1 NORTHSIDE INDEPENDENT SCHOOL DISTRICT Facilities Construction May 2017 Leroy San Miguel ASSIST. SUPERINTENDENT FOR FACILITIES & OPERATIONS Henry Acosta EXECUTIVE DIRECTOR CONSTRUCTION & ENGINEERING Jim Berg DIRECTOR OF FACILITIES CONSTRUCTION Glenoaks Elementary School

2

3 2014 BOND PROJECTS

4 HARLAN HIGH SCHOOL (Formerly KALLISON RANCH HIGH SCHOOL) Architect Garza Bomberger & Associates Project Architect Roy Lewis NISD Project Manager James Evans Contractor Joeris General Contractor GMP - $110,800, Construction Period October 2014 May 2017 Construction Status: 96% Complete Project Scope New 2800 Student High School Site grading, utilities and landscaping. Interior CMU walls, drywall framing, electrical, plumbing, and HVAC installation, Window installation, interior painting, exterior brick veneer. Fire pump, concrete drives and parking areas in progress. Punch ongoing.

5 HARLAN HIGH SCHOOL (Formerly KALLISON RANCH HIGH SCHOOL) Aerial (March 20, 2017)

6 HARLAN HIGH SCHOOL (Formerly KALLISON RANCH HIGH SCHOOL) Front Entrance

7 HARLAN HIGH SCHOOL (Formerly KALLISON RANCH HIGH SCHOOL) (May 12, 2017)

8 HARLAN HIGH SCHOOL (Formerly KALLISON RANCH HIGH SCHOOL) (May 12, 2017)

9 HARLAN HIGH SCHOOL (Formerly KALLISON RANCH HIGH SCHOOL) (May 12, 2017)

10 HARLAN HIGH SCHOOL (Formerly KALLISON RANCH HIGH SCHOOL) (April 11, 2017)

11

12 KALLISON ELEMENTARY SCHOOL (KALLISON RANCH #2 ELEMENTARY) Architect Garza Bomberger Project Architect Roy Lewis NISD Project Manager Marilyn Sevedge Contractor Guido Construction Contract Amount - $24,640, Construction Period March 2016 May 2017 Construction Status: 75% Complete Project Scope New 800 Student Elementary School Masonry, brick, metal steel framing and sheetrock, MEP ductwork and roofing, ceramic tile in kitchen/restrooms, millwork install, paint/texture in progress.

13 KALLISON ELEMENTARY SCHOOL Aerial (May 16, 2017)

14 KALLISON ELEMENTARY SCHOOL Front Entrance

15 KALLISON ELEMENTARY SCHOOL (May 12, 2017)

16 KALLISON ELEMENTARY SCHOOL (May 12, 2017)

17 KALLISON ELEMENTARY SCHOOL (May 12, 2017)

18 KALLISON ELEMENTARY SCHOOL (May 12, 2017)

19 KALLISON ELEMENTARY SCHOOL (May 16, 2017)

20 KALLISON ELEMENTARY SCHOOL (May 16, 2017)

21

22 MORA ELEMENTARY SCHOOL (GROSENBACHER AREA ES) Architect Noonan Rittiman Project Architect John Rittiman NISD Project Manager Chris Parker Contractor DL Bandy Contract Amount - $24,465,000 Construction Period March 2017 May 2018 Construction Status (5% Complete) Project Scope New 800 Student Elementary School (Prototype of Boldt ES and Cole ES) Site work and building pad in progress.

23 MORA ELEMENTARY SCHOOL (Prototype of Boldt ES and Cole ES)

24 MORA ELEMENTARY SCHOOL (April 2017)

25 MORA ELEMENTARY SCHOOL (April 2017)

26 MORA ELEMENTARY SCHOOL (April 2017)

27 MORA ELEMENTARY SCHOOL (April 2017)

28

29 ADDITIONS AND RENOVATIONS PROJECTS IN PROGRESS

30 GLENOAKS ELEMENTARY - Administration Upgrades/Security Lobby Architect NextGen Architects Project Architect Joel Hernandez NISD Project Manager Marilyn Sevedge Contractor McGoldrick Construction Co. Contract Amount - $3,750, Construction Period June 2016 June 2017 Construction Status: 80% Complete Project Scope New Administration Building Roof, interior walls and masonry, HVAC, plumbing, electrical, brick, glazing, ceiling grid & tech cabling, painting & finishes in progress.

31 GLENOAKS ELEMENTARY (Rendering of Front Elevation)

32 GLENOAKS ELEMENTARY Administration Upgrades (May 12, 2017)

33 GLENOAKS ELEMENTARY Administration Upgrades (May 12, 2017)

34 GLENOAKS ELEMENTARY Administration Upgrades (May 12, 2017)

35 NORTHSIDE ACTIVITY CENTER RENOVATIONS Architect Richard Sanchez Architects, Inc. Project Architect Richard Sanchez NISD Project Manager Thomas Curiel Contractor O Haver Contractors Co. Contract Amount - $5,319, Tentative Construction Period February 2017 January 2018 Construction Status 7% Complete Project Scope Addition/Renovation Foundation and Site utilities work in progress.

36 NORTHSIDE ACTIVITY CENTER RENOVATIONS (May 15, 2017)

37 NORTHSIDE ACTIVITY CENTER RENOVATIONS (May 15, 2017)

38 NORTHSIDE ACTIVITY CENTER RENOVATIONS (May 15, 2017)

39 PAUL TAYLOR FIELD HOUSE RENOVATIONS Architect Garza Bomberger Architects Project Architect Roy Lewis NISD Project Manager Thomas Curiel Contractor Stoddard Construction Management, Inc. Contract Amount - $3,400, Construction Period February 2017 August 2017 Construction Status 16% Complete Project Scope ADA Interior/Exterior Renovations Demolition and Foundation framing work underway, elevator shaft work underway, plumbing work in Progress.

40 PAUL TAYLOR FIELD HOUSE RENOVATIONS (May 10, 2017)

41 PAUL TAYLOR FIELD HOUSE RENOVATIONS (May 10, 2017)

42 PAUL TAYLOR FIELD HOUSE RENOVATIONS (May 10, 2017)

43 CHILD NUTRITION CENTER Center Renovation Architect Shawn Kaarlsen & Associates Project Architect Shawn Kaarlsen NISD Project Manager James Evans Contractor Workman Commercial Contract Amount - $5,726, Construction Period July 2016 May 2017 Construction Status: 97% Complete Project Scope Warehouse Renovation Contract in progress. Renovation funded from Child Nutrition 2016 Growth & Improvement funds and 2010 Bond Savings. New switch gear being installed and new CPS transformer on its way. Walk-in cooler/freezers, walls, racks and ceilings being installed. Condensers set. Secondary power is installed. Testing of walk-in freezer will start May 5 th. Substantial completion scheduled for May 22, 2017.

44 CHILD NUTRITION CENTER Center Renovation (April 2017)

45 CHILD NUTRITION CENTER Center Renovation (April 2017)

46 2017 SECURITY LOBBIES at (9) ELEMENTARY SCHOOLS Architect NextGen Architects Project Architect Joel Hernandez NISD Project Manager Marilyn Sevedge Contractor CGC General Contractors Contract Amount - $1,293, Construction Period June 2017 August 2017 Project Scope New Security Lobby for (9) Elementary Schools: Adams Hill ES, Allen ES, Beard ES, Braun Station ES, Forester ES, Hoffmann ES, Knowlton ES, Timberwilde ES, and Villarreal ES Notice to Proceed issued March 20, 2017 Construction scheduled to start June 5, Submittal process has commenced.

47 2017 SUMMER FLOORING REPLACEMENTS Carson ES, Neff MS, & Warren HS Architect Huckabee Architects Project Architect Jeff Rodriguez NISD Project Manager Chris Parker Contractor SAFFI Contract Amount $339, Tentative Construction Period June 2017 August 2017 Project Scope Replacement of Flooring Notice of Award Issued March 29, Construction scheduled to start June 5, Submittal process has commenced.

48 COLONIES NORTH ELEMENTARY Window Upgrades / ADA Work Architect Huckabee Architects Project Architect Jeff Rodriquez NISD Project Manager Chris Parker Contractor Central Builders Contract Amount - $2,022, Tentative Construction Period June 2017 October 2017 Construction Status (0% Complete) Project Scope Window Upgrades and ADA Work Notice of Award Issued March 29, Construction scheduled to start June 5, Submittal process has commenced.

49 KNOWLTON ELEMENTARY Cafeteria / Kitchen Renovations / Library Addition Architect Pfluger Project Architect Carr Hornbuckle NISD Project Manager Chris Parker Contractor O Haver Contract Amount $2,335, Tentative Construction Period June 2017 November 2017 Construction Status (0% Complete) Project Scope Renovations and Additions to Cafeteria, Kitchen & Library Notice of Award Issued March 29, Construction scheduled to start June 5, Submittal process has commenced.

50 NEFF MS COMPETITION GYM FLOORING AND BLEACHERS Architect Garza Architects Project Architect Jesse Garza NISD Project Manager Chris Parker Contractor Henock Construction, LLC Contract Amount $243, Tentative Construction Period June 2017 August 2017 Construction Status (0% Complete) Project Scope Replacement of Flooring and Bleachers Notice of Award Issued March 29, Construction scheduled to start June 5, Submittal process has commenced.

51 GLENOAKS ELEMENTARY - Window Upgrades / ADA Work Architect NextGen Architects Project Architect Joel Hernandez NISD Project Manager Marilyn Sevedge Contractor Central Builders, Inc. Construction Budget - $1,100, Tentative Construction Period June 2017 August 2017 Construction Status (0% Complete) Project Scope Window Upgrades and ADA Work Schematic Design approved by Board in January. Notice of Award issued April 26, Construction scheduled to start June 5, Submittal process has commenced.

52 GLENN ELEMENTARY School Building Replacements / Security Lobby Architect LPA Project Architect Mark Oppelt / Lowell Tacker NISD Project Manager Marilyn Sevedge Contractor Suburban Construction Construction Budget - $6,850, Tentative Construction Period June 2017 August 2018 Construction Status (0% Complete) Project Scope Replacement of Administration/Classroom Building Notice of Award issued April 26, Construction scheduled to start June 5, Submittal process has commenced.

53 TIMBERWILDE ELEMENTARY Cafeteria/Kitchen Renovations/Library Addition Architect Shawn Kaarlsen & Associates Project Architect Shawn Kaarlsen NISD Project Manager Chris Parker Contractor Workman Commercial Construction Construction Budget $2,231, Tentative Construction Period June 2017 November 2017 Project Scope Renovations and Additions to Cafeteria, Kitchen & Library Notice of Award issued April 26, Construction scheduled to start June 5, Submittal process has commenced.

54 2017 FLOORING REPLACEMENTS Elrod, Glenn, Glenoaks, & Michael Elementary Architect CWS Architect Project Architect Robert Watts NISD Project Manager Chris Parker Contractor San Antonio Floor Finishers, Inc. Contract Budget $133, Tentative Construction Period June 2017 August 2017 Construction Status (0% Complete) Project Scope Replacement of Flooring Notice of Award issued April 26, Construction scheduled to start June 5, Submittal process has commenced.

55 2014 BOND PROJECTS IN BID/DESIGN PHASE SUMMER 2017

56 HOLMES HS FINE ARTS - AUDITORIUM Architect Alamo Architects Project Architect Jerry Lammers NISD Project Manager Thomas Curiel Contractor Bartlett Cocke Construction Budget - $27,000, Construction Period June 2017 December 2018 Project Scope Fine Arts Building Replacement Amendment No. 2 Signed. Building Demolition scheduled to start June 5, Abatement completed.

57 HOLMES HS FINE ARTS - AUDITORIUM (Rendering Perspective)

58 HOLMES HS FINE ARTS - AUDITORIUM (April 11, 2017)

59 HOLMES HS FINE ARTS - AUDITORIUM (April 11, 2017)

60 BOONE ELEMENTARY - Administration Upgrades, Bus/Student Canopy & Security Lobby Architect Garza Architects Project Architect Jesse Garza NISD Project Manager James Evans Contractor TBD Construction Budget - $4,900, Tentative Construction Period June 2017 August 2018 Project Scope Administration Upgrades, Bus/Student Walkway Canopy Modifications Contractor submitted for May Board Approval.

61 GLASS ELEMENTARY Window Upgrades / ADA Work Architect Marmon Mok Project Architect Monty Howard NISD Project Manager Chris Parker Contractor TBD Construction Budget - $1,500, Tentative Construction Period June 2018 August 2018 Project Scope Window Upgrades and ADA Work Schematic Design and Master Plan in progress.

62 GLENOAKS ELEMENTARY Library and Classroom Building Architect NextGen Architects Project Architect Joel Hernandez NISD Project Manager Marilyn Sevedge Contractor TBD Construction Budget - $10,000, Tentative Construction Period June 2018 December 2018 Project Scope Library and Classroom Building Schematic Design in progress.

63 2017 DOOR HARDWARE Glass ES, Westwood Terrace ES and Holmes HS Architect Chesney Morales Project Architect Richard Morales NISD Project Manager James Evans Contractor TBD Construction Budget $117, Tentative Construction Period June 2017 August 2017 Project Scope Replacement of Door Hardware for Accessibility Contractor submitted for May Board Approval.

64 2017 GROWTH & IMPROVEMENT

65 2017 ATHLETIC AREAS UPGRADES Hobby MS, Pease MS, and Taft HS Architect Nextgen Architects Project Architect Joel Hernandez NISD Project Manager Chris Parker Contractor CGC General Contractors Contract Amount $1,222, Construction Period June 2017 August 2017 Construction Status: 0% Complete Project Scope Installation of Athletic Storage Mobile Shelving and Interior Renovations. Notice of Award Issued March 29, Construction scheduled to start June 5, 2017.

66 JORDAN MIDDLE SCHOOL Interior Painting Project Architect Noonan Rittimann Project Architect Noonan Rittimann NISD Project Manager James Evans Contractor Cleanology Service & Supply Construction Budget $265, Construction Period June 2017 August 2017 Construction Status: 0% Complete Project Scope Paint Interior of the School. Notice of Award issued May 2, Painting scheduled to start June 5, 2017.

67 ATHLETIC STORAGE BUILDING AT TAFT HS AND JOHN JAY HS Architect Garza Bomberger Project Architect Roy Lewis NISD Project Manager James Evans Contractor Hector Barrera Construction, LLC Contract Budget $142, Construction Period June 2017 July 2017 Construction Status: 0% Complete Project Scope Installation of Athletic Storage Buildings. Notice of Award issued April 27, Construction Scheduled to start June 5, 2017.

68 2016 HAIL DAMAGE ROOFING PROJECTS PHASE I

69 LIST OF SCHOOLS Phase I Hail Damage Roofing Projects - In Design Roofing Consultant Hollon & Cannon Beard Elementary School Contract Amount - $566, Construction Period June 2017 December 2017 Project Scope Roof Replacement and Restoration Carnahan Elementary School Contract Amount - $2,125, Construction Period June 2017 December 2017 Project Scope Roof Replacement Clark High School Contractor Port Enterprises, LTD Contract Amount - $2,490, Construction Period June 2017 December 2017 Project Scope Roof Replacement

70 LIST OF SCHOOLS Phase I Hail Damage Roofing Projects - In Design Roofing Consultant Raba Kistner South Transportation Contractor Cram Roofing Contract Amount - $261, Construction Period June 2017 December 2017 Project Scope Roof Replacement Stevenson Middle School Contractor Cram Roofing Contract Amount - $1,904, Construction Period June 2017 December 2017 Project Scope Roof Replacement & Restoration

71 LIST OF SCHOOLS Phase I Hail Damage Roofing Projects - In Design Roofing Consultant Austech Carlos Coon Elementary School Contractor Beldon Roofing Contract Amount - $1,409, Construction Period June 2017 December 2017 Project Scope Roof Replacement & Restoration Elrod Elementary School Contractor Port Enterprises Contract Amount - $784, Construction Period June 2017 December 2017 Project Scope Roof Restoration Fernandez Elementary School Contractor Empire Roofing Contract Amount - $1,102, Construction Period June 2017 December 2017 Project Scope Roof Replacement & Restoration

72 2016 HAIL DAMAGE ROOFING PROJECTS PHASE II

73 LIST OF SCHOOLS Phase II Hail Damage Roofing Projects - In Design Roofing Consultant Austech Brauchle ES, Raba ES, and Leon Springs Elementary School Contractor TBD Budget Amount - $896, Construction Period December 2017 March 2018 Project Scope Roof Replacement & Restoration Burke Elementary School Contractor TBD Budget Amount - $964, Construction Period December 2017 March 2018 Project Scope Roof Replacement & Restoration

74 LIST OF SCHOOLS Phase II Hail Damage Roofing Projects - In Design Roofing Consultant Hollon & Cannon Connally Middle School Contractor TBD Budget Amount - $1,637, Construction Period December 2017 April 2018 Project Scope Roof Replacement & Restoration Esparza Elementary School Contractor TBD Budget Amount - $1,493, Construction Period December 2017 April 2018 Project Scope Roof Replacement & Restoration