1 Environmental Monitoring Report Semester Report August VIE: Strengthening Water Management and Irrigation Systems Rehabilitation Project (ADB5) - Component 2: Construction and Rehabilitation of Bac Hung Hai Irrigation and Drainage Infrastructure Prepared by Southeast Asia Institute for Water Resources and Environment for the Central Project Office (CPO) MARD and the Asian Development Bank.

2 CURRENCY EQUIVALENTS (1 st June 2013) Currency unit Viet Nam Dong (VND) VND 1,00 = $ $1.00 = VND ABBREVIATIONS ADB Asian Development Bank AFD Agence Francaise Development Ban QLDA Projects Management Unit BHH Bac Hung Hai irrigation and drainage system BVMT Environmental protection CBOs Community Based Organizations CEMP Community Environmental Management Program CPMU Central Project Management Unit CPO Central Project Office EMP Environmental Management Plan GOV Government M&E Monitoring & Evaluation PPMU Provincial Project Management Unit PRA Public Relative Assessment QLMT Environmental management SEMP Site Environmental Management Program TN&MT Environment and National Resources TOR Term of References TVGS Supervision consultant DONRE Department of Natural Resources and Environment IEE Initial Environmental Examination QCVN Vietnam National Environmental Standards MEASURES UNIT ha Hectare kg Kilogram km Kilometer m Meter t Ton NOTES In this report, "$" refers to US dollars This environmental monitoring report is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature. In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area

3 TABLE OF CONTENTS LIST OF TABLES... ii LIST OF FIGURES... ii CHAPTER 1: SUMMARY OF PROJECT AND IMPLEMENTATION PROGRESS Introduction of project Objectives of components Main works items of project Implementation location of components Implementation progress of project... 4 CHAPTER 2: MONITORING RESULTS The monitoring time The results of community based monitoring Implemented contents Results of community based monitoring Environmental monitoring results of construction supervision consultant Implementation contents Environmental monitoring results of construction supervision consultant On site inspection Contents of On site inspection Results of on site inspection The analysis results of surface water samples in the fifth monitoring Synthesing results of the fifth and the sixth monitoring CHAPTER 3: CONCLUSION AND RECOMMENDATION Conclusion Achieved results Pending issues Recommendations Plan for next 3 months monitoring APPENDIX Appendix 1: Location of sub - project Appendix 2: Some photos in the monitoring time Appendix 2-1: Some photos in the fifth monitoring Appendix 2-2: Some photos in the sixth monitoring... 50

4 Appendix 3: Analysis results of environmental samples Appendix 4: Meeting minutes with stakeholders Appendix 4-1: Monitoring minutes and list of participant in the fifth monitoring Appendix 4-2: Monitoring minutes and list of participant in the sixth monitoring Appendix 5: The monitoring forms LIST OF TABLES Table 1.1: Sub projects in BHH system... 2 Table 1.2: Implementation progress of sub - projects... 5 Table 2.1: Results of community based monitoring Table 2.2: Number of environmental monitoring forms implemented by construction supervision consultant Table 2.3: Synthesizing the assessment based on score given by construction supervision consultant Table 2.4: Assessment results of construction supervision consultant Table 2.5: Locations of on site inspection of sub - projects Table 2.6: Summary the results of on site inspection in the fifth monitoring Table 2.7: Synthesizing the pending issues of sub projects Table 2.8: Description of air sampling location Table 2.9: Description of surface - water sampling location Table 2.10: Synthesis of the sixth monitoring LIST OF FIGURES Figure 1.1: Diagram of sub- projects... 3 Figure 2.1: DO concentration in surface water at monitoring location HP2 the fifth monitoring Figure 2.2: SS concentration in surface water at monitoring location HP2 the fifth monitoring Figure 2.3: COD concentration in surface water at monitoring location HP2 the fifth monitoring Figure 2.4: BOD5 concentration in surface water at monitoring location HP2 the fifth monitoring Figure 2.5: NH 4 + concentration in surface water at monitoring location HP2 the fifth monitoring Figure 2.6: NO 2 - concentration in surface water at monitoring location HP2 the fifth monitoring... 36

5 CHAPTER 1: SUMMARY OF PROJECT AND IMPLEMENTATION PROGRESS 1.1 Introduction of project Strengthening Water Management and Irrigation Systems Rehabilitation project, invested by ADB and AFD, includes three components: (i) Components 1: Construction of New Educational Facilities for Water Resources University. (ii) Components 2: Construction and rehabilitation of Bac Hung Hai irrigation and drainage system infrastructure. (iii) Components 3: Strengthening capacity of BHH Service Providers Objectives of components 2 Long term objectives: To improve water supply and drainage for: transforming cropping-pattern by irrigation and drainages solutions, that can continuously supply to stable production and water use for 100% residents in the Bac Hung Hai until 2020; Reduce the drought frequency in the agricultural cultivation areas upto 85% by year 2020; Decrease the damages caused by flood in the region, specially in the low land of Hung Yen and Hai Duong provinces. Hence, it can create a stabilize condition to human life and production activities in considering an sustainable socio - economic development, ecological environmental protection, prevent surface water pollution and deterioration of water resources. Short term objectives: - Providing sufficient water for agricultural, aquaculture activities, meet the water supply demand for the industrial zones, residential areas and remedy environmental pollution situation by development and enhance the capacity of the rrigation system in the project areas. - Modernizing and improving irrigation-system performance - Innovating, improving management practices and service quality - Strengthening institution for sustainable exploitation of the system to achieve proposed targets - Establishing, strengthening and developing institution for the regional management and exploitation agencies in appropriate, effective and sustainable way; - Strengthening management and operation practices with community s participation through education, communication and public consultation Main works items of project The works items relate to environmental assessment including (Table 1.1): - Constructing 8 new pumping stations, of which 1 irrigation and 7 drain pumping stations; - Rehabilitating and upgrading 2 drain pumping stations. 1 Package 14 Monitoring the implementation of environmental management plan for the

6 Table 1.1: Sub projects in BHH system No. Name of Sub project 1 Phu My irrigation pump-station New construction / upgrade/ Rehabilitati on New construction Capacity ( m 3 /s) Location 13.2 Dinh To commue - Thuan Thanh district Bac Ninh province Remark Use water from Duong river 2 Lien Nghia drain pumpstation 3 Nghi Xuyen drain pumpstation New construction New construction 25 Lien Nghia commue - Van Giang district - Hung Yen province. 55 Thanh Cong provincr - Khoai Chau district - Hung Yen province Pumping to drain to the Red river Construction of sewer to upstream of Cuu An river to create drainage basin. 4 Chua Tong drain pumpstation 5 Kenh Vang II drain pumpstation 6 Nhat Trai drain pumpstation 7 Co Ngua pump-station 8 Cau Dua drained pumpstation New construction Rehabilitatio n (change machine) New construction New construction New construction 11 Trung Hung commune - Yen My district Hung Yen province 44 Trung Kenh commune - Luong Tai district - Bac Ninh province 30 Minh Tan commune - Luong Tai district - Bac Ninh province 7 Van Giang commune - Ninh Giang district - Hai Duong province 17 Van To commune - Tu Ky district - Hai Duong province Pumping to drain to the Red river Pumping to drain to the Kim Son river Improvement of pump devices and electric auxiliary, restoring capacity pump station of 44 m 3 /s Draining water to Thai Binh river Pumping to drain to the Luoc river Pumping to to the Luoc river 9 Doan Thuong drain pump - station New construction 15.6 Doan Thuong commune - Gia Loc district - Hai Duong province Draining water to Dinh Dao river 2 Package 14 Monitoring the implementation of environmental management plan for the

7 No. Name of Sub project 10 My Dong drain pumpstation New construction / upgrade/ Rehabilitati on Upgrading (change machine) Capacity ( m 3 /s) Implementation location of components 2 Location 22 Tien Phong commune - Thanh Mien district - Hai Duong province Remark Pumping to drain to Luoc river Bac Hung Hai System (BHH) is located in the center of the Red River Delta, in the administrative boundaries of four provinces: 2 districts on the southeast of Hanoi, the entire of Hung Yen Province, 7 districts of Hai Duong and 3 districts of Bac Ninh province. BHH system is enclosed with four main rivers in the areas: Duong river is in the North, Luoc river is in the South, Red river is in the West and Thai Binh river is in the East. The total irrigation area of the system is 192,045 ha, of which, 142,479 ha is agricultural land can be served by these rivers system. The total inhabitant in the region is 2.8 million, but more than 2.2 million people are working in agricultural field. BHH system is also divided into 10 sub-regions: Gia Lam, Gia Thuan, Chau Giang, Bac Kim Son, Cam Giang - Hai Duong city, An Thi. Binh Giang - Bac Thanh Mien, Tu Loc (Gia Loc-Tu Ky), Southwest of Cuu An, Southeast of Cuu An.. Ten sub- project locations can be seen in the Figure 1.1 to Appendix 1. Figure 1.1: Sub- projects location map 3 Package 14 Monitoring the implementation of environmental management plan for the

8 1.2 Project progress implementation Updating to August 04,, The sumarises of the project progress implementation are (also in the table 2.1). Of which : - The sub projects: Phu My, Kenh Vang, Cau Dua, Doan Thuong, My Dong, Lien Nghia and Nghi Xuyen achieved construction progress on time that s indicated in approved schedule. - The Sub projects of Chua Tong, Nhat Trai are delayed construction progress by some reasons:. - Chua Tong sub project: + Because of the narrow road for material vehicles transportation, the vehicle is difficulty to transoport sheeting piles and concretes. + Due to additional design for strengthening sheeting piles at household s side to households - Nhat Trai sub - project: due to high groundwater level, it is in process of waiting designing units to change construction execution. The summaries of main actitivities of pumping station sub projects as follows: - Phu Mysub project: the construction of management house, surrounding area of management house; discharge canal (section from discharge tank to culvert under dyke), pumping house and discharge tank have been done. volume approximately achieved 35% - Kenh Vang sub project : the construction of management house, pumping house, centre controlling house, head - works construction (sewer grates systems, intake tank, retaining dam) have been done. Construction volume achieved 90% - Nhat Trai sub project: the constructions of diversion canal, work stations on canal and culverts under dyke has been done. - Chua Tong sub project: the construction has been stopped by addtional design of reinforcing sheeting pile at household s side - Lien Nghia sub project : filled up water-saturated sand, installed scaffolding for floor pump, concrete floor, reinforced the wall of pumping house, intake tank and digged the diversion channel at the inlet. - Cau Dua sub project: the construction of intake canal s slope, concrete engine s floor; transportation of soil from river for levelling ground have been done - Doan Thuong sub project: lot A has been completing the management house and pumping house; Lot B, the canal has been dredging and completing Giang bridge s surface (Toan Thang commune) - Co Ngua sub project: preparation site plan, gathering construction material have been done. - My Dong: construction of pumping house, discharge tank, discharge tube of intake tank, roller bridge of intake tank and culvert under dyke have been done. Discharge canal and entry road of management house have been reinforced.. - Nghi Xuyen sub project: Processing, installing of formworks, reinforcement of pumping house, pump floor; construction of diversion canal and erecting electric pole of high voltage line have been done. 4 Package 14 Monitoring the implementation of environmental management plan for the

9 2013 Table 1.2: The Implementation progress of sub projects No. Name 1 Phu My pumping station Name of contractor Joint venture of Dong A International Joint Stock Company Anh Phuong construction JSC Ha Tay Irrigation Construction JSC Date of Signing Contract and Commenc ement Date of signing contract: April 01, 2013 Date of commence ment: April 19, 2013 Imple men - ting time 24 months In monitoring period (1/3/ - 31/7/) - The Management block and pumping station have been constructed - The Discharge tank and discharge canal has been constructing (section from discharge tank to culvert under dyke); Constructed items Cummulative work to 31/7/ - The Management house and pumping station house have been done; - Discharge tank, intake tank and discharge canal has been constructing (section from discharge tank to culvert under dyke); Testing pile has been done In monitoring period (1/3/ - 31/7/) - Earthwork of of the canal: 1,569.4 m 3 - Pumping station and Discharge tank: Excavation and transportation of 2,400m 3 of soil - Poured concrete canal slope : 600 slab Constructed volume Cummulative work to 31/7/ need to be done - Volume of Management house: 75% - Volume Campus of Management house: 9% - Discharge canal: 68% - Testing pile: 100% - Pumping station house and Discharge tank: 63% - Intake canal: 2% - Poured wall concrete to +3,5m Assessment of construction progress compared with schedule Construction progress has been delayed due to much rain, difficulties in the construction of the pump station foundation 2 Kenh Vang II pumping station Joint venture of Ninh Giang Construction Company Ltd - Date of signing contract: March 04, 24 months -Infrastructure of pumping The station has been - Headworks has completed. The discharge tank, sewer grate - Management house has been plastered with plastering - Excavation, transportation of mud, soil: more than 5000 m 3 ; Achieved construction progress comparison in 5 Package 14 Monitoring the implementation of environmental management plan for the whole project - Project Strengthening water management and irrigation systems

10 2013 No. Name 3 Nhat Trai Name of contractor Tan Thinh Construction Company Ltd - Irrigation Construction Joint Stock Company Lot A: Association Date of Signing Contract and Commenc ement 2013 Date of commence ment: April 19, Date of signing Imple men - ting time 36 months In monitoring period (1/3/ - 31/7/) finished; - Management block: filling sand, poured concrete; Build retaining wall have been done; - Sand has been filled, graded aggregate; poured concrete the road and Built drains -Infrastructure electric equipment and materials has been done - the construction Constructed items Cummulative work to 31/7/ system, intake tank, retaining dam have been done - Management house, pumping house, centre controlling house; Infrastructure have been finished the erection - Management house: fill the sand, poured concrete; Build retaining wall; - Contractor filled sand, graded aggregate, poured concrete the road into pumping station and constructed drain - Construction camps have been In monitoring period (1/3/ - 31/7/) volume: 3,350m 2 - Pumping station house has been painted with area of 2,900m 2 - Completed soil excavation to Constructed volume Cummulative work to 31/7/ need to be done - Concrete piles have been drived by 700m, bamboo plies by 3000m; - Poured concrete: 500m 3 - Completed soil excavation to altitude Assessment of construction progress compared with schedule with proposed plan (90% of contract value) -Approximately achieved 6 Package 14 Monitoring the implementation of environmental management plan for the whole project - Project Strengthening water management and irrigation systems

11 2013 No. Name pumping station Name of contractor between Song Hong irrigation construction JSC ; Construction and Development JSC; A Chau industrial Engineering JSC Lot B: An Binh construction corporation Date of Signing Contract and Commenc ement contract 25/12/ Date of commence ment 19/02/ - Date of signing contract 25/12/2013 -Date of commence ment 19/02/ Imple men - ting time 36 months In monitoring period (1/3/ - 31/7/) camps have been constructing - Contractor has been excavating foundation of pumping station house, intake tank, discharge tank stage 1; casting pile; processing pile steel - Diversion canal: pouring concrete traffic marker; concrete slab; Slope and bottom canal reinforcement - Works on Constructed items Cummulative work to 31/7/ constructed - Contractor has been excavating foundation of pumping station house, intake tank, discharge tank stage 1; casting pile; processing pile steel - Diversion canal: excavating canal, pouring concrete traffic peg; concrete slab; Slope and bottom canal reinforcement - Works on canal: In monitoring period (1/3/ - 31/7/) altitude of -1.0m - Construction camps: 50% - Casting tip of pile : Traffic peg: 170 peg; - Slab for reinforcement canal slope: 650 slab; - Slab for reinforcement bottom canal: Constructed volume Cummulative work to 31/7/ need to be done of -1.0m - Construction camps: 50% - Casting tip of pile : Excavation: 6,155m 3 ; - Foot beam block: 227 block - Traffic peg: 170 cái - Slab for reinforcement canal slope: 650 slab - Slab for Assessment of construction progress compared with schedule 3,5/58,8 billion VND (6% of contract value) - Construction progress has been delayed for 2 months due to have to design the road drainage for construction services -Approximately achieved 4.4 billion VND - Construction progress has been delayed because high groundwater 7 Package 14 Monitoring the implementation of environmental management plan for the whole project - Project Strengthening water management and irrigation systems rising

12 2013 No. Name 4 Chua Tong pumping station Name of contractor Hung Yen Irrigation and Dyke Construction JSC Date of Signing Contract and Commenc ement - Date of signing contract: January 27, 2013 Imple men - ting time 28 months In monitoring period (1/3/ - 31/7/) canal: Processing reinforcement formwork, reinforcement steel, pouring concrete pile; local bridge for the residents - Culverts under the dike: processing reinforcement formwork, reinforcement steel, pouring concrete pile - Retaining dam at upstream has been done Constructed items Cummulative work to 31/7/ Processing reinforcement formwork, reinforcement steel, pouring concrete pile; local bridge for the residents - Culverts under the processing reinforcement formwork, reinforcement In monitoring period (1/3/ - 31/7/) Constructed volume Cummulative work to 31/7/ need to be done Assessment of construction progress compared with schedule 8 Package 14 Monitoring the implementation of environmental management plan for the whole project - Project Strengthening water management and irrigation systems dike: steel, pouring concrete pile - Retaining dam at upstream has been done - Testing pile has been done 582 slab - Middle concrete piles 8m (99 piles); tip of piles: 8.5m (70 piles) Retaining dam at upstream has been done reinforcement bottom canal: 582 slab - Middle concrete piles 8m (110 piles); tip of piles: 8,5m (200 piles) -Construction of road base has been finished: 680m; Levelling ground volume: 70%; level, have to redesign to change to construction methods Construction progress has delayed in comparison with proposed

13 2013 No. Name 5 Lien Nghia pumping station Name of contractor Lot A: Association between Hai Phong Irrigation Construction Joint Stock Company - Date of Signing Contract and Commenc ement - Date of commence ment: April 18, Date of signing contract: September 20, Date of commence ment: Imple men - ting time 33 months In monitoring period (1/3/ - 31/7/) - Watersaturated sand were embanked, installed scaffolding pumping station floor; Constructed items Cummulative work to 31/7/ - Has constructed intake tank, discharge tank, the pumping station house Pumping station house: Worked piles shuttering / pressed concrete pile connections; excavated and transported soil of foundation; In monitoring period (1/3/ - 31/7/) Poured concrete pumping station floor and wall : 400m 3 Constructed volume Cummulative work to 31/7/ need to be done - Earthwork of 250m of diverson canal has been done. - Retaining dam at upstream has been done - Excavation and transportation of excavated soil: 12,400 m3 - Piles 9700m - Sanding 1660m 3 -Processing formworks: 4700m 2 Assessment of construction progress compared with schedule plan for 2 months due to narrow road for material transportation, causing difficulties for material transportation; - Additional components designed reinforced steel piles to ensure the safety of the people s house Construction progress has been ensured in comparison with approved plan 9 Package 14 Monitoring the implementation of environmental management plan for the whole project - Project Strengthening water management and irrigation systems

14 2013 No. Name Name of contractor Agriculture and Rural Development Construction Corporation Investment Advisory Northern Power Development JSC Date of Signing Contract and Commenc ement October 08, 2013 Imple men - ting time In monitoring period (1/3/ - 31/7/) - Excavation of soil in divertion canal; - Pouring concrete the floor, wall of the pumping station house, chest wall of intake tank Constructed items Cummulative work to 31/7/ waterproofing Larsen pile - Poured concrete foundation slab; Cast side wall; excavated foundation of discharge tank In monitoring period (1/3/ - 31/7/) Constructed volume Cummulative work to 31/7/ need to be done - Poured concrete: 1400m 3 Assessment of construction progress compared with schedule Lot B: Hung Yen Irrigation Construction Company - Date of signing contract: September 20, Date of commence ment: October 08, months Lasher of discharge canal s gate has been done - Testing piles: Pending profiles to cut dykes - Lasher of discharge canal s gate has been done - Cast lining brick for discharge canal slope - Discharge canal: excavated reserve pits; - Processing formworks: 2700m 2 ; - Excavation of Foundation : 500m 3 ; - Recycled plastic coverings: 800m 2 ; - Paving precast concrete slabs: Processing formworks: 2700m 2 ; - Excavation of Foundation : 500m 3 ; - Recycled plastic coverings: 800m 2 ; - Paving precast concrete slabs: 190m 3 ; - Poured rock: 5900m 3 Construction progress has been ensured in comparison with approved plan 10 Package 14 Monitoring the implementation of environmental management plan for the whole project - Project Strengthening water management and irrigation systems

15 2013 No. Name 6 Cau Dua pumping station 7 Doan Thuong Name of contractor Joint venture of Thanh Hoa Agricultural Construction and Rural Development Company - Thai Binh Irrigation Construction Joint Stock Company lot A: Joint venture of Hai Date of Signing Contract and Commenc ement - Date of signing contract: April 25, Date of commence ment: June 01, Date of signing Imple men - ting time 24 months 24 months In monitoring period (1/3/ - 31/7/) - Constructed intake canal slope to altitude m - Poured concrete floor engine, electric floor; discharge tank foundation ½ east; - Transported the excavated soil from outside the river bank for levelling ground - Bridge for catching raw Constructed items Cummulative work to 31/7/ - Culverts under the dike: pending dikes cut - Constructed sewer discharge, discharge canal; discharge canal outside the river; Factory engine floor; intake tank, intake cannal; Side wall of intake tank; Eastern units discharge tank (foundation) - Plain management house have constructed In monitoring period (1/3/ - 31/7/) 190m 3 ; - Pour rock: 5900m 3 - Concrete: 650m 3 - Levelling ground: 2,000 m 3 soil Constructed volume Cummulative work to 31/7/ need to be done Assessment of construction progress compared with schedule 11 Package 14 Monitoring the implementation of environmental management plan for the whole project - Project Strengthening water management and irrigation systems been - Bridge for catching raw - Has completed the - Levelling ground giai stage 1: 15,971m 3, - Driving concreted pille: 546 pilles. - Earthworking: 41,000m 3. - Driving sheeting pile: 208,93Tons - Concrete: 2,189m 3 - Bricks: 180m 3 - Plastering wall 2,200m 2. - Has completed the reinforcement steel: Construction progress has been ensured in comparison with approved plan - Construction progress has

16 2013 No. Name Name of contractor Duong Irrigation Construction and Electrical Installation Company Lot B: Thao Nguyen Date of Signing Contract and Commenc ement contract: April 10, Date of commence ment: June 01, Date of signing Imple men - ting time 24 months In monitoring period (1/3/ - 31/7/) garbage has been done; Installed electrical pillars; substation line and constructied substation. - Pumping house has been constructing from engine floor to the end of roof; House management: from foundation to the end of second floor - Canal has been dredged, Constructed items Cummulative work to 31/7/ garbage has been done; Installed electrical pillars; substation line and constructied substation. - Pumping house has been constructing from engine floor to the end of roof; House management: from foundation to the end of second floor. - Reinforced concrete piles has been pouring - Construction of drainage culvert, In monitoring period (1/3/ - 31/7/) reinforcement steel: Tons; - Bricks: m 3 -Poured concrete: m 3 - Concrete: m3; Constructed volume Cummulative work to 31/7/ need to be done 327.7Tons; Shapes steel: 17.18Tons - Bricks: m 3 - Poured concrete: 3,240,. m 3 - Canal dredging: 133,733.8m 3, Assessment of construction progress compared with schedule been ensured in comparison with approved plan ; -Approximately achieved 80% of contract value - Construction progress has 12 Package 14 Monitoring the implementation of environmental management plan for the whole project - Project Strengthening water management and irrigation systems

17 2013 No. Name 8 Co Ngua pumping station Name of contractor Company Ltd Association between Construction JSC no.12 and Thai Binh irrigation construction consultant JSC and Hai Duong Date of Signing Contract and Commenc ement contract: April 10, Date of commence ment: June 01, Date of signing contract: April 05, Date of commence ment:: August 01, Imple men - ting time 520 days In monitoring period (1/3/ - 31/7/) canal slope has been reinforced for canal section K2,2-K2,6 - Four bridges for the local people has been constructing ; - Construction of discharge culvert under dyke has been completing Construction volume has not been available Constructed items Cummulative work to 31/7/ gravity canal, dredging canal, strengthening canal slope have been finished (canal section K2,2- K2,6); - Four bridges for the local people have been constructing; - Construction of discharge culvert under dyke has been completing Construction volume has not been available In monitoring period (1/3/ - 31/7/) - Reinforcement 43,883Tons; Shapes steel: 18,453Tons. - Rocks: m 3 ; Bricks: m 3. - Excavated soil and filled soil: 38,434 m 3 ; Construction volume has not been available Constructed volume Cummulative work to 31/7/ need to be done - Reinforced canal slope by stone: 1,944.3m 3 ; Bricks: m 3 ; - Pouring concrete: 2,352.8m 3, - Round steel: 179,256Tons; Shape steel: 44.63Tons; - Filled soil: 29,500m 3 - Concrete piles: 120 piles. Construction volume has not been available Assessment of construction progress compared with schedule been ensured in comparison with approved plan ; -Approximately achieved 80% of contract value Commencement has been delayed in comparison with plan because the procedures of land acquisition based on new 13 Package 14 Monitoring the implementation of environmental management plan for the whole project - Project Strengthening water management and irrigation systems

18 2013 No. Name 9 My Dong pumping station 10 Nghi Xuyen Name of contractor pump manufacture JSC Joint venture of Dai An Investment and Construction Joint Stock Company and Construction Joint Stock Company No. 12 Lot A: Joint venture of Song Date of Signing Contract and Commenc ement Imple men - ting time In monitoring period (1/3/ - 31/7/) Constructed items Cummulative work to 31/7/ In monitoring period (1/3/ - 31/7/) Constructed volume Cummulative work to 31/7/ need to be done Assessment of construction progress compared with schedule. regulations have to complete. - Date of 24 - Discharge - Discharge tank, -Pouring - Pouring concrete: - Construction signing months tank, culvert, culvert, roller concrete: ,250 m 3 ; progress has contract: roller bridge bridge of intake m 3, - Excavated soil and been ensured in May 06, of intake tank; tank; gate of - Excavated soil filled soil: 9,788 m 3 comparison 2013 gate of culvert culvert under dyke and filled soil: - Bricks: m 3 with approved - Date of under dyke have been done; 6,053 m 3 - Plastering: 4,075.6 plan; commence have been - Reinforced - Bricks: 10 m 3 m 2 -Approximately ment: done. discharge canal - Transportation of achieved 55% June 11, - Reinforced and driveways into waste: 171,680 m 3 of contract 2013 discharge management house value canal and - Pumping station driveways house has been into constructing management house - Pumping station house - Date of signing 36 months has been constructing - Processing and installing - Base treatment and pouring - Formwork for pumping house, - Excavated soil: 24,000m 3 ; - Construction progress has 14 Package 14 Monitoring the implementation of environmental management plan for the whole project - Project Strengthening water management and irrigation systems

19 2013 No. Name Pumping station Name of contractor Hong Construction JSC Thanh Hoa Agriculture and Rural Development Company 6.3 Joint Stock Company Date of Signing Contract and Commenc ement contract: August 21, Date of commence ment: September 08, 2013 Imple men - ting time In monitoring period (1/3/ - 31/7/) of formwork, reinforcement steel for foundation, wall of pumping house, pumping floor have been done; -Poured concrete station wall; pumping floor; - Constructed diversion canal; - High voltage transmission line tower has been installing. Constructed items Cummulative work to 31/7/ concrete for bottom slab of management house; Driving Lasen sheeting pile; Cofferdam construction; mechanical and high-voltage lines; - Foundations formwork and reinforcement, walls, pumping floor have been done; - Poured concrete foundation and walls of the pumping station; - Install the stop log gians of pumping house and sewer grate. In monitoring period (1/3/ - 31/7/) side wall: 2,000m 2 - Reinforcement steel: 50 ton; - Foundation and wall of pumping house has been poured: 2,600m 3. Constructed volume Cummulative work to 31/7/ need to be done - Driving pile for base treatment: 2.144m; - Driving Lasen sheeting pile: 8,280m; - Formworks for foundation and wall of pumping station house: 10,000 m 2 - Concrete: 5,137.6 m 3. - Reinforcement steel: 531,866 ton; Assessment of construction progress compared with schedule been ensured in comparison with approved plan; some work items exceed construction progress such as construction of electrical line, management house; -Approximately achieved 46% of contract value 15 Package 14 Monitoring the implementation of environmental management plan for the whole project - Project Strengthening water management and irrigation systems

20 2013 No. Name Name of contractor Lot B: Hai Phong irrigation construction JSC and Mien Bac electrical investment and development Company Date of Signing Contract and Commenc ement - Date of signing contract: August 21, Date of commence ment: September 12, 2013 Imple men - ting time 36 months In monitoring period (1/3/ - 31/7/) - Processing and installing of formwork, reinforcement steel of foundation and wall have been done; - Culvert with section no.1 and no.2 have been poured with concrete; - Foundation of culvert has been filled with soil to altitude m Constructed items Cummulative work to 31/7/ - Processing and installing of slit valve; reinforcement steel of foundation and wall have been done - Canal and culverts under dykes have been concreted; Excavated discharge canal - Dyke has been filled with soil to altitude +8.75m; - Gate of culvert under dyke has been processing and installing. In monitoring period (1/3/ - 31/7/) - Processing and installing of formwork: 1,536 m 2 - Reinforcement steel: 80 tons; - Concreted: 1,100 m 3 - Filled soil volume for culvert foundation: 11,800m 3. Constructed volume Cummulative work to 31/7/ need to be done - Excavated soil: 23,000m 3 ; - Volume of filled soil for culvert foundation: 13,200m 3 - Concreted: 5, m 3 ; - Driving pile for base treatment: 5,920m; - Steels: tons - Formworks: 7,900 m 2 Assessment of construction progress compared with schedule - Construction progress has been ensured in comparison with approved plan; Approximately achieved 57% of contract value. 16 Package 14 Monitoring the implementation of environmental management plan for the whole project - Project Strengthening water management and irrigation systems

21 CHAPTER 2: MONITORING RESULTS 2.1 The monitoring time (i) The fifth monitoring time: - On 29th April : Worked with CPO regarding on the contents in the fifth monitoring and collecting the relevant documents of components 2 - From May 05 to May 15, : visit the construction site of sub projects of components 2 ( in Bac Ninh, Hai Duong and Hung Yen province) (ii) The sixth monitoring time: - On August 01, : worked with CPO regarding on the contents in the sixth monitoring and collecting the relevant documents of components 2. - From August 04 to August 14, : visit the construction site of sub projects of components 2 ( in Bac Ninh, Hai Duong and Hung Yen province) 2.1 The results of community based monitoring Implemented contents Interviewing local authorities and local people in the project area about construction s impacts on environment, society and resolving conflicts which have been arised during construction. Numbers of interviewee include 360 people, in which: - Gender based classification: 296 males and 64 females - Position classification : 8 Chairmans of commune, 10 Vice chairmans of commune, 6 land administration staffs, 2 village s leader and 234 local people in affected area. The detailed list of interviwees in the fifth monitoring can be seen in Appendix 5. - Collecting form no. 4: Because of no information response of environmental safety of community that there is no form no The results of community based monitoring Table 2.1: The results of community based monitoring Sub project s name (for all No pumping station in The fifth monitoring areas) 1 Phu My The issues of environmental sanitation, occupational safety have been done well; got on well with the local authority and the local people 2 Kenh Vang II - Civil contractors have collaborated well with commune government regarding the issues of traffic Response The sixth monitoring The issues of traffic safety and occupational safety has been ensured at the construction site. Contractors have implemented well the environmental mitigation measures - Construction is coming to finish, clean, and there is no impact on environment of surrounding area - Security at construction site is 17 Package 14 Monitoring the implementation of environmental management plan for the

22 No Sub project s name (for all pumping station in areas) The fifth monitoring safety and order security in the region. - Local people have no responses about impacts of construction activities. 3 Nhat Trai According to the assessment of People s Committee of Minh Tan commune, although being a complicated area, the sub project has implemented well the issues of worker s management, security at the construction site as well as in the region However, People s Committee of commune has some recommendations.: - The business road through construction site is narrow; the vehicle transport the material and waste soil need to be covered and reduce dust by transporting. - In case of problems uprising, the collaboration between local authority and relevant parties have to take the lead to resolve the issues 4 Chua Tong - The construction site is relatively clean. People s Committee of Trung Hung commune highly appreciated the work to protect environment and workers at the construction site. - Contractor need to build special sign boards or warning sign board (ie. water holes warning sign board) to local people near construction Response ensured The sixth monitoring - The issues of ensuring traffic safety, occupational safety at construction site have been implemented by Civil contractors well - There are no impacts on current traffic situation, security, and people s living - Minh Tan commune has not been received the construction progress information and the, construction plan of packages - The contractor has not used water to watering the road surface regularly, causing the dust clouds flew to the construction site - The construction site is relatively clean, the sub project has been stopped temporary, there is no impact on environment - People s Committee of Trung Hung commune appreciated the collaboration between sub project s PMU and locality in resolving, overcoming the landslide signal in case of constructing foundation that leading to unsafety for Nguyen Dang Quang s household 18 Package 14 Monitoring the implementation of environmental management plan for the

23 No Sub project s name (for all pumping station in areas) The fifth monitoring site, especially for children 5 Lien Nghia - Civil contractors have implemented well about the collecting domestic waste and guaranteed environmental sanitation at the construction site - Local people always support and desire the project complete on time. 6 Cau Dua - There is no impact on environment and people s living, because the construction site is located far from residential area. - Contractors have implemented well to the issues of traffic, occupational safeties at the construction site and keep a good contact with the local authority 7 Doan Thuong Lot A: has not impacted on people s living areas. Lot B : - Road surface in front of People s Committee office of Doan Thuong commune is muddy due to rain and dusty when it dries. The Contractors need to speed up construction work to get it back in starting stage. - PMU needs to make some solutions (build a temporary pumping station) for irrigation water supply to whole cultivable land areas that have been affected by landslide canal leading to no water irrigation Response The sixth monitoring - During the construction time, contractors activities did not impact on surrounding environment - Safety for vehicles going through construction site has been ensured - Security has been implemented well in region. - The Sub project got on well with locality - Surounding environment has not been affected - Security has been ensured - The civil contractors have been requested to follow the constructing schedule in order to the local people get more benefits from the project - The civil contractors of Lot B and Lot A kept a good collaborated with local authority and people living around - The pending issues in the previsous monitoring of Lot B have been overcome: road surface for which section is in front of People s Committee s office and school of Doan Thuong commune are reinstated. The protection wall along the Thach Khoi canal for ensuring traffic safety was built - There is no impact on security situation in region 19 Package 14 Monitoring the implementation of environmental management plan for the

24 Sub project s name (for all No pumping station in The fifth monitoring areas) 8 Co Ngua - People s Committee of Van Giang commune, Ninh Giang district has not received EMP s report and information of the package s progress. PMU of sub project should make a collaboration to local authority when a construction is started 9 My Dong - Contractors have implemented the issues of environmental protection, working site sanitation. They provided the local with several support to retain bank for irrigation canal in order to provide irrigation water supply for agricultural production of the local 10 Nghia Xuyen Pumping station - Contractor and insurance company have been calculated the household damage caused by construction(the civil contractor has paid for the household compensation VND 50 Mill, but total estimated cost for damage based on insurance company is VND 80 Mill). Presently, this household has satisfied and there is no more complaint. - Security at the construction site has been ensured. Workers are aware of protection environment at the Response The sixth monitoring - People s Committee of Van Giang commune has received EMP report and information of package s construction progress - There is a few workers; there is no arising problem. Workers should be reminded not going out too late for ensuring safety - Contractor needs to make a contract with local collecting group to collect workers domestic waste - Material transporting vehicles need to be covered avoiding constructions material/waste falling on road - Information of progress, construction plan has been informed to People s committee of Tien Phong commune - There is no impact on people s living and surrounding environment - The construction site is clean; workers are aware of environmental protection 20 Package 14 Monitoring the implementation of environmental management plan for the

25 No Sub project s name (for all pumping station in areas) The fifth monitoring construction stie as well as surrounding areas - Contractor has good collaboration with the local authority and the local people Response The sixth monitoring - Contractor needs to speed up construction progress in dry season In general, almost of Civil contractors kept a good colllaboration with local authorities, supported and created favourable working conditions for local government and resident. Construction activities also are not impacted much to the environment, society. Some details are as following: - The sub projects of Phu My, Kenh Vang II, Lien Nghia, Cau Dua and Nghi Xuyen have been highly appreciated to implement well the EMP by the local community: - At the fifth monitoring: Civil contractor of Lot B (Doan Thuong sub - project) has not fully treated the issues of reinstating the road surface, such as the section front of school and People s Committee office, hence people living in the areas did not agree with it. Nhat Trai sub project has not paid more attention on watering road surface that lead the dust at road section going through to the construction site. - At the sixth monitoring: Nhat Trai sub project has not used watering road surface that that leading to dust from business road went through to the construction site. In additional, the civil contractors have not sent the necessary information of construction progress, construction plan of packages to People s Committee of Minh Tan commune. The reinstating road surface for the section of front of People s Committee office and school of Doan Thuong commune has been done. 2.2 Environmental monitoring results of construction supervision consultant Implementation contents In the fifth and sixth monitoring, consultant collected the environmental monitoring results from construction supervision consultants, are as follows: - The environmental monitoring form of construction supervision consultant as provided by PMUs of sub projects. The number of collected form is described below and also listed in table 2.2): + Form no. 1: 58 collecting environmental monitoring information forms have been taken. The construction supervision consultants have assessed the implementation measures to mitigate the construction impacts on environment, society by giving the following score: 1: no implementation 2: sketchy implementation 3 : fully implementation 4 : very good implementation 21 Package 14 Monitoring the implementation of environmental management plan for the

26 + Form no. 2: Monitor, manage arising risk: because there was no arising risk recorded, then the form no.2 is not necessary to conduct - The Consultant interviewed CSC to clarify the the daily notes recorded regarding to the implementation of EMP by the Constractors. Table 2.2: The number of implemented environmental monitoring form by construction supervision consultant No. Sub project s name (Pumping station) The monitoring time 22 Package 14 Monitoring the implementation of environmental management plan for the 5th 6th Form no.1 Form no.2 Form no.1 Form no.2 1 Phu My Kenh Vang II Nhat Trai Chua Tong Lien Nghia Cau Dua Doan Thuong Co Ngua My Dong Nghi Xuyen Total The Environmental monitoring results of construction supervision consultant Table 2.3 shows the syntheszed results of forms assessing by the construction supervision consultants: Table 2.3: Synthesizing the assessment based on score given by construction supervision consultant TT Name of Sub project (Pumping station) The fifth monitoring Number of contents with score < 3 Number of contents with score 3 The sixth monitoring Number of contents with score < 3 Number of contents with score 3 1 Phu My Kenh Vang II Nhat Trai Chua Tong Lien Nghia Cau Dua

27 TT Name of Sub project (Pumping station) 7 Doan Thuong The fifth monitoring Number of contents with score < 3 Number of contents with score 3 The sixth monitoring Number of contents with score < 3 Number of contents with score 3 Lot A Lot B Co Ngua My Dong Nghi Xuyen Lot A Lot B Total (i) The assessment results of the construction supervision consultants in the fifth monitoring: - About 8/10 sub projects (more than 11 contents) have been obtained the score 3. Of which, sub projects of Kenh Vang II, Nhat Trai, Cau Dua and Nghi Xuyen have achieved the average score 3 for 12/12 contents. - 8 contents achieved the average score 3 in My Dong sub project; Four contents get the score lower than < 3 are remained. - The sonstruction supervision consultants indicated that some sub projects have not thoroughly overcome the comments of previous monitoring, such as the sub project of Doan Thuong, Chua Tong and My Dong (table 2.4 ). The pending issues are following : + Car washing station at the entrance points of the construction sites of the Phu My, Chua Tong and Doan Thuon sub projects have not been set + The recycle bin and mobile toilets have not been available at construction site for workers in the sub projects of Chua Tong and Phu My + Location of material storage is nearby the local people s house and traffic road without being covered Rock and soil are frequency felt down on the road during transportation, they have not been cleaned (My Dong sub - project) + The temporary fences to separate construction area from people s house and manufacture areas have not been set up in the sub-projects of Phu My, Chua Tong and Nhat Trai. The sign board light and signal system at night have not been installed as well (Nhat Trai sub - project) (ii) The assessment results from the sixth monitoring time of construction supervision consultant: - There are 8/10 Sub projects obtained the average score of 3 (11 12/12 contents). In which, the sub projects of Kenh Vang 2, Nhat Trai, Cau Dua, Co Ngua and Nghi Xuyen achieved 100% of contents with the score Package 14 Monitoring the implementation of environmental management plan for the

28 - Doan Thuong sub - project (Lot B), about 8 contents achieved the score 3, but 4/12 contents achieved the score lower than 3. In comparision between 2 monitoring times, the results show that a number of contents with the score 3 increased from 123 to 124 contents; the number of content with the score lower than 3 decreased from 9 to 8 contents. The sub projects of Phu My, Kenh Vang 2, Lien Nghia, Cau Dua and Nghi Xuyen in the sixth monitoring time, several issues (mitigation measures) from the fifth minitoring are remain. In the sub projects of Doan Thuong (Lot B) and My Dong, some current issues can be listed: + Doan Thuong sub project (Lot B): There is no recycle bin, mobile toilet at construction site for workers; the implementation of spraying lime for dredged canal s surface disinfection has not been done; red light at night in the construction site should be considered. + My Dong sub - project: the construction site has not been clean regularly; waste has not been collected and transported to dumping site properly; falling rock, soil during transportation haves not been cleaned promptly. No. Sub project s name (pumping station) Table 2.4: The Assessment results of construction supervision consultant Pending issues in the fifth monitoring 1 Phu My - Mobile toilet at construction site was not available - The wheel washing station was not set up at the entrance point of construction site 2 Kenh Vang II Workers working at construction site have not fully worn protective clothes 3 Nhat Trai - The temporary fence to separate construction area from people s house and manufacture area has not been set up - Construction sign boards as well as light signal system at night have not been installed 4 Tong Chua - Recycle bins and mobile toilets were not available at the construction site for workers - Wheel washing station was not set up at the entrance point of the construction site Pending issues in the sixth monitoring The wheel washing station was not set up at the entrance point of construction site There is no pending issues Lot A: The light signal system at night has not been installed at the construction site The construction has been stopped temporarily 5 Lien Nghia There is no pending issues There is no pending issues 6 Cau Dua There is no pending issues There is no pending issues 24 Package 14 Monitoring the implementation of environmental management plan for the

29 No. Sub project s name (pumping station) Pending issues in the fifth monitoring 7 Doan Thuong - There is no wheel washing station at the entrance point of the construction site; - Reinstating road surface for the section in front of the People s Committee office and school of Doan Thuong commune has not been done. Lot A: Pending issues in the sixth monitoring - The wheel washing station was not set up at the entrance point of construction site Lot B: - Recycle bins and mobile toilets were not available at construction site for workers - The implementation of spraying lime for disinfection on dredged canal s surface has not been done - Red light at night has not been installed at construction site 8 Co Ngua Construction has not been started Wheel washing station was not set up at the entrance point of construction site 9 My Dong - Material storage has been located closely to the residents house (< 50m) - Falling rock and soil during transportation have not been cleaned - The construction site has not been cleaned regularly; 10 Nghi Xuyen There is no pending issues There is no pending issues 2.3 On site inspection 2.3.1The contents of on site inspection The on site inspection has beeen implemeted by observation at construction site, directly interviewing workers and professional staffs, taking pictures, filling information in inspection form. The aspects of inspection include: + The implementation of environmental impact mitigation measures; + The implementation of social impact mitigation measures; + The implementation of occupational safety measures; + The implementation of traffic safety measures. - Collecting form no. 3 (Monitoring workers health participating construction): PMU has provided four forms of no.3 implemented by Civil contractor of Doan Thuong and Cau Dua sub project Locations of on site inspection are listed in table 2.5: 25 Package 14 Monitoring the implementation of environmental management plan for the

30 No. Sub project s name (pumping station) Table 2.5: The on site inspection locations of sub - projects The locations of on site inspection in the fifth monitoring 1 Phu My The construction area of management house, pumping house, discharge tank, intake tank and campsite of workers 2 Kenh Vang II The construction area of management house, pumping house, central controlling house, sewer grates system and intake tank 3 Nhat Trai Worker s campsite at the construction area of pumping station, diversion canal and area of forming testing pile 4 Chua Tong The area of retaining dam, worker s campsite, pumping house and surrounding area of the construction site 5 Lien Nghia The area of excavating discharge canal, excavating foundation of pumping house 6 Cau Dua The construction area of management house s foundation, intake tank, culvert under dyke and worker s campsite 7 Doan Thuong Lot A: The construction area of pumping house, intake tank, discharge tank Lot B: The area of dredging and embankment for Thach Khoi canal in front of People s Committee office of Doan Thuong commune, gravity culvert and bridge across canal 8 Co Ngua The site plane area for preparing construction of pumping station and The locations of on site inspection in the sixth monitoring The construction area of management house, pumping house, discharge tank, intake tank and campsite of workers surrounding area of construction site The construction area of management house, pumping house, central controlling house, sewer grates system and intake tank Worker s campsite at The construction area of pumping station, diversion canal and area of forming testing pile and road section going through construction site The area of retaining dam, worker s campsite, pumping house and surrounding area of the construction site The area of excavating discharge canal, pumping house The construction area of management house s foundation, intake tank, and worker s campsite Lot A: The construction area of pumping house, intake tank, discharge tank Lot B: The area of dredging and embankment for Thach Khoi canal in front of People s Committee office of Doan Thuong commune The site plan area for preparing construction of pumping station 26 Package 14 Monitoring the implementation of environmental management plan for the

31 No. Sub project s name (pumping station) The locations of on site inspection in the fifth monitoring workers campsite 9 My Dong The area of reparing pumping house, culvert and surrounding area 10 Nghi Xuyen The construction area of culvert under dyke; management house, pumping house and workers campsite The locations of on site inspection in the sixth monitoring and workers campsite The area of reparing pumping house, culvert and surrounding area including affected houses The construction area of culvert under dyke; management house, pumping house and workers campsite and surrounding area of construction site No The results of on site inspection The results of on site inspection have been synthesized in table 2.6: Table 2.6: The summaries of the on site inspection results in the fifth monitoring Sub project s name (pumping station) 1 Phu My 2 Kenh Vang II 3 Nhat Trai Recommendation in the fourth monitoring Making immediately fence to separate, warning construction works from fields area of the local people Making immediately fence to separate, warn construction works from fields area of the local people Making package s information boards, traffic sign boards, construction sign Recommendation in the fifth monitoring Making fence to separate construction works from paddy of the local people Setting up wheel washing station at the entrance points of the construction site to reduce dust - Replacing sign board of occupational safety following specification at the construction site - Transporting waste soil to dumping site as regulation - Installing construction sign boards as well as signal light system at Implemented x x Not implemented yet x x 27 Package 14 Monitoring the implementation of environmental management plan for the

32 No. Sub project s name (pumping station) Recommendation in the fourth monitoring boards Recommendation in the fifth monitoring night Implemented Not implemented yet - Making fence to separating construction site from paddy of the local people x - Regularly watering on road section which going through construction site to reduce dust x - Covering material transportion means and waste soil 4 Chua Tong There is no recommendations Making fence to separating construction site from the local people s house x 5 Lien Nghia Signing contract with the local collecting group to collect domestic waste Making sign board at the construction area of management house (field side) Installing sign board at construction area of management house (field side) x x Providing recycle bins and mobile toilets at construction site for workers x 6 Cau Dua Equipping protective clothes for workers at construction site during construction x Transporting waste soil as regulation and clean falling rock, soil during transportation process x 28 Package 14 Monitoring the implementation of environmental management plan for the

33 No. 7 Sub project s name (pumping station) Doan Thuong 8 Co Ngua 9 My Dong Recommendation in the fourth monitoring Making immediately protection fence along dredged canal section to ensure safety for traffic user. Cleaning road section in front of school and People s Committee office affected by construction Sending EMP report and progress information of package to People s Committee of Van Giang commune, Division of Natural Resources and Environment of Ninh Giang district Making package s information board, traffic sign board and construction sign board - PMU of My dong sub project collaborates with local authority in order to thoroughly overcome situation of cracking wall and yard of ancillary Recommendation in the fifth monitoring - Making immediately protection fence during constructing Thach Khoi canal to ensure safety for traffic participants Making fence to separate construction site from residential area and agricultural area Setting up wheel washing station at entrance points of construction site to reduce dust Sending EMP report, information progress of package to People s Committee of Van Giang commune and Division of Natural resources and Environment of Ninh Giang district - Transporting waste soil to dumping site as regualtion - Cleaning falling rock, soil during transportation process Implemented Not implemented yet 29 Package 14 Monitoring the implementation of environmental management plan for the x x x x x x x

34 No. Sub project s name (pumping station) Recommendation in the fourth monitoring construction of a family s house. Speeding up construction progress to return road surface for local people Recommendation in the fifth monitoring Implemented Not implemented yet - Replacing material storage to appropriate location and far from people s house at least 50 m - Placing prohibition sign boards out side of the construction site Equipping fully protective clothes for workers during construction Equipping fully protective clothes for workers during working hours x Equipping fully protective clothes for workers during construction Equipping fully protective clothes for workers during construction process x 10 Nghi Xuyen Assigning staff to monitor construction safety issue and train occupational safety for workers x Reinstating dyke section which is for construction of culvert under dyke before rainy season x a- The achieved results of on site inspection: - Kenh Vang II sub project the transportation of waste soil to dumping site has been followed the regulations; fences to separate construction site from fields of local people, the replacement of occupational safety sign board as regulation at construction site have been made - Nhat Trai sub project: Boards of package s information, traffic sign and construction sign have been built; vehicles transport material and waste soil from the construction site have been covered. 30 Package 14 Monitoring the implementation of environmental management plan for the

35 - Chua Tong sub -project: almost of the pending issues in the fifth monitoring have been resolved. Such as: + Presently, the house of Mr. Nguyen Dang Quang at Long Vi, Thanh Long commune (adjacent to pit) has been reinforced; the cracks between house and road are stop developing because the construction has been temporarily stopped. PMU bought and disaseembled 2 houses (adjacent to pit) to reduce load on sheet pile as well as ensure safety for people s house. + The issues of making temporary fence, warning sign board for the local people have been done. Security gate has been built to prevent unexpected people going through the construction area - Lien Nghia sub project: sign board at construction area of management house has been done (field side) and the signed contract for collecting domestic waste of workers with local collecting group is made. - Cau Dua sub - project: waste soil has been transported as regulation and cleaned falling rock during transportation process - Doan Thuong sub project (Thach Khoi canal operation): the protection fences are constructed to ensure the safety to the road users; the road section located front of school and People s Committee office of comune is cleaned regularly, the fences to separate construction site from residential areas and agricultural field are built - Co Ngua sub - project: The EMP report, information progress of package have been sent to People s Committee of Van Giang commune and Division of Natural resources and Environment of Ninh Giang district. The package s information board, trafic sign boards, construction sign board have been made. - My Dong sub - project: excavated soil has been transported to dumping site as regulation properly. Falling rock during transportation is gathered on time - Nghi Xuyen sub project has fully equipped protective clothes for workers in working hours b- The pending issues need to be resolved The pending issues of sub project have been synthesized in table 2.7 No. Sub project s name (pumping station) Table 2.7: The summaries of the pending issues Pending issues in the fifth and the sixth monitoring 1 Phu My - There is no fence to separating construction works from field of the local people - There is no warning sign board for deep hole at construction site (Figure17 - Appendix 2-2) Note The pending issues from the fifth monitoring 31 Package 14 Monitoring the implementation of environmental management plan for the

36 No. Sub project s name (pumping station) 2 Kenh Vang II Pending issues in the fifth and the sixth monitoring - Workers at construction site has not been fully equipped the protective clothes (Figure 18 - Appendix 2-2) - Contractors still allow the local people to go in the construction site for fishing in construction time 3 Nhat Trai - Road surface has not been cleaned and sprayed water to reduce dust for the road section going through the construction site (Figure 5 - Appendix 2-1) - There is no fence to separate construction works from road and paddy field of the local people (Figure 6 - Appendix 2-1) - Medicine box has not been available for the workers - Warning sign board for deep hole has not been available at the construction site - Temporary fence along with road of which section going through the construction site has not been installed (Figure 19 - Appendix 2-2) - Sign boards at the construction site are wrong specification and sketchy (Figure 20 - Appendix 2-2) 4 Chua Tong Contractor needs to regularly pay attention to status of Nguyen Dang Quang s house ( especially in case of constructing)to have promptly recovery measures 5 Lien Nghia Protective clothes for workers have not fully equipped at the construction site (Figure 21 - Appendix 2-2) 6 Cau Dua The pending issues in the fifth monitoring have not been overcomed thoroughly: Recycle bins and mobile toilets have not been provided at the construction site for the workers 7 Doan Thuong LotB: The measure to ensure irrigation water for cultivation has not been available Note The pending issues from the fifth monitoring the pending issues remains from the fifth monitoring 32 Package 14 Monitoring the implementation of environmental management plan for the

37 No. Sub project s name (pumping station) Pending issues in the fifth and the sixth monitoring 8 Co Ngua Materials have not been gathered, they are easy to generate dust (Figure 22 - Appendix 2-2) 9 My Dong Protective clothes for the workers in working hours have not been fully equipped while repairing pumping house (Figure 23 - Appendix 2-2) 10 Nghi Xuyen - The dyke has not been restated to origional altitude +11,83 m (Figure 24 - Appendix 2-2). Note the pending issues remains from the fifth monitoring the pending issues remains from the fifth monitoring The analysis results of surface water samples in the fifth monitoring According to regulation, taking samples to evaluate environmental quality (2 times/ year in March and November). In the fifth monitoring, several additional samples in 2013 have not been taken at sub projects because the construction plan was not started. A numbers of analysed samples in the fifth monitoring were 3 surface water and 4 air samples. The samples should be indicated, expreseed and described to sampling locations, weather conditions, natural environment, landscape, dust level, vibration, noise and emission resources, river flow condition; potential factors affect to environmental quality such as: traffic, construction and human activities, etc. The methods of sample collection, preservation, analysis procedure in laboratory and assessment method for environmental quality should be combined and followed Vietnam environmental quality control regulations (QCVN): - For exmaing and analysing air quality pollution based on QCVN 05: 2009/BTNMT, noise assessment based on QCVN 26: 2010/BTNMT, vibration assessment follows QCVN 27: 2010/ BTNMT. - Surface water quality assessment according to QCVN 08: 2008/BTNMT a) The analysis results of air samples Air sampling location description: Air samples were taken on May 05, to May 07, in weather condition of slight sunny, no wind. Location description of air sampling is in Table 2.8. No. Symbol Sampling location Table 2.8: Description of air sampling location The site description in the fifth monitoring 33 Package 14 Monitoring the implementation of environmental management plan for the

38 1 HP2-KK3 Nhat Trai pumping station 2 HP2-KK5 Lien Nghia pumping station 3 HP2-KK8 Co Ngua pumping station 4 HP2-KK10 Nghi Xuyen pumping station At the construction site closed to main road, workers were processing steel at construction area of pumping house, less dust Sampling location at the construction site, far from road, workers were processing steel at the construction area of pumping house, less dust. Sampling location at the construction site, no construction activities and no dust Sampling location at the construction site, far from road, in sampling time, workers were pouring concrete of culvert under dyke, no dust. The results of air samples analyse: The results obtained from air sample analysis (Table 3.1, Appendix 3) showed that the parameters of noise, vibration and dust at the location are below the permision level accordance with the regulations of Vietnam QCVN 05:2009, QCVN 26:2010. The Construction activities such as processing steel, pouring concrete and transportation means did not impact to the air environment at the construction place, because the activities were not operated. There are no construction activities at Co Ngua sub project site at present. However, the samples took at Nhat Trai pumping station sub project show the dust concentration was 0.28 mg/m3 approximate approach allowable standards in comparison with QCVN 05:2009) because contractor did not use water to watering road surface regularly. Hence, Civil contractors should pay attention to reduce dust in order to not impact on environment. b) Theresults of surface water samples analysis in the fifth monitoring time Describle the location of surface water sampling: The samples were taken from May 05, to May 07,, the weather conditions at that time are slight sunny and no wind. Table 2.9 shows the results Table 2.9: Description of surface - water sampling location No. Symbol Sampling location 1 HP2- NM3 Lien Nghia pumping station 2 HP2- NM6 Co Ngua pumping station The site description in the fifth monitoring - Taking sample in the Dong Que river near pumping station s construction, wrokers were cutting steel for constructing pumping house in sampling time. - No flow, dark green water, slight ordour, less garbage - Taking water sample at the Co Ngua pumping station, no construction activities in sampling time. - No flow, brown water colour, slight smell, 34 Package 14 Monitoring the implementation of environmental management plan for the

39 DO (mg/l) SS (mg/l) A HP2-NM7 Nghi Xuyen pumping station less garbage. - Taking sample in the Cuu An river near excavation of foundation position, no construction activities in sampling times. - No flow, green water colour, slight smell, no garbage, much weeds. The analysis results of surface water sample The analysis results of surface water quality of the fifth monitoring are listed in table 2 -appendix 3 and comparison charts from figure 2.1 to 2.6 show that: - At the Lien Nghia pumping station sub project (HP2-NM3): COD, NH + - 4, NO 2 are the main pollutants exceeding the permitted standards. COD concentration was 32.6 mg/l, exceeded the irrigation water standard about 1.09 times; NH + 4 (0.96 mg/l) concentration, - exceeds 1.92 times in comparison with irrgation water standard; NO 2 (0,05 mg/l) concentration exceeds 1.25 times standard level. According to the obsevation of consultant and locality s feedback, water quality at sampling location has been mainly polluted due to effect of waste from residential area,the construction activities did not impact on river water quality ( - At the sampling location of Co Ngua pumping station sub project (HP2-NM6): there are 3 pollution indicators exceeding allowable standards including: SS (59.32 mg/l) concentration exceeded standards about 1.19 times; NH 4 + (0.78 mg/l) concentration exceeded standard about 1.56 times; NO 2 - (0.06 mg/l) concentration exceeds allowable standards 1.5 times. River water has been polluted by domestic wastewater from the residential area living along river because in sampling time there was no construction activities at the construction site. - At the sampling location of Nghi Xuyen pumping station sub project (HP2-NM7): there are 4 indicators exceeding the limited value at column B1 QCVN 08:2008 including: SS (52.16 mg/l); COD (42.18 mg/l), NH 4 + (1.46 mg/l), NO 2 - (0.08 mg/l) exceed allowable standards representively 1.04 times; 1.21 times; 1.01 times and 1.28 times. Construction activities have not impacted on surface water quality because it s far from water resources. River water has been polluted due to impact of domestic wastewater of the residential areas living along river HP2-NM3 HP2-NM6 HP2-NM HP2-NM3 HP2-NM6 HP2-NM7 DO (mg/l) QCVN 08:2008 B1 Kí hiệu mẫu SS (mg/l) QCVN 08:2008 B1 Kí hiệu mẫu Figure 2.1: DO concentration in surface water at monitoring location HP2 the fifth monitoring Figure 2.2: SS concentration in surface water at monitoring location HP2 the fifth monitoring 35 Package 14 Monitoring the implementation of environmental management plan for the

40 NH4+ (mg/l) NO2- (mg/l) COD (mg/l) BOD5 (mg/l) , , HP2-NM3 HP2-NM6 HP2-NM7 COD (mg/l) QCVN 08:2008 B1 Kí hiệu mẫu 13,5 HP2-NM3 HP2-NM6 HP2-NM7 BOD5 (mg/l) QCVN 08:2008 B1 Kí hiệu mẫu Figure 2.3: COD concentration in surface water at monitoring location HP2 the fifth monitoring Figure 2.4: BOD5 concentration in surface water at monitoring location HP2 the fifth monitoring 1,2 1 0,8 0,6 0,4 0,2 0 HP2-NM3 HP2-NM6 HP2-NM7 0,07 0,06 0,05 0,04 0,03 0,02 0,01 0 HP2-NM3 HP2-NM6 HP2-NM7 NH4+ (mg/l) QCVN 08:2008 B1 Kí hiệu mẫu NO2- (mg/l) QCVN 08:2008 B1 Kí hiệu mẫu Figure 2.5: NH 4 + concentration in surface water at monitoring location HP2 the fifth monitoring 2.4 The pending issues and recommending to correct action plan Figure 2.6: NO 2 - concentration in surface water at monitoring location HP2 the fifth monitoring The monitoring results in the fifth and the sixth monitoring have been summaried in Table 2.9: 36 Package 14 Monitoring the implementation of environmental management plan for the

41 No. Sub - project Pending issues and recommendation 1 Phu My - Setting up the wheel washing station at the entrance point of the construction site to mitigate dust 2 Kenh Vang II - Making fence to separate the construction works from paddy field of the local residents - Installing sign board for deep, dangerous holes at the construction site - Workers at construction site need to wear the protective clothes - Local people have to be forbidden in construction time and its site 3 Nhat Trai Sending information of the construction progress and the construction plan of packages to People s Committee of Minh Tan commune - Regularly spraying water on road surface for the section going through the construction site to reduce dust - Making fence to separate construction works from paddy field of local people and installing temporary fence along with road which is going through the construction site - Providing medicine box for workers Table 2.10: The summaries of pending issues Agency/individual take responsibility Civil contractors of Phu My sub - project Civil contractors of Kenh Vang II sub - project Supervision/ monitoring Bac Ninh PMU with support of construction supervision consultant and environmental monitoring consultant Bac Ninh PMU with support of construction supervision consultant and environmental monitoring consultant Bac Ninh s PMU Environmental monitoring consultant Civil contractors of Nhat Trai sub - project Bac Ninh PMU with support of construction supervision consultant and environmental monitoring consultant - Replacing the sign boards which are wrong 37 Package 14 Monitoring the implementation of environmental management plan for the whole project - Project Strengthening water management and irrigation systems Time August 15, August 15, August August 20,

42 No. Sub - project Pending issues and recommendation specification at the construction site Agency/individual take responsibility Supervision/ monitoring Time - Making sign board for warning deep holes at the construction site 4 Chua Tong Cracking situation of Mr. Nguyen Dang Quang s house need to be monitored in order to have promptly overcoming measures (especially when construction is restarted) Civil contractors of Chua Tong sub - project Hung Yen PMU with support of construction supervision consultant and environmental monitoring consultant From now to the end of project 5 Lien Nghia Fully equipping protective clothes for workers at the construction site Civil contractors of Lien Nghia sub- project Hung Yen PMU with support of construction supervision consultant and environmental monitoring consultant August 6 Cau Dua Providing recycle bins for workers at the construction site Civil contractors of Cau Dua sub project Hai Duong PMU with support of construction supervision consultant and environmental monitoring consultant August 7 Doan Thuong Setting up wheel washing station at the entrance points of the construction site to mitigate dust Civil contractors of lot A Doan Thuong sub - project Hai Duong PMU with support of construction supervision consultant and environmental monitoring consultant August 15, Implementing primary treatment measure such as spraying lime for disinfection on surface of dredged canal Civil contractors of lot B Doan Thuong sub - project Hai Duong PMU with support of construction supervision consultant and environmental monitoring consultant August 15, Building temporary pumping station for irrgation PMU of Hai Duong Environmental monitoring August 15, 38 Package 14 Monitoring the implementation of environmental management plan for the whole project - Project Strengthening water management and irrigation systems

43 No. Sub - project Pending issues and recommendation water supply for whole agricultural areas which have been affected by landslide of the local irrgation canal 8 Co Ngua Setting up wheel washing station at entrance points of the construction site Material need to be tidily gathered to avoid dust 9 My Dong Fully equipping protective clothes for workers during construction time of reparing pumping house Agency/individual take responsibility Supervision/ monitoring Time consultant Civil contractors Environmental monitoring consultant Civil contractors of My Dong sub - project BHH s PMU with support of construction supervision consultant and environmental monitoring consultant August 10, August 15, 10 Nghi Xuyen Reinstating dyke section which is cut for construction of culvert under dyke to altitude +11,83m Civil contractors of Nghi Xuyen sub - project CPO with support of construction supervision consultant and environmental monitoring consultant November 11 All sub - projects Periodical medical examination for workers at the construction site needs to be implemented (6 months/ times All Civil contractors CPO with support of construction supervision consultant and environmental monitoring consultant August 20, 39 Package 14 Monitoring the implementation of environmental management plan for the whole project - Project Strengthening water management and irrigation systems

44 3.1 Conclusion CHAPTER 3: CONCLUSION AND RECOMMENDATION The achieved results (i) For PMU of sub project - PMUs have implemented well the issues of periodical inspection regarding on contractors compliance. PMU of Chua Tong sub project and Bac Hung Hai s PMU kept in touched and made a good collaboration with local authority and people, resolved well uprising problems during construction process. - Monthly, PMUs of Nghi Xuyen, Lien Nghia sub projects organised the training for workers regarding on environmental protection, occupational safety, traffic safety during construction,. (ii) For civil contractors Civil contractors of My Dong and Chua Tong sub - project have a good collaboration with local authorities and PMU in resolving arsing problems, The construction activities were not impacte to environment, society in the place. The sub projects have been appreciated well the issue of the implementation of EMP including: Phu My, Kenh Vang II, Lien Nghia, Cau Dua and Nghi Xuyen (iii) For construction supervision consultant - Construction supervision consultant fully recorded and submitted periodical environmental forms to PMUs of sub projects. The information of environmental safety, traffic safety, occupational safety and other arising problems at construction site have been reflected fully and exactly - In the fifth and the sixth monitoring: Construction supervision consultants of sub projects of Phu My, Kenh Vang, Nhat Trai (lot A) have reflected to PMUs and civil contractors in detail regarding on the concerned environmental issues during construction process; therefore, Civil contractors have overcome promptly the pending issues and implemented well the environmental impact mitigation measures. (iv) For local authorities/ communities The results of interviewing the local government, local people in projet area showed that People s Committee of communes in project area have fully taken their responsibility to monitor community, regularly inspect, reflect to PMU of sub projects regarding on the construction s impacts on environment and society. At the same time, the locality and local residents created favourable condition in land clearance, registering temporary accommodation for workers and in construction activities. (v) Regarding on construction s impact on environmental quality The analysis results of air and surface water in the fifth monitoring are following ( in the sixth monitoring, environmental samples were not taken because of rainy season): - Regarding on air environment: the construction activities of sub project have not impacted on air quality in region because most of contractors complied with noise, dust mitigation measures: Using the construction machines met the standard of exhaust gas, noise and vibration as regualtion; Regularly watering road surface to reduce dust, covering material storage yard... not much construction volume, and civil contractors implemented well the 40 Package 14 Monitoring the implementation of environmental management plan for the

45 mitigation measures for arising dust. At the sampling location of Nhat Trai pumping station, dust concentration is 0.28 mg/m 3 (approximately approaching allowable value in QCVN 05:2009) because the civil contractors did not regularly water on road surface. Thus, the civil contractor of Nhat Trai sub project need to pay attention on dust mitigation measure in order not to impact on environment. - Regarding on surface water quality: the construction activities of sub project basically have not impacted on surface water quality. The construction site, campsite, material storage and activities of loading material have to ensure the distance of 200m than surrounding water area. Cleaning construction machine are not allowed near water sources to avoid waste grease discharge to the water environment The pending issues The pending issues of sub project mostly relate to environmental sanitation, safety and health of workers, safety for community and traffic safety, the details are following: (i) Regarding on project information: The PMU of Bac Ninh has not sent the necessary information of construction progress and construction plant of Nhat Trai s packages to Minh Tan commune, Luong Tai district (ii) Regarding on environmental sanitation: - Recycle bins and mobile toilets have not been fully provided at the construction site: Cau Dua, Doan Thuong (Lot B) sub - project - Wheel washing station at entrance points of the construction site has not been set up: sub project of Phu My, Doan Thuong (Lot A), Co Ngua - Watering on road surface has not been regularly implemented: Nhat Trai sub - project - Material has not been gathered tidily to avoid dust: Co Ngua sub - project. (iii) Occupational safety: - Fence for separating construction works from the residential area and production area is not available (Phu My, Nhat Trai sub - project); - Warning sign board sfor deep holes at the construction site has not been available at the construction site (sub project of Nhat Trai, Phu My); - Protective clothes have not been fully equipped for workers during construction time (Sub project of My Dong, Lien Nghia, Kenh Vang II). - All contractors have not implemented periodical medical examination (6 months/time) for workers at the construction site. (iv) Community safety: - Nghi Xuyen sub project has not returned dyke to origional altitute; - Kenh Vang II sub project still allowed local people to go in the construction site for fishing during construction time (v) Traffic safety: - Nhat Trai sub project has not installed construction sign board as well as sign light at night; 41 Package 14 Monitoring the implementation of environmental management plan for the

46 - My Dong sub project did not clean promptly falling rock during transportation process Recommendations - For PMUs of sub projects need measures to force civil contractors into implementing recommendations and implementation time for regulations in the table 2.10 and minutes have been made while on site inspection (appendix 4). - For civil contractors need to overcome the pending issues of the previous monitoring, in the fifth and the sixth monitoring (see in the table 2.10). - For construction supervision consultants, beside filling in form no. 1, they have to monitor the implementation of recommendations in the previous monitoring; arising problems need to be filled in the form no.2 and timely reflect to PMU. 3.3 Plan for next 3 months monitoring The next monitoring plan of Environmental monitoring consultant will be implemented in November with the following contents: - Implement on site inspection - Synthesize monitoring forms of construction supervision consultant - Implement community based monitoring - Implement sampling to evaluate environmental quality 42 Package 14 Monitoring the implementation of environmental management plan for the

47 APPENDIX Appendix 1: Location of sub - projects Appendix 2: Some pictures at the monitoring place Appendix 3: Analysis results of environmental samples Appendix 4: Monitoring minutes and list of participants participated in the fifth and sixth monitoring Appendix 5: Monitoring forms 43 Package 14 Monitoring the implementation of environmental management plan for the

48 Appendix 1: Location of sub - project Figure 1: Location of Phu My sub - project Figure 2: Location of Kenh Vang II sub - project Figure 3: Location of Nhat Trai sub - project Figure 4: Location of Chua Tong sub - project Figure 5: Location of Lien Nghia sub - project Figure 6: Location of Cau Dua sub - project 44 Package 14 Monitoring the implementation of environmental management plan for the

49 Figure 7: Location of Doan Thuong sub - project Figure 8: Location of Co Ngua sub - project Figure 9: Location of My Dong sub - project Figure 10: Location of Nghi Xuyen sub - project 45 Package 14 Monitoring the implementation of environmental management plan for the

50 Appendix 2: Some pictures at the monitoring place 46 Package 14 Monitoring the implementation of environmental management plan for the

51 Appendix 2-1: Some pictures at the monitoring place Pic 1: : There was no fence separating construction site from paddy field of people Phu My sub - project Pic 2: Workers did not wear protective clothes in working hours - Phu My sub - project Pic 3: Sketchy sign board Kenh Vang II sub - project Pic 4: Waste soil has not been transported to dumping site Kenh Vang II sub-project Pic 5: Road section going through construction site was dirty Nhat Trai sub - project Pic 6: There was no fence separating construction site from paddy field of people Nhat Trai sub - project 47 Package 14 Monitoring the implementation of environmental management plan for the

52 Pic 7: Sign of crack between yard and pavement Chua Tong sub - project Pic 8: Sign of crack between road and house of Mr. Nguyen Dang Quang Chua Tong sub - project Pic 9: Falling soil on dyke surface - Cau Dua sub - project Pic 10: Waste soil has not transported to dumping site as regulation Cau Dua sub - project Pic 11: There was no protection barrier and sign board when Thach Khoi canal has been constructed with section going through school at Lot B Doan Thuong sub - project Pic 12: Location of collapsed irrigation canal Doan Thuong sub - project (Lot B) 48 Package 14 Monitoring the implementation of environmental management plan for the

53 Pic 13: Waste soil has not transported to dumping site My Dong sub - project Pic 14: Workers who were pouring concrete did not wear fully protective clothes Nghi Xuyen sub - project Pic 15: Taking air sample - Nghi Xuyen sub - project Pic 16: Mr. Nguyen Gia Long, Chairman of Tien Phong commune (My Dong sub - project) reflect the construction s impact on environment and society 49 Package 14 Monitoring the implementation of environmental management plan for the

54 Appendix 2-2: Some pictures at the monitoring place in the sixth monitoring Pic 17:There is no warning sign board for deep hole at construction site Phu My sub - project Pic 18: Workers did not wear protective clothes Kenh Vang II sub - project Pic 19: Protection fence to separate construction site from road has not been installed - Nhat Trai sub - project Pic 20: Construction sign board is wrong specification Nhat Trai sub - project Pic 21: Workers did not wear protective clothes Lien Nghia sub - project Pic 22: Material has not been gathered tidily Co Ngua sub - project 50 Package 14 Monitoring the implementation of environmental management plan for the

55 Pic 23: Workers did not wear fully protective clothes TDA My Động Pic 24: dyke has not returned to original altitude (+11,83m) Pic 25: Interviewed Mrs. Nguyễn Thị Thủy at Nghi Xuyên, Chi Tan commune Nghi Xuyen sub - project Pic 26: Interviewed Mr. Pham Dang Nen at Nhat Trai, Minh Tan commune Nhat Trai sub - project Pic 27: Interviewed Mr. Do Van Thanh at My Dong 1, Tien Phong commune (affected household) Chua Tong sub - project Pic 28: road section has been returned with protection wall (In front of People s Committee office and school of Doan Thuong commune) Doan Thuong sub - project 51 Package 14 Monitoring the implementation of environmental management plan for the

56 Appendix 3: Analysis results of environmental samples 1. Phú Mỹ PS 2. Liên Nghĩa PS 3. Nghi Xuyên PS 4. Chùa Tổng PS 5. Kênh Vàng II PS 6. Nhất Trai PS Figure 1: Diagram of sampling locations 52 Package 14 Monitoring the implementation of environmental management plan for the

57 Table 1: Analysis results of air samples at sub projects (the fifth monitoring) 53 Package 14 Monitoring the implementation of environmental management plan for the

58 Table 2: Analysis results of surface water samples of components 2 (the fifth monitoring) No Indicator Unit Analysis result QCVN 08:2008 HP2-NM3 HP2-NM6 HP2-NM7 column B1 1 ph DO mg/l SS mg/l COD mg/l BOD 5 mg/l NH NO 2-8 NO 3-9 PO 4 3- mg/l mg/l mg/l mg/l As mg/l Hg mg/l Pb mg/l Zn mg/l Dầu mỡ mg/l Coliform MPN/100ml Note: - HP2-NM3: Lien Nghia Pumping Station - HP2-NM6: Co Ngua Pumping Station - HP2-NM7: Nghi Xuyen Pumping Station QCVN 08:2008/ BTNMT column B1: National Technical regulation on surface water quality Ha Noi,. May Analysis staff Manager of Analysis Laboratory Department Institute for water and Environment Le Van Cu Master. Vu Quoc Chinh 54 Package 14 Monitoring the implementation of environmental management plan for the

59 Appendix 4: Meeting minutes with stakeholders 55 Package 14 Monitoring the implementation of environmental management plan for the

60 Appendix 4-1: Monitoring minutes and list of participant in the fifth monitoring 56 Package 14 Monitoring the implementation of environmental management plan for the

61 57 Package 14 Monitoring the implementation of environmental management plan for the

62 58 Package 14 Monitoring the implementation of environmental management plan for the

63 59 Package 14 Monitoring the implementation of environmental management plan for the

64 60 Package 14 Monitoring the implementation of environmental management plan for the

65 61 Package 14 Monitoring the implementation of environmental management plan for the

66 62 Package 14 Monitoring the implementation of environmental management plan for the

67 63 Package 14 Monitoring the implementation of environmental management plan for the

68 64 Package 14 Monitoring the implementation of environmental management plan for the

69 65 Package 14 Monitoring the implementation of environmental management plan for the

70 66 Package 14 Monitoring the implementation of environmental management plan for the

71 67 Package 14 Monitoring the implementation of environmental management plan for the

72 68 Package 14 Monitoring the implementation of environmental management plan for the

73 69 Package 14 Monitoring the implementation of environmental management plan for the

74 70 Package 14 Monitoring the implementation of environmental management plan for the

75 71 Package 14 Monitoring the implementation of environmental management plan for the

76 72 Package 14 Monitoring the implementation of environmental management plan for the

77 73 Package 14 Monitoring the implementation of environmental management plan for the

78 74 Package 14 Monitoring the implementation of environmental management plan for the

79 75 Package 14 Monitoring the implementation of environmental management plan for the

80 76 Package 14 Monitoring the implementation of environmental management plan for the

81 77 Package 14 Monitoring the implementation of environmental management plan for the

82 78 Package 14 Monitoring the implementation of environmental management plan for the

83 79 Package 14 Monitoring the implementation of environmental management plan for the

84 80 Package 14 Monitoring the implementation of environmental management plan for the

85 81 Package 14 Monitoring the implementation of environmental management plan for the

86 82 Package 14 Monitoring the implementation of environmental management plan for the

87 83 Package 14 Monitoring the implementation of environmental management plan for the

88 84 Package 14 Monitoring the implementation of environmental management plan for the

89 85 Package 14 Monitoring the implementation of environmental management plan for the