1 MONTHLY PROGRESS REPORT IIM RAIPUR Development of Phase I Campus including building for IIM Raipur at Naya Raipur (PMC by Naya Raipur Development Authority) MONTHLY PROGRESS REPORT AS ON 31 st March -2018

2 MONTHLY PROGRESS REPORT CONTENTS 1.0 EXECUTIVE SUMMARY PROJECT BRIEF PROJECT SNAPSHOT STATUS OF WORK & PERT CHART PICTORIAL STATUS OF WORK

3 1.0 EXECUTIVE SUMMARY Letter of Acceptance has been issued to M/s NCC for the development of Phase I Campus including building for IIM Raipur at Naya Raipur on 18 th Jan 2016 NCC has submitted the Performance Guarantee on 25 th Jan 2016 Date of commencement: 2 nd Feb 2016 Agreement signed on : 11 th Feb PROJECT BRIEF: a. Original total built up area - 76,842 Sqm (Phase I) (Revised built up area is 76,842 Sqm excluding finishing of Library, Sports, Faculty Housing-5&6) b. Total Original Contract Value for Phase-1 is Rs. 305 Crore Description Amount (in Crores) Remarks Cost of Phase 1A Rs As per reduced scope Add for Cost of MDC & allied infrastructures (+)Rs As instructed by IIM/NRDA vide letter dated Add for Cost of Civil Structure of Housing-5&6 & allied infrastructure (+) Rs As instructed by IIM/NRDA vide letter dated Add for Cost of Civil Structure of Sports Building & allied infrastructure (+) Rs As instructed by IIM/NRDA vide letter dated Expected savings (-) Rs Total Expected Contract Value as per the Present scope Rs c. Name of Contractor: M/s NCC Ltd d. Stipulated Period of Completion: 24 months Stipulated date of completion: 1 st Feb, 2018 (Provisional Extension granted up to 30 th April-2018)

4 A) SCOPE OF WORK: Civil & Structural Works Ext & Internal Plumbing works Ext & Internal Electrical Works HVAC Works Ext & Internal Fire Fighting Works Internal Finishing & Façade Works Auxiliary Services like STP, ETP, Area development, Roads etc. 3.0 PROJECT SNAPSHOT Plot No Plot Area Permissi Max. ground Marginal set backs (Sqm.) ble FAR coverage Khasra as per approved master plan % Setback Front: 25 m Side : 9m BUILDINGS UNDER CONSTRUCTION OF PHASE IA S. No. Building / Block No of Floors Area in SQM 1 Admin & Faculty Block G Academic Block G MDC Building (Work stopped on & order for restarting the work issued on ) G Library, Research & Incubation Centre B+G Sports Complex ( In Phase -1A) Vide Letter No 4(2)/NRDA/IIMR/ /329 dated , NCC has been instructed to complete the Civil work & External Finishing works of Sports Complex above Basement. B+G (revised scope) 6 Hostel (PGP) 5 Blocks G

5 7 Dining Hall B+G Director House G Faculty Housing 4 Towers under construction. Vide Letter No 4(2)/NRDA/IIMR/ /329 dated ,NCC has been instructed to complete the Civil work & External Finishing works of Faculty Housing-5&6 G (revised scope) 10 Staff Housing ( 1 Tower ) I BHK G Facilities (Shopping Complex, Facility Centre) G Substation and sewage treatment plant G Total Minor structures such as Gate 1,Gate-2 Covered Pathway etc Grand Total STATUS OF WORKS AS ON 31 st Mar-2018: A. Mobilization of Resource: About 800 labour available at Site. Tower Crane: Both Tower Crane removed from site. Mobile Crane: Three number of Mobile Crane available at site. Procurement of Reinforcement steel : about 330 Ton available at site Form Work material : Shuttering material for current requirement is available at site. Site office, Store, Quality Control Lab, Cement godown, Labour camp etc. are in place at site. Temporary Power connection to State Electricity Board obtained for construction purpose. Two bore wells are functional at site for construction purpose.

6 Sl No B. Building wise Status is as follows: Name of Building Scheduled date of completion as per original Plan Date committed by NCC in the 17 th CCC Meeting Projected Handing over date. Remarks/Status as on 31 st Mar A ACADEMIC COMPLEX Administrative & Faculty Block up to 3 rd floor front 31-Oct Mar April-18 On schedule. Supply of Electrical, HVAC, BMS 1 portion Equipments needs to be Balance portion of 3 rd & 4 th 31-Oct Mar May-18 expedited to meet the floor target dates 2 Academic Block(except 30-Oct Apr May-18 Auditorium) 3 Library(Finishing upto Ground Floor) 31-Oct Apr May Oct Oct Oct-18 Terrace slab casting MDC Block completed. B RESIDENTIAL COMPLEX 1.a) Faculty Housing-1 30-Oct Dec Apr-18 Delay in physical 1.b) Faculty Housing-2 25-Oct Dec Apr-18 completion mainly due 1.c) Faculty Housing-3 26-Oct Dec Apr-18 (a) completion of final 1.d) Faculty Housing-4 31-Oct Dec Apr-18 coat paint before final handing over (b) Delay in delivery of Light fittings & fixtures & further final commissioning activities. 2.a) Hostel-1 31-Oct Dec Apr-18 Delay in physical 2.b) Hostel-2 31-Oct Dec Apr-18 2.c) Hostel-3 30-Oct Jan Apr-18 2.d) Hostel-4 31-Oct Dec Apr-18 2.f) Hostel-5 30-Oct Jan May-18 3 Director's Residence 28-Oct Dec May-18 completion mainly due (a) completion of final coat paint before final handing over (b) Delay in delivery of Light fittings & fixtures & further commissioning activities (c) Manpower shortage in MEP activities. Finishing activities like Tiling/Flooring, Sanitary & CP Fittings, in nearing completion. 4 Staff Housing 30-Oct Mar May-18 Almost On schedule 5 Dining Block 30-Oct Mar May-18 6 Facility Block 30-Oct Dec April-18 7 Shopping Block 30-Oct Jan April-18 Almost on schedule/procurement of centrifugal chiller is delayed which may delay the completion. Delay due to mainly (a) Delivery of the Structural Glazing material (b) Delivery of the Electrical Fittings Delay due to mainly (a) Delivery of the Structural Glazing material (b) Delivery of the Electrical Fittings.

7 8 Sports Block 30-Oct Feb Dec-18 Apprehended to be delayed due to delay in the delivery of the some spare materials of WTP, which will result in the overall delay of 30 days C SUBSTATION & EXTERNAL UTILITIES 1 Substation Buildings 29-Apr Dec May-18 Electrical Equipments like HT Panels installation in progress. 2 External HVAC 29-Apr Nov Nov-17 Completed 3 External Plumbing 29-Apr Nov Nov-17 Completed 4 External Fire Fighting 29-Apr Nov Nov-17 Completed 5 Road Network & external Electrification 03-Jul Jan Mar-18 Top Layer of Bituminous Road completed as per the current scope.

8 (C) STATUS OF PROCUREMENT OF LONG LEAD ITEMS: Sl. Item of Work Approval Vendor Name Date of PO Revised PO Revised Expected No of data placed by placed by NCC date of delivery sheet NCC after GST (Before implementation GST) A. Electrical Works DG Set Yes M/s Jackson Limited Already Installed 800KVA Substation Compact Yes M/s ABB India Ltd Already Installed 800KVA Copper wound Cast Resin Dry Type Transformer 1000KVA Copper wound Cast Resin Dry Type Transformer Yes Failed to deliver. Revised Order placed to Crompton Greaves. Yes Failed to deliver. Order placed to Crompton Greaves Already Installed Already Installed. 11KV HT Panel(11 Yes M/s Crompton Greaves Approved Delivered at site. panel board) Power & Industrial Solutions Limited 33KV HT Panel(3 Panel Yes M/s Crompton Greaves Approved Delivered at site. Board Power & Industrial Solutions Limited 11KV panel Synchronizing Yes M/s Crompton Greaves Power & Industrial Approved Delivered at site. Solutions Limited 6.3MVA 33/11 KV Yes M/s Crompton Greaves Already Installed. Copper Wound oil Type Power & Industrial Transformer Solutions Limited Passenger Lifts Yes M/s ThyssenKrupp Elevator (India) Pvt. Ltd Delivered at site. Ring main Unit Yes M/s Schneider Electric Infrastructure Limited Already Installed. Networking System No M/s Siemens Delivered at site. B. Fire Fighting Works

9 Fire Pumps Yes Kirloskar All material delivered at site. C. HVAC Chillers (Screw Type) Delivered at site nos. Chillier (centrifugal type-2 nos. Yes Daiken Data Sheet resubmitted on Approval obtained from Technical Consultant. AHU s (Faculty & Admin Block) Yes Zeco Out of 19 nos,13 nos. reached at site. Balance 06 no s, Data sheet approval under process for upper floors. AHU s& FCU(Academic Block) Yes Zeco All AHU & FCU available at site except 01 no s for Auditorium. AHU s& FCU (Library Block) Yes Zeco All AHU & FCU available at site. AHU s& FCU (Dining Block) Yes Zeco All AHU & FCU available at site. Cooling Tower Yes Paharpur All delivered at site and installation completed. D. Plumbing Works Sewage Treatment yes M/s Aztek Private Ltd % material reached Plant at site and installation in progress. Solar Heating System Yes M/s Aditya Solar Energy Pvt. Ltd Entire material reached at site on 2 nd Dec-2017 and Installation in progress. Water Treatment Plant Yes M/s Aztek Pvt. Limited Major material (90%) (RO) delivered at site. and Installation in progress.

10 E Civil Works Fire rated Doors Under M/s Shakti Hormann All. Doors delivered. process Pvt Ltd. D. Financial Progress: a. Financial progress in respect of ongoing construction work Rs Crore up to (Net value of work done Rs Crore + secured advance on material at site Rs Crore) Out of Rs.22.5 Crore of Mobilization and plant & machinery advance; Rs.7.21 Crore is outstanding & balance Rs Crore has been recovered up to 31 st March b. Percentage Progress (Including the MDC Building) : I. With respect to revised tender cost (Rs Crore): / = 69.20% (Financial progress of ongoing work Rs Crore, Revised tender cost, including MDC, civil & structural works of Faculty Housing-5&6& Sports Complex = Rs Crore) II. With respect to project cost (Rs. 333 Crore): / 333 = 67.48% (Approved DPR cost Rs.333 Crore, up to date expenditure Rs Crore) III. With respect to overall project i /c phase -I &II : / = 27.48% (Proposed DPR cost Rs Crore, up to date expenditure Rs Crore & advance = Crore)

11 (c) Project Expenditure Vs Budget(as per revised scope) (All amount in Crores) Sl No Agency Description Item of work Bill Raised but Payment payment already made pending Expenditure Booked so far Balance Amount Total Estimate ## Remarks Towards Work Done Towards secured advance Towards mobilization advance NCC Ltd Towards tools and plant advance Interest on a/c of mobilisation and T&P Bill raised up to advance Ongoing work Towards Escalation ** EPF & ESI reimbursement Service tax/gst reimbursement TOTAL TCE Bill payment ( i /c service tax) ARCOP Bill payment ( i /c service tax) NRDA Actual cost reimbursement ( i /c service tax) IIT Delhi Proof Checking Bill raised up to March -18 Bill raised upto Jan-18 Bill raised upto Jan-18 6 Left out work Furniture & furnishing, IT Equipment, Horticulture etc Complete d Work Compound wall

12 8 to Local Authoritie s Planning Approval Water and Electricity connection Grand Total ## After inclusion of MDC, Civil structures of Faculty -5&6, Sports Complex. *For other financial details related to M/s NCC Ltd as on please refer last page. * Checking of RA Bill number 29 is under progress and the amounts shown here may vary. *Due to steep rise in labour wages the cost of Escalation which was estimated as Crore may not be sufficient. d). Payment status of Contractor M/s NCC Ltd. RA Bill No Value of Bill in Rs Crores ( Net value of work done) Date of submission by NCC to PMC Date of submission by PMC TO IIM Date of Payment by IIM Payment in days Delay in payment (Beyond 21 working days)

13 RA bill no 1 & 4 are related to mobilisation advance. TOTAL 269 Days As per clause 7 of agreement payment shall be made within 21 working days after submission of bill by the contractor i.e. M/s NCC Ltd. f) Time Over run: Date of Completion as per Agreement : Expected date of Completion (Excluding MDC) : Expected date of completion of MDC : Expected date of completion of Sports Block (above basement & Faculty Housing-5&6):

14 e) Financial progress Vis a Vis planned progress (in Rs. Crores) is as under 300 S Curve - For Total time period Revised Planned Progress (in Crore) Actual Finanacial Progress cumulative (in Crore)

15 S Curve - Revised Feb/ Mar/16 Apr/16 May/16 Jun/16 Jul/16 Aug/16 Sep/ Oct/16 Nov/16 Dec/ Jan/17 Feb/17 Mar/17 Apr/ May/17 Jun/17 Jul/17 Aug/ Sep/17 Oct/17 Nov/17 Dec/17 Jan/18 Feb/18 Mar/18 Revised Planned Progress (in Crore) Actual Finanacial Progress cumulative (in Crore) Planned Financial Progress Mob, T&P Advance Planned (in Crore) Revised Monthly Planned financial Progress (in Crore)

16 Monthly Revised Financial Progress Feb/16 Mar/16 Apr/16 May/16 Jun/16 Jul/16 Aug/16 Sep/16 Oct/16 Nov/16 Dec/16 Jan/17 Feb/17 Mar/17 Apr/17 May/17 Jun/17 Jul/17 Aug/17 Sep/17 Oct/17 Nov/17 Dec/17 Jan/18 Feb/18 Mar/18 Mob, T&P Advance Planned (in Crore) Actual Advance Paid (in Crore) Revised Monthly Planned financial Progress (in Crore) Actual Monthly Finanacial Progress (in Crore) MAJOR MILESTONES OF THE CONTRACT (As per Clause 5 of Agreement): S No Description of Milestones Date of Milestone Actual Progress Remarks 1 Mobilization & Completion of Site Office 2 Completion of Foundation for all the works including buildings completed Photographs attached (Page 17-18) Completed Completed 3 Completion of earthwork for roads & parking area Work in progress Photographs attached 4 Completion of RCC for all buildings, roads, drainage, trenches, culverts, water bodies, area development, STP etc Works in progress Photographs attached 5 Completion of All external services Nearing completion Photographs attached 6 Completion of internal services Work in progress Photographs attached

17 7 Completion of all internal Finishing & Facade Works Work in progress Photographs attached 8 Final inspection and completion of all works in all respects, ready for the handing over including minor, touch-up and cleaning Works to be taken up after completion of internal finishing works 5. BOTTLENECKS AND HINDRANCES There is delay in receipt of Architectural, Structural Drawings, Services Drawings and Shop drawings from the technical consultant M/S ARCOP. A bituminous road and WBM Road is passing through the construction area of the site which needs to be shifted by Local Authority. 6. URGENT ACTION REQUIRED Calling of tender of left out items such as for Furniture & furnishing,after submission of Tender documents by M/s ARCOP. MOBILIZATION 3 No. of Mobile Tower Crane available at Site

18 Reinforcement Steel about 330 ton available at site Material Testing Lab

19 WORK IN PROGRESS Faculty Housing (FH1) AS ON EXTERNAL PAINTING (Final Coat) COMPLETED Ready for handing over

20 INTERNAL FINISHING WORK AS ON Lift Erection completed along with Granite cladding in Lobby Fire Door erection completed Faculty Housing (FH2) AS ON AS ON External Painting completed Ready for handing over INTERNAL FINISHING WORK

21 AS ON Granite Cladding Work at Lift Wall completed along with the Lift erection Ceiling Fans fixing completed Faculty Housing (FH3) AS ON EXTERNAL PAINTING (Final Coat) completed Ready for Handing Over after completion of miscellaneous fixtures. INTERNAL FINISHING WORK

22 AS ON AS ON Fire Doors installed at stilt level Electrical Room Lift Erection & Granite cladding completed at Lobby Faculty Housing (FH4) AS ON AS ON External Painting (Final coat) completed Ready for Handing Over after completion of miscellaneous fixtures. INTERNAL FINISHING WORK

23 AS ON Granite Cladding work completed & Lift Erection nearly completed Fire Hose Door Cabinets fixing completed in all floors Director s Residence AS ON AS ON External Paint (1 st Coat ) nearly completed Area development work in progress. INTERNAL FINISHING WORK

24 Granite fixing work in stair case in progress Wooden Door Frames fixed Faculty and Administrative Block AS ON External Painting (final coat) nearly completed & DGU fixing completed External Painting Final coat 90% completed & DGU fixing completed. INTERNAL FINISHING WORK

25 AS ON Fire Door Frames fixed for the Electrical Rooms at Corridor Toilet Tiling work along with basin counter work (GF to 2 nd floor completed) & progress in 3 rd & 4 th floor. Entrance Glass Canopy fixed at the Entrance Library block AS ON Pergola Beam at Terrace Level completed & Window Glazing work in progress Pergola Beam at Terrace Level completed & Window Glazing work in progress INTERNAL FINISHING WORK

26 AS ON Wall Tiling work at Ground Floor in progress in Toilets Granite fixing work nearly completed at Ground Floor Lobby Academic Block AS ON External Painting work in progress & Aluminium window DGU work nearing completion External Painting work in progress & Aluminium window DGU work nearing completion

27 INTERNAL FINISHING WORKS AS ON Granite work completed at Ground Floor Lobby In Laminated Flush Door shutter fixing completed. Basin fixing work nearly completed Dining Block AS ON External Base Coat Painting in progress Structural Glazing work in progress Internal Finishing Work

28 AS ON HVAC Ducting work at Dining Ground Floor completed False ceiling, work started Facility Block AS ON External Painting work in progress Kota Flooring work completed.

29 Internal Finishing Works AS ON AS ON Aluminium Window Frame & glass fixing in progress. Mechanical work of Cooling Towers in progress. Shopping Block AS ON External Painting & Window/Door Glazing work in progress Glazing work in progress

30 Finishing works AS ON AS ON Aluminium Door Glazing fixing work completed Aluminium Door frame work in progress in Ground Floor. Sports Complex AS ON RCC Column casting above ground floor in progress 60% RCC column casting above ground floor completed. Internal Finishing Works (Basement)

31 AS ON Kota Flooring work in Basement Stair completed Tile fixing of water Tank completed. Student Hostel Block (H1) AS ON AS ON External Painting final coat completed Paver block & plinth protection completed

32 INTERNAL FINISHING WORKS Toilet Door/Window of Sand blasted Acrylic sheet fixing completed. SS Wash Basin fixing completed. Student Hostel Block (H2) AS ON External painting (1 st coat) completed & Final coat in progress External painting Final coat completed.

33 INTERNAL FINISHING WORKS AS ON Tiling work completed & Sanitary Fixtures fixing in progress(except basin) Sanitary Fixtures & Wash basin fixing completed. Student Hostel Block (H3) AS ON External painting (1 st coat) completed External painting Final coat in progress.

34 INTERNAL FINISHING WORKS AS ON Toilet CP Fittings work in progress Toilet CP Fittings work completed. Student Hostel Block (H4) AS ON External painting (Final coat) completed External Painting Final coat along with MS Louvers completed

35 INTERNAL FINISHING WORKS AS ON CP Fittings along with basin fixing for Toilets is completed Stair Railing Painting 2 nd Coat completed. Student Hostel Block (H5) AS ON External Painting (1 st coat) in progress External Painting (1 st coat) completed.

36 INTERNAL FINISHING WORKS AS ON AS ON Toilet Door fixing along with edge polishing completed Toilet Tiling work completed. Staff Housing AS ON AS ON External Painting (Base Coat) work in progress External Painting (1 st Coat) work completed.

37 INTERNAL FINISHING WORKS AS ON Staff Housing Lobby Kota Flooring completed in all floors Water proofing work at Terrace completed. Electrical Substation I AS ON AS ON External painting (1 st Coat) completed Aluminium ventilator frame fixing completed.

38 INTERNAL FINISHING/SERVICES WORKS AS ON MVA Oil Type Transformer Erection completed. Compact Substation Erection Work completed Electrical Substation III AS ON AS ON External Painting (1 st coat) work in progress External Painting (1 st coat) work completed.

39 INTERNAL FINISHING/SERVICES WORKS AS ON Electrical Panel erection work completed. Dry Type transformer installation completed. Electrical Substation IV AS ON AS ON External Painting (1 st Coat) in progress External Painting (1 st Coat) work completed.

40 Dry Type Transformer erection completed RMU installation/ventilation ducting work completed Entry gate I

41 External Painting completed & Aluminium glazing work completed. External Painting & Aluminium glazing work completed HVAC/ELECTRICAL EQUIPMENTS AS ON UPS installation work completed in Admin/Faculty block Installation of Raceways for Networking cables completed in Academic Block

42 AHU installation work in progress at AHU Rooms of faculty Admin Fire Fighting Pumps installed at Sports basement External Area Development & Roads AS ON Stone paving work in nearly completed outside the Academic Building in Final Coat Bitumen work (BC layer) completed in all Roads

43 External development of Plantation Box by RR masonry in progress. Plantation work also in progress Horticulture/Plantation work also in progress in the Road Median SEWAGE TREATMENT PLANT AS ON

44 External Plastering work nearly completed Internal Finishing Works External Plastering work nearly completed AS ON AS ON Inside Wall Plastering work nearly completed Ceiling Plastering also nearing completion