MARCH 29, 2018 SECTION MARRIOTT MIDTOWN DUAL BRAND BULLETIN NO. 11 AC/MOXY SECTION BULLETIN NO. 11

Size: px
Start display at page:

Download "MARCH 29, 2018 SECTION MARRIOTT MIDTOWN DUAL BRAND BULLETIN NO. 11 AC/MOXY SECTION BULLETIN NO. 11"

Transcription

1 MARCH 29, 2018 SECTION BULLETIN NO. 11 AC/MOXY PART 1 - GENERAL 1.1 GENERAL REQUIREMENTS SECTION BULLETIN NO. 11 A. The Contract Documents for the above project are revised as described herein. The changes shall take precedence upon receipt of Notice to Proceed, and all other provisions of the Contract Documents shall remain in force. B. This is not a notice to proceed. The Contractor shall analyze the work included in this Bulletin, shall determine if an increase or a decrease to the Contract Sum or Contract Time is called for, and shall submit a proposal to the Owner. The Owner has the right to reject, accept, or negotiate the Contractor s proposal. If the Owner accepts the Contractor's proposal, the work shall proceed with the change in scope, and the Contract Sum and Contract Time shall be revised. If the Owner rejects the proposal, the work shall proceed as if the bulletin had never been issued. PART 2 - DRAWING CHANGES 2.1 NEW DRAWINGS A. The following additional Drawings dated March 29, 2018, are issued with this Bulletin, and are deemed a part thereof. In addition, these Drawings are added to the List of Drawings within the Contract Drawings. Number General G0.01B Drawing Index 2.2 REVISED DRAWINGS A. The following Drawings have been revised, bear revision date March 29, 2018, are issued with this Bulletin, and are deemed a part thereof. The changes to be made are identified on each Drawing. Number Architecture A1.01 Reference Floor Plans - Level 1 / MOXY Lobby & Level 2 / AC Lobby A1.02 Reference Floor Plans - Level 2.5 / Parking 0.5 & Level 3 / Parking 1 A1.04 Reference Floor Plans - Level 6 / Pool Deck (Guest Room 1) & Level 7 / Guest Room 2 A1.05 Reference Floor Plans - Level 8&9 / Guestroom 3&4 and Level 11 / Guestroom 6 A2.01 Enlarged Plan - MOXY Lobby - Level 1 - Zone A A2.11 Enlarged Plan - AC Lobby - Level 2- Zone A A2.12 Enlarged Plan - AC Lobby - Level 2 - Zone B A2.13 Enlarged Plan - AC Lobby - Level 2 - Zone C A2.20A Enlarged Plan Level 6 - Zone A A2.20C Enlarged Plan Level 6 - Zone C A3.01 Reference Ceiling Plans - Level 1 / MOXY Lobby & Level 2 / AC Lobby A3.04 Reference Ceiling Plans - Level 6 / Pool Deck (Guest Room 1) & Level 7 / Guest Room 2

2 MARCH 29, 2018 SECTION BULLETIN NO. 11 AC/MOXY Number Architecture (continued) A3.05 Reference Ceiling Plans - Level 8&9 / Guestroom 3&4 and Level 11 / Guestroom 6 A3.11 Enlarged RCP - MOXY Lobby - Level 1 - Zone A A3.12 Enlarged RCP - MOXY Lobby- Level 1 - Zone B A3.13 Enlarged RCP - MOXY Lobby- Level 1 - Zone C A3.14 Enlarged RCP - MOXY Lobby- Level 1 - Zone D A3.21 Enlarged RCP - AC Lobby - Level 2- Zone A A3.22 Enlarged RCP - AC Lobby - Level 2 - Zone B A3.31 Enlarged Plans & RCPs - Tower BOH Areas A3.32 Enlarged Plans & RCPs - Tower BOH Areas A3.33 Enlarged Plans & RCPs - Tower BOH Areas A4.01 Building Elevations A4.02 Building Elevation A5.05 Component - Nw Corner A6.14 Exterior Enlarged Section Details A8.26 Enlarged AC Suites - Construction Plans & RCP- AC Ste. C- AC ACC STE A8.36 ADA Roll-In Shower & Tub Details A8.37 ADA Roll-In Shower & Tub Details A8.38 Tub/Shower Details A8.38A ADA Roll-In Shower & Tub Details A8.41 Enlarged Restrooms Plans & RCPs A8.43 Enlarged Corridors A8.44 Enlarged Corridors A9.10 Door Schedule - Public & BOH Levels 1 Thru Level 5 A9.11 Door Schedule - Public & BOH Levels 06 Thru Roof Interior Design - Baskervill ID0.02 ID1.01 ID2.01 ID2.02 ID2.03a ID2.04 ID2.05 ID2.06 ID3.01 ID3.04 ID8.01 ID8.02 ID8.03 ID8.04 ID8.05 ID8.06 ID8.07 ID8.08 ID8.09 ID8.10 ID8.11 ID8.12 Materials, Finish Legend, Ta Legend & Details ID Reference Plan - Level 2 / AC Lobby Enlarged ID Plan - AC Lobby - Level 2 - Zone A Enlarged ID Plan - AC Lobby - Level 2 - Zone B Enlarged Plan - Level 6/Pool Deck FF&E & Pool Restrooms Enlarged ID Plan - Level 6 / Meeting Rooms & Fitness Center Enlarged ID Plan - AC Lobby Level/Meeting Rooms Enlarged ID Plan - Level 2 / Public Restrooms, Level 6 / Meeting Room Restrooms ID Reference Ceiling Plan - Level 2 - AC Lobby ID Reference Ceiling Plans - Level 6 / Pool Deck (Guestroom 1) & Level 7 / Guestroom 2 Enlarged AC Guestroom - Furniture & Finish Plans & RCP - AC K1 Enlarged AC Guestroom - Furniture & Finish Plans & RCP - AC K1.C Enlarged AC Guestroom - Furniture & Finish Plans & RCP - AC K2 Enlarged AC Guestroom - Furniture & Finish Plans & RCP - AC K3 Enlarged AC Guestroom - Furniture & Finish Plans & RCP - AC K4 Enlarged AC Guestroom - Furniture & Finish Plans & RCP - AC K5 Enlarged AC Guestroom - Furniture & Finish Plans & RCP - AC Qq1 Enlarged AC Guestroom - Furniture & Finish Plans & RCP - AC QQ1.C Enlarged AC Guestroom - Furniture & Finish Plans & RCP - AC QQ2 Enlarged AC Guestroom - Furniture & Finish Plans & RCP - AC QQ3 Enlarged AC Guestroom - Furniture & Finish Plans & RCP - AC ACCK1.S Enlarged AC Guestroom - Furniture & Finish Plans & RCP - AC ACCK1.T

3 MARCH 29, 2018 SECTION BULLETIN NO. 11 AC/MOXY Number Interior Design Baskervill (continued) ID8.13 Enlarged AC Guestroom - Furniture & Finish Plans & RCP - AC ACCQQ1.S ID8.14 Enlarged AC Guestroom - Furniture & Finish Plans & RCP - AC ACCQQ1.T ID8.15 Enlarged AC Guestroom - Furniture & Finish Plans & RCP - AC Ste.C ID8.16 Enlarged AC Guestroom - Furniture & Finish Plans & RCP - AC ACCSTE ID8.17 K1 ID8.18 K2 ID8.19 K3 ID8.20 K4 ID8.21 K4.C ID8.22 K5 ID8.23 K6.C ID8.24 K7 ID8.25 K8.C ID8.26 K9.C.Hi ID8.27 Qq1 ID8.28 QQ1.C ID8.29 QQ2.C ID8.30 ACCK1.S ID8.31 ACCK1.T ID8.32 ACCQQ1.C.T ID8.33 ACCSTE.C.S. ID8.34 Ste ID8.35 Enlarged AC Guestroom - Furniture & Finish Plans & RCP - AC Qq4 ID8.36 Enlarged AC Guestroom - Furniture & Finish Plans & RCP - AC Qq5.C ID8.37 K10 ID8.38 K11 ID8.39 K6 ID9.01 Elevations - AC Lobby ID10.00 Details - AC Guestroom ID10.04a Millwork - AC Kitchen ID10.04b Millwork - AC Kitchen and POS Counter ID10.07 Millwork - AC Library & BOH ID10.13 Millwork/Details MOXY Guestroom Interior Design Street Sense SID 3.04 Enlarged Millwork Plan, Elevations, and Details Mechanical M0.8 HVAC Details & Risers M2.01B Level 1 HVAC M2.02A Level 2 HVAC

4 MARCH 29, 2018 SECTION BULLETIN NO. 11 AC/MOXY Number Mechanical (continued) M2.06A M2.06B Plumbing P1-06AS P1-06AW Level 6 HVAC Level 6 HVAC Plumbing Enlarged Floor Plan - Level 6 Pool Deck -S,W,&V Plumbing Enlarged Floor Plan - Level 6 Pool Deck -AW Electrical E1.01C AC Lobby Level Floor Plan - Lighting E2.01C AC Lobby Level Floor Plan - Lighting E2.06A Electrical Plan Level 6 Pool/Deck A - Lighting E2.06B Electrical Plan Level 6 Pool/Deck B - Lighting E2.07A Electrical Plan Level 7 Guestroom A - Lighting E2.08A Electrical Plan Level 8 Guestroom A - Lighting E2.09A Electrical Plan Level 9 Guestroom A - Lighting E2.10B Electrical Plan Level 10 Guestroom B - Lighting E2.11B AC Electrical Guest Unit Plans E4.03 AC Electrical Guest Unit Plans PART 3 - SPECIFICATION CHANGES 3.1 NEW SPECIFICATIONS A. The following additional Specification sections dated March 29, 2018, are issued with this Bulletin, and are deemed a part thereof. In addition, these sections are added to the Table of Contents within the Project Manual. Section Number Bulletin No REVISED SPECIFICATIONS A. The following Specification sections have been revised, bear revision date March 29, 2018, are issued with this Bulletin, and are deemed a part thereof. The changes to be made are identified on the revised pages of each section, attached hereinafter, unless noted otherwise. Section Number TOC Table of Contents END OF SECTION

5 REVISED MARCH 29, 2018 TOC- 1 VOLUME ONE MISCELLANEOUS Responsibility Matrix Revised 01/18/17 PROCUREMENT AND CONTRACTING REQUIREMENTS Division 00 Procurement and Contracting Requirements Marriott Design Standards Revised 01/18/17 * Existing Condition Information To be Issued Geotechnical Data Agreement Form To be Issued General Conditions To be Issued Addendum No. 1 Issued 08/24/ Addendum No. 2 Issued 10/25/ Addendum No. 3 Issued 01/18/ Bulletin No. 1 Issued 03/24/ Bulletin No. 2 Issued 05/19/ Bulletin No. 3 Issued 06/09/ Bulletin No. 4 Issued 07/11/ Bulletin No. 5 Issued 08/15/ Bulletin No. 6 Issued 08/18/ Bulletin No. 7 Issued 09/26/ Bulletin No. 8 Issued 11/17/ Bulletin No. 9 Issued 01/26/ Bulletin No. 10 Issued 02/22/ Bulletin No Issued 03/29/18 SPECIFICATIONS Division 01- General Requirements Summary Revised 01/18/17 * Summary To be Issued Allowances Revised 01/18/ Unit Prices Issued 01/18/ Contract Modification Procedures Request for Information Procedures Payment Procedures Interim Contractor's Affidavit and Waiver of Liens Final Contractor's Affidavit and Waiver of Liens Project Coordination Project Meetings Construction Progress Documentation Submittal Procedures Special Inspections References Quality Control Inspecting and Testing Services Temporary Facilities and Controls Temporary Project Identification Product Requirements

6 REVISED MARCH 29, 2018 TOC- 2 Division 01- General Requirements (continued) Field Engineering Cutting and Patching Construction Waste Management and Disposal Closeout Procedures Sustainable Design Requirements * Sustainable Design Requirements (Commercial Interiors) To be Issued Commissioning Requirements Division 02 Existing Conditions Selective Demolition Division 03- Concrete Cast-In-Place Concrete * Polished Concrete Finishing To be Issued Concrete Finishing Issued 03/24/17 * Polished Concrete Finishing Deleted 03/24/ Post-Tensioning Reinforcement for Concrete Precast Architectural Concrete Glass-Fiber-Reinforced Concrete (GFRC) Deleted 01/18/ Lightweight Insulating Concrete Division 04- Masonry * Clay Unit Masonry-Thin Brick Issued 08/24/ Brick Masonry Deleted 01/18/ Concrete Unit Masonry * Anchored Stone Masonry Veneer To be Issued * Adhered Manufactured Masonry Veneer Issued 08/24/ Cast Stone Masonry Division 05- Metals Structural Steel Steel Joists/ Girders Steel Deck Epicore MSR Composite Floor Deck System Cold-Formed Steel Framing Pre-Panelized Load-Bearing Steel Stud Wall Metal Fabrications Metal Pan Stairs Revised 03/24/ Pipe and Tube Railings Revised 08/24/ Barrier Cable System Bar Gratings * Decorative Metal Issued 08/24/ Decorative Metal Railings * Decorative Metal Railings To be Issued * Glazed Decorative Metal Railings Revised 01/18/ Decorative Formed Metal Issued 08/24/16

7 REVISED MARCH 29, 2018 TOC- 3 Division 06 Wood, Plastics, and Composites Miscellaneous Rough Carpentry Sheathing Interior Finish Carpentry Deleted 01/18/17 * Interior Finish Carpentry Issued 01/18/17 * Interior Architectural Woodwork Issued 08/24/ Wood-Veneer-Faced Architectural Cabinets Deleted 08/24/16 * Wood-Veneer-Faced Architectural Cabinets Issued 08/24/ Plastic-Laminate-Faced Architectural Cabinets Deleted 08/24/16 * Plastic-Laminate-Faced Architectural Cabinets Issued 08/24/16 * Plastic-Laminate-Faced Wood Paneling Issued 08/24/ Cultured Marble Fabrications Deleted 08/24/16 * Cultured Marble Fabrications Issued 08/24/16 * Plastic Paneling Solid Polymer Fabrications Issued 08/24/16 Division 07- Thermal and Moisture Protection Self-Adhering Sheet Waterproofing Revised 01/18/17 * Hot Fluid-Applied Waterproofing To be Issued Hot Fluid-Applied Rubberized Asphalt Waterproofing Revised 08/24/ Cold Fluid-Applied Waterproofing Issued 06/09/ Crystalline Waterproofing Traffic Coatings Water Repellants Issued 01/26/ Thermal Insulation Revised 01/18/ Foamed-In-Place Insulation Water-Drainage Exterior Insulation and Finish System (EIFS) Vapor Retarders Fluid-Applied Membrane Air Barriers Deleted 01/18/ Formed Metal Wall Panels Revised 03/24/ Metal Composite Material Wall Panels Revised 01/18/ Thermoplastic Polyolefin (TPO) Roofing Sheet Metal Flashing and Trim Revised 01/18/ Roof Specialties Revised 01/18/ Roof Accessories Applied Fireproofing Intumescent Fireproofing Deleted 01/18/ Penetration Firestopping Revised 08/24/ Joint Firestopping Revised 08/24/ Preformed Joint Seals Joint Sealants Division 08- Openings Hollow Metal Doors and Frames Revised 01/18/17 * Aluminum Frames To be Issued * Wood Doors To be Issued Flush Wood Doors * Access Doors and Panels To be Issued Access Doors and Frames Coiling Counter Doors Issued 01/18/ Overhead Coiling Doors Folding Doors Issued 08/24/ Aluminum-Framed Entrances and Storefronts Revised 01/18/17 * All-Glass Entrances and Storefronts To be Issued Sliding Automatic Entrances Revised 01/18/ Revolving Door Entrances Revised 01/18/17

8 REVISED MARCH 29, 2018 TOC- 4 Division 08- Openings (continued) Aluminum Windows Issued 01/18/17 * Stainless Steel Window Deleted 01/18/ Door Hardware Revised 06/09/ Electronic Guest Room Security Systems Glazing Mirrors Deleted 08/24/16 * Mirrors Issued 08/24/ Fixed Louvers Division 09- Finishes * Interior Finish Index Issued 08/24/ Moisture Vapor Emission Control Issued 08/18/ Gypsum Board Shaft Wall Assemblies Non-Structural Metal Framing Gypsum Board Revised 06/09/17 * Gypsum Board To be Issued Tiling Deleted 08/24/16 * Ceramic Tiling Revised 01/18/17 Division 09- Finishes (continued) * Stone Tiling Issued 08/24/ Acoustical Panel Ceilings Deleted 08/24/16 * Acoustical Panel Ceilings Issued 08/24/16 * Acoustical Tile Ceilings Issued 08/24/16 * Acoustical Metal Pan Ceilings Issued 01/18/17 * Stone Flooring To be Issued * Wood Flooring To be Issued Resilient Base and Accessories Deleted 08/24/16 * Resilient Base and Accessories Issued 08/24/ Resilient Tile Flooring Deleted 08/24/16 * Resilient Tile Flooring Issued 08/24/ Static-Control Resilient Flooring * Resilient Athletic Flooring Deleted 01/18/ Tile Carpeting Deleted 08/24/16 * Tile Carpeting Issued 08/24/ Sheet Carpeting Deleted 08/24/16 * Sheet Carpeting Issued 08/24/ Wall Coverings Deleted 08/24/16 * Wall Coverings Issued 08/24/ Exterior Painting Revised 08/24/16 * Interior Painting Issued 08/24/16 * Textured Finishing Issued 08/24/16 Division 10- Specialties * Visual Display Surfaces Issued 08/24/16 * Signage Deleted 01/18/ Panel Signage Deleted 01/18/ Plastic-Laminate-Clad Toilet Compartments Deleted 08/24/16 * Plastic-Laminate-Clad Toilet Compartments Issued 08/24/ Phenolic-Core Shower and Dressing Compartments Deleted 08/24/16 * Plastic Shower and Dressing Compartments Issued 08/24/ Accordion Folding Partitions Deleted 01/18/ Operable Panel Partitions Deleted 01/18/ Folding Panel Partitions Deleted 08/24/16 * Folding Panel Partitions Issued 08/24/16 * Folding Glass-Panel Partitions To be Issued

9 REVISED MARCH 29, 2018 TOC- 5 Division 10- Specialties (continued) Wall and Door Protection Deleted 08/24/16 * Wall and Door Protection Issued 08/24/ Toilet, Bath, and Laundry Accessories Deleted 08/24/16 * Toilet, Bath and Laundry Accessories Issued 08/24/16 * Tub and Shower Doors Issued 08/24/ Shower Doors Deleted 08/24/ Manufactured Fireplaces * Manufactured Fireplaces To be Issued Fire Protection Cabinets Revised 08/24/16 * Fire Protection Cabinets To be Issued Fire Extinguishers * Fire Extinguishers To be Issued Metal Lockers Deleted 08/24/16 * Metal Lockers Issued 08/24/16 * Metal Storage Shelving Issued 08/24/16 * Wire Closet and Utility Shelving Issued 08/24/ Awnings Revised 01/18/ Canopies Revised 01/18/ Plaza-Mounted Flagpoles Deleted 01/18/17 VOLUME TWO Division 11- Equipment Commercial Laundry Equipment Deleted 01/18/17 * Commercial Laundry and Dry Cleaning Equipment To be Issued Tie-Back and Life-Line Anchors * Registration Equipment Issued 08/24/16 * Residential Appliances Deleted 01/18/ Foodservice Equipment Revised 03/24/ Projection Screens * Facility Waste Compactors To be Issued Division 12- Furnishings Horizontal Louver Blinds Deleted 01/18/17 * Curtains and Drapes Deleted 01/18/ Roller Window Shades Deleted 08/24/16 * Roller Window Shades Deleted 01/18/17 * Architectural Woodwork To be Issued * Manufactured Wood-Veneer-Faced Casework To be Issued * Manufactured Plastic Laminate Clad Casework To be Issued Plastic-Laminate-Clad Countertops Deleted 08/24/16 * Plastic-Laminate-Clad Countertops Issued 08/24/ Simulated Stone Countertops Deleted 08/24/16 * Simulated Stone Countertops To be Issued * Cultured Marble Countertops Issued 08/24/16 * Solid Surfacing Countertops Issued 08/24/16 * Quartz Agglomerate Countertops Issued 08/24/16 * Formed Concrete Countertops Revised 01/18/ Entrance Floor Mats and Frames Deleted 08/24/16 * Entrance Floor Mats and Frames Issued 08/24/16 * Hospitality Furniture Installation Issued 08/24/16 * Site Furnishings To be Issued Bicycle Racks Revised 03/24/17

10 REVISED MARCH 29, 2018 TOC- 6 Division 13- Special Construction Swimming Pools To be Issued Division 14- Conveying Equipment Electric Traction Elevators Revised 08/24/ Laundry and Linen Chutes Trash Chutes Deleted 01/18/17 Division 15 to Division 20 (Not Applicable) Division 21- Fire Suppression Common Work Results for Fire Suppression Fire-Suppression Standpipes Revised 01/18/ Wet-Pipe Sprinkler Systems Dry-Pipe Sprinkler Systems Revised 01/18/ Electric-Drive, Centrifugal Fire Pumps Division 22- Plumbing Common Work Results for Plumbing General Duty Valves for Plumbing Piping Hangers and Supports for Plumbing Piping and Equipment Identification for Plumbing Piping and Equipment Plumbing Insulation Revised 01/18/ Plumbing Commissioning Requirements Facility Water Distribution Piping Domestic Water Piping Revised 01/18/ Domestic Water Piping Specialties Facility Natural Gas Piping Facility Sanitary Sewers Sanitary Waste and Vent Piping Revised 01/18/ Sanitary Waste Piping Specialties Revised 01/18/ Storm Drain Piping Storm Drainage Piping Specialties Revised 01/18/ Fuel-Fired, Domestic Water Heaters Revised 01/18/ Plumbing Fixtures Division 23- Heating, Ventilating, and Air-Conditioning (HVAC) Common Work Results for HVAC Hangers and Supports for HVAC Piping and Equipment Revised 10/07/ Identification for HVAC Piping and Equipment Revised 01/18/ Testing, Adjusting, and Balancing for HVAC Revised 01/18/ HVAC Insulation Revised 01/18/ HVAC and Commissioning Requirements To be Issued Instrumentation and Control for HVAC Revised 01/18/ Sequence of Operations for HVAC Controls Revised 10/07/ Refrigerant Piping Metal Ducts Air Duct Accessories Revised 01/18/ Air Outlets and Inlets Particulate Air Filtration Air-Cooled Condensers Revised 01/18/ Dedicated Outdoor-Air Units Revised 01/18/ Packaged Terminal Air-Conditioning Units Revised 01/18/17

11 REVISED MARCH 29, 2018 TOC- 7 Division 23- Heating, Ventilating, and Air-Conditioning (HVAC) (continued) Split-System Air-Conditioners Deleted 01/18/ Variable Refrigerant Flow HVAC Systems Revised 01/18/17 Division 24 to Division 25 (Not Applicable) Division 26- Electrical (Not Applicable) Common Work Results for Electrical Low-Voltage Electrical Power Conductors and Cables Grounding and Bonding for Electrical Systems Raceways and Boxes for Electrical Systems Identification for Electrical Systems Electrical Commissioning Requirements Low-Voltage Transformers Switchboards and Panelboards Wiring Devices Division 26- Electrical (continued) Enclosed Switches and Circuit Breakers Enclosed Controllers Power Factor Correction Equipment Lightning Protection for Structures Interior Lighting * Interior Lighting To be Issued Exterior Lighting Lighting Accessories * Lighting Accessories To be Issued Division 27- Communications (Not Applicable) Division 28- Electronic Safety and Security (Not Applicable) Fire Alarm and Detection Systems Division 29 to Division 30 (Not Applicable) Division 31- Earthwork Site Clearing Earth Moving Dewatering Rock Excavation Excavation Support and Protection Augered Cast-In-Place (ACIP) Piles Division 32- Exterior Improvements Asphalt Paving Concrete Paving Unit Paving Pavement Markings and Removal Chain Link Fences and Gates Issued 01/18/ Decorative Metal Gates Segmental Retaining Walls Irrigation Deleted 01/18/ Soil Preparation (Performance Specification) Deleted 01/18/17

12 REVISED MARCH 29, 2018 TOC- 8 Division 32- Exterior Improvements (continued) Turf and Grasses Deleted 01/18/ Plants Deleted 01/18/17 Division 33- Utilities Common Work Results for Utilities Storm Utility Drainage Piping VOLUME THREE AC Hotels by Marriott: Design Standards; October 2013, Revised August 2015 AC Hotels Marriott: Interior Product and Finish Specifications, dated October 31, 2013, Revised December 21, 2015 AC Hotels Marriott: Heart of House Guide 2015 VOLUME FOUR Marriott Hotels: Hotel Design Standards, January 2013, Revised April 2015 Revised 01/18/17 Marriott Hotels, North America, Guest Room + Corridors + Suites: Design Approach, June 2, 2014 Moxy Hotels: U.S. / Canada - Hotel Design Standards; March 2015, Revised May 2015 Moxy Hotels: Interior Product + Finish Specifications, North America, December 31, 2015 END OF