Major construction projects current and upcoming. March 19, 2018

Size: px
Start display at page:

Download "Major construction projects current and upcoming. March 19, 2018"

Transcription

1 Major construction projects current and upcoming March 19, 2018

2 Project Management unit

3 McTavish Gate Project

4 Existing conditions Gate deterioration Water drainage issues Redpath Hall stairs deterioration Underground water mains need to be upgraded.

5 Project description Restoration of the gate itself. Resurfacing of the roadway/sidewalk. Addition of bike racks, hydraulic bollards. Improve lighting. Improve connection with University Centre terrace. Waterproof Redpath Hall foundation (north side only). Redpath Hall stairs reconstruction. Replacement of 2 water mains and addition of a meter chamber.

6 Proposed design By EKM

7 Leacock Amphitheatre Project

8 Existing conditions Leacock Building (1965) façades and foundation show varying degrees of damages and deterioration. Concrete structure west and south of Leacock has deteriorated over time due to water infiltration and insufficient drainage capacity.

9 Project description Phase I Leacock Building: Repairs to façades and exterior glass walls ( curtain walls ) Improvements to vestibules to make them universally accessible Waterproofing of the foundation Phase II - Areas south and west of Leacock Building: Will be demolished, rebuilt and redesigned Will be transformed into a multi-purpose exterior amphitheatre.

10 Proposed design

11 Proposed design

12 Schedule PROJECT PHASE START DATE END DATE Phase I (Leacock Building) March 2018 Oct Phase II (Amphitheatre) April 2019 Sept. 2019

13 McIntyre/LSC garage Repair damaged structure Project

14 Project description Repair or rebuild deteriorated sections of concrete slabs Replace existing HVAC systems Replace existing drainage systems Code upgrades

15 Project description (cont d) Exterior: envelope repairs to south portion of parking

16 Schedule PROJECT PHASE START DATE END DATE Construction June 2018 Aug Substantial Completion / Commissioning Aug Oct Occupancy / Delivery Oct. 2020

17 University Centre Replacement of HVAC system & electrical distribution Project

18 Existing conditions Ventilation system and perimeter heating systems are obsolete (1965); replacement parts are no longer available. Electrical distribution system also needs to be replaced.

19 Project description Replace entire existing HVAC system. Build new mechanical room for kitchen HVAC system in basement of the building. Replace the building s electrical distribution systems. Addition of a new washroom given high building occupancy. Bring building up to the most recent building codes with respect to the electromechanical systems.

20 Schedule PROJECT PHASE START DATE END DATE Construction April 2018 Winter 2019 Occupants relocation March/April 2018 Progressive return Full occupancy Jan. 2019

21 Bensadoun School of Retail Management Project

22 Project description Phase 1: Renovation of the east façade and part of the south façade of the Bronfman Building for the Bensadoun School of Retail Management (part of the Desautels Faculty of Management). Phase 2: Renovation of a section of the main and second floors of the Bronfman Building for the Bensadoun School of Retail Management.

23 Project description Main floor 2 nd floor Sherbrooke façade McTavish façade

24 Proposed design

25 Schedule PROJECT PHASE DATE Phase I Summer 2018 Phase II Fall 2018

26 Stewart-Biology Building West wing redevelopment Project

27 Project update Work completed: Lot 0: users moved out in September 2017 Lot 1: selective demolition and partial asbestos decontamination in January 2018 Work to come: Lot 2: complete demolition and asbestos decontamination by July 2018 Lot 3: tender process by May and June 2018 for fit-out Tentative end date: by Winter 2020 (Lot 3/fit-out - substantial completion)

28 Proposed design (south-east façade)

29 Proposed design (lab, W2 level)

30 Macdonald-Harrington Building Envelope renovation Project

31 Project update Work completed Excavation, installation of drainage system, soil decontamination and backfilling Foundation: Repairs and waterproofing Masonry: South façade and south chimney Windows: All wooden windows removed, restoration in progress. Roof: Annex roof completed Work to come (& tentative end dates): Masonry: North, east, and west façades masonry repair (by Oct. 2018) Windows: Wooden windows restoration and installation, aluminum windows replacement (by Jan. 2019) Roof: Main roof (by Oct. 2018) Tentative project completion date: March 2019

32 Macdonald Engineering Masonry restoration Project

33 Project update Work completed: North and south sections of Macdonald wing: reconstruction of masonry walls to be completed by end of April 2018 Work to come: Central section of the Macdonald wing: masonry restoration and rain water management interventions Electrical wing: masonry restoration and roof replacement. Tentative end date: Full project completion by spring of 2019.

34 Roddick Gates Restoration and redesign Project

35 Project update Work completed: Rehabilitation of monument incl. foundation, two center columns and stonework Improvement of drainage system Renovation of half-moon by the city Installation of paving stones and landscaping on east side Work to come: Complete the replacement of underground electrical cables and conduit infrastructure. Installation of granite benches, hydraulic and fixed bollards, new lighting and interactive wayfinding tactile screen. Landscaping and furniture installation on the west side Tentative completion date: May 2018

36 Other projects Replacement of HVAC systems (to be completed between March and December 2018) Lyman Duff Rutherford Burnside Ferrier Education Macdonald-Stewart Library

37 Other projects (cont d) Other current projects (funded by SIF program): Wong: upgrades to the high-temperature metals laboratory ( foundry ) August 2018 Rutherford: upgrades to the Nanotools Microfabrication Laboratory August 2018 Construction of new emergency power facility (to house two generators) November 2018

38 Other projects (cont d)