Ohio Department of Transportation Central Office 1980 West Broad Street Columbus, OH John R. Kasich, Governor Jerry Wray, Director

Size: px
Start display at page:

Download "Ohio Department of Transportation Central Office 1980 West Broad Street Columbus, OH John R. Kasich, Governor Jerry Wray, Director"

Transcription

1 Ohio Department of Transportation Central Office 1980 West Broad Street Columbus, OH John R. Kasich, Governor Jerry Wray, Director 5/1/2013 Project Addendum No. 1 PID No CUY Lakefront West; West 73 rd Street New Bridge Letting: May 30, 2013 Notice to all Bidders and Suppliers to please be advised of the attached Proposal Addendum. For internet access to information referenced in this addendum, please see the ODOT web site at -> ftp://ftp.dot.state.oh.us/pub/contracts/attach/cuy-86481/ The Department utilizes Bid Express ( as the official medium for electronic bid submittal. All bidders must prepare bids and submit them online via Bid Express. Addenda amendments must be acknowledged in the miscellaneous section of the Expedite (EBS) file and all amendments loaded in order for your bid to be considered for award of this project. Bid express will not accept bids that do not have amendments incorporated. Failure to incorporate changed quantities or items in your Expedite (EBS) submissions will result in the rejection of your bid. ODOT is an Equal Opportunity Employer and Provider of Services

2 Completion Date Change: No Proposal Addendum For CUY-Lakefront West West 73 rd Street; PID Project Bid Item Changes, Additions or Deletions: Yes Funding Splits Required: Yes Revised Bid Items: Ref. Total Item No. No. Quantity Unit Description Section E FT NO. 2 AWG 600 VOLT DISTRIBUTION CABLE E FT CONDUIT, 2, E FT TRENCH, 24 DEEP E TON SPECIAL ENVIRONMENTAL, MISC.: WORK INVOLVING HAZARDOUS WASTE E TON SPECIAL ENVIRONMENTAL, MISC.: WORK INVOLVING NON-REGULATED MATERIALS E TON SPECIAL ENVIRONMENTAL, MISC.: WORK INVOLVING SOLID WASTE E ,392 LB EPOXY COATED REINFORCING STEEL 0017 Added Bid Items: Ref. Item No. No. Total Quantity E LS E LS E LS Please be advised of the following: Unit Description Section SPECIAL ENVIRONMENTAL, MISC.: WORK INVOLVING WORK PLAN SPECIAL ENVIRONMENTAL, MISC.: WORK INVOLVING PUBLIC INVOLVEMENT STRUCTURAL STEEL, MISC.: VERIZON UTILITY SUPPORTS AND INSTALLATION 1. Title sheet date revised for updated Special Provision (PRIMARY ELECTRICAL SERVICE DISTRIBUTION SYSTEM, 4/11/2013). 2. Utility (CPP, CEI, Verizon) revisions affected plan sheets, cross sections, summary sheets. 3. Environmental revisions include updates to notes and summary sheets. 4. Bridge sheet revisions updated temporary shoring

3 Add the following Note: No Revise the following Special Provision: Yes PRIMARY ELECTRICAL SERVICE DISTRIBUTION SYSTEM, 4/11/2013 (the PDF of this document has been placed on the server) Plan sheet revisions: Yes Revised Sheets: 1, 18, 19, 53, 99, 105, 106, 107, 108, 109, 110, 111, 112, 113, 114, 115, 116, 117, 118, 119, 120, 121, 122, 123, 124, 125, 126, 127, 128, 129, 130, 131, 132, 133, 134, 135, 164, 165, 271, 272, 349, 354, 355, 357, 358, 359, 363, 364, 365, 366, 367, 368, 369, 370, 371, 374, 391, 394, 395, 397, 408, 409, 410, 411, 420, 421, 425, 435, 437 Answers to Prebid Questions: No

4 SPECIAL PROVISION PRIMARY ELECTRICAL SERVICE DISTRIBUTION SYSTEM 4/11/2013 PART 1 GENERAL 1.01 SECTION INCLUDES SCOPE OF WORK 1.02 Scope of Work A. This work consists of designing and constructing a Cleveland Public Power Underground Primary Electrical Service Distribution System replacement, at the locations shown on the drawings and as described below. The Contractor shall furnish all labor, plans, drawings, design calculations and all material and equipment required to design and construct the Primary Service Line Replacement in accordance with this Specification. The replacement concrete encased duct bank will consist of a series of 6 foot x 12 foot x 7 foot standard CPP Manholes with a 6 5 PVC concrete encased duct bank. The duct bank will commence at the existing CPP manhole located in the Southwest corner of the intersection of Father Frascati Drive and W. 73 rd Street, extends north along W. 73 rd Street through the railroad underpass and then east to interface with an existing CPP manhole located adjacent to the bridge abutment along Edgewater Drive. B. Work will include the removal, and replacement of existing CPP primary electrical facilities, both aerial and underground at the following locations: 1. Aerial service beginning from a wood pole at the intersection of W. 70 th Street and Father Caruso Drive (W. 70 th Street, Sta Lt.±), crossing over Father Caruso Drive to a wood pole located at Father Caruso Drive, Sta Lt.±. 2. Aerial service from the intersection of W.70 th Street and Father Caruso Drive, (Father Caruso Drive, Sta Lt.±), crossing north over the Norfolk Southern Railroad tracks to a wood pole located at Father Caruso Drive, Sta Lt.±, and traversing down the hillside to a wood pole located along Eastbound Exit Ramp Four of the West Shoreway /Edgewater Drive Interchange (Pathway, Sta Rt.±). At this service pole the aerial service transitions to an underground duct bank to an adjacent manhole (Pathway, Sta Rt.±). 3. Underground facilities from the adjacent manhole located along Eastbound Exit Ramp Four of the West Shoreway/Edgewater Drive Interchange (Pathway, Sta Rt.±)., extending to an existing manhole located adjacent to a bridge abutment at the intersection of Eastbound

5 Exit Ramp Four and Edgewater Drive (Edgewater Drive, Sta Lt. ±) passing through a second manhole located on the right side at the end of Eastbound Ramp Four (W. 73 rd Street, Sta Rt. ±). 4. The aerial service located along the left side of Father Caruso Drive between W. 67 th Street and W. 70 th Street will require removal to permit the construction of temporary railroad tracks, to shift the railroad alignment south to permit construction of the proposed W. 73 rd Street railroad overpass structure. CPP will install a temporary aerial service feeder to replace the section of aerial feeder between W. 67 th and W. 70 th Streets. Upon installation of the temporary aerial feed by CPP, the existing aerial service will require removal. Coordination with CPP will be required. 5. All proposed work will be coordinated with, and approved by CPP prior to any construction work beginning. 6. The 6 5 concrete encased duct bank shall be installed a minimum of four feet in depth below top of grade/top of roadway sub base. A minimum of 1 foot of clearance will be required between the duct bank and all other utilities. Any deviation from the minimum depth and minimum clearance between the utilities must be coordinated and approved by CPP prior to any construction work beginning. 7. Coordinate with CPP for manhole and duct bank details and requirements. 8. The removal and relocation of an existing aerial/underground telecommunications line following a similar alignment with the electrical primary service is required. The design/build status of this work will be determined during construction and is not included with this work. The contractor will contact and coordinate with the appropriate telecommunications company for guidance on the removal and relocation of this line. Any required work will be coordinated with the Engineer for direction. C. Subsequent to Notice to Proceed and prior to beginning any design and/or construction work on the Primary Electrical Service Distribution System, the Contractor shall schedule a Site Visit and Pre Design Meeting with Cleveland Public Power to review and coordinate all of the work required and have a full understanding of Cleveland Public Power s standard requirements and specifications for the work involved. Cleveland Public Power s standard specifications and requirements will supersede any requirements and conditions outlined in this specification. Additional information and/or standard details not included with this Special Provision may be provided by Cleveland Public Power for compliance with their standard requirements. The proposed primary service duct bank design must be submitted to ZCPP for their review and approval. Shop drawings of all required materials must be submitted to CPP for their review and approval.

6 D. It may be necessary to employ the services of Norfolk Southern flagmen to cover the work requirements on and/or adjacent to Norfolk Southern property. Coordinate with Norfolk Southern the project design and construction requirements to determine the requirement for Norfolk Southern flagmen. Cost for the flagmen will be part of the bid cost. Separate payment will not be made PRE APPROVED LIST A. The prime Contractor must select one of the specialty contractors prequalified with the Department per the Ohio Revised Code through and shall identify the specialty contractor on his proposal at the bid opening. No substitution will be permitted without written approval of the Engineer. Substitution after the bid opening will not be grounds for changes in bid prices AVAILABLE INFORMATION A. Available information provided by CPP, but not limited to, shall include the following items:

7

8

9

10

11

12

13

14

15

16

17

18

19

20

21

22 1.05 PRIMARY ELECTRICAL SERVICE LINE DESIGN REQUIREMENTS DESIGN SUBMITTALS

23 A. At least 45 days before the planned start of the Primary Electrical Service Distribution System, submit complete design calculations and working drawings to the Cleveland Public Power for review and approval. Include all details, dimensions, quantities, ground profiles and cross sections necessary to construct the Primary Electrical Service Distribution System. Verify the limits of all existing electrical service lines before preparing the drawings. The working drawings shall be prepared to the ODOT standards. Shop drawings shall be furnished as per all applicable requirements of The drawings and calculations shall be signed and sealed by a Professional Engineer registered in State of Ohio. Cleveland Public Power will approve or reject the Contractor s submittals within 30 calendar days after the receipt of the complete submission. The Contractor will not begin construction or incorporate materials into the work until the submittal requirements are satisfied and found acceptable to Cleveland Public Power CONTRACTOR QUALIFICATIONS In order to meet the requirements of ODOT Specification , the personnel performing Electrical work shall have acquired work experience which is not less than the level of experience as defined below: A. The Electrical contractor shall have completed at least 5 permanent Primary Electrical Line Installations during the past 5 years. B. Provide a Registered Professional Engineer with experience in the construction of Primary Electrical Service line installations on at least 3 completed projects over the past 3 years. The Contractor may not use consultants or manufacturer s representatives to meet the requirements of this section. Provide onsite supervisors and electricians with experience installing Primary Electrical Service Line installations on at least three projects over the past 3 years. The Department will take action pursuant to ODOT Specifications, including but not limited to Specification , in order to be assured that all personnel have the sufficient and requisite skill and experience to perform properly the work assigned to them SUBMITTALS A. The Contractor shall submit a brief description of at least 5 projects within the last 5 years, including the owning agency s name, address, and current phone number; location of project; project contract value; and scheduled completion date and actual completion date for the project. B. Resumes of the Contractor s staff shall be submitted to the Project Engineer for review per section 105 of the 2008 CMS. At least 60 calendar days before starting Primary Electrical Service Distribution System work, identify the Engineer, on site supervisors, and electricians assigned to the project, and submit a summary of each individual s experience. Only those individuals designated as meeting the qualifications requirements shall be used for the project. The Contractor cannot substitute for any of these individuals without written approval of the Engineer. The Engineer shall approve or reject the Contractor qualifications and staff within 15 working days after receipt of the submission. Work shall not be started on the Primary Electrical Service Distribution System nor materials ordered until the Contractor s qualifications have been approved by the Engineer. The Engineer may suspend the work if

24 the Contractor substitutes unqualified personnel for approved personnel during construction. If work is suspended due to the substitution of unqualified personnel, the Contractor shall be fully liable for additional costs resulting from the suspension of work and no adjustment in contract time resulting from the suspension of the work will be allowed. C. At least 30 days before starting Primary Electrical Service Distribution System, submit a Construction Plan to the Engineer that includes the following. 1. The start date and proposed detailed Primary Electrical Service Distribution System construction sequence. 2. Portions of the Primary Electrical Service Distribution System may need to be advanced to accommodate the scheduled phasing of other work, particularly the alignment for the replication of the Norfolk Southern tracks. D. The Engineer shall approve or reject the Contractor s Construction Plan within 30 working days after the submission. Approval of the Construction Plan does not relieve the Contractor of his responsibility for the successful completion of the work UNDERGROUND DUCTS AND RACEWAYS FOR ELECTRICAL SYSTEMS DESCRIPTION 1.2 SUMMARY A. This Section includes the following: 1. Conduit, ducts, and duct accessories for direct-buried duct banks. 1.3 DEFINITION A. RNC: Rigid nonmetallic conduit. 1.4 SUBMITTALS A. Product Data: For the following: 1. Duct-bank materials, including separators and miscellaneous components. 2. Ducts and conduits and their accessories, including elbows, end bells, bends, fittings, and solvent cement. 3. Warning tape. 4. Warning planks.

25 E. Duct-Bank Coordination Drawings: Show duct profiles and coordination with other utilities and underground structures. 1. Include plans and sections, drawn to scale, and show bends and locations of expansion fittings. 2. Drawings shall be signed and sealed by a qualified professional engineer. G. Qualification Data: For professional engineer and testing agency. H. Source quality-control test reports. I. Field quality-control test reports. 1.5 QUALITY ASSURANCE B. Comply with ANSI C2. C. Comply with NFPA DELIVERY, STORAGE, AND HANDLING A. Deliver ducts to Project site with ends capped. Store nonmetallic ducts with supports to prevent bending, warping, and deforming. 1.7 PROJECT CONDITIONS B. Interruption of Existing Electrical Service: Do not interrupt electrical service to facilities occupied by Owner or others unless permitted under the following conditions and then only after arranging to provide temporary electrical service according to requirements indicated: 1. Notify Construction Manager and Cleveland Public Power no fewer than two days in advance of proposed interruption of electrical service. 2. Do not proceed with interruption of electrical service without Construction Manager's and Cleveland Public Power s written permission. 1.8 COORDINATION A. Coordinate layout and installation of ducts with final arrangement of other utilities, site grading, and surface features as determined in the field. B. Coordinate elevations of ducts with final locations and profiles of ducts as determined by coordination with other utilities, underground obstructions, and surface features. Revise locations and elevations from those indicated as required to suit field conditions. C. MATERIALS 1.9 CONDUIT B. Rigid Steel Conduit: Galvanized. Comply with ANSI C80.1.

26 D. RNC: NEMA TC 2, Type EPC-40-PVC, UL 651, with matching fittings by same manufacturer as the conduit, complying with NEMA TC 3 and UL 514B NONMETALLIC DUCTS AND DUCT ACCESSORIES B. Available Manufacturers: Subject to compliance with requirements, manufacturers offering products that may be incorporated into the Work include, but are not limited to, the following: 1. ARNCO Corp. 2. Beck Manufacturing. 3. Cantex, Inc. 4. CertainTeed Corp.; Pipe & Plastics Group. 5. Condux International, Inc. 6. ElecSys, Inc. 7. Electri-Flex Company. 8. IPEX Inc. 9. Lamson & Sessions; Carlon Electrical Products. 10. Manhattan/CDT; a division of Cable Design Technologies. 11. Spiraduct/AFC Cable Systems, Inc. D. Underground Plastic Utilities Duct: NEMA TC 6 & 8, Type DB-120-PVC, ASTM F 512, with matching fittings by the same manufacturer as the duct, complying with NEMA TC 9. E. Duct Accessories: 1. Duct Separators: Factory-fabricated rigid PVC interlocking spacers, sized for type and sizes of ducts with which used, and selected to provide minimum duct spacings indicated while supporting ducts during concreting or backfilling. 2. Warning Tape: Underground-line warning tape. F. CONSTRUCTION 1.11 UNDERGROUND DUCT APPLICATION C. Ducts for Electrical Feeders: RNC, NEMA Type EPC-40-PVC, in direct-buried duct bank, unless otherwise indicated. D. Ducts for Electrical Branch Circuits: RNC, NEMA Type EPC-40-PVC, in direct-buried duct bank, unless otherwise indicated.

27 J. Underground Ducts for Telephone, Communications, or Data Circuits: RNC, NEMA Type DB-120-PVC, in direct-buried duct bank, unless otherwise indicated EARTHWORK B. Excavation and Backfill: Comply with Division 31 Section "Earth Moving," but do not use heavy-duty, hydraulic-operated, compaction equipment. D. Restore surface features at areas disturbed by excavation and reestablish original grades, unless otherwise indicated. Replace removed sod immediately after backfilling is completed. E. Restore areas disturbed by trenching, storing of dirt, cable laying, and other work. Restore vegetation and include necessary topsoiling, fertilizing, liming, seeding, sodding, sprigging, and mulching. Comply with Division 32 Sections "Turf and Grasses" and "Plants." F. Cut and patch existing pavement in the path of underground ducts and utility structures according to Division 01 Section "Cutting and Patching." 1.13 DUCT INSTALLATION D. Curves and Bends: Use 5-degree angle couplings for small changes in direction. Use manufactured long sweep bends with a minimum radius of 48 inches (1220 mm), both horizontally and vertically, at other locations, unless otherwise indicated. E. Joints: Use solvent-cemented joints in ducts and fittings and make watertight according to manufacturer's written instructions. Stagger couplings so those of adjacent ducts do not lie in same plane. H. Building Wall Penetrations: Make a transition from underground duct to rigid steel conduit at least 10 feet (3 m) outside the building wall without reducing duct line slope away from the building, and without forming a trap in the line. Use fittings manufactured for duct-to-conduit transition. I. Sealing: Provide temporary closure at terminations of ducts that have cables pulled. Seal spare ducts at terminations. Use sealing compound and plugs to withstand at least 15-psig (1.03- MPa) hydrostatic pressure. J. Pulling Cord: Install 100-lbf- (445-N-) test nylon cord in ducts, including spares. K. Direct-Buried Duct Banks: 1. Support ducts on duct separators coordinated with duct size, duct spacing, and outdoor temperature. 2. Space separators close enough to prevent sagging and deforming of ducts, with not less than 4 spacers per 20 feet (6 m) of duct. Secure separators to earth and to ducts to prevent displacement during backfill and yet permit linear duct movement due to expansion and contraction as temperature changes. Stagger spacers approximately 6 inches (150 mm) between tiers.

28 3. Excavate trench bottom to provide firm and uniform support for duct bank. Prepare trench bottoms as specified in Division 31 Section "Earth Moving" for pipes less than 6 inches (150 mm) in nominal diameter. 4. Install backfill as specified in Division 31 Section "Earth Moving." 5. After installing first tier of ducts, backfill and compact. Start at tie-in point and work toward end of duct run, leaving ducts at end of run free to move with expansion and contraction as temperature changes during this process. Repeat procedure after placing each tier. After placing last tier, hand-place backfill to 4 inches (100 mm) over ducts and hand tamp. Firmly tamp backfill around ducts to provide maximum supporting strength. Use hand tamper only. After placing controlled backfill over final tier, make final duct connections at end of run and complete backfilling with normal compaction as specified in Division 31 Section "Earth Moving." 1. Install ducts with a minimum of 3 inches (75 mm) between ducts for like services and 6 inches (150 mm) between power and signal ducts. 1. Depth: Install top of duct bank at least 36 inches (900 mm) below finished grade, unless otherwise indicated. 2. Set elevation of bottom of duct bank below the frost line. 1. Install manufactured duct elbows for stub-ups at poles and equipment and at building entrances through the floor, unless otherwise indicated. Encase elbows for stub-up ducts throughout the length of the elbow. 2. Install manufactured rigid steel conduit elbows for stub-ups at poles and equipment and at building entrances through the floor GROUNDING a. Couple steel conduits to ducts with adapters designed for this purpose, and encase coupling with 3 inches (75 mm) of concrete. b. For equipment mounted on outdoor concrete bases, extend steel conduit horizontally a minimum of 60 inches (1500 mm) from edge of equipment pad or foundation. Install insulated grounding bushings on terminations at equipment. A. Ground underground ducts and utility structures according to Division 26 Section "Grounding and Bonding for Electrical Systems." 1.15 FIELD QUALITY CONTROL A. Perform the following tests and inspections and prepare test reports: 1. Demonstrate capability and compliance with requirements on completion of installation of underground ducts and utility structures.

29 2. Pull aluminum or wood test mandrel through duct to prove joint integrity and test for outof-round duct. Provide mandrel equal to 80 percent fill of duct. If obstructions are indicated, remove obstructions and retest. B. Correct deficiencies and retest as specified above to demonstrate compliance CLEANING A. Pull leather-washer-type duct cleaner, with graduated washer sizes, through full length of ducts. Follow with rubber duct swab for final cleaning and to assist in spreading lubricant throughout ducts MEASUREMENT AND PAYMENT A. The final pay quantity shall include all costs associated with design and construction of the Primary Electrical Service Distribution System required by the Plans and this Specification. This work shall include, but not be limited to, design, drawings, complete Primary Electrical Service Distribution System installations, tests, excavation in excess of Item 203 quantities per contract plans, backfill, and all design, sampling, testing and reporting required by the Plans and this Specification. B. Measurement shall be Lump Sum. The final pay quantity shall be the design quantity increased or decreased by any changes authorized by the Engineer. C. The accepted quantities, measured as provided above, will be paid for at the contract unit price per unit of measurement for the pay items listed below that are shown on the bid schedule. Payment will be full compensation for the work prescribed in this section. Payment will be made under: Pay Item Pay Unit Lighting, Misc.: Primary Electrical Service Distribution System Design and Construction Lump Sum

30

31 CPP CONSTRUCTION NOTES Contact Ohio Utilities Protection Service, two working days prior to start of construction. In Ohio, call toll free It's The Law. All power conduit runs are to be constructed by using 2", 4", 5", or 6" pvc schedule EB conduits, encased with a 3" concrete envelope, unless otherwise noted. The concrete envelope is to be 4000psi (City of Cleveland Concrete Mix). A rugged polyethylene material warning tape capable of resisting high or low ph conditions must be placed above the electrical conduit bank. This warning tape is to be six inches wide, red in color, and imprinted with the words, "DANGER - BURIED HIGH VOLTAGE CABLES BELOW". This tape is to be placed 6" above the newly installed duct bank. This shall conform to the standards as set by Ohio Utilities Protection Service. As an option, contractor may elect to encase CPP's conduits in red concrete. Both methods are approved by Cleveland Public Power and are recommended by Ohio Utilities Protection Service. All conduits runs are to be installed at a minimum depth of 2'-6" below the existing and/or proposed grades, or as shown on the profile sheets, except those that are under any railroad or RTA tracks. The conduits will be installed at a minimum depth of 60" below the rail ties. Also, at any railroad crossings, conduits are to be encased in a steel pipe. See drawings issued by Cleveland Public Power for details. Vertical and horizontal curves shall have a minimum radius of no less than 30 feet. These curves are to be constructed by using the appropriate 5 couplings, and associated chord lengths of conduits as noted on the plan view and/or as shown on the Conduit Curve Construction Chart. Any other curve design, field changes, or the use of preformed radius bends must be approved by the Engineering Department of Cleveland Public Power. All manhole outside walls and conduits runs are to have a minimum clearance of 5' (face to face), horizontally from all water lines. Vertical clearance shall be at a minimum of 1'-6", or as shown on the profile sheets of the project. Clearance between other utilities shall be 1, unless noted otherwise. CPP's duct bank shall cross over or under other utilities at an angle of no less than 45. Any conduit runs that are crossing any steam lines shall have a minimum clearance of 5', or as shown on the profile sheet of the project. In the event that this cannot be accomplished, notify the Engineering Department of Cleveland Public Power prior to the installation of our conduits. Each newly constructed manhole shall be free of all foreign objects and debris. The contractor shall also provide a pulling line in each of the new conduits. All manhole covers should be inscribed with the Cleveland Public Power logo "CPP". The contractor shall provide Cleveland Public Power with as-built plans of the newly installed conduit system, showing both vertical and horizontal locations. These locations shai1 be at 50' intervals. All elevations are to be based on Cuyahoga County Regional Geodetic Surveys. Page 7 of 20

32 BACKFILL MATERIAL AND BACKFILLING PROCEDURES All backfill material used under any pavement shall be crushed limestone or gravel as per ODOT Item 304-Aggregate Base. Crushed air-cooled slag meeting #304 gradation may be used with prior written approval of the Division of Engineering and Construction inspector. The use of sand or #57 aggregate as a premium backfill if prohibited. Sand may only be used as indicated on the plan details for items such as conduit cover. The sand material shall be natural river or bank sand; free of silt, clay, loam, friable or soluble materials and organic matter. The backfill shall be installed in 4 inch (4") lifts and compacted using mechanical means only. Compact to within 12" of sub grade and each layer of backfill to 95% maximum dry density as determined by Standard Proctor Test (ASTM D698). The use of water for compaction is prohibited, e.g. flooding or puddling. Sand used as embankment construction and as backfill around structures shall be ODOT Item 203-Embankment or meeting the requirements of 703- Speciail Backfill Material of the section. Employ a placement method that does not disturb or damage conduit encasement. Do not backfill over wet, frozen or unstable subgrade surfaces. FLOWABLE FILL SPECIFICATIONS FOR UTITLITY TRENCHES PART I CERTIFICATE OF COMPLIANCE Material must come from a plant with a current Certificate of Compliance demonstrating the ability of the mix design to meet the specified requirements. Certificates in excess of one year will not be accepted. Certificates must contain the name of supplier, date, contract number and mix design data on each delivery ticket. PART II MATERIALS All materials shall conform to the applicable requirements stated herein. 1. Cement shall be ASTM C-150Type I. 2. The use of Fly Ash is strictly prohibited. 3. Fine aggregate shall conform to ODOT Specification Fine aggregate for Mortar and Grout (ODOT Construction and Materials Specifications most current edition). The use of spent foundry sand or core sand is strictly prohibited. PART III PERFORMANCE ENHANCING ADMIXTURE An air-enhancing admixture shall be incorporated in the mix that will have the effect of lowering the water/cement ratio to between 95 and 105 lbs/cubic foot. The air entrained content for the mix shall be 30% to eliminate/minimize the excessive water and segregation. Compressive strengths shall have a range of 50 PSI to 80 PSI at 28 days will be required if additional excavation by machine or hand is required. Page 8 of 20

33 Approved Admixtures Manufacturer Product a) Mater Builders Rheofill b) Axim Flow Air c) W.R. Grace DaraFill d) Or approved equal PART IV FLOWABLE FILL MIX DESIGN The mix design shall be proportioned as follows: Cement (Type I) Sand (SSD) Water Admixture (Air) 50 lbs/cubic yard 2475 lbs/cubic yard 25 gallons/cubic yard 3 oz/cubic yard Variations of the aforementioned mix design are strictly prohibited PART V APPLICATION 1. Flowable fill shall begin 12 inches above the top of pipe and continue in the trench to the concrete base. 2. Material for pipe bedding and pipe zone to a minimum depth of 12 inches over the top of pipe shall be as specified by the utility. 3. Exposed bolts and valves exposed in the trench should be wrapped with polyethylene material conforming to ODOT (8 mil thick). 4. Cover all joints in clay pipe in the trench area with polyethylene material before pouring flowable fill. Repair all observed openings in any pipe or manhole in the trench area prior to backfilling with flowable fill. Repair techniques shall be in accordance with the utility company s standard repair procedures. 5. Contact the respective utility owner for repair procedures. Page 9 of 20

34 CONCRETE DESIGN MIX (CTIY OF CLEVELAND MIX) Under this section of these specifications the contractor is required to submit a separate mix design for each combination of cement type, aggregate type, and concrete supplier they will use under this contract. Each mix shall be designed in accordance with ASTM C94-94 Option C and as herein modified. REQUIREMENT Minimum twenty-eight (28) 4000 PSI for 28 days compressive strength test. Four cylinders will be taken and tested as per ASTM C One to be tested at seven days and the remaining three will be tested at twenty-eight days. Acceptance will be based on the average results of the three cylinders. Minimum Cement Constant 650 lbs. per cubic yard. The cement shall conform to ASTM C or C Water Cement Ration Slump 0.45 Maximum. Nominal three inches (3'') as per ASTM C (2"-4" actual). The use of chemical admixtures meeting ASTM C-494, to increase the slump to a maximum of 7", may be used with prior written approval of the Division of Engineering and Construction inspector. If this option is selected the admixture and resultant maximum slump shall be submitted for approval. Air Content Four percent (4%) to seven an done-half percent (7 1/2 %) ASTM C or C Aggregate Size No. 57 for course aggregate shall be limestone, gravel or crushed air-cooled blast furnace slag. Both course and fine aggregate as per ASTM C If crushed air-cooled blast furnace slag is used it shall meet all of the requirements of ODOT and ODOT Copies of all tests and certifications for the crushed air-cooled blast furnace slag, if used, shall be submitted as part of the concrete mix design. When high early strength is required, ASTM C Type III A cements or admixtures in accordance with ASTM C shall be used. Page 10 of 20

35 PAVEMENT REPAIR Concrete Pavement All pavement openings shall be sawed full depth and have smooth vertical faces. Dowels shall be required as per dowel table. Concrete repaving shall be performed in such a manner that the entire lane and/or slab in which the repair area is located shall be restored. Should any portion of the repair area extend into an adjacent lane and/or slab, that lane or slab shall also be repaved. Asphalt Pavement All pavement openings shall be sawed full depth and have smooth vertical faces. Dowels shall be required as per dowel table. Asphalt resurfacing shall be performed in such a manner that the entire lane in which the repairs are located shall be restored. Should any portion of the repair area extend into an adjacent lane, that lane shall also be resurfaced. For pavements with a width of 40' or less, a lane shall be considered 1/2 the pavement width. Extend over cut in longitudinal direction two feet (2') unto undisturbed subgrade. Brick Pavement All streets within the City of Cleveland that are currently brick paved shall be replaced with brick, or as directed by the inspector representing the Division of Engineering and Construction of the City of Cleveland. The contractor under this section of the specifications shall construct concrete base, pavement, sidewalk, driveway aprons, curb, curb and gutter sections, handicap ramps, and integral radius curb and walk. This includes the restoration of all adjacent surfaces which are disturbed by this construction at no cost to the City of Cleveland and/or Cleveland Public Power. Contractor shall take any and all measures necessary to ensure concrete is not defaced with graffiti, foot prints, tire tracks, and rocks, etc. by vandals. Page 11 of 20

36 REGULATIONS GOVERNING THE LAYING OF CONCRETE SIDEWALKS, APRONS, AND CURBING Concrete walks shall be of one-course construction and shall be four inches (4") in thickness, except in the downtown district where they must be six inches (6") in thickness. Concrete for walks, curbs, drives, and aprons shall be Class "C" concrete as per item 608 and Special of the "Supplemental to State Specifications for the City of Cleveland-1967". When concrete walks are laid on clay, and extra excavation to a depth of one-and- one-half inches (1 1/2'') must be made and filled with sand or gravel, to act as a foundation to the 4 of sidewalk proper. No blocks of concrete shall be larger than six feet (6') and the joints must be cut by the use of an approved "Grooving Tool" making a groove one-fourth inch (1/4") deep. All edges shall be rounded with an approved "Edging Tool" to a radius of one-fourth inch (1/4"). Existing aprons and "drive areas" of the walk must be constructed of concrete. Aprons and the area of walk over which vehicles drive must be no less than six inches (6") in thickness, and must be laid in accordance with Supplemental to State Specifications for the City of Cleveland. At all water-meter covers, gas boxes, hydrants, or other obstructions, neatly fitted openings shall be cut in the sidewalk. No walk shall be laid until all these obstructions have been raised or lowered to the correct elevations. No obstructions shall be placed in front of any catch-basin, fire hydrant, fire alarm box or letter box, or near enough to the same to interfere with their use. No change in the width of the walk to be laid shall be made from that of existing walks on the street at the time work is done under this permit, unless specifically permitted by the Director of Public Service. Trees, lawns, and shrubbery shall not be interfered with or destroyed by any work performed by the contractor. Walks must be laid to the same grade as existing walks on the street, unless permission for change of grade is obtained from the Director of Public Service. Only one-half (1/2) of the sidewalk in the business district can be obstructed at one time, unless contractor has an obstruction permit. Gutters must be left open at all times. The spacing between the walk and the curb line must be graded to allow water drainage, and must be of a gradual slope from the walk to the curb line. The Contractor is responsible for removing all dirt and rubbish caused by his work. CURBING: Curbing shall conform to the standards established for size and quality in the district in which it is to be installed. Cast-in-place concrete curbs and integral curbs, where used, shall conform to detail Plan No. ME-246 of the City of Cleveland. Copies of these specifications and plans for Pavement Repair and Laying of Concrete Sidewalks may be obtained, upon request, from the Division of Engineering and Construction of the City of Cleveland. Page 12 of 20

37 PAGE 7 OF 7 SPECIFICATIONS/DESCRIPTIONS OF PRODUCTS AND/OR SERVICES MANHOLES, CASTINGS AND GRATING DPU MH-0413 DPU MH-0611 D DETAILED SPECIFICATIONS D.1 TYPE OF DESIGN PRECAST CONCRETE MANHOLES Manholes shall be reinforced precast concrete design to meet or exceed the latest ASTM standards for "Underground Precast Concrete Utility Structures" (ASTM C858, latest revision) and "Minimum Structural Design Loading for Underground Precast Concrete Utility Structures" (ASTM 857, latest revision) - HS20 Bridge Loading. D.1.1 Concrete Precast concrete minimum strength shall be 5,000 psi after 28 days. Minimum wall thickness shall be six inches (6"). D.1.2 Reinforcing All reinforcing steel to be Grade 60 or more. Minimum concrete cover for reinforcing steel shall be three-quarters of an inch (3/4"). D.1.3 Joints All precast-to-precast joints shall be sealed with a preformed plastic gasket similar to Ram-Nek Preformed Plastic Gasket as manufactured by K. T. Snyder Company. Federal Specifications SS-S for sealing compounds. D.1.4 Openings All openings to meet job requirements shall be supplied at no additional charge. Reinforcing around openings shall be supplied so as to assure structural integrity. D.1.5 Pulling Irons All pulling irons to meet job requirements shall be supplied at no additional charge. Location of pulling irons in each manhole is to be determined during the design of the new CPP underground infrastructure and is to be approved by CPP before each manhole is cast. ITEM 8

38

39

40

41

42

43

44

45

46

47

48

49

50

51

52

53

54

55

56

57

58

59

60

61

62

63

64

65

66