Stonegate at Rush Creek Project No Change Order No.1

Size: px
Start display at page:

Download "Stonegate at Rush Creek Project No Change Order No.1"

Transcription

1 April 4, 2016 DATE ORIGINATING DEPT Jupe Hale, P.E. Assistant City Engineer REQUEST FOR COUNCIL ACTION AGENDA ITEM Stonegate at Rush Creek Project No Change Order No.1 3G AGENDA ITEM CITY ADMINISTRATOR APPROVAL PREVIOUS ACTIONS: At their June 1, 2015 meeting, Council awarded a contract in the amount of $641, to Friedges Contracting, Inc. for the Stonegate at Rush Creek Project No RECOMMENDED COUNCIL ACTION: Motion to approve Change Order No.1 to the Stonegate at Rush Creek Project No providing for inflationary unit price increases and revised project schedule. Total contract increase is proposed to be $19,237.65, contract time for substantial completion is proposed to be 88 calendar days from Notice to Proceed, and final contract completion date is proposed to be June 17,2017. COMMENTS: Original project schedule anticipated a late summer 2016 start date, dependent on completion of mass grading on the site by the developer. Mass grading was not complete on site until late September/early October, at which point weather and temperature variability introduced significant risk in starting the project, with no commensurate benefit to the public improvements. Consequently, project start was delayed until The revised unit prices reflected in Change Order No. 1 are consistent with industry-wide inflation of materials and labor, generally understood to be in the neighborhood of 3%. It bears noting that Friedges Contracting, Inc.'s original bid was substantially less than the next lowest bidder, such that acceptance of this inflationary Change Order No.1 and revised schedule is desirable as compared to pursuing the next lowest bidder or rebidding the work entirely. It is recommended that Council approve the attached Change Order No.1, increasing the contract amount by $19, to a total contract amount of$660,729.95, and modifying the project schedule to 88 calendar days with a final completion date of June 17,2017.

2 Consulting Group, Inc. ENGINEERS PLANNERS DESIGNERS SRF No CHANGE ORDER NO.1 City of Maple Grove Arbor Lakes Parkway Maple Grove, MN PROJECT: CONTRACTOR: WHEREAS: STONEGA TE AT RUSH CREEK STREET AND UTILITIES CITY OF MAPLE GROVE PROJECT NO FRIEDGES CONTRACTING CO., LLC Kenrick Avenue Lakeville, MN Site grading of this residential development is being performed by the developer under a private grading contract; and The completion of the site grading has been postponed by the developer until spring of 20 16; and City Project was to commence upon completion of the site grading and be substantially complete in Completion dates for CP must be modified to dates in 2016; and The low bidder for CP 14-20, Friedges Contracting has agreed to perform the work as bid in 2015, with unit price adjustments consistent with industry indices; and Friedges Contracting is entitled to additional project completion time per General Conditions of the Contract, Section 7. NOW, THEREFORE IT IS MUTUALLY AGREED AND UNDERSTOOD THAT: 1. Original 2015 unit prices are hereby deleted and replaced with the attached 2016 adjusted unit prices. REVISED CONTRACT VALUE a. Origina12015 Contract b. Adjusted 2016 Contract Increase $641, $660, $19, One Carlson Parkway North, Suite 150 I Minneapolis, MN I Fax: All Equal Opportlfllity Employer

3 Change Order No. 1 Stonegate at Rush Creek Page 2 of2 2. Consistent with The City of Maple Grove Standard Specifications for Utility and Street Construction 2015, Conditions of the Contract Section 7, Section S-15 of the Contract Special Provisions is hereby deleted and replaced with the following: (1806) DETERMINATION AND EXTENSION OF CONTRACT TIME Section 1806 is hereby deleted, except for Sections A and B of Section , and the following substituted therefore: Contract time for substantial completion shall be on a calendar day basis as follows that begins 14 calendar days from a Notice to Proceed: Utilities and Road Work through all but the final wear surfacing, all sidewalk, turf establishment and interim casting adjustments for the entire project shall be completed 88 calendar days from a Notice to Proceed. This includes installation time and coordination for small utilities. Contract time for final completion shall be on a completion date basis as follows: The final completion date including final casting adjustments, bituminous wear paving, any remaining contract work and all punch list work and clean up shall be completed by June 15,2017. Completion shall be construed to mean when all items have been installed, tested, inspected and approved. 3. The Contractor will not make claim of any kind or character whatsoever for any additional costs or expenses he may have incurred or that he may hereafter incur in performing the work and furnishing the materials described in the proposal, or for work performed relating to the described work. 4. In accordance with the terms of the Contract you are hereby authorized and instructed to perform the improvements as described above. ISSUED BY: ~.~ SRF ~ ING GROUP, INC. DArt / DAtE I APPROVED: CITY OF MAPLE GROVE DATE Attachment H:IProjects\8635\Hl-MU\DOC\8635 _CO 1_ doc

4 ,, Kenrick Avenue Lakeville, MN Phone: Fax: COST ESTIMATE 2015 PROJECT NAME: STONEGATE ENGINEER: SRF OWNER: CITY OF MAPLE GROVE DESCRIPTION OF WORK QUANTITY UNIT PRICE EXTENSION 1 MOB. lls $10, , REMOVESTM 31 LF $ REMOVEC&G 40 LF $ REMOVE CONe. WALK 150 SF $ REMOVE BIT 2790 SF $0.62 1, REMOVE STM STRUCT. lea $ SALVG.V SEA $ , SALVo HYD 5EA $ , SUBGRADE EXC. 400 CY $6.70 2, SEL GRAN BORROW 0/ 1620 CY $ , GEO FAB 1970 SY $1.52 2, HAUL EXCESS MAT. 400 CY $8.25 3, SUBGRADE PREP 10.7 RS $ , STREET SWEEP 40 HR $ , AGG. BASE CL CY $ , " MINUS 430 CY $ TACK 300 GAL $3.60 1, " BIT BASE 3930 SY $ , " BIT WEAR 3930SY $ , ROCK STABILIZATION 50 TN $ , " FES lea $ " FES lea $ oes lea $7, , " D.T 160 LF $ , " RCP 173 LF $ , " RCP 43 LF $ , " RCP 52 LF $ , CONN. TO EX SAN SEWER 3EA $5, , CONN. TO EX SAN SEWER MH lea $10, , SEWER RISER 120 LF $ , " x4" WYE 21 EA $ , " BEND 63 EA $ " PVC 1180 LF $ , " STEEL JACKED 138 LF $ , " PIPE SEWER 807 LF $ , " PVC SDR LF $ , " PVC SDR LF $ , " PVC SDR LF $ , " PVC SDR LF $ , " PVC SDR LF $ Pog.lo,2

5 DESCRIPTION OF WORK QUANTTIY UNIT PRICE EXTENSION 4 1 8" PVC SDR LF $ ,100,00 42 CONN, TO EX WfR 7EA $1, ,375,00 43 HYD 5EA $ ,050,00 44 G,V SEA $ ,700,00 45 ADJ G.V 2EA $260,00 520,00 468" X 6" RED 2EA $408,00 816,00 478" 22 2EA $ ,00 486" 22 lea $ , " 45 lea $345, " 45 lea $ , " 22 2EA $1, , " 11 lea $ I" CORP 21 EA $ ,930,00 548" x 6" TEE 2EA $610,00 1,220,00 558" X 8" TEE lea $ " X 6" TEE lea $2, , "G.V SEA $1,480,00 7,400, "G.V 5EA $2, , I" CURB STOP 21 EA $ ,030,00 601" PE 1032 LF $ ,732,80 616" PVC 293 LF $ , " PVC 788 LF $ ,863, " PVC 939 LF $ , STRUCTG lea $1,450,00 1, STRUCT SPEC 1 9EA $1, , STRUCT SPEC 2 2EA $1, ,950,00 67 ADJ, CAST 9EA $382,00 3,438,00 68 CONN, TO EX STMH lea $825,00 825, " SAN MH EA $2,170,00 21,700,00 70 SAN OVERDEPTH 88 LF $165,00 14,520,00 71 RIPRAP 10 CY $ ,120, " CONCWALK SF $ , " BIT, WALK 3190 SF $2,75 8, CONC CURB SPECIAL 2350 LF $ , TRUNCATED DOME 64 SF $ , CONC BARRIER 176 LF $ , " CONDUIT 1400 CF $3.10 4, TRAFFIC CONTROL ll5 $2, ,575,00 79 F & I SIGN 2EA $ SILT FENCE 2470 LF $1.80 4, INLET PROTECT 21 EA $180,00 3, STABIUZE EXIT ll5 $ SEEDING 1.8 AC $ SEED MIX LB $ SODDING 2990 SY $ , MULCH 3.4 TN $ DISC 1.8 AC $ FERT. 130 LB $ TOTAL 660, Respectfully submitted, FRIEDGES CONTRACTING llc Brady Enright Estimator / Project Manager 3/15/2016 Date P. g. 2 or 2