits Med Gas Certification Rough Wall Inspections Hang Sheet Rock Rough Elec to D.W. Clgs Rough GRD's to D.W. Clgs Adjust Fire Protect Heads to D.W. Clgs Above Clg Rough Inspections Hang Sheet Rock Clgs / Soffits OH Tele / Data / Security / Fire Alarm Rough Tape & Prime & 1st Coat ACT Celing Grid Tile and Grout Floor & Walls (Shower bases) Wood Panel Ceiling ICU / CCU Doors Install Curtain Track Lights at Grid GRD's at Grid Adj. Fire Sprinkler Heads at Grid Above Ceiling Inspection Intital Install Ceiling Tile Elec / Tele Data Trim Casework / Millwork Lockers LVT Sheet Vinyl - Rooms Carpet Install Elevator - Rails, Entrances, Infill Hang Doors / Hdw Plumbing Fixtures & Final Trim Interior Glazing Sheet Vinyl - Corridors Toilet Acc. Final Paint Window Curtains / Blinds Wall & Corner Guards Balance of Ceiling Tile Interior Signage Install Curtain GHP Pre Punch / Clean up Critical Page 10 of 13

12 499 SP.PCU Elevator Adjustment & Inspections 5 16-Dec Dec PCU CLOSEOUT Apr May PC.PCU TAB 5 17-Apr Apr PC.PCU A/E Punch 2 22-Apr Apr PC.PCU Final Inpsections 5 24-Apr Apr PC.PCU Fix Punchlist 5 24-Apr Apr PC.PCU Weather Days May May PC.PCU PCU Completion 0 22-May CUP Nov Mar ROUGHINS Nov Feb RO.CUP Layout / Top Track / Hangers 5 04-Nov Nov RO.CUP Form + Pour Equipment Pads 4 11-Nov Nov RO.CUP Waste / Vent rough 5 11-Nov Nov RO.CUP Set Boilers 3 15-Nov Nov RO.CUP Set Panels 5 20-Nov Nov RO.CUP Set Pumps 2 20-Nov Nov RO.CUP HVAC Piping Nov Dec RO.CUP Plumbing Rough Nov Dec RO.CUP Natural Gas Rough Nov Dec RO.CUP Medical Air Piping Rough Nov Dec RO.CUP Set Tanks & Misc Eqpt Nov Dec RO.CUP Elec Rough - Equipment Nov Dec RO.CUP Pull Wire / Term Nov Dec RO.CUP Temp Control Rough Dec Jan RO.CUP Fire Protection Dec Jan RO.CUP Final Connections Dec Jan RO.CUP Factory Startup & Testing 6 21-Jan Jan RO.CUP Point to Point 5 29-Jan Feb FINISHES Dec Jan IN.CUP Light Fixtures / Trim 5 10-Dec Dec IN.CUP Casework / Millwork 5 14-Jan Jan CUP CLOSEOUT Jan Mar PC.CUP A/E Punch 5 21-Jan Jan PC.CUP Fix Punchlist Jan Feb PC.CUP TAB Feb Feb PC.CUP Final Inpsections 5 19-Feb Feb PC.CUP Weather Days Feb Mar PC.CUP CUP Completion 0 18-Mar BASEMENT RENOVATION Jul Jan ELECTRICAL ROOM Jul Jan IR.2B Demo 3 16-Jul Jul IR.2B Masonry Walls 5 19-Jul Jul IR.2B Install Transformer - BY OWNER Jul Aug IR.2B Metal Stud Framing 3 26-Jul Jul IR.2B Hang Sheet Rock 3 31-Jul Aug IR.2B Tape & 3 05-Aug Aug IR.2B Prime & 1st Coat 3 08-Aug Aug IR.2B Electrical Switch Gear Oct Nov IR.2B Install Generator Nov Jan IR.2B Switchover 3 11-Jan Jan-20 Elevator Adjustment & Inspections Demo Masonry Walls Install Transformer - BY OWNER Metal Stud Framing Hang Sheet Rock Tape & Prime & 1st Coat Layout / Top Track / Hangers Form + Pour Equipment Pads Waste / Vent rough Set Boilers Set Panels Set Pumps HVAC Piping Plumbing Rough Natural Gas Rough Medical Air Piping Rough Set Tanks & Misc Eqpt. Elec Rough - Equipment Pull Wire / Term Temp Control Rough Fire Protection Final Connections Light Fixtures / Trim Electrical Switch Gear Factory Startup & Testing Point to Point Casework / Millwork A/E Punch Fix Punchlist TAB Install Generator Switchover Final Inpsections TAB Weather Days A/E Punch CUP Completion Final Inpsections Fix Punchlist Weather Days PCU Completion Critical Page 11 of 13

13 549 IR.2B Electrical Room Closeout 5 14-Jan Jan LEVEL 1 - CORRIDOR UPGRADES (North / South) Oct Jan PART Oct Dec IR.2B Temp Partitions 2 28-Oct Oct IR.2B Demo 4 30-Oct Nov IR.2B Upgrade Partitions - Rock/T&F/ Paint 5 05-Nov Nov IR.2B ACT Grid 4 12-Nov Nov IR.2B Light Fix Nov Nov IR.2B GRDs 3 21-Nov Nov IR.2B Above Ceiling Inspections 1 26-Nov Nov IR.2B Balance of Ceiling Tile 2 27-Nov Dec IR.2B Flooring 5 03-Dec Dec IR.2B Final Paint 3 10-Dec Dec IR.2B Remove Partition 1 13-Dec Dec PART Dec Jan IR.2B Temp Partitions 2 16-Dec Dec IR.2B Demo 3 18-Dec Dec IR.2B Upgrade Partitions - Rock/T&F/ Paint 3 23-Dec Dec IR.2B ACT Grid 3 27-Dec Dec IR.2B Light Fix Jan Jan IR.2B GRDs 3 07-Jan Jan IR.2B Above Ceiling Inspections 1 10-Jan Jan IR.2B Balance of Ceiling Tile 1 13-Jan Jan IR.2B Flooring 3 14-Jan Jan IR.2B Final Paint 2 17-Jan Jan IR.2B Remove Partition 1 21-Jan Jan IR.2B Corridor Upgrade Closeout 5 22-Jan Jan NEW ROOF / KNEE WALL Sep Oct IR.2B Demo 3 25-Sep Sep IR.2B Knee Wall 5 30-Sep Oct IR.2B Sheathing 4 07-Oct Oct IR.2B Roof System 5 11-Oct Oct MINOR RADIOLOGY RENO Sep Oct SEQUENCE A 9 05-Sep Sep IR.R Temp Partition 2 05-Sep Sep IR.R Remove Existing Casework & Sink 2 09-Sep Sep IR.R Set HM Frame 1 11-Sep Sep IR.R Hang Door & Hdw 2 12-Sep Sep IR.R Remove Partition 2 16-Sep Sep SEQUENCE B Sep Oct IR.R Temp Partition 2 18-Sep Sep IR.R Set HM Frame 1 20-Sep Sep IR.R Frame Walls 2 23-Sep Sep IR.R Plumbing Rough 3 25-Sep Sep IR.R Rock / Tape & 3 30-Sep Oct IR.R Hang Door & Hdw 2 03-Oct Oct IR.R Paint 1 07-Oct Oct IR.R Radiology Closeout 3 08-Oct Oct PHASE 2C Jan Apr MEP CEILING WORK Jan Apr-20 Electrical Room Closeout Demo Knee Wall Temp Partition Sheathing Temp Partitions Demo Roof System Upgrade Partitions - Rock/T&F/ Paint ACT Grid Light Fix. GRDs Above Ceiling Inspections Balance of Ceiling Tile Flooring Final Paint Remove Partition Temp Partitions Demo Remove Existing Casework & Sink Set HM Frame Hang Door & Hdw Remove Partition Temp Partition Set HM Frame Frame Walls Plumbing Rough Rock / Tape & Hang Door & Hdw Paint Radiology Closeout Upgrade Partitions - Rock/T&F/ Paint ACT Grid Light Fix. GRDs Above Ceiling Inspections Balance of Ceiling Tile Flooring Final Paint Remove Partition Corridor Upgrade Closeout Critical Page 12 of 13

14 599 PART Jan Feb IR.2C Temp Partitions 2 22-Jan Jan IR.2C Demo 4 24-Jan Jan IR.2C ACT Grid 4 30-Jan Feb IR.2C Light Fix Feb Feb IR.2C GRDs 3 10-Feb Feb IR.2C Above Ceiling Inspections 1 13-Feb Feb IR.2C Balance of Ceiling Tile 2 14-Feb Feb IR.2C Final Paint 3 18-Feb Feb IR.2C Base 2 21-Feb Feb IR.2C Remove Partition 1 25-Feb Feb PART Feb Apr IR.2C Temp Partitions 2 26-Feb Feb IR.2C Demo 4 28-Feb Mar IR.2C ACT Grid 4 05-Mar Mar IR.2C Light Fix Mar Mar IR.2C GRDs 3 16-Mar Mar IR.2C Above Ceiling Inspections 1 19-Mar Mar IR.2C Balance of Ceiling Tile 2 20-Mar Mar IR.2C Final Paint 3 24-Mar Mar IR.2C Base 2 27-Mar Mar IR.2C Remove Partition 1 31-Mar Mar IR.2C Phase 2C Closeout 5 01-Apr Apr-20 Temp Partitions Demo ACT Grid Light Fix. GRDs Above Ceiling Inspections Balance of Ceiling Tile Final Paint Base Remove Partition Temp Partitions Demo ACT Grid Light Fix. GRDs Above Ceiling Inspections Balance of Ceiling Tile Final Paint Base Remove Partition Phase 2C Closeout Critical Page 13 of 13