Capital Improvement Program Monthly Status Report

Size: px
Start display at page:

Download "Capital Improvement Program Monthly Status Report"

Transcription

1 Projects Upgrades in Multipurpose Building 1300 In order to meet the needs of the building s three distinct uses administrative gatherings, recreational program space, and as a general venue and event area the upgrades to the Multipurpose Room focus on providing an enhanced acoustical treatment and experience, badminton striping and equipment, and an overall increase in user satisfaction. Creating a common environment among these uncommon activities leads to the introduction of zones by means of floor patterning or ribbons as a unifying architectural feature. The sport striping, the meeting areas, and the distribution of different zones in the multipurpose room emerge as a singular user experience. Delivery Method: Design-Bid-Build Synthetic Turf Field Replacement (Districtwide Project) Synthetic Turf was first installed at East Side High Schools athletic fields during the summer of 2011 and The recommended product life of the turf installed is 5-6 years. This project is a scheduled replacement of the synthetic turf at Andrew P. Hill, James Lick, Oak Grove, Piedmont Hills, Santa Teresa and Yerba Buena. New synthetic turf will be installed at Foothill. Delivery Method: TBD Hardscape Improvements (Districtwide Project) Replace and repair hardscape in select areas that have become safety and aesthetic issues and need to be improved for vehicular access and exterior activity areas, such as play courts. The design solutions will consider the natural forms, intuitive wayfinding and exterior use patterns of the campus. Improvements will be made at Andrew Hill, Santa Teresa and Yerba Buena. Delivery Method: TBD

2 Schedule LEGEND Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Pre-Construction Upgrades in Multipurpose Building 1300 Construction Procurement DSA Review Construction Occupancy/Beneficial Use Schedule subject to change due to factors beyond our control *These Districtwide Project schedules only show construction at this site. For more information about other phases of the projects, please see the Districtwide CIP Monthly Report. Districtwide Project schedules are shown if available.

3 Project Funding Sources & Uses Measure E (2008) Measure I (2012) Project Fund 23 Fund 24 Total Upgrades in Multipurpose Building 1300 $106 K $600 K $706 K Total $106 K $500 K $706 K *The budgets for Districtwide Projects are shown on the Districtwide CIP Monthly Report.

4 Expenditures Snapshot as of February 28, 2018

5 Andrew Santa Teresa P. Hill High School Projects Schedule Business Partners Highlights/Issues Business Partners Upgrades in Multipurpose Building 1300 Construction Manager Gilbane Building Company Architect Artik Art & Architecture Contractors Venezia Construction, Inc. Pathway Communications, Ltd Harry L. Murphy, Inc.. Inspector N/A Special Testing & Inspection N/A Furniture, Fixtures & Equipment (FF&E) Greatmats.com TarpsNow *Business Partners for Districtwide Projects are shown on the Districtwide CIP Monthly Report.

6 Andrew Santa Teresa P. Hill High School Projects Schedule Business Partners Highlights/Issues Highlights/Issues Upgrades in Multipurpose Building 1300 The remaining scope of work will includes new FRL wall panels, chair rails, framing for wall panels, and a new speaker system. Fiberglass Reinforced Laminate (FRL) will be applied to the walls to increase durability of the lower portions as well as a design element to tie in all the elements in the Multipurpose Room. Work began at the end of March.