BN SENA SPECIALIST HOSPITAL

Size: px
Start display at page:

Download "BN SENA SPECIALIST HOSPITAL"

Transcription

1 BN SENA SPECIALIST HOSPITAL

2 Page1

3 Table of content: 1. PROJECT OVERVIEW PROJECT DESCRIPTION PROJECT GENERAL INFORMATION SCOPE OF THE WORK PROJECT DASHBOARD STATUS FINANCIAL STATUS AND DATA HISTORY OF PAYMENTS: VARIATION ORDERS (VO) WORKPROGRESS MAN-DAYS STATUS OF THE PERIOD SAFETY SAFETY MANAGEMENT SAFETY MEETINGS ACCIDENT STATUS NOTICE OF UNSAFE CONDITION ENVIRONMENTAL COMPLIANCE MEETINGS SITE VISITORS MATERIAL AND EQUIPMENT DELIVERED TO SITE PROGRESS AND SCHEDULING MAJOR ACTIVITIES EXECUTED THIS PERIOD SUMMARY OF MAJOR ACTIVITIES SCHEDULED FOR AUGUSET 2018: SUBMITTALS : PROGRESS PHOTO Page2

4 1. Project Overview 1.1 Project Description Seven story hospital building that will have around 190 beds, which will provide various types of medical services to Jenin city & Governorate. Page3

5 1.2 Project General Information Project name Contract No Ibn Sena Specialist Hospital- Finishing work Award Date January 09, 2018 NTP Date March 01,2018 Start Date Of Construction Activity April 01,2018 Contractual Period Of Performance 550 Days Contractual Completion Date September 01,2019 Project Location (Area and governorate) The project is located in Jenin Governorate 1.3 Scope of the work 2 Supply & install all required materials & equipment to complete all finishing works for the hospital to make it ready to receive furniture & medical equipment in preparation of having it operational, for further detailed scope, kindly see below: 1. Architectural Finishing a. Metal work. b. Thermal & moisture protection. c. Aluminum, glass doors & windows. d. Wood and decoration finishing. e. Finishing works-painting, tiling, marble, suspended ceiling etc. f. Special room s finishing-surgery operation, ICU, CCU, isolation rooms, x-ray, emergency Etc. g. External works. 2. finishing & equipment s : a. HVAC System. b. Water System c. Firefighting System d. Drainage System e. Gas and Oil System f. Solar System 3. Electrical finishing & equipment s : a. Cables and wiring b. Lighting Fixtures c. Distribution Boards d. Low current (Telephone, data and TV Systems) e. Fire Detection and Alarm Addressable System f. Lightning protection system g. Lightning protection system h. Earthing system i. Elevators j. Barriers k. Transformer Page4

6 2.2 Project Dashboard Status Contract Elapsed Time as of Aug 31, 2018 [%] % Planned Percentage of Completion through Aug [%] 10 % Actual Percentage of Completion through Aug [%] 5% 2. Financial Status and Data 2.1 History of Payments: No. Payment Description Date Submitted By Contractor Date Approved By P. M Date Paid Amount (NIS) Remarks TOTAL 2.2 Variation Orders (VO) Variation # Variation Description Variation Value(NIS) 01 - Total Page5

7 3.WorkProgress A) Period: Aug 01, 2018 Aug 31, 2018 Progress percentages from project start until August 31, 2018 as the following: Section No. Architectural WORKS Description Progress % Scheduled Actual Variance 1.0 Mobilization and demonization 100% 100% 0% 2.0 Masonry works (Block works ) 90% 85% -5% 3.0 Metal Works 0% 0% 0% 4.0 Wood Works 0% 0% 0% 5.0 Thermal and moisture protection 0% 0% 0% 6.0 Doors and windows 18% 2% -16 % 7.0 Finishing work (plastering,tiling,painting, marble & ceiling) 15% 8 % -7% 8.0 Specialties works 0% 0% 0% 9.0 External Finishing works 0% 0% 0% MECHANICAL WORKS Air conditioning and ventilation installation 4% 2% -2.0% system Water system 2% 3% +1% Drainage system 2% 3% +1% Gas and oil system 0% 0% 0% Solar water collector 0% 0% 0% Electrical WORKS 16.1 Cables and wiring 0% 0% 0% 16.2 Lighting Fixtures 0% 0% 0% 16.3 Distribution Boards 1.5% 0% -1.5% 16.4 Low current(telephone, data and TV Systems) 2% 2% 0% 16.5 Fire Detection and Alarm Addressable System 0% 0% 0% Page6

8 16.6 Public address and access control systems 0% 0% 0% 16.7 Lightning protection system 0% 0% 0% 16.8 Earthing system 0% 0% 0% 16.9 Elevators 0% 0% 0% Barriers 0% 0% 0% Transformer 0% 0% 0% 4. Man-Days Status of the Period During this reporting period, nine Non working days recorded; official holidays (Fridays). The below table summarize the working and non-working days during the reporting period. Month / Year (Aug 01 Aug 31) / Total Number of Calendar Days of the period 31 2 Total Number of Working Days of the period 22 3 Total Number of Holidays (Friday 5 days & Eid al- Adha 4 Days) 4 Non-Working Days Due to Bad Weather Accumulated Number of Calendar Days (up to date) Accumulated Number of Working Days (up to date) 8 Original Completion Period (Calendar) Percentage of Elapsed Calendar Days with respect to the total Completion Period % 5. Safety 5.1 Safety Management 1. Personnel Protective Equipment (P.P.E) was worn by staff & manpower. 2. Fire extinguisher and first aid kits were installed on site. 3. Safe electrical power supply was installed on site for site work in each floor. 5.2 Safety Meetings There were no safety meetings during the current reporting period. Page7

9 5.3 Accident Status There were no Accidents during this reporting period. 5.4 Notice of Unsafe Condition None reported during this reporting period. 6. Environmental Compliance. There is no environmental non-compliance recorded during this reporting period. 7. Meetings One site meeting for progress of work & purchasing committee was held in addition to daily technical meeting & discussions. 8. Site Visitors The following table shows the site visitors during this reporting period: Date Time Representative Representing Remarks 9. Material and equipment delivered to Site Item Description Unit Qty. 1. Concrete Hollow block m Plaster ready mix m Cement ton Steel door frames No Passive fire stop rod ML wall porcelain tile 60*120 cm m Wall ceramic tile 70*25 cm m Floor ceramic tile 40*40 cm 9. Floor ceramic tile 45*45 cm 10. Marble 30*60 cm m2 35 m2 159 m2 756 Page8

10 10. Progress and Scheduling Floor General Basement Floor Civil & Arch. Ground Floor Civil & Arch. First Floor Civil & Arch Second Floor.Civil & Arch Electrical Third Floor Civil & Arch Electrical Fourth Floor Civil & Arch Activities Materials and shop drawing Submittals are in progress Cleaning and housekeeping works for all floors Start aluminum work (supply and install curtain wall W37 in front elevation ) Continue finishing works for supervisors site offices Continue mechanical first fix for water supply ( pex pipe ), Niagara, drainage pipe 2 and make systems pressure test Continue plastering works for the erected partitions Start installation galvanized steel doorframe for the modified rooms Start installation pex pipe, Niagara and drainage pipe 2 Continue demolishing works for the new architectural modifications Start building hollow block walls as the new architectural drawings Continue painting works Continue plastering works for the erected partitions & for marble cladding areas Continue toilets tile work (walls and floors ) Continue porcelain tile works for walls and floors Continue toilet and wet areas waterproofing Start installation PPR, chilled water and firefighting pipes ( for the modified areas ) Finish electrical first fix for nurse call and power systems Start electrical works of the medical gases system Continue painting works Continue toilet and wet areas waterproofing Continue porcelain tile works for floors Continue plastering works for marble cladding areas Finish installation pex pipes, drainage pipe 2 and all mechanical work under tile Continue electrical first fix for nurse call, air conditioning and power system s Finish building hollow block walls Page9

11 Electrical Fifth Floor Civil & Arch Continue plastering works for the erected partitions and at marble areas Start installation galvanized steel door frames Continue installation pex pipes, drainage pipe 2 and perform pipe pressure test Start electrical first fix for power system Start demolishing works for the new architectural modifications 11. Major Activities Executed This Period Architectural and Structural Works No. Starting Date Activity Location 1 04,Aug,2018 Start installation galvanized steel door frames at the modified areas Ground Floor 2 13,Aug,2018 Start demolishing works Fifth Floor 3 14,Aug,2018 Start aluminum work (supply and install curtain wall Project front W37) elevation 4 18,Aug,2018 Start installation galvanized steel door frames at the modified areas Fourth Floor Electrical Works No. Starting Date Activity Location 1 11,Aug,2018 Start electrical first fix for air conditioning Third Floor 2 16,Aug,2018 Start electrical first fix for power system Fourth Floor Mechaical Works No. Starting Date Activity Location 1 07,Aug,2018 Start mechanical first fix at walls Ground Floor 2 15,Aug,2018 Start installation pex pipes,niagara and drainage pipe 2 Ground Floor 3 25,Aug,2018 Start installation of PPR and chilled water pipes Second floor 4 28,Aug,2018 Start installation firefighting pipes Second floor Page10

12 12. Summary of Major Activities Scheduled for Septemper 2018: No. Major Activities Scheduled Progress (%) 1. Demolishing and erecting block works at all floors 100% 2. Complete the previous phase -Electromechanical first fix 100% 3. Plastering works for the erected partitions & marble cladding areas 80% 4. Tiling work for walls and floors for Ground Floor 30% 5. Paint and false ceiling works 20% 6. Aluminum Works (curtain walls) 20% 7. Lift Lobby Wall Marble Cladding 10% 13. Submittals : No. Description No of submitted during this reporting period Cumulative No of Submittal as of Aug 31, Site memorandum 02 Correspondence out(from Contractor to ISH) Arch & civil 03 Inspection Requests (IR) Electrical 0 15 Arch & civil Material submittals Electrical Arch & civil Shop drawings Electrical Arch & civil 1 13 Request for Information 06 Electrical 1 2 (RFI) Material Testing reports Variation Order Requests (VOR) 0 0 Page11

13 15. Progress photo Building concrete Hollow Block walls for First floor Page12

14 Toilets tile work for second floor toilets Page13

15 Tile works for second & third floors (walls & floors) Page14

16 Toilets and wet areas water proofing for second & third floors Page15

17 Supply & install Aluminum curtain wall (W37 ) - front elevation Page16