BN SENA SPECIALIST HOSPITAL

Size: px
Start display at page:

Download "BN SENA SPECIALIST HOSPITAL"

Transcription

1 BN SENA SPECIALIST HOSPITAL

2 Page1

3 Table of content: 1. PROJECT OVERVIEW PROJECT DESCRIPTION PROJECT GENERAL INFORMATION SCOPE OF THE WORK PROJECT DASHBOARD STATUS FINANCIAL STATUS AND DATA HISTORY OF PAYMENTS: VARIATION ORDERS (VO) WORKPROGRESS MAN-DAYS STATUS OF THE PERIOD SAFETY SAFETY MANAGEMENT SAFETY MEETINGS ACCIDENT STATUS NOTICE OF UNSAFE CONDITION ENVIRONMENTAL COMPLIANCE MEETINGS SITE VISITORS MATERIAL AND EQUIPMENTDELIVERED TO SITE PROGRESS AND SCHEDULING MAJOR ACTIVITIES EXECUTED THIS PERIOD SUMMARY OF MAJOR ACTIVITIES SCHEDULED FOR MAY 2018: SUBMITTALS COMMENTS PROGRESS PHOTO Page2

4 1. Project Overview 1.1 Project Description Seven story hospital building that will have around 190 beds, which will provide various types of medical services to Jenin city & Governorate. Page3

5 1.2 Project General Information Project name Contract No Ibn Sena Specialist Hospital- Finishing work Award Date January 09, 2018 NTP Date March 01,2018 Start Date Of Construction Activity April 01,2018 Contractual Period Of Performance 550 Days Contractual Completion Date September 01,2019 Project Location (Area and governorate) The project is located in Jenin Governorate 1.3 Scope of the work Supply & install all required materials & equipment to complete all finishing works for the hospital to make it ready to receive furniture & medical equipment in preparation of having it operational, for further detailed scope, kindly see below: 1. Architectural Finishing: a. Metal work. b. Thermal & moisture protection. c. Aluminum, glass doors & windows. d. Wood and decoration finishing. e. Finishing works-painting, tiling, marble, suspended ceiling etc. f. Special room s finishing-surgery operation, ICU, CCU, isolation rooms, x-ray, emergency Etc. g. External works. 2. Mechanical finishing & equipment : a. HVAC System. b. Water System c. Firefighting System d. Drainage System e. Gas and Oil System f. Solar System 3. Electrical finishing & equipment : a. Cables and wiring b. Lighting Fixtures c. Distribution Boards d. Low current (Telephone, data and TV Systems) Page4

6 e. Fire Detection and Alarm Addressable System f. Lightning protection system g. Lightning protection system h. Earthing system i. Elevators j. Barriers k. Transformer 1.4 Project Dashboard Status Contract Elapsed Time as of April 30, 2018 [%] 11.0 % Planned Percentage of Completion through April [%] 3.0 % Actual Percentage of Completion through April [%] 2.55 % 2. Financial Status and Data 2.1 History of Payments: No. Payment Description Date Submitted By Contractor Date Approved By P. M Date Paid Amount (NIS) Remarks TOTAL 2.2 Variation Orders (VO) Variation # Variation Description Variation Value(NIS) 01 - Total Page5

7 3.Work Progress A) Period: April 01, 2018 April 30, 2018 Progress percentages from project start until April 30, 2018 as the following: Section No. Architectural WORKS Description Progress % Scheduled Actual Variance 1.0 Mobilization and demonization 100% 100% 0% 2.0 Masonry works (Block works ) 45% 45% 0% 3.0 Metal Works 0% 0% 0% 4.0 Wood Works 0% 0% 0% 5.0 Thermal and moisture protection 0% 0% 0% 6.0 Doors and windows 0% 0% 0% 7.0 Finishing work (plastering,tiling,painting, marble & ceiling) 2.0% 0.8 % -1.2% 8.0 Specialties works 0% 0% 0% 9.0 External Finishing works 0% 0% 0% MECHANICAL WORKS Air conditioning and ventilation installation 0% 0% 0% system Water system 0% 0% 0% Drainage system 0% 0% 0% Gas and oil system 0% 0% 0% Solar water collector 0% 0% 0% Electrical WORKS 16.1 Cables and wiring 0% 0% 0% 16.2 Lighting Fixtures 0% 0% 0% 16.3 Distribution Boards 0% 0% 0% 16.4 Low current(telephone, data and TV Systems) 0% 0% 0% 16.5 Fire Detection and Alarm Addressable System 0% 0% 0% 16.6 Public address and access control systems 0% 0% 0% 16.7 Lightning protection system 0% 0% 0% Page6

8 4. Man-Days Status of the Period 16.8 Earthing system 0% 0% 0% 16.9 Elevators 0% 0% 0% Barriers 0% 0% 0% Transformer 0% 0% 0% During this reporting period, Four Non working days occurred; official holidays (Fridays). The below table summarize the working and non working days occurs during the reporting period. Month / Year (April 01 April 30) / Total Number of Calendar Days of the period 30 2 Total Number of Working Days of the period 26 3 Total Number of Holidays 4 4 Non-Working Days Due to Bad Weather Accumulated Number of Calendar Days (up to date) Accumulated Number of Working Days (up to date) 8 Original Completion Period (Calendar) Percentage of Elapsed Calendar Days with respect to the total Completion Period % 5. Safety 5.1 Safety Management 1. Personnel Protective Equipment (P.P.E) was worn by staff & manpower. 2. Fire extinguisher and first aid kits was installed on site. 3. Safe electrical power supply was installed on site, for site work in each floor. 5.2 Safety Meetings There is no safety meetings during the current reporting period. Page7

9 5.3 Accident Status There is no Accident during this reporting period. 5.4 Notice of Unsafe Condition None reported during this reporting period. 6. Environmental Compliance. There is No environmental Non-Compliance recorded during this reporting period. 7. Meetings Progress meeting Ref (01) was held during this reporting period dated (Wednesday, 11 April, 2018) to review the progress of work and discuss project issues. 8. Site Visitors The following table shows the site visitors during this reporting period: Date Time Representative Representing Remarks 9. Material and equipment delivered to Site Item Description Unit Qty. 1 Single size back fill Ton 33 2 Concrete Hollow block (15cm thick) M Plaster ready mix M Banderol Paint Gallon 20 5 Paining putty Gallon 30 6 Toilet ceramic tile M 2 30 Page8

10 10. Progress and Scheduling Floor General Basement Floor Civil & Arch. Ground Floor Civil & Arch. Second Floor Civil & Arch. Third Floor Civil & Arch. Fourth Floor Civil & Arch Activities Materials and shop drawing Submittals are on progress. Preparing electrical study for the building to ensure design conformity with international standards. Cleaning and housekeeping works for all floors. Continue demolishing works for the new architectural modifications. Continue building hollow block walls for the new architectural modifications. Continue demolishing works for the new architectural modification. Continue building hollow block walls for the new architectural drawings. Finish demolishing works for the new architectural modifications. Finish building hollow block walls for the new architectural drawings. Continue backfilling under tiles. Continue plastering works for the erected partitions. Apply and paint of under coat and bond coat layers. Continue toilet waterproofing works. Finish Toilet Ceramic tile sample. Finish demolishing works for the new architectural modifications. Finish building hollow block walls for the new architectural drawings. Continue toilet waterproofing works. Start plastering works for the erected partitions. Continue demolishing works for the new architectural modifications. Start building hollow block walls for the new architectural modifications. Page9

11 11. Major Activities Executed in This Period (Apr 01-Apr 30,2018) Architectural and Structural Works No. Starting Date Activity Location 1 01,April,2018 Building concrete hollow block walls Third Floor 2 03,April,2018 Building concrete hollow block walls Fourth Floor 3 16,April,2018 Start paint works (repair cracks and paint under coat layer) Second floor 4 16,April,2018 Demolishing works for the second phase of the new Basement and architectural modifications Ground floors 5 21,April,2018 Building hollow block walls for the second phase of the Basement and new architectural modifications Ground floors 6 21,April,2018 Start plastering works for the erected partitions Third floor 12. Summary of Major Activities Scheduled for May 2018: No. Major Activities Scheduled Progress (%) 1. Demolishing and erecting block works at all floors 100% 2. Complete the previous phase -Electromechanical first fix 30% 3. Plastering works for the erected block partitions 50% 4. Backfill under tiles 35% 5. Tiling work for floors and walls 10% Page10

12 13. Submittals : No Description Site memorandum Correspondence out (from Contractor to ISH) Inspection Requests (IR) Material submittals Shop drawings Material Testing reports Request for Information (RFI) Variation Order Requests (VOR) No. of submitted during this reporting period Cumulative No. of Submittal as of April 30, Comments : a) Painting material was approved by Ibn Sina. b) Aluminum material will be approved during 7 days. c) Tiling material is approved & the contractor install sample for toilet tiles (ground & Walls). Page11

13 15. Progress photo Demolishing works at basement, ground, second, third and fourth floors Page12

14 Building concrete Hollow Block walls at basement,ground & Fourth floors Page13

15 Backfilling single size under tiles at second & third floors Toilets water proofing at second & third floors Page14

16 Plastering work at second & third floors for modified partitions Painting works (repair defects and paint under coat and bond layers)at second floor Toilet Ceramic tile sample at second floor Page15