1 Construction Status Dec 2017

2 Phase I

3 TOWER 7 - Masonry & plastering works in progress

4 TOWER 8 - Masonry & plastering works in progress

5 TOWER 9 - Internal & External Plastering works in progress

6 TOWER 10 - Internal & External Plastering works in progress

7 TOWER 11 - Masonry & plastering works in progress

8 TOWER 14 - Masonry works in progress

9 TOWER 15 - Masonry works in progress

10 TOWER 16 - Ninth slab - Eighth floor / Ninth floor - 8th Floor Slab Concrete

11 TOWER 17 - Seventh slab - Sixth floor / Seventh floor - 8th Floor Slab Concrete

12 Phase II

13 Tower 1 - BASEMENT FLOOR / STILT FLOOR - Earth Refilling work in progress

14 Tower 4 - FOURTH SLAB - THIRD FLOOR/ FOURTH FLOOR Column Raising up to 3rd Floor

15 TOWER12 - SECOND SLAB - FIRST FLOOR / SECOND FLOOR First Floor/Second floor slab Reinforcement

16 CLUB HOUSE

17 S. No ACTIVITIES A PURVA KENWORTH KENWORTH MARKETING PROGRESS REPORT - DECEMBER 2017 PHASE 1 - TOWERS PHASE 2 - TOWERS Club Retaini T - 07 T -08 T-09 T-10 T-11 T-14 T-15 T-16 T-17 T-01 T-02 T-03 T-04 T-05 T-06 T-12 T-13 House ng wall 1 Earth Work Excavation 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 55% 100% 100% 100% 2 Plain Cement Concrete 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 50% 100% 100% 100% 3 Footing Concrete 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 50% 100% 100% 100% BASEMENT FLOOR / STILT FLOOR 1 Column upto Plinth 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 45% 45% 100% NA 2 Earth Refilling 100% 100% 100% 100% 100% 100% 100% 100% 100% 95% 45% 100% 100% 3 Plinth beam 100% NA NA 100% 100% 100% 100% 100% 100% 100% NA NA 4 Grade Slab PCC 100% 100% 100% 100% 100% 100% 100% 100% 100% 45% 100% 100% 5 masonry(stilt floor) 95% B FIRST SLAB - STILT FLOOR / FIRST FLOOR 1 Column Concrete from Basement Floor to Stillt Floor/Stilt floor to First floor 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 2 Stilt Floor/ First floor Slab Shuttering 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 3 Stilt Floor /First floor Slab Reinforcement 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 4 Stilt Floor / First floor Slab Concrete 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 5 Masonry (Stilt floor/first floor ) 35% 75% 75% 75% 50% 95% 6 Ceiling Plastering 7 Internal Wall Plastering External plastering C SECOND SLAB - FIRST FLOOR / SECOND FLOOR 1 Column Raising upto First Floor/Second floor 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 50% 2 First Floor /Second floorslab Shuttering 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 35% 3 First Floor/Second fllor slab Reinforcement 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 20% 4 First Floor /second floorslab Concrete 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 5 Masonry(First floor /second floor) 100% 100% 100% 100% 100% 85% 90% NA 6 Ceiling Plastering 100% 100% 100% 100% 100% NA 7 Internal Wall Plastering 85% 100% 100% 100% 100% NA 8 Rough Plastering 100% 100% 100% 100% 100% External plastering 40% D THIRD SLAB - SECOND FLOOR/ THIRD FLOOR 1 Column Raising upto 2nd Floor 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 2 2nd Floor Slab Shuttering 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 3 2nd Floor slab Reinforcement 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 4 2nd Floor Slab Concrete 100% 100% 100% 100% 100% 100% 100% 100% 100% 5 Masonry 100% 100% 100% 100% 100% 90% 6 Ceiling Plastering 100% 100% 100% 100% 80% 7 Internal Wall Plastering 55% 65% 100% 100% 58% 8 Rough Plastering 100% 100% 100% 100% External plastering 40% E FOURTH SLAB - THIRD FLOOR/ FOURTH FLOOR 1 Column Raising upto 3rd Floor 100% 100% 100% 100% 100% 100% 100% 100% 100% 35% 2 3rd Floor Slab Shuttering 100% 100% 100% 100% 100% 100% 100% 100% 100% 3 3rd Floor slab Reinforcement 100% 100% 100% 100% 100% 100% 100% 100% 100% 4 3rd Floor Slab Concrete 100% 100% 100% 100% 100% 100% 100% 100% 100% 5 Masonry 100% 100% 100% 100% 100% 2% 6 Ceiling Plastering 100% 100% 100% 100% 45% 7 Internal Wall Plastering 7% 90% 100% 8 Rough Plastering 33% 100% 100% 88% External plastering 40% F FIFTH SLAB - FOURTH FLOOR/FIFTH FLOOR 1 Column Raising upto 4th Floor 100% 100% 100% 100% 100% 100% 100% 100% 100% 2 4th Floor Slab Shuttering 100% 100% 100% 100% 100% 100% 100% 100% 100% 3 4th Floor slab Reinforcement 100% 100% 100% 100% 100% 100% 100% 100% 100% 4 4th Floor Slab Concrete 100% 100% 100% 100% 100% 100% 100% 100% 100% 5 Masonry 100% 100% 100% 100% 100% 6 Ceiling Plastering 25% 75% 86% 100% 7 Internal Wall Plastering 85% 100% 8 Rough Plastering 100% 100% 9 External plastering 40% G SIXTH SLAB - FIFTH FLOOR/ SIXTH FLOOR 1 Column Raising upto 5th Floor 100% 100% 100% 100% 100% 100% 100% 100% 100% 2 5th Floor Slab Shuttering 100% 100% 100% 100% 100% 100% 100% 100% 100% 3 5th Floor slab Reinforcement 100% 100% 100% 100% 100% 100% 100% 100% 100% 4 5th Floor Slab Concrete 100% 100% 100% 100% 100% 100% 100% 100% 100% 5 Masonry 90% 98% 100% 100% 85% 100% 6 Ceiling Plastering 75% 93% 100% 7 Internal Wall Plastering 75% 100% 8 Rough Plastering 100% 100% 9 External plastering

18 PURVA KENWORTH KENWORTH MARKETING PROGRESS REPORT - DECEMBER 2017 PHASE 1 - TOWERS S. No ACTIVITIES Club Retaini T - 07 T -08 T-09 T-10 T-11 T-14 T-15 T-16 T-17 House ng wall H SEVENTH SLAB - SIXTH FLOOR / SEVENTH FLOOR 1 Column Raising upto 6th Floor 100% 100% 100% 100% 100% 100% 100% 100% 95% 2 6th Floor Slab Shuttering 100% 100% 100% 100% 100% 100% 100% 100% 85% PHASE 2 - TOWERS T-01 T-02 T-03 T-04 T-05 T-06 T-12 T th Floor slab Reinforcement 100% 100% 100% 100% 100% 100% 100% 100% 75% 4 6th Floor Slab Concrete 100% 100% 100% 100% 100% 100% 100% 100% 50% 5 Masonry 85% 95% 100% 100% 80% 6 Ceiling Plastering 90% 100% 7 Internal Wall Plastering 40% 8 Rough Plastering 100% 9 External plastering I EIGHTH SLAB - SEVENTH FLOOR/ EIGHTH FLOOR 1 Column Raising upto 7th Floor 100% 100% 100% 100% 100% 100% 100% 100% 15% 2 7th Floor Slab Shuttering 100% 100% 100% 100% 100% 100% 100% 100% 3 7th Floor slab Reinforcement 100% 100% 100% 100% 100% 100% 100% 100% 4 7th Floor Slab Concrete 100% 100% 100% 100% 100% 100% 100% 100% 5 Masonry 42% 86% 100% 100% 75% 6 Ceiling Plastering 82% 100% 7 Internal Wall Plastering 25% 8 Rough Plastering 100% 9 External plastering J NINTH SLAB - EIGHTH FLOOR / NINETH FLOOR 1 Column Raising upto 8th Floor 100% 100% 100% 100% 100% 100% 100% 85% 2 8th Floor Slab Shuttering 100% 100% 100% 100% 100% 100% 100% 70% 3 8th Floor slab Reinforcement 100% 100% 100% 100% 100% 100% 100% 60% 4 8th Floor Slab Concrete 100% 100% 100% 100% 100% 100% 100% 50% 5 Masonry 70% 72% 100% 90% 2% 6 Ceiling Plastering 40% 7 Internal Wall Plastering 8 Rough Plastering 9 External plastering K TENTH SLAB - NINTH FLOOR /TENTH FLOOR 1 Column Raising upto 9th Floor 100% 100% 100% 100% 100% 100% 90% 5% 2 9th Floor Slab Shuttering 100% 100% 100% 100% 100% 100% 80% 3 9th Floor slab Reinforcement 100% 100% 100% 100% 100% 100% 70% 4 9th Floor Slab Concrete 100% 100% 100% 100% 100% 100% 50% 5 Masonry 5% 55% 100% 90% 6 Ceiling Plastering 7 Internal Wall Plastering 8 Rough Plastering 9 External plastering L ELEVENTH SLAB - TENTH FLOOR / TERRACE FLOOR 1 Column Raising upto 10th Floor 100% 100% 100% 100% 100% 100% 10% 2 10th Floor Slab Shuttering 100% 100% 100% 100% 100% 100% 3 10th Floor slab Reinforcement 100% 100% 100% 100% 100% 100% 4 10th Floor Slab Concrete 100% 100% 100% 100% 100% 100% 5 Masonry 4% 35% 95% 20% 6 Ceiling Plastering 7 Internal Wall Plastering 8 Rough Plastering 9 External plastering M TWELTH SLAB - TERRACE FLOOR 1 Column Raising upto Terrace Floor 100% 100% 100% 100% 100% 90% 2 Terrace Floor Slab Shuttering 100% 100% 100% 100% 100% 75% 3 Terrace Floor slab Reinforcement 100% 100% 100% 100% 100% 70% 4 Terrace Floor Slab Concrete 100% 100% 100% 100% 100% 50% 5 Above Terrace column 100% 100% 100% 100% 100% 6 SHR Slab 100% 100% 100% 100% 100% 7 OHT Slab 35% 75% 100% 45% 20% 8 Block work 70% 70% 90% 45%

19 Provident Housing Limited, 130/1, Ulsoor Road, Bangalore , Call , crm@puravankara.com