1 CALL TO ORDER PLEDGE OF ALLEGIANCE AGENDA Board of Directors Special Board Meeting Monday, October 30, :30 AM 9300 Fanita Parkway, Santee, CA OPPORTUNITY FOR PUBLIC COMMENT Opportunity for members of the public to address the Board (Gov. Code ) REPORTS The following items are reports and are placed on the Agenda to provide information to the Board and the public. There is no action called for on these items. The Board may engage in discussion upon which a specific subject matter is identified but may not take any action other than to place the matter on a future agenda. 1. EASTERN SERVICE AREA SECONDARY CONNECTION PROJECT (JN ) - CONSTRUCTION UPDATE AND TOUR Recommendation: 1. Tour of the construction site located at 8954 El Dorado Pkwy, El Cajon 2. Reference construction progress report for July SITE VISIT TO LAKE JENNINGS LOCATED AT 9535 HARRITT RD IN LAKESIDE, CA FOR TRACER STUDY RELATED TO EAST COUNTY ADVANCED WATER PURIFICATION PROJECT ADJOURNMENT NOTICE TO THE PUBLIC This agenda was posted at least 24 hours before the meeting in a location freely accessible to the public. No action may be taken on any item not appearing on the posted agenda, except as provided by Gov. Code Section The complete agenda package is available for public review on the District s website, Any written materials provided to a majority of the Board of Directors within 72 hours prior to the meeting regarding any item on this agenda will be made available for public inspection at the District s Customer Service Center located at 9300 Fanita Parkway. For questions or request for information related to this agenda contact Amy Pederson, Board Secretary, at or apederson@padre.org. [October 30, 2017] Page 1 of 2 [Agenda]

2 Upon request, this agenda will be made available in appropriate alternative formats to persons with disabilities, as required by Section 202 of the American with Disabilities Act of Any person with a disability who requires a modification or accommodation in order to participate in a meeting should contact our ADA Coordinator: Larry Costello at or lcostello@padre.org PUBLIC COMMENT PROCEDURES Members of the public may address the Board regarding items not appearing on the posted agenda, which are within the subject matter jurisdiction of the Board. Speakers are requested to state name, address and topic, and observe a time limit of 3 minutes each. Public comment on a single topic is limited to a total of 15 minutes. Anyone desiring to address the Board regarding an item listed on the agenda should fill out a request to speak form and provide it to the Board Secretary. These forms are available in the Board Room on the counter near the entrance doors. CERTIFICATION OF POSTING I certify that on October 27, 2017, I posted a copy of the foregoing agenda near the regular meeting place of the Board of Directors of Padre Dam Municipal Water District, said time being at least 24 hours prior to the meeting, in accordance with Gov. Code Section (a). Amy Pederson, Board Secretary [October 30, 2017] Page 2 of 2 [Agenda]

3 COMMITTEE AGENDA REPORT Meeting Date: 10/30/2017 Dept. Head: Al Lau, P.E. Submitted by: Michael Hindle, P.E. Department: Engineering Approved by: Allen Carlisle, GM SUBJECT: EASTERN SERVICE AREA SECONDARY CONNECTION PROJECT (JN ) - CONSTRUCTION UPDATE AND TOUR RECOMMENDATION(S): Reference attached construction progress report for September 2017 and attend a tour of the construction site located at 8954 El Dorado Pkwy, El Cajon. ALTERNATIVE(S): 1. N/A ATTACHMENT(S): 1. Monthly Construction Progress Report for September 2017 FUNDING: Requested amount: N/A Budgeted amount: Are funds available? Yes No Project cost to date: PRIOR BOARD/COMMITTEE CONSIDERATION: STRATEGIC PLAN IMPLEMENTATION: This agenda item is consistent with the District s Strategic Plan & meets one or more of the following Strategic Goals: Provide safe, reliable water, recycled water and sewer services; Ensure fiscal health and competitively sustainable rates; Enhance customer communications and education; Increase water, wastewater and energy independence; Maintain workforce excellence; Expand park and recreation opportunities. Reviewed by: Dept Head Finance Legal Standard Form Action Required: Motion Resolution Ordinance None Policy Updates: Rules & Regulations Standard Practices & Policies Action Taken: As Recommended Reso/Ord. No. Other

4 SUMMARY: Padre Dam Municipal Water District issued a Notice to Proceed on December 8, 2016 for the construction of the Eastern Service Area Secondary Connection Project. The construction duration is expected to last approximately 500 calendar days. According to this schedule, the Project would be completed in the spring of RECOMMENDATION(S): Reference attached construction progress report for September 2017 and attend a tour of the construction site located at 8954 El Dorado Pkwy, El Cajon. Page 2 of 2

5 Attachment 1 EASTERN SERVICE AREA SECONDARY CONNECTION PROJECT PDMWD JN MONTHLY CONSTRUCTION PROGRESS REPORT SEPTEMBER 2017 PREPARED FOR PADRE DAM MUNICIPAL WATER DISTRICT PREPARED BY BRADY (CONSTRUCTION MANAGER)

6 CONSTRUCTION COST MANAGEMENT Updated Cost Report Original Cost Amount $14,692, Changes to Date Amount $69, Total Contract Amount $14,761, Total Completed to Date $5,072, Prior Invoice Total $590, This Month s Invoice $860, Retention to Date $253, Project Violation Penalty to date $0.00 Expenditure Progress Percent Complete Dollars (approximate) 34% Expenditure this Period 6% RESERVOIR WALL CONSTRUCTION SCHEDULE RESERVOIR COLUMN FOOTING Calendar days in Contract: 500 Calendar days complete: 288 Remaining calendar days: 212 Rain days allowed: 21 Rain days used: 11 Contract Completion Date: April 22, 2018 CHANGE ORDERS AND PENDING ISSUES New This Period PCO 14 - Alpine Emergency Work, PCO 07 - Main Pipeline Pothole Profile Changes, and PCO 06 - DC 03 Water Authority Communication Cabinet and Card Access changes are being reviewed and negotiated. TOP FIVE ISSUES/DECISIONS/CHANGES/RISKS TO PROJECT RESERVOIR COLUMN FORM AND SCAFFOLDING Interpretation of System Supplier in specification section and loop drawing responsibilities VAG Plunger Valve Casting UT/MT Testing in Istanbul, Turkey Coordination of Underground Electrical Conduit installation for the Pump Station Understanding welding procedures and testing to meet Water Authority and Helix WD requirements Additional Costs for the revised Supply & Discharge Pipeline alignments derived from pothole data ESASCP Monthly Report September of 3 Printed 10/17/2017

7 CONSTRUCTION ACTIVITIES RESERVOIR ROOF FORMWORK Main Site (Reservoir, Pump Station, & Flow Control Facility) (JN ) Poured concrete for reservoir wall sections 5 through 8. All wall pours complete. Formed and poured reservoir column bases and placed column rebar and formwork. Erected scaffolding and formed roof deck. Pump station suction lateral piping encased. SDCWA Flow Control Facility concrete slab formed and poured. Installed 20 supply pipe from FCF to Reservoir. Excavated jack and bore pit for tunnel. Viejas Cultural Monitor and ASM Archaeologist present for all soil disturbing activities. Discharge Pipeline (JN ) N/A Viewside Lane Project (JN ) N/A. El Capitan Pipeline Vault (JN ) N/A PLANNED WORK FOR OCTOBER 2017 FCF FORM REMOVAL AFTER SLAB POUR Los Coches Creek Crossing Supply Pipe Installation Form and pour reservoir columns and roof deck. Post tensioning of reservoir wall vertical tendons. Electrical contractor installation of pump station conduits to allow for concrete slab installation Form and pour thickened footing for pump station. Form and pour FCF wall. Construct FCF CMU retaining wall. Begin shaft excavation, set up jacking equipment and begin tunnel boring operation under I-8 Freeway. SCHEDULE ANALYSIS Contract Schedule Project Completion slipped 10 CD, from 29MAY18 to 08JUN18, 47 CD later than the original and current CCD of 22APR18 Significant rainfall occurred on the following days: N/A. (0 rain days this month, total 11) Variances - N/A PUMP STATION LOOKING WEST ESASCP Monthly Report September of 3 Printed 10/17/2017

8 CONSTRUCTION MANAGEMENT QUALITY ASSURANCE/QUALITY CONTROL Non-compliances issued No NCR s issued to date Tests taken and Results Concrete compression test results for Reservoir Wall Pours 6 & 7: 28-day 5580 psi; Pour 8: 7-day 4650 psi; Column Footing: 7-day 3260; (4500@28 days required). Compaction tests for backfill at pump station and along Main Site pipelines. ENGINEERING PUMP STATION LOOKING WEST LOOKING SOUTH AT TUNNEL BORING PIT LOCATION, SE CORNER OF MAIN SITE Design Changes DC-01: Drawing C-16 detail 8 wall schedule DC-02: Drawing C-5 NE retaining wall steps DC-03: PD7 FCF Communication Cabinet and Card Access Control System (10 drawings) DC-04: VOID DC-05: Revised pipeline profiles (multiple drawings) DC-06: Drawing ST-2, add rock subdrain below reservoir Engineering Challenges Coordination with Helix Water District to provide protection to the 12-inch ACP traversing the north side of the Main Site, 20-inch supply pipe profile raised 0.7 feet and slurry backfill to be installed. Coordination with Helix Water District for November/December shutdown to connect to existing 48- inch Flume. Coordination with SDCWA for submittal reviews and QA/QC tests and inspections. Factory inspections of Water Authority Plunger Valve in Turkey and Germany and Monolithic Isolation Joints in Houston, Texas. MEETINGS Weekly Construction Progress Meetings: 9/7, 9/14, 9/21, 9/28. Other Meeting with PD staff, Filanc and the CM team to review the conduit layout for the Pump Station provided in Submittal SAFETY TUNNEL BORING PIT No safety issues were reported for work in September. SMART Safety Group performed a safety audit on 9/28 with only minor corrections required. ESASCP Monthly Report September of 3 Printed 10/17/2017

9 Photo Log 1 Reservoir wall form 2 Reservoir wall pour 3 Reservoir wall rubber base installation 4 PS discharge piping welding 5 PS flowmeter vault 6 PS suction lateral encasement 7 PS electrical room conduits 8 20 suction piping double ball joint 9 Suction pipe joint taping 10 Welding & coating 20 pipe for Los Coches Creek crossing 11 Excavation of jack and bore pit 12 Jacking pit backstop