NOTTAWASEPPI HURON BAND of the POTAWATOMI

Size: px
Start display at page:

Download "NOTTAWASEPPI HURON BAND of the POTAWATOMI"

Transcription

1 NOTTAWASEPPI HURON BAND of the POTAWATOMI Widoktadwen Prospective Bidder Informational Meeting April 26, 2012 The SKILLMAN Corporation Project Administration Construction Management

2 The Widoktadwen Team Nottawaseppi Huron Band of the Potawatomi Dan Green-Chief Planner The Skillman Corporation-Project Administration & Construction Management Courtney James-Project Manager Randy Kitchel-Site Manager Bill Osborn-NA Employment Michael Kounelis-Account Executive Wightman & Associates Design Andy Mollison-Project Architect

3 Goals for Meeting Informational Meeting Pow Wow Project Health Center Addition & Remodeling Department Public Works Building Community Water System Centralized Sanitary Sewer System Government Building Market/General Store Bid Phase & Time Line Contractor/Sub Contractor/Vendor Participation

4 Site Plan

5 Pow Wow Construction Activity Update For information & reference Final phase of construction June Pow Wow August Gathering

6 Pow Wow Grounds

7 Water/Sanitary/Trail Project Increase water and provide sanitary service & distribution to: Pow Wow - Government Center - DPW - Health Center - Community Center - Administration - Homes 8 PVC water main & sanitary sewer piping Directional boring Ductile iron water fittings and sewer fitting Gate valves-hydrants-connections & fittings 1 water service 2 water service Asphalt patching/repair & site restoration

8 Community Water System

9 Centralized Sanitary Sewer

10 Health Center 3,300 SF New Addition Selective remodeling to existing spaces Selective remodeling to existing systems

11 Health Center

12 Health Center Lobby, From New Entry

13 Health Center View of Lobby From Inside Reception Area

14 Public Works Building Load Bearing Masonry Building Interior Masonry Walls 2 Service & Maintenance Bays 1 Wash Bay

15 Public Works Building Translucent Wall Gable Ends Light Gauge Steel Roof Truss Assembly Insulated Shingled Roof System Mezzanine Storage Epoxy Wall & Floor Finishes Wash Bay & Automated Wash System Radiant Floor Heating System HVAC-AC Mini Split System in Office Area Shop-Fluids-Storage-Offices-Restroom-Shower Vehicle Lift-Wash Equipment-Hoist-Oil/Air-Exhaust Ports

16 Public Works Building Aerial View

17 Public Works Building View From Pamptopee

18 Public Works Building

19 Public Works Building

20 Government Center Prairie Option New Building 31,650 sf Basement 8,405sf Main Floor 17,045sf Second Floor 6,200sf

21 Government Center Concrete foundations & basement 2 story structural steel main/center area Perimeter/wings HD steel stud wall assembly Exterior concrete-stone-brick-metal panels-glass-siding Elevator operation to basement, 1 st and 2 nd floors Fire suppression system/sprinkled building Aluminum windows and sun shades Shingled & metal roofing system Higher end finishes in entrance-lobby-corridor-legislative & council offices

22 Government Center

23 Government Center

24 Government Center

25 Government Center View From Parking Lot View From 1 ½ Mile Road

26 Government Center Main Building Entry

27 Government Center Lobby, From Main Entry Vestibule

28 Government Center Seating Alcove Off Lobby

29 Government Center Lobby, North Wall

30 Government Center Lobby, From Main Corridor

31 Schedule Design Bidding Construction Bid Packages Bid Phase Construction Phase 1. Health Center April/May May-January Gov. Center BP #1 May June 3. Gov. Center BP #2 June July-September Public Works June July-February Water/Sewer/Trail July August-January

32 Bidding Information Pre Bid Meeting for each Project Prime Contracts with NHBP administered by Skillman Sub-contractor-Vendor-material supplier participation Performance & Payment Bond Requirements Davis Bacon Wage Rates NA employment participation via NHBP Job Bank Skillman will assist Contractors

33 Bidding Information Notice to Bidders will be posted FREE electronic files of plans and specifications Contractor Prequalification form for Notice issuance Site Tour with Randy Kitchel BE SURE TO SIGN IN TODAY

34 Questions and Answers Thank you!

35

36

37